Issues raised
Introduction
2.1
Witnesses and submitters raised a range of environmental issues in
relation to the Roe 8 project and the perceived failure of regulators to
address concerns. This chapter discusses the following issues:
-
the environmental significance of the area of the Roe 8 stage of
the Freight Link;
-
the environmental damage the implementation of the Roe 8 stage of
the Freight Link has already caused;
-
potential non-compliance of contractors with the project's Fauna
Environment Management Plan (FEMP), including poor trapping standards for
southern brown bandicoots, deficiencies in the reptile and turtle removal
programs, the lack of adequate fencing to protect fauna in areas being cleared,
and an insufficiently rigorous survey of black cockatoo and other bird nesting
sites before construction began;
-
alleged non-compliance of contractors to the binding conditions
of the Construction Environmental Management Plan (CEMP), on dieback and
plant disease, asbestos waste disposal and the management of dust; and
-
the inadequate response of the state and Commonwealth governments
to concerns raised about potential violations of the project's management
plans.
Environmental and cultural significance
2.2
As noted in chapter 1, the area of development has high environmental
value as well as encompassing Aboriginal heritage areas. Professor Richard
Hobbs, a member of the Beeliar Group, provided the committee with an overview
of the environmental importance of the Beeliar Wetlands:
The southwest [part of Western Australia] is one of the
declared biodiversity hotspots of the world, so that means that it has a huge
diversity of species—flora and fauna—many of which are found nowhere else in
the world. The Beeliar Wetlands is one of the jewels in that crown, if you
like, and it is very special not just because of its biological status but
because of its location in the middle of a city. The biological value is huge,
but the social value is huge as well. People love that area. People use it for
recreation—and they appreciate the birds, the animals and so on. That is why
you get such an emotive response from people when it is being destroyed.[1]
2.3
The committee also received evidence about the importance of the area
for the southern brown bandicoot, the Carnaby's black cockatoo, the forest
red-tailed black-cockatoo, glossy-leafed hammer orchid, grand spider orchid and
beaked lepidosperma as well as some migratory birds.[2]
Environmental damage caused by Roe 8 works
2.4
The committee heard evidence that the works undertaken for the Roe 8
extension have already caused serious environmental damage to the Beeliar
Wetlands. Ms Katharine Kelly, Convenor, Save Beeliar Wetlands, provided the
committee with an overview of the destruction that has occurred on the
construction site since works began in late December 2016:
The following Monday [after the High Court revalidation of
the Roe 8 environmental approvals], the bulldozers moved into the Coolbellup
woodlands and destroyed about five hectares over 19 and 20 December 2016.
We watched in
horror as the beautiful orchids, banksias, bandicoots, little skinks, tall
jarrah trees, little sedges, bushes and grass trees alike were violently pushed
together and then piled up for mulching. There was no translocation of any
trees. Many of us saw bandicoots running and birds fleeing trees as they were
toppled. We knew there was lots of dumped asbestos in the area and, because of
the lack of water trucks and lack of any wetting down, huge plumes of dangerous
dust rose in the air and drifted over homes. That night and even whilst we
washed the dust and tears and anger off our bodies and clothes, many of us were
wondering how the construction contractors could be getting away with such
blatant shows of noncompliance. At this stage the environmental management
plans had been published for a scant two weeks.[3]
2.5
Mr Logan Howlett, Mayor, City of Cockburn, commented on the damage that
has been done to date is 'vandalism'. He noted the concerns with the
destruction of ancient trees:
...we have seen 300- to 500-year-old trees bulldozed down and
mulched up and wood chipped up. There are also the two Norfolk Island pine
trees that were planted by John Dixon and his wife on the occasion of their
wedding in 1900. Those Norfolk pine trees, which were planted in 1900, have
been cut down to a height of, probably, five metres each and been left there
almost as a signal to the community that this project will proceed at any cost.
The Dixon family and the community are devastated in the context of that
arrogance, as I would term it. It is total arrogance.[4]
2.6
While much damage has been done to the wetlands after only a few months
of work, significant areas of bushland have not yet been cleared. Miss Phoebe Corke,
a member of Wetland Watchers, commented:
Two of the most beautiful parts of the project are still
standing. At the other end of the project, there is some beautiful bushland
still there so it is not over yet in terms of the destruction. As to what has
been destroyed, it is basically a 25 to 30 metre strip that runs at the moment
for 4½ kilometres. There are crushed limestone paths being put into a great
deal of this and they are about four to five metres wide, and that is where we
are at the moment.[5]
Implementation of the Fauna Environment Management Plan
2.7
Professor Hobbs commented that the implementation of the FEMP has been
flawed in several ways.[6]
The committee also received evidence that there may have been violations of the
legally binding terms of the FEMP, as well as the conditions of approval under the
Environment Protection and Biodiversity Conservation Act 1999 (the EPBC
Act), including by:
-
contraventions of trapping practices, particularly for bandicoots;
-
poorly designed and implemented programs for turtle trapping;
-
insufficient provision of fencing and netting to protect fauna
from injury or mortality while bushland is cleared; and
-
potentially inadequate surveys of local bird populations before
clearing began—particularly nesting sites of threatened species of black cockatoo.
Trapping of southern brown
bandicoots
2.8
Ms Kelly, Save Beeliar Wetlands, made it clear to the committee that the
southern brown bandicoots are protected under the EPBC Act, and that they
played a central part in the health of the local ecosystem:
The southern brown bandicoots are a priority species under
the EPBC Act. This urban woodland and wetland system is one of the last
remaining fragments of urban bushland and wetlands on the Swan coastal plain.
It contains nature woodlands, which the bandicoots particularly love. There is
an incredible relationship between the health of the system and the bandicoots
being there. They are like constant little gardeners. They actually move about
three tonnes of soil each a year. So they aerate the soil and make the trees
able to have a [mycorrhizal] function. The micro-algal function is the way in
which the trees communicate with one another and ensures that the health of the
whole ecosystem is kept intact. They are actually essential for the health of
the urban woodland and wetland system.[7]
2.9
The FEMP stipulates a number of conditions for the trapping of southern
brown bandicoots before clearing can begin, including that:
-
3–4 days of trapping must take place before clearing, and that
this must continue until traps are clear of bandicoots for 2 consecutive
trapping nights;[8]
-
should bandicoots still be found in traps for 2 consecutive after
a 3–4 day trapping program is completed, a fauna expert must be consulted, and
their recommendations must be implemented until the number of bandicoots trapped
significantly reduces;[9]
-
traps will be closed in hot weather (i.e. above 30 degrees and/or
for consecutive days), and reopened in the late afternoon to avoid bandicoot mortality;[10]
and
-
traps will be closed in periods of heavy rain, and reopened in
the late afternoon to avoid drowning of trapped animals due to flooding.[11]
2.10
Some witnesses gave evidence suggesting that trapping undertaken by
contractors to prepare areas for clearance had not adhered to stipulations of
the FEMP.[12]
For example, Ms Corke, Wetlands Watchers, gave several examples that had been documented
by the group:
On three occasions we have seen bandicoots removed the
morning before they cleared an area. We have also been told that the area is
scheduled for clearing the next day, which we find extremely bizarre because
how can you schedule something before you know what the result of the previous
night's trapping will be? Also, on two occasions on the same day, we saw
bandicoots being removed from an area which they started clearing that afternoon,
and right at the beginning, on the second day of clearing in January, we saw
bandicoots being removed 90 minutes before they cleared an area.[13]
2.11
Ms Corke provided the committee with photos documenting poor trapping
practices taken by members of Wetlands Watchers, as well as an Excel
spreadsheet documenting these incidents. These included documentation of traps
set in poor locations (too close to roads or perimeter fences and in noisy or
well-lit locations), and traps set too close together or with insufficient
covers (both for camouflage and trapped animal protection against the
elements).[14]
It also appears that some bandicoots have been placed on the ground while in
bags, or that these bags have been stacked on top of each other and left in the
sun.
2.12
In addition, Ms Corke suggested some areas being cleared obviously had a
number of bandicoots who had not been removed from the site. She stated that:
There have been bandicoots run over on road. We have seen
bandicoots running from an area that is currently being cleared and others died
on the nets which have been very inefficiently put in and they have not been
able to leave the area and died of lack of water or panic.[15]
2.13
Dr Felicity Bairstow, a retired veterinarian appearing in a private
capacity, suggested that traps had not been closed on hot days, and:
...on a 36 degree day, I became distressed enough—from a
professional perspective—at the thought of animals being out there in traps
that I called to made a report to the RSPCA.[16]
2.14
Dr Bairstow also raised more general concerns about the trapping
program, particularly potential difficulties faced by bandicoots relocated to
other areas:
I...spoke to the chief wildlife officer of [the Department of
Parks and Wildlife WA] with regard to the translocation of the southern brown
bandicoots and the futility of transplanting them to adjacent areas. The
southern brown bandicoots are very territorial. If you put bandicoots into an
area where there are already bandicoots, which there will be if it is a good
habitat for bandicoots, they will get beaten up, kicked out onto the road and
run over—and that is what happened. The reply from the chief wildlife officer
was that it was not his department. We have heard that an awful lot in the last
few months.[17]
Trapping of reptiles and turtles
2.15
The committee also received some evidence that reptile and turtle
trapping programs had not been designed or implemented effectively.
2.16
Professor Hobbs, The Beeliar Group, commented that, whereas he
considered the plan was reasonable regarding some species, it had omitted
appropriate provisions to deal with reptiles and turtles on the site:
These animals are largely cryptic and very hard to track
effectively, so the length of time given to that trapping is probably
insufficient to ensure that you are getting the animals that you want. In
addition to that, the [original] plan did not cover turtles, which were
discovered as the project began...[18]
2.17
Ms Corke, Wetlands Watchers, also provided the committee with her letter
to the Western Australian Environmental Protection Authority. This letter noted
the CEMP's deficiencies for turtle trapping:
Turtle trapping at this time of year is also extremely
ineffectual as in the warm months Oblong Turtles bury themselves in the mud,
where they remain. According to a turtle expert trapping should be for a
minimum of two to three weeks and should take place in the autumn and winter,
not in the summer. The turtle traps in Stage 5 were set for only two nights and
were set too high in the water for effective trapping even in the correct
season.[19]
2.18
Reptiles may also have been handled inappropriately; poor handling of
reptiles increases levels of stress while they are being captured for
relocation.
Fencing and netting to protect
fauna
2.19
Some witnesses argued that contractors had not provided sufficient
fencing and netting to protect fauna in areas that were being cleared.[20]
The FEMP provides that contractors must 'Install fauna fencing to exclude
terrestrial vertebrate fauna from the construction footprint and the operational
highway', that will:
-
comprise of a mesh fence to a height of no less than 1.2 m and be
dug into the ground to a depth of no less than 350 mm;
-
include temporary fauna fencing during construction, but will
conform to the standards required for permanent fencing;
-
be designed to exclude the Southern Brown Bandicoot within the
development envelope; and
-
include escape gates to allow fauna trapped in the road reserve
an exit route.[21]
2.20
Professor Hobbs commented that there had been many instances of this fencing
being non-compliant with FEMP conditions:
Another obvious and persistent breach relates to the failure
to correctly install fauna-proof mesh on the fences surrounding the areas. This
failure actually makes it impossible to categorically state that areas being
cleared are free of bandicoots.[22]
2.21
Ms Corke also provided evidence from Wetlands Watchers documenting
several occasions when protective netting had not been dug into the ground, was
missing from fences, or was clearly inadequate to keep animals out of areas
being cleared.[23]
2.22
Professor Hobbs conceded that many of the fauna experts onsite were
doing the best job they could, but they were constrained by the protocols of
the FEMP:
...I think the fauna specialists have had a tough job to do
here, and at least some of them are doing the best job they can. But, having
said that, there are many parts of the implementation—and you have heard about
them during the day already, with the problems with the trapping and so on. The
one I highlighted was the problem of not having mesh fencing put into the
barrier fences. To me, that makes it very difficult to see how the trapping
protocols can be called effective, because there is no way that you can keep
bandicoots out, and so as soon as they are trapped, some are likely to move in.[24]
Surveys of local bird populations,
particularly black cockatoos
2.23
Some submissions and witnesses questioned the adequacy of bird detection
and removal programs undertaken for the Roe 8 construction works, particularly
surveys of potential nesting sites for the threatened Carnaby's black cockatoo
and the vulnerable red-tailed black cockatoo.[25]
2.24
Dr Hugh Finn, appearing in a private capacity, provided the committee with
expert evidence based on his extensive field research into black cockatoos, and
questioned whether there had been an adequate survey of potential nesting sites.
In particular, he highlighted Condition 4 of the Commonwealth approval
conditions for Roe 8, which states:
To avoid and mitigate impacts to black cockatoos, during the
breeding season (August—December), within 7 days prior to clearing, the approval
holder must ensure all potential nesting trees are investigated to detect the
presence of black cockatoos using hollows. The investigation must be undertaken
by a suitably qualified and experienced person.
If any black cockatoos are detected using a hollow in a tree
or trees, the approval holder must:
- clearly
identify all such trees with fencing and signage that must be located within
two (2) metres of the base of each such tree;
- not clear any
such tree or any vegetation within 10 metres of any such tree; and
- undertake
all reasonable measures to avoid any such tree from being cut down, felled, removed,
killed, destroyed, poisoned, ring-barked, uprooted or burned until a suitably
qualified and experienced person has verified in writing that the hollow(s) in
each such tree are no longer being used by black cockatoos.[26]
2.25
The committee notes the federal approval specifically defines potential
nesting trees as:
Means those 38 trees specified in the list held by the
Department and provided confidentially to the Approval holder.[27]
2.26
Dr Finn expressed doubts whether adequate surveys meeting these
conditions could have been undertaken in a single day, given the need to check
every hollow big enough for nesting by using cherry pickers, drones, arborists
climbing trees, or some kind of long-term behavioural observation undertaken by
bird population experts.[28]
2.27
This view was supported by the evidence given by Ms Corke, Wetlands
Watchers. She noted that her organisation was onsite on the day when the
cockatoo nesting site survey was completed, and had not noticed any teams
moving through the area, or any equipment like cherry pickers or drones being
used to inspect trees.[29]
2.28
The Department of the Environment and Energy (the department) told the
committee that surveys of black cockatoo nesting sites were undertaken on
14 December 2016, within the stipulated 7 days of work being commenced on
19 December 2016. The department went on to note that:
We did look further to satisfy ourselves that the condition
had been met. We understand that ACON was engaged to do those. It does not
specifically say surveys, it says an investigation of the tree hollows. ACON
went on-site to investigate those hollows. They found, I think, 26 trees that
had hollows in them. Of the 26 they said 24 of those hollows were not suitable
habitat for the black cockatoos and two may or may not have been. What they
have done is taken a precautionary approach and not felled any of the trees
with hollows during the breeding period. My understanding is that 24 of the
26 trees still remain standing on the site.[30]
2.29
Concern over the checking of local bird populations prior to works
beginning were not limited to cockatoos. Ms Kelly, Save Beeliar Wetlands, told
the committee:
I am not convinced that all those trees were properly checked
for chicks. We know, for example, that many rainbow bee-eater nests were just
run over by the machines [clearing bushland]. We saw tawny frogmouths and owls
fleeing trees as they were toppled.[31]
2.30
The department has undertaken to provide the committee with further
details of the survey of bird nesting sites carried out on 14 December 2016.[32]
Rates of wildlife mortality
2.31
Mr Dean Huxley, Manager, Native ARC Inc., outlined a number of concerns
with the number of native animals left in the construction zone, many of which
were injured or killed:
In my capacity at Native ARC, I am overseeing the care of the
wildlife that are admitted to the centre, and, to date, we have received
photographs of injured and/or deceased wildlife from the public...We have
received injured or deceased animals found by the public adjacent to and on the
fence line of the Roe 8 clearing. We have received written and verbal
information from the public detailing displaced wildlife sightings in many
suburbs surrounding the Roe 8 clearing site. We have received only one injured quenda,
which was admitted via the Murdoch Pet Emergency Centre, which came via a Roe 8
contractor.
We understand that the animals targeted for capture and
relocation are quendas, jewelled ctenotus, lined skink, black-striped snake and
the south-west carpet python. Our concern is for all wildlife within the
clearing zone and the outcomes of those animals not captured or relocated. We
suspect there is a large number. These include, but are not limited to,
obviously, possums, lizards, snakes, frogs, turtles and internationally
protected rainbow bee-eaters.[33]
2.32
Ms Diane Munrowd, Manager, Native ARC Inc., questioned what protocols were
followed on the construction site for the care of injured animals:
We need to understand what the compliance is with the
treatment and rehabilitation of animals that are actually injured as part of
this clearing, and we have no idea about that at all. There are protocols for
treatment, there are protocols for rehabilitation and there are none available.
I have no idea where those animals go. I understand the ones that are not
injured are put in a holding site and then they will go to the offset areas. But
you cannot expect that there will be no animal that is injured in this process.
So if they do not get killed on the site, where are those animals taken? What
are the protocols? Because there are protocols that are required in terms of
their treatment and rehabilitation.[34]
Other concerns
2.33
A range of other concerns were raised by submitters including
non-adherence to dieback protocols by contractors, the lack of protection for
Banksia woodlands that were being cleared, the inadequate flora surveys
undertaken before environmental approval was granted for Roe 8, and flaws in
the environmental offsets for the project.
Banksia woodlands
2.34
The committee understands that the Beeliar Wetlands contain some Banksia
woodlands that the construction work will destroy. Dr Bairstow outlined the
importance of Banksia habitats to a range of native species, noting that their
destruction would impact a range of plant and animal species.[35]
2.35
The committee understands that the Roe 8 works are clearing a large area
of Banksia woodlands, which is listed as threatened species that is protected
under the EBPC Act. Moreover, the committee is aware that this woodland is
vulnerable to diseases including dieback, which is discussed below.
2.36
Officers from the Commonwealth Department of the Environment and Energy explained
that, as that Banksia woodlands scheduled for clearance for Roe 8 were listed
as endangered on 16 September 2016, and so had not been considered as part of
the environmental assessment for the project.[36]
The committee was told that this:
...is a common thing that does happen. The list of species that
is being protected and assessed over time is always evolving, and so are
projects being referred to us. It is not uncommon to have a referral decision
and then subsequently, not due to any malfeasance or anything like that, the
listing levels for different species change over time as the scientific
assessment develops.[37]
2.37
The department made it clear that it was only able to consider currently
listed species when making decisions, and could not retrospectively amend
decisions on projects:
...the relevant legislative provisions in the act are set out
in section 158A, which makes it quite clear that we are only able to make
decisions about matters that are the subject of a listing at the time the
referral is made. We are not able to factor in matters that are listed
subsequent to that date.[38]
2.38
The committee notes the independent review of the EPBC Act undertaken by
Dr Allan Hawke (the Hawke Review) which was completed in 2009 recommended
amendments to the Act to provide for emergency listings. In 2011, the Commonwealth
government committed to implement those recommendations, but did not bring a reform
package to the Parliament.
2.39
In 2011, the Parliament considered a private members bill, the Environment
Protection and Biodiversity Conservation Amendment (Emergency Listings) Bill
2011 which would have implemented those elements of the Hawke Review, and would
have addressed the effect of section 158A. Section 158A of the EPBC Act
prevents consideration of threatened species or ecological communities which
are listed after the time a referral is made. This bill lapsed at the
prorogation of the 43rd Parliament.
Flora management
2.40
Dr Bairstow pointed out the difficulty of undertaking surveys of the
area's flora, when some species only flowered sporadically:
The thing with a lot of those species, especially the orchids,
is that they are very sporadic when they are coming out. One of the issues we
have had with this project is that the flora studies were done at inappropriate
times and not sufficiently well, and so it is not surprising that they may not
have found some of those orchids.[39]
Offsets of land cleared for Roe 8
2.41
The committee understands that some of the Beeliar Wetlands cleared for
the construction of Roe 8 will be offset with new or existing bushland. Professor
Hobbs, the Beeliar Group, outlined the shortcomings of offset provisions for
the Freight Link:
The problem is that the implementation of the offsets
policies is complete rubbish. There is just no actual method for making sure
that the offsets that are set are actually having any good impact at all,
especially in the case of this Roe 8 offset, where we are allowing nearly 100
hectares of bushland to be destroyed completely and the offset is a simple
designation change on existing bushland. There is no net gain in habitat, and
so therefore it is a bit of a furphy, if you ask me. The offset does include
other management activities to improve habitat around the Beeliar area, but you
have to question how the decision was made that these offsets were actually
going to compensate for the loss of the woodland.[40]
2.42
Dr Bairstow was of a similar view and stated that:
The concept of offsets in general has developed into a system
of nothing much better than smoke and mirrors. We are not creating new habitat.
We are destroying habitat and trying to convince people that somehow by putting
an area into a conservation reserve it becomes new habitat.[41]
2.43
Dr Bairstow went on to comment that many animal species such as the bandicoot
are territorial and are not necessarily going to move to the offset area.
Problems with cockatoos are emerging:
Every day we have reports of people with flocks of cockatoos
in their backyards that are hungry. They are looking for food and they are
looking for somewhere to roost. It is quite tragic. That offset, which is in
Lake Clifton, is not going to provide any food or roosting habitat for those
cockatoos.[42]
2.44
Professor Hobbs also noted how long it takes for offset planting to
provide environmental benefits:
The problem is that if you are destroying a banksia woodland
with trees in it that are 300 or 400 years old [as in the Beeliar Wetlands],
obviously it is going to take you 300 or 400 years to get back to that habitat.
If it is replacing Carnaby's cockatoo habitat it is going to take the banksia
trees 10, 20, 30 years to recover their ability to produce food for the
cockatoos and so on. So there is a big lag between when the damage is done and
when the reparation is made.[43]
2.45
A further matter raised by Professor John Bailey, The Beeliar Group, related
to the double counting of offset areas. He stated:
...I would like to draw your attention to the other offsets...A
number of those in my view are actually double counted. They are commitments to
do things that were already made, independently of Roe 8, and have just been
listed again under Roe 8 offset requirements. One example is improved
management of Thomsons Lake. The offset conditions there are drawn directly
from the Thomsons Lake management plan that was prepared many years ago. So I
think we have to be very careful in recognising what offset requirements are
truly new and what are just the rebadging and double counting of existing
commitments.[44]
Implementation of the Construction Environmental Management Plan
2.46
Some witnesses raised concerns about the way contractors managed dieback
protocols, asbestos waste, dust produced onsite by clearance work, and the
handling of other potential contaminants.
Dieback protocols
2.47
The committee received evidence that the CEMP's dieback protocols had
not been followed by some contractors working on the site.[45]
Miss Corke, Wetlands Watchers, outlined some examples to the committee:
We have seen workers, utes, police cars and horses, a
cherry-picker, a water truck and a bulldozer drive between uninterpretable and
unaffected sections of the site without any form of hygiene or wash down
procedures, in contravention of dieback protocols in table 10 of the CEMP.[46]
2.48
Dr Bairstow, appearing in a private capacity, described what dieback is,
before outlining a number of potential violations of the project's dieback
protocols:
Dieback is a fungal infection of certain species of
vegetation and, once introduced to an area, it cannot be eradicated. There are
standard protocols to be followed, and they have not been followed in this
case. In particular, repeated movements of vehicles from uninterpretable
dieback areas to uninfested dieback areas of native vegetation have been
observed. On two separate days, I made reports directly to the [WA Office of
the Environmental Protection Authority] regarding the lapse in protocols. On
the second day, I rang back after several hours to find out what was happening.
I was told that the auditors had reported back and there was no clearing taking
place, to which I replied, 'I am watching a live stream of a video of clearing
taking place across the road right now.' I was told, 'We will send him back
in.'[47]
2.49
Dr Bairstow suggested current conditions were ideal for dieback
spreading, so a great deal more caution should be exercised by contractors:
This particular period has created a very, very favourable
situation where we are still in summer, we have warm soil, the fungus is
flourishing and we have summer rain. That could lead to a catastrophic transfer
of dieback. If we were ever, anywhere, going to be careful about something like
dieback protocol—and I am not saying that all the other bits of bush do not
deserve to be looked after too, but if we cannot do it here, where can we do
it?[48]
2.50
Dr Bairstow also noted that dieback in some areas of vegetation could
have serious repercussions for many species of local fauna:
The thing about the banksia woodlands and the wetlands
through that area is that they are incredibly complex, integrated systems. So,
when you start killing off a whole suite of plants, you are going to have a knock-on
effect on many other plant and animal species.[49]
Management of asbestos waste
2.51
Some witnesses and submitters were concerned that asbestos found in the
clearance process had been handled poorly.[50]
For example, Mr Bob Bryant, a retired technical specialist in occupational
health and safety and a safety coach who was appearing in a private capacity,
spoke of the flagrant disregard some contractors had for WorkSafe standards,
including regarding:
...[the disposal of] asbestos; it is the emissions of dust, the
control, the clean-up. For example, people have been observed picking up pieces
of asbestos, breaking pieces of asbestos, and carrying them and putting them in
the back of vehicles...[namely, the] contractors, supposedly the asbestos removal
specialists. In the early days none of those people were wearing proper
personal protective equipment. They subsequently have, in just very recent
times, started to wear proper gear, but there is even evidence of noncompliance
with that.[51]
2.52
Mr Bryant provided the committee with the results of laboratory testing
of asbestos he had found on 'a random walk through some of the areas' on the
construction site.[52]
This confirmed 42 samples of asbestos were found, including the most dangerous
type, blue asbestos.[53]
2.53
Ms Alison Wright, Coordinator, Coolbellup Concerned Residents, pointed
to the uncertainty that poor asbestos handling practices created for local
residents:
We have witnessed bulldozers tearing through the bush and
then uncovering dumped asbestos materials. We are left wondering whether there
was any missed asbestos left in the giant piles of mulch. We have requested and
requested support from government agencies and we are still left wondering. We
have voluntarily conducted asbestos surveys, tested these samples and found
that 85 per cent of the samples were asbestos. From our cursory survey
conducted by citizens, we have identified more than 100 pieces throughout the
Roe 8 site, and yet the clearing has continued.[54]
2.54
Ms Wright told the committee that the Western Australian government had
undertaken tests for asbestos on the site, after concerns had been raised repeatedly
by local residents over a long period:
I can tell you that we put a suspected contaminated site form
into the Department of Environment Regulation on 16 December. I received some
correspondence back from them just before early January saying, 'Thank you very
much, but we can't see any reason to continue looking into that'. Yet,
surprisingly, in early January I got another letter from the Department of
Environment Regulation that said, 'Actually, we are looking into this'. I made
a phone call to them and they have since examined the site and found that it is
not contaminated.
Meanwhile, that is 52 days that people in Coolbellup had this
sense of fear and anxiety about whether there is airborne asbestos.[55]
2.55
Ms Wright expressed some doubts whether sufficient testing of the site
had been undertaken, given the results of other surveys:
Despite the report back from the Department of Environment
Regulation, I am sorry but I do not have confidence that they have been able to
go through piles and piles of mulch that are really high and can tell me
unequivocally that there is no asbestos in there. We found 100 pieces of
asbestos throughout the entire site on a cursory survey.[56]
2.56
Ms Wright also highlighted the anguish that had been caused to local
residents, given the long uncertainty over asbestos contamination of the site:
It is quite extraordinary to see a group of people, who are
entirely sensible people, so commonly brought to tears. In these meetings that
I am convening, there are people who are often on the brink of tears because of
the level of anxiety. I think that is mainly due to the fear and worry about
what is going on across the road...[57]
Dust management
2.57
The committee heard that many local residents and communities had been
affected by the dust emanating from the clearance work undertaken by
contractors.[58]
Ms Corke, Wetlands Watchers, told the committee it was clear that good dust
management practices, as outlined by the CERP,[59]
were not being followed onsite, given surrounding homes and pools had been
covered with 'films of dust':
The first, most obvious signs of noncompliance were with dust
management. According to table 6 of the CEMP, water carts are to be operational
at all times in dry and windy conditions. Throughout the clearing, if a cart
has actually been on site, it has rarely been used and never effectively.[60]
2.58
Mr Logan Howlett, Mayor of the City of Cockburn, noted the city had
investigated around 50 complaints of ill-health from excessive dust pollution:
We have accounts of families, children and seniors being ill
because of the dust impacts. There was one statement by a ratepayer who had
been to their doctor saying that the result of their aggravation or their
asthma was from the dust emanating from the clearing.[61]
2.59
Mr Howlett went on to stated that the city had raised a formal complaint
with relevant state agencies:
On Tuesday, 17 January and Friday, 20 January 2017, in
response to complaints from residents, city officers witnessed dust from
mulching operations considered to be unreasonable, and under normal
circumstances the city would issue instructions to a contractor to cease
operating immediately. There was no evidence of any water trucks or any wetted
sand in the cleared areas. The officers experienced dust settling on them and
irritating their eyes. A request was sent to the Roe 8 project environmental
manager about intentions to improve dust control without delay. The city
contacted Main Roads WA, the OEPA and the DER about the unreasonable dust
emissions from the works at the Roe 8 extension and requested that they
investigate and take appropriate action without delay.[62]
2.60
Mr Howlett also commented that this had led to the city undertaking its
own sampling and analysis of dust samples from the vicinity of the Roe 8 works.
Asbestos fibres had not been detected and he suggested that the results of similar
analyses undertaken by contractors should be made public to reduce community
concerns:
The results from an independent laboratory indicated that no
asbestos fibres were detected in any of dust samples. While the city believes
that these results give the community confidence that asbestos associated with
the Roe 8 clearing works does not represent a public health risk, it is also
aware that the contractor carried out dust monitoring. The city has formally
requested a report, but the contractor is yet to provide the information. They
have advised that asbestos fibres have not been detected in the dust samples
collected. If that is so then the formal laboratory test results should be
released to the public.[63]
2.61
Ms Wright added that, as well as poor health outcomes for some locals,
there was still lingering uncertainty over whether the dust also contained
asbestos fibres:
But on top of [immediate impacts on health] there is the
great unknown: are there asbestos fibres in the dust? It is very clear that the
dust is there, because it is layering over people's houses. In fact, we were so
worried about the dust that we as a group of residents conducted asbestos
sampling off our own bat, because we just were not getting the evidence back.[64]
Other contaminants
2.62
The committee was made aware that contractors were potentially treating
other contaminants in a manner that was non-compliant with CEMP conditions. For
example, Ms Corke told the committee that she had witnessed a barrel of
'unidentified contents' ruptured by a bulldozer, with its contents subsequently
left to leak onto the ground. She argued that that clearing work had gone on
around the leakage, which was in breach of CEMP conditions, which stipulate
that all work should stop until any contaminant is contained, identified, and
cleared safely.[65]
Flaws with Management Plans for the project
2.63
The committee received evidence that argued the management plans for the
Roe 8 implementation were badly written and difficult to understand. As a
consequence, it was difficult for contractors to adhere to environmental and
construction conditions. For example, Ms Kelly, Save Beeliar Wetlands, stated
that:
In the beginning, the opinions of scientists and fauna
experts whom we worked with to understand the stated protocols versus industry
best practice, as laid out in the environmental management plans, told us that
their plans showed a lack of skill and expert advice in their construction. We
believed that it may have been speed and a lack of skills in the authorship of
those plans which were driving the noncompliance at that early stage.[66]
2.64
Professor Hobbs also suggested that the plans showed signs of being
completed in a rush. Additionally, he noted they have not been subjected to any
independent review. These factors, he said, would make implementation very
difficult for contractors:
The first problem was when the plan was completed, which was
a few days after initial work started on the project and a few days before the
initial clearing started. There was no opportunity for any outside review of
this plan at all. The plan was viewed by people from the Department of Parks
and Wildlife a year earlier, and presumably it was adjusted in relation to
those discussions...It is all to do with the speed of the process, really. It is
the rush of trying to get this happening that makes the implementation of the
plan very difficult.[67]
2.65
Ms Kelly also commented that the plans were only published a few weeks
before the clearing work began on 18 December 2016, which may not give
contractors sufficient time to engage with them.[68]
Responses of the state and Commonwealth to potential breaches
2.66
The committee took evidence from several witnesses that suggested the
Commonwealth and state governments had not been willing to acknowledge concerns
about potential breaches adequately. For example, Ms Corke suggested that she
had reported potential breaches to relevant authorities on a daily basis, and
had not received a reply from the Commonwealth, and a single cursory letter
from the EPA:
Every day we watch, and nearly every day I send an email to
both the EPA and to the federal Minister for the Environment and Energy, who
claimed on 15 February that neither he nor his department has received any
reports of breaches on site. These emails contain photos that outline the
breaches we have just observed and that try to prevent further breaches
occurring. There have been 20 emails so far and about 50 breaches reported. To
date, there has been one response from the EPA less than two pages long—one eight-paragraph
letter—responding to around 125 pages of emails.[69]
2.67
Ms Kelly, Save Beeliar Wetlands, shared her experience with the
committee:
On 20 December, the second day of clearing, we sent our first
letter to Mr Kim Taylor from the EPA and other agency heads calling for
Roe 8 to be halted whilst the issues with noncompliance were investigated. That
letter was 22 pages long...We have still not received a letter in reply from
the EPA, although later we did receive a letter from Minister Frydenberg which
names the EPA as the only agency responsible for compliance issues.[70]
2.68
Mr Howlett, Mayor of the City of Cockburn, noted the angst among the
community that was caused when government agencies did not engage with people
who had raised concerns about potential breaches:
Numerous emails copied to myself have clearly indicated to
the state government departments responsible that they need to step in and take
action. My understanding is that many of those emails have been not responded
to, which, again, is a sad indictment of what is happening around this project...
When there is silence from the other end, you start to
wonder...Those things are very powerful in terms of the perception in the
community about a project and that the government and the relevant departments
and/or the contractor seem to have little value for it in providing information
back.[71]
2.69
The department provided the committee with evidence on the complaints it
had received and stated that committee that it had received a 'large volume of
correspondence' relating to potential breaches of the Roe 8 works. Given
this, the department outlined several actions it had adopted to assess the
validity of these claims:
We had officers on site on 16 January and again on 7 February
this year. We have also spoken to Main Roads and asked them to provide
information. We have also spoken with the EPA and asked them to provide
information. We have also followed up on the qualifications where experts were
required to do things.[72]
2.70
In relation to compliance with Condition 4—the survey of trees during
the breeding season—the department stated that it had satisfied itself that the
condition had been complied with. It was also noted that those undertaking the
tree survey had extensive experience in survey work. Ms Collins concluded 'what
we found was that any potential nesting trees, even though they had been ruled
out as suitable, were retained on the site'.[73]
2.71
The department stated they had found no breaches of the conditions for
the project's approval, apart from one area:
There is one area where there was a minor noncompliance in
relation to reports being provided to the department later than the expected
time, and the department did issue a warning letter to Main Roads in relation
to that late supply of report. Other than that, we have looked into the
allegations that have been made and we have not found evidence to demonstrate
that matters protected under the EPBC Act or under this approval have been
breached.[74]
2.72
On this matter, Mr Matt Cahill added that some issues were still being
investigated by the department:
We do still have allegations that have been put forward, and
so while we have made some conclusions with regard to the material to date, we
still have other material in front of us that we are still considering.[75]
2.73
At the Environment and Communications Legislation Committee estimates
hearing on 27 February 2017, the department indicated that the investigation
report, which addresses all of the relevant conditions, was being finalised.[76]
Timing of commencement of construction
2.74
A number of witnesses questioned the timing of the commencement of
construction. With the state election scheduled for 11 March 2017, witnesses
argued that construction should have been delayed until after that date.[77]
The commencement of construction was seen as a rushed move to ensure that as
much land as possible was cleared so that 'it cannot be undone'.[78]
2.75
Ms Kelly, Save Beeliar Wetlands, also commented:
Given the proximity to the state election where a change of
government will shelve this project, many in the community strongly question
the need for bulldozing such an important spiritual, ecological and community
place of great beauty with such an unnecessary amount of haste and proper
oversight.[79]
Committee view
2.76
This inquiry has heard incontrovertible evidence that the Roe 8 works
have breached the Environment Management Plans repeatedly and in serious ways. These
breaches have profound consequences, not only for the health of the natural
environment of the Beeliar Wetlands and its flora and fauna, but also for the
health of the communities that live near the Roe 8 works.
2.77
The RRAT committee inquiry last year showed that the Perth Freight Link
was poorly conceived and badly designed. It compellingly made the case that the
project would blow a once-in-a-generation opportunity to get infrastructure in
Western Australia right, squandering around $1.2 billion of Commonwealth funds
at a time when the national budget is under increasing pressure. It also
indicated the project would have disastrous environmental implications, and
that it was characterised by poor consultation by the Commonwealth and state
governments, and an unwillingness to communicate with communities that would be
affected the most.
2.78
It is clear the implementation of Roe 8 has confirmed these findings. In
particular, the committee considers that the Roe 8 works have followed a
disastrous trajectory, and have been rushed and shoddily implemented by the
Barnett administration before the shutdown period preceding the state election
on 11 March 2017.
A disastrous environmental legacy
2.79
The work on Roe 8 has had disastrous environmental effects, not only
from its destruction of part of the Beeliar Wetlands, one of Western
Australia's most significant natural assets, but also from potential breaches
of its CEMP by contractors.
2.80
The committee was concerned that the conditions to manage native fauna
on the site seem to have been breached many times by contractors. Trapping
plans for bandicoots and other species appear to have been badly designed and implemented,
which has resulted in the needless trauma of animals being removed for
relocation, and the deaths of many others.
2.81
It also appears that surveys of birdlife habitats in the Roe 8 area have
been undertaken in a cursory way. This could put several species at further
risk, particularly the endangered Carnaby's and red-tailed black cockatoos. The
committee will look forward to receiving further information on these surveys
from the department, especially regarding their compliance with section 4 of
the environmental approvals for the project.
2.82
Additionally, the Roe 8 works have already cleared a great deal of the
unique and protected Banksia woodland of the Beeliar Wetlands; this woodland is
also threatened by contractors not following dieback protocols. The committee
notes that this woodland was listed as endangered on 16 September 2016, but can
be cleared, as its listing occurred after the referral of the project.
2.83
The committee believes that the Environment Management Plans show signs
of having been produced quickly, with insufficient independent oversight or
monitoring of their contents before their release by Main Roads WA. As a
consequence, contractors have had insufficient time to engage with, understand,
and to work to meet the environmental standards they are legally bound to
adhere to under the Plans.
2.84
The hurried implementation of Roe 8, the lack of appropriate oversight
of contractors by the Commonwealth and state governments, as well as the poor
drafting of the Environment Management Plans, has meant that an invaluable part
of the natural heritage of Western Australia—and, indeed, our nation—has been
destroyed for the initial stages of a project that is fundamentally flawed and
should be scrapped.
Poor health outcomes for local
communities
2.85
The hurried implementation of the Roe 8 works has also meant that many
communities who live near the Roe 8 works have had real and potential health
impacts caused by non-compliance with dust and asbestos management plans.
2.86
It is evident that the site contains a great deal of hazardous asbestos,
and that local communities have been able to collect and identify dangerous
material from mulch produced in the clearance process.
2.87
Moreover, the committee is concerned about poor health outcomes that can
be caused by poor dust management practices, even if the tests that have been
done on dust from the site have not contained asbestos fibre. It seems that a
number of locals have had health complications caused by the dust, including
those with asthmatic or sensitive respiratory conditions. Dust also impacted a
school with 250 children, just 100 metres from the construction site.
2.88
It is apparent that communities have commissioned their own asbestos
testing, given that contractors and the state governments have shown unwilling
to release the results of their own analyses. The committee considers that the
results of tests undertaken by government agencies and contractors should be
made public, so as to reassure local communities.
Conclusion
2.89
The evidence the committee received overwhelmingly showed that, since
the Roe 8 works commenced only a few months ago, there have been a number of
potential breaches of the legally binding conditions contained in the project's
Management Plans approved by the state government. Moreover, the committee has
heard serious allegations about violations of conditions attached to the
environmental approvals granted by the Commonwealth for the Roe 8 project, in
particular Condition 4 related the survey of black cockatoo nesting trees.
2.90
The committee notes that the Western Australian government's project
approval assessment was carried out under the bilateral assessment
arrangements. The department stated that the Western Australian government has
been 'accredited to meet our environmental requirements under the EPBC Act'.
While the Western Australian government has made a number of recommendations
related to state matters these are also subject to Commonwealth scrutiny. The
department commented:
What we do then is look at those recommendations. We
reference and assess those against our requirements in making an approval or
not. What we will do is try to reduce duplication. Where there are management
plans that are covered already by the state, we will try to reflect that in our
approval.[80]
2.91
The committee acknowledges that the Commonwealth's regulatory role is
confined to the extent to which the management plans relate to matters of
national environmental significance. However, the Carnaby's black cockatoo is
listed by the Commonwealth as a threatened species while the Red-tailed black
cockatoo is listed as vulnerable. The committee considers that the failure to
undertake adequate surveys of nesting tree raise significant concerns about
whether condition 4 has been satisfied.
2.92
The committee therefore considers that the Commonwealth should act to
suspend approval for the project. The Commonwealth Minister for the Environment
has the power, under subsection 144(2A) of the EPBC Act, to undertake this
action and should do so immediately.[81]
Recommendation 1
2.93
The committee recommends that, pursuant to subsection 144(2A) of the Environment
Protection And Biodiversity Conservation Act 1999, the Minister for the
Environment suspends the Roe 8 construction works until he has ascertained that
all the conditions of the approval issued for the Roe 8 works have been met by
the Western Australian government and by relevant contractors.
Recommendation 2
2.94
The committee recommends that—whatever the outcome of the Western
Australian state election taking place on 11 March 2017—the Commonwealth works
with the state government and other stakeholders to develop productive and
economically viable infrastructure projects in Western Australia that
incorporate rigorous environmental assessments and conditions.
Recommendation 3
2.95
The committee recommends that the Commonwealth government act urgently
to amend the EPBC Act to provide for emergency listings of threatened species
and ecological communities, and to consider addressing the effect of section
158A of the EPBC Act which currently prevents consideration of threatened species
or ecological communities which are listed after the time a referral is made.
Recommendation 4
2.96
The committee recommends that the Australian National Audit Office
(ANAO) conduct an audit of the Perth Freight Link project including in relation
to:
-
whether appropriate steps were taken to protect the Commonwealth's
interests and obtain value for money in respect to the $1.2 billion in
Commonwealth funding committed to the Western Australian government for the
Perth Freight Link project;
-
the effectiveness of federal environmental protection laws, in
particular the extent to which the Department of the Environment and Energy:
-
complied with its own policies (specifically including Offsets
policy and protection of species with Recovery Plans),
-
adequately assessed impacts on matters of national significance
during the assessment process,
-
adequately investigated and enforced compliance with approval
conditions,
-
adequately responded to evidence significant and systematic breaches
with management plans were being ignored by the state government;
-
the adequacy of penalties to the approval holder for
non-compliance under federal environmental protection laws; and
-
political interference with the environmental assessment and
compliance process.
Senator Peter Whish-Wilson
Chair
Navigation: Previous Page | Contents | Next Page