Introduction
1.1
On 16
February 2017, the Senate agreed to the following motion referring the matters
related to the Perth Freight Link to the Environment and Communications
References Committee (the committee) for inquiry and report by 6 March 2017:
- the Senate notes the failure to
comply with the Senate orders for the production of documents agreed to on 13
and 14 February 2017, relating to the Perth Freight Link;
- in order to investigate the
subject of the Senate orders, the following matter be referred to the
Environment and Communications References Committee for hearing on or before 24
February 2017, and reporting on or before 6 March 2017—The continuation of
construction of the Perth Freight Link in the face of significant environmental
breaches;
- it be an instruction to the
committee that it hold at least one hearing in Perth; and
- the following witnesses be
invited and answer questions:
-
Department of
the Environment and Energy compliance and environmental standards officers,
- the Minister
for the Environment and Energy , Mr Josh Frydenberg,
- Federal Legal
Counsel to the Minister and the Department,
- the Western
Australian Minister for Environment, Mr Albert Jacob, the Office of the
Environmental Protection Authority, in particular, senior compliance
managers Mr Ian Munro and Mr Paul Zahara,
-
the
proponent, Main Roads Western Australia,
- Leightons
contractors,
- subcontractors
completing the surveying work, fencing and trapping,
- witnesses who
have directly documented breaches with federal approval conditions, and
reported these to the minister, and
- other
witnesses as determined by the Environment and Communications References
Committee.[1]
Background
1.2
The Perth Freight Link is a $1.9 billion project intended to improve
freight infrastructure and traffic congestion in Perth, by providing a direct
high-standard freight connection between the Roe Highway and Fremantle Port.[2]
Its implementation has been designed in three stages:
-
Section One—Roe Highway Extension (Roe 8): A 5.2 kilometre four
lane dual carriageway from the Kwinana Freeway to Stock Road and an interchange
connecting to Stock Road.
-
Section Two—Winterfold Tunnel: a surface route along Stock Road
between Roe 8 and Winterfold Road, then a 3.3 kilometre tunnel
proceeding North-West to the Stirling Highway/High Street junction.
-
Section Three—Roe Highway pinch point widening: Widening of a
1 kilometre section of the existing Roe Highway between the Tonkin Highway
and Welshpool Road, to alleviate a pinch point on the heavy vehicle charging
network.[3]
1.3
This inquiry is predominantly concerned with Section One Roe 8, see
Figure 1.1 below for the route.
Figure 1.1: Route for the Roe 8 extension

Proposed benefits of the Freight
Link
1.4
The Department of Infrastructure and Regional Development provided an
overview of the proposed benefits of the project on its website:
The Perth Freight Link project will deliver significant
travel time savings for freight and passenger vehicles across the Perth
network. It will also improve road safety, reduce transport costs and improve
the efficiency of heavy vehicle movements between Perth’s industrial areas and
the Port of Fremantle. The project is also expected to reduce freight traffic
and congestion on local arterial roads, resulting in improved safety, reduced noise
and enhanced amenity. The project will also provide a more effective southern
connection to the Murdoch Activity Centre, which, when fully developed has the
potential to account for 35,000 jobs.
Further, the project will deliver environmental benefits through
non-stop traffic movements, resulting in lower fuel use, less exhaust emissions
and reduced noise levels.[4]
1.5
The Department of Infrastructure and Regional Development also provided
a summary of how the Freight Link will complement other infrastructure projects
in Western Australia:
The project will
complement the Australian Government’s investment in the Gateway WA and
NorthLink WA projects. Together, these substantial network improvements
will establish the Roe Highway as the preferred East-West route into the Port
of Fremantle. The current Inner Harbour is operating well below capacity and as
the Port grows to reach its anticipated capacity of 1.2 million containers
per year over the next decade, this growth will significantly increase current
freight volumes. The Perth Freight Link project will address these challenges
and in the long term the Roe Highway Extension will service not only the Inner
Harbour but also the Outer Harbour.[5]
Funding for the Freight Link
1.6
The Perth Freight Link was first announced by the Commonwealth
Government on 19 May 2014, as part of the Infrastructure Growth Package
contained in the 2014–15 Commonwealth Budget.[6]
1.7
This committed the Commonwealth Government to providing $925 million in
funding, with a further $650 million contributed by the Western Australian
Government.[7]
A further $260.8 million was committed by the Commonwealth on
12 April 2016 for tunnelling some of Section Two of the Perth Freight
Link.[8]
This means the Commonwealth's contribution to the project is currently almost
$1.2 billion of the total funding of around $1.9 billion.
1.8
The committee understands that recently released documents obtained
under Commonwealth freedom of information (FOI) legislation indicate that the
cost of the project could be much higher than forecast.[9]
The Freight Link Business Case and
its assessment by Infrastructure Australia
1.9
To support the project, the Commonwealth and state governments developed
a Business Case for the Freight Link, outlining its development, funding,
implementation and proposed benefits. Although the full Business Case remains
confidential, a 30-page executive summary of the Business Case was released in
December 2014, omitting 'commercially sensitive material'.[10]
1.10
The Executive Summary estimated total costs for all stages of the
Freight Link would be $1.575 billion (discounted to represent
2014 dollars), based on a P50 cost estimate (i.e., assuming a 50 per cent
probability that the cost estimate would not be exceeded).[11]
1.11
The Business Case noted that the project was 'economically viable' and projected
it would deliver a benefit-cost ratio (BCR) of 2.8:1, with the major benefit
stemming from 'a 9 ½ minute travel time saving and a $8.15 saving per trip for
freight vehicles (Kwinana Freeway to Fremantle)'.[12]
1.12
The full Business Case was used by the board of Infrastructure Australia
to assess the Freight Link proposal in May 2015.[13]
Although Infrastructure Australia recommended that the project was viable, it
expressed some serious reservations about its estimated budget and BCR return. Most
significantly, Infrastructure Australia estimated total capital for the project
at $1.742 billion (nominal, undiscounted and using a P90 estimate)—almost
$200 million more than the total capital forecast by the Business Case.[14]
1.13
Given this, Infrastructure
Australia estimated the Freight Link would deliver a BCR return of 2.5:1,
smaller than the Business Case's BCR of 2.8:1.[15]
1.14
Infrastructure Australia also clearly stated some other assumptions that
informed the Business Case estimates were founded on unrealistic expectations:
The costs estimated for this stated BCR exclude costs
associated with the heavy vehicle tolling system thereby underestimating
capital costs but included a CPI adjustment for the real capital cost estimates
thereby overestimating capital costs. Including these offsetting cost impacts,
consistent with Infrastructure Australia and National Transport Guidelines,
this would result in the BCR remaining at 2.5:1.[16]
1.15
Recently, FOI documents obtained by Ms Allanah McTiernan MP indicate
that costs could be much higher, even than the capital costs estimated by
Infrastructure Australia. Mrs Kim Dravnieks, Coordinator, Rethink the Link, gave
the committee a summary of what these documents reveal about the Freight Link
project:
Only now, just days before a state election, have we finally
received documents to examine that were fought for through the Freedom of
Information Commissioner and the arbitration tribunal. These documents show the
extreme haste with which this project was put together and the disregard for
due process.[17]
Criticisms of the Freight Link
1.16
Since its announcement in the 2014–15 Budget, the Freight Link Proposal
has accrued a great deal of criticism from many sectors, including local
government and communities that will be affected by the project, as well as
from the private business and transport industry that the Freight Link was
designed to assist.
1.17
These concerns were summed up by the Senate inquiry undertaken by the Rural and Regional Affairs
and Transport References Committee (RRAT committee) in the previous parliament.
The inquiry tabled a report on 3 May 2016, which considered the many
criticisms that have been levelled at the project.[18]
1.18
The RRAT committee's report was highly critical of the development and
implementation of the Freight Link. It recommended that the Commonwealth's
commitment to the Freight Link project should be frozen, as:
This
amount of funding [for the Freight Link] is a once-in-a-generation opportunity
to invest in the infrastructure needs and long-term economic prosperity of
Western Australia.
However,
if the Perth Freight Link proceeds, it will blow this opportunity on a project
that will not achieve what it proposes to do, and is not wanted—not only by the
communities that it would run through but also by the business and transport
sectors it purports to assist.[19]
1.19
The RRAT committee considered that the Freight Link was 'poorly and
hurriedly conceived by the Commonwealth' with 'no consultation with the
government of Western Australia'.[20]
Moreover, it found that Infrastructure Australia's approval of the project was
'lukewarm at best', and noted the potential for the estimated cost of the
project in the Business Case to blow out massively in the project's
implementation.[21]
1.20
In this, it suggested that the Business Case was 'fundamentally flawed',
and that there was insufficient consultation and transparency in the project's
development—including a failure to consider potential options for infrastructure
to support Western Australia's freight capacity and transport network.[22]
1.21
The report noted that the implementation of the Freight Link had already
been subject to uncertainty and delay, due to court challenges to the Roe 8
stage on environmental and indigenous heritage grounds.[23]
1.22
It was also clear to the RRAT committee that the development of the
project had lacked a sufficient consultation process with the local
governments, industry stakeholders and the communities who would be affected
the most by its construction. In particular, the committee noted the strong
community opposition to the project who had not been consulted sufficiently on
several issues, including:
-
the damage the Roe 8 extension would do to the natural
environment of the Beeliar Wetlands;
-
the uncertainty faced by families who lived along the Freight
Link's proposed route, particularly those whose houses were being forcibly
acquired by the state government; and
-
negative effects due to increased traffic flows, air pollution,
and potentially more dangerous roads in some areas.[24]
Environmental approval
1.23
The Environmental Protection and Biodiversity Conservation Act 1999 (Cth)
(EPBC Act) requires a person taking an 'action' that is likely to have a
significant impact on a matter of national environmental significance to obtain
approval from the Minister for the Environment and Energy.
1.24
The Roe 8 stage of the Perth Freight Link passes through the Beeliar Regional Park between the
North Lake and Bibra Lake. These areas are considered high value
environmental with potential impacts on listed threatened species and
communities, and listed migratory species. It also encompasses Aboriginal
heritage areas.[25]
As a consequence, the proponent (Main Roads Western Australia) referred the
proposed action for approval on 22 June 2009.[26]
1.25
Public comments on the referral were invited by the Department of the
Environment and Energy (the department) with submitters providing comments on
concerns about the impact on migratory birds and Carnaby's Black Cockatoo
populations that are known to occur in that area, social impact on the
community, Aboriginal and National Heritage and the Beeliar Wetland system.
1.26
It was decided that the proposed action was a controlled action and
environmental assessment would be undertaken in accordance with the EPBC Act.
Assessment was conducted under the bilateral agreement between the Commonwealth
and Western Australia by the Western Australia Environmental Protection Authority
(EPA).
Western Australia EPA approval
process
1.27
In September 2013, following a Public Environmental Review, the EPA
advised the department that it had published its Assessment Report which
recommended that the proposed action be approved with conditions. On 2 July
2015, at the conclusion of the state appeals process, the Western Australian
Minister for the Environment, the Hon Dean Nalder MLA approved the project.[27]
1.28
The approval conditions included the development of plans and surveys.[28]
These include details of conditions contractors must meet regarding the
treatment of the flora and fauna or the Beeliar Wetlands, and stipulations on
the monitoring of the ecological health of wetlands through the construction
process.
1.29
They also include plans designed to mitigate the effects of construction
on the site, including provisions to: prevent the introduction of weeds;
minimise the impact of dust created by the works; prevent the introduction of
any disease and pathogens—including dieback; and provide directions for the
management of any potential contaminants, including acid sulphate soils and
asbestos.
1.30
In announcing environmental approvals for Roe 8, the Western Australian
Minister for the Environment highlighted a number of initiatives to mitigate
the impacts of construction:
-
provision of fauna underpasses to maintain fauna connectivity and
develop plans to manage and monitor fauna and flora, wetland health and water
drainage;
-
purchase of 10 packages of land identified by the Department of
Parks and Wildlife to satisfy all or part of the 523 hectares of native
vegetation offset requirements for the project;
-
provision of nesting hollows for birds and the trapping and
tagging of more than 100 southern brown bandicoots living in the area and
relocating them to the offset areas;
-
building the road on land partly cleared for overhead power lines
in order to minimise the environmental footprint;
-
undertaking a wetland restoration program at North Lake and Horse
Paddock Swamp;
-
building two bridges through the wetlands—a 120 metre long bridge
over Roe Swamp and a 70 metre bridge over Horse Paddock Swamp;
-
employing a top-down construction approach at Roe Swamp Bridge to
minimise clearing footprint and compaction during construction; and
-
ensuring wetlands bridges are used in required locations to
maintain ecological connections for local fauna.[29]
1.31
The plans, and potential contraventions of their conditions, are
discussed further in the following chapter of this report.
Commonwealth approval process
1.32
The Commonwealth approval process was completed on 21 October 2015 with
approval being given, under section 133 of the EPBC Act, to construct the
highway. The approval of the proposed action was made with 16 conditions. The
conditions included:
-
adherence to clearance limits outlined in the WA approval
conditions in order to minimise impacts to threatened species and communities
and migratory species;
-
to avoid and mitigate impacts to black cockatoos, during the
breeding season (August–December), within 7 days prior to clearing, the approval
holder must ensure all potential nesting trees are investigated to detect the
presence of black cockatoos using hollows with the investigation being
undertaken by a suitably qualified and experienced person. Should any black
cockatoos be detected using a hollow in a tree or trees, the approval holder must:
-
clearly identify all such trees with fencing and signage that
must be located within two (2) metres of the base of each such tree;
-
not clear any such tree or any vegetation within 10 metres of any
such tree; and
-
undertake all reasonable measures to avoid any such tree from
being cut down, felled, removed, killed, destroyed, poisoned, ring-barked,
uprooted or burned until a suitably qualified and experienced person has
verified in writing that the hollow(s) in each such tree are no longer being
used by black cockatoos.
-
in order to minimise impacts to threatened species and
communities, and migratory species, the approval holder must develop and
implement all Plans or Surveys, in accordance with the requirements of the WA
approval conditions;
-
to offset the loss of black cockatoo habitat, prior to
commencement, the approval holder must provide the department with written
evidence that funds have been provided to the Department of Parks and Wildlife
for the acquisition of an environmental offset property;
-
within three months of every 12 month anniversary of the
commencement of the action, the approval holder must publish a report on their
website addressing compliance with each of the conditions of this approval,
including implementation of any Plans or Surveys as specified in the
conditions. Documentary evidence providing proof of the date of publication and
non-compliance with any of the conditions of this approval must be provided to
the Department at the same time as the compliance report is published;
-
upon the direction of the Minister, the approval holder must
ensure that an independent audit of compliance with the conditions of approval
is conducted and a report submitted to the Minister. The independent auditor
must be approved by the Minister prior to the commencement of the audit. Audit
criteria must be agreed to by the Minister and the audit report must address
the criteria to the satisfaction of the Minister.
-
the approval holder must maintain accurate records substantiating
all activities associated with or relevant to the conditions of approval,
including measures taken to implement the Plans or Surveys required by this
approval, and make them available upon request to the Department. Such records
may be subject to audit by the Department or an independent auditor in
accordance with section 458 of the EPBC Act, or used to verify compliance with the
conditions of approval. Summaries of audits will be posted on the Department's website.
The results of audits may also be publicised through the general media; and
-
unless otherwise agreed to in writing by the Minister, the
approval holder must publish all Plans or Surveys referred to in these
conditions of approval on their website. Each management plan must be published
on the website within 1 month of being approved.[30]
Legal challenges to Roe 8 on environmental grounds
Environmental challenges to Roe 8
1.33
A challenge to the EPA's approval of the highway extension was lodged in
the Western Australian Supreme Court by the Save Beeliar Wetland Group. Supreme
Court Chief Justice Wayne Martin found that the EPA's assessment and subsequent
recommendation to the WA government was invalid. Professor John Bailey
commented that:
...the EPA was found to have taken no account of its own
published policies at the time, and specifically the policy that said that for
significant residual impacts to critical environmental assets, such as those
impacted by Roe 8, environmental offsets would not be an appropriate means of
rendering the proposal environmentally acceptable.[31]
1.34
However, the Western Australian Government won an appeal with a
unanimous decision from the Court of Appeal which found that the EPA was not
obliged to take its own policies into account. The court found that policies
were a permissive relevant consideration, not a mandatory relevant
consideration.
1.35
On 16 December 2016, the High Court found that that there was
'insufficient grounds' for Save Beeliar Wetlands to appeal the Court of Appeals
decision.[32]
1.36
Prior to the finding of the High Court on 16 December, the Western
Australian government erected temporary fencing on the site on 4 December
2016, in preparation for clearing work to begin.[33]
Indigenous heritage challenges to
Roe 8
1.37
A challenge to Roe 8 was lodged in the Supreme Court of Western Australia,
arguing that the Beeliar Wetlands was a site of Indigenous spiritual
significance.[34]
This case was dismissed on 24 August 2016.[35]
Order for the
production of documents
1.38
On 13 and 14 February 2017, the Senate agreed to orders for
the production of documents related to the Perth Freight Link. The first order
of 13 February 2017 related to the production of the business case and cost
benefit analysis for the Perth Freight Link:
That the Senate—
-
notes:
-
the Abbott-Turnbull election
commitment that infrastructure projects attracting more than $100 million of
federal funding would require a full cost benefit analysis,
-
that the Abbott-Turnbull
Government has committed funding now worth $1.2 billion to the Perth Freight
Link for which no business case has ever been provided, for which Stages 2 and
3 have not even been planned or assessed, and which does not reach the Port,
-
that it is important that Federal
money granted to a state be spent in a manner that represents value for money
and that the Senate has an oversight obligation in this regard, and
-
public interest immunity in
response to Senate orders for the production of documents must not just be
asserted, rather established;
- rejects the
grounds for public interest immunity made in relation to six previous Senate
orders for production of documents, concerning the release of the business
case, and specifically those made by the Minister for Finance on 19 April and 1
September 2016;
- orders that
the full business case and cost benefit analysis for the Perth Freight Link be
laid on the table by the Minister for Finance by no later than 12.30 pm on 14
February 2017; and
- resolves
that, if the documents specified in paragraph (c) are not laid on the table by
12:30 pm on 14 February 2017, the Minister for Finance be required to attend
the Senate at that time and provide an explanation for his failure to table the
documents, and that at the conclusion of the explanation any senator may move
to take note of the explanation.[36]
1.39
Later that day, the Senate agreed to a further order for production of
documents related to investigation of nesting trees:
That the Senate—
- notes Condition 4 of the federal
approval decision for the Roe Highway Extension, which specifies that all
potential nesting trees are to be investigated to detect the presence of black
cockatoos using hollows within 7 days prior to clearing, and that the
investigation must be undertaken by a suitably qualified and experienced
person; and
-
orders that there be laid on the
table by the Minister representing the Minister for the Environment and Energy,
by 5 pm on 13 February 2017, the following information:
-
the date the investigation of
nesting trees was completed,
-
how the investigation was
undertaken,
-
the qualifications of the person/s
who undertook the investigation, and
-
a copy of the investigation,
including all results.[37]
1.40
In response to the first order of 13 February 2017, the Minister for
Finance, Senator the Hon Mathias Cormann, noted that the Senate had on five
previous occasions passed orders for the production of documents related to the
Perth Freight Link business case and the cost-benefit analysis. The Minister
stated:
In response to those orders the government has provided all
the information and all the documents that it could provide without harm to the
public interest. The information and documents not provided in response to all
these Senate orders in relation to the Perth Freight Link documents were either
cabinet-in-confidence documents for the WA state government or contained
information that is commercial and sensitive in nature. If they were released
in a full and unredacted form they would prejudice commercial negotiations
and/or would potentially damage the relations between the Commonwealth and a
state government, namely the Western Australian state government, namely the
Western Australian state government.[38]
1.41
The Assistant Minister to the Prime Minister, Senator the Hon
James McGrath, also tabled documents previously tabled concerning related
orders for the production of documents.[39]
1.42
In response to the second order for the production of documents, the
Special Minister of State, Senator the Hon Scott Ryan, tabled a letter to the
President of the Senate from the Minister for Education and Training, dated 13
February 2017, responding to the order for the production of documents.[40]
The letter stated that:
The Department of the Environment and Energy has been
informed by the Office of the Environmental Protection Authority of Western
Australia that:
-
The Office of the Environmental Protection Authority has had
auditors on site for each day of the works.
-
All potential nesting trees in the area to be cleared were
investigated on 14 December 2016, prior to the commencement of clearing work on
19 December 2016.
-
The Office of the Environmental Protection Authority is collating
detailed information regarding the potential nesting habitat, including the
dates on which investigations occurred, the person who undertook these
investigations and the outcomes of their investigations. This task is expected
to be completed by Friday, 17 February 2017.
The Department of the Environment and Energy has also been
informed by the Main Roads Western Australia that although no Cockatoo nests
were observed to be present in any of the trees to be cleared, as a
precautionary measure, trees that were identified with hollows were retained in
situ for the remainder of the breeding season.
The Department of the Environment and Energy has requested
the abovementioned information from the Office of the Environmental Protection
Authority and will respond further to the Senate's Order on the next sitting
day of the Senate after the information is received.
1.43
On 14 February 2017, the Senate agreed to the following order for the
production of documents:
That the Senate—
- notes, in
relation to the Perth Freight Link 'Roe 8' Highway extension, that significant
breaches have been documented and reported to the Minister in relation to
approval conditions and management plans, relating to dust suppression,
asbestos management, and trapping and relocation of endangered species; [and]
- orders
that there be laid on the table by the Minister representing the Minister for
the Environment and Energy, by no later than 12.45 pm on 15 February 2017,
the following documents:
- a summary of correspondence or
reports made to the Minister for the Environment and Energy or the Department
of the Environment and Energy with evidence of compliance breaches with
approval conditions since construction commenced, and the response to each, and
- a record of the dates, times
and locations where state or federal compliance officers have been on site
since construction began.[41]
1.44
On 15 February 2017, the Minister for Finance, Senator the Hon
Mathias Cormann, tabled a letter to the President of the Senate from the
Minister for Education and Training responding to the order of the Senate of 14
February 2017.[42]
The Minister's letter provided the following information:
The Department of Environment and Energy has advised that
neither the Minister nor the Department has received correspondence or reports with
evidence of compliance breaches with approval conditions.
The Department of Environment and Energy has also confirmed
that state or federal compliance auditors have been on site on each day of
works since construction began.[43]
Conduct of this inquiry
1.45
The committee
received five submissions. These submissions are listed at appendix 1 of this
report, and can be accessed through the committee's website.[44]
1.46
The committee
held a public hearing in Perth on 23 February 2017. A list of witnesses who
gave evidence at this hearing can be found at Appendix 2 of this report, and a
Hansard transcript of evidence is available on the committee website.
Participation
of the Western Australian government and contractors
1.47
The terms of reference for this inquiry stipulated that the committee
invite the Western Australian government Minister for the Environment, some
senior officers from the state's EPA and the agency Main Roads Western
Australia.[45]
1.48
Moreover, the terms of reference also stated that certain contractors
undertaking work on the Roe 8 extension would be called to give evidence at the
public hearing, namely Leightons, and any subcontractors responsible for
surveying, fencing and trapping work.
1.49
The committee notes that both the Western Australian government and
relevant contractors declined the committee's invitation to attend the hearing
and give evidence.
1.50
The committee understands that the Western Australian government entered
a caretaker period in early February 2017 for the state general election on
11 March 2017. However, the committee also notes that the Western
Australian government has consistently displayed an unwillingness to be
transparent about the Freight Link, including repeatedly refusing to
participate in the RRAT committee inquiry into the project in the 44th
Parliament.
1.51
Given this, the committee would like to express its disappointment that
the Western Australian government and relevant contractors have not assisted
the work of this inquiry.
Structure of this report
1.52
This report consists of two chapters:
-
this chapter sets out the administrative details of the inquiry,
and gives a brief background of the Perth Freight Link project; and
-
the second chapter outlines the issues raised by submissions and
witnesses, as well as the committee's views and recommendations.
Acknowledgements
1.53
The committee thanks all individuals and organisations that participated
in the inquiry by making submissions and giving evidence at the public hearing.
Navigation: Previous Page | Contents | Next Page