Chapter 5 - The rights of traditional owners
Government is shutting out Bininj law, they won’t recognise our
law.[1]
5.1
This chapter analyses the process of
consultation with Traditional Aboriginal Landowners that has taken place in
regard to the Jabiluka project. It focuses on the negotiations leading up to
the 1982 Jabiluka Agreement negotiated between Pancontinental and the Northern
Land Council, and also discusses events surrounding the Deed of Transfer in
1991, the negotiations between ERA and the Northern Land Council in 1997 over
the ‘change in scope’ of the project, and recently renewed pressures from ERA
for Traditional Owners to agree to the milling of Jabiluka ore at the Ranger
mine. The chapter concludes that there is persuasive evidence to suggest that
the 1982 Agreement was negotiated unconscionably and that the Northern Land
Council failed to fulfil its obligations under the Commonwealth Land Rights Act
to properly consult with and act on the instructions of Traditional Owners. The
Committee concludes that there is a strong prima facie case for a revision of
the Jabiluka Agreement, and it is deeply concerned at indications that ERA may
resort to the unwelcome practices of the past to obtain consent for the Ranger
Mill Alternative.
Introduction
5.2
Aboriginal rights, and specifically rights
accruing to Traditional Owners, exist in relation to the Jabiluka project in
two main areas.
- The right to be consulted about, negotiate the terms of or veto
development which takes place on or affects their lands; these rights are
provided for in the Aboriginal Land Rights (Northern Territory) Act 1976
and subsequent amendments; and
-
Measures for the protection of Aboriginal sacred sites and
cultural heritage. These are provided for in the Commonwealth’s Environment
Protection (Impact of Proposals) Act 1974, Australian Heritage
Commission Act 1975, Aboriginal and Torres Strait Islander Heritage
Protection Act 1984, and the NT Northern Territory Aboriginal Sacred
Sites Act 1989.
5.3
These rights are described thus in the context
of their artificial separation by Western legal and administrative process. In
Aboriginal eyes they are part of a seamless living culture, and much confusion
and anguish has arisen from this demarcation. In relation to Jabiluka, the
Traditional Owners feel that they have been marginalised and their rights
unfairly alienated in the negotiation and approval of the mine agreement. This,
and distrust about the intentions of white authorities, has meant that they
have been reluctant to cooperate in more limited provisions for the protection
of cultural heritage.
5.4
Issues relating to cultural and living heritage
are dealt with in Chapter 4, largely because nominal provision is made for the
protection of this heritage through the EIA process. However, it is clear to
the Committee that the protection of this heritage in the Jabiluka EIA process
has already failed. This chapter concentrates on the question of rights in
relation to mining and country.
The Legislative Framework:
The Aboriginal Land Rights (Northern Territory) Act 1976
5.5
Aboriginal rights in relation to the Jabiluka
development are conferred by the provisions of the Aboriginal Land Rights
(Northern Territory) Act 1976 (the Land Rights Act). This Act purports to
give effect to a general objective that any development on Aboriginal lands
only occurs with the explicit consent of the traditional owners.
5.6
The Act provides for ministerial consent to
mining only after agreement between the miner and a representative of
Traditional Owners has been reached. Separate agreements must be reached for
the exploration stage and for the full development stage of mines. In the case
of Jabiluka, legal status was conferred by the Act on Pancontinental and on the
Northern Land Council as the proper negotiating parties. In turn, the Land
Council is required to undertake consultations with Traditional Owners affected
by the development and to demonstrate that it has acted on their instructions.
5.7
Section 48A of the Act states that an agreement
will only have legal force if the Minister for Aboriginal Affairs is satisfied
that the Northern Land Council (NLC) has negotiated according to the wishes of
the Traditional Owners, and that ‘the traditional Aboriginal owners of the land
understand the nature and purpose of the agreement and, as a group, consent to
it’. Section 23(3) of the Act also prevents Land Councils from undertaking any
action in consent to a development unless it is satisfied that:
- the traditional Aboriginal
owners (if any) of that land understand the nature and purpose of the proposed
action and, as a group, consent to it; and
- any Aboriginal community or group
that may be affected by the proposed action has been consulted and has had
adequate opportunity to express its view to the land council.
5.8
These parts of the Act provide for a potential
veto of the development by Traditional Owners.[2]
However, this potential veto is weakened by Section 40(b) of the Act, which
provides for the grant of a mining or exploration licence by a proclamation of
the Governor General that ‘the national interest requires that the licence be
granted’. In such a case, Aboriginal consent to the grant of either an
exploration licence or mining interest would not be needed; but negotiations
over the terms and conditions of the grant would be required.[3]
5.9
The Sections are also intended to provide for
the adequate consultation of Traditional Owners, and to ensure that they have
adequate scope to express their views and have them taken into account.
However, the Committee’s attention was drawn to the provisions of Section
48D(3) which, in the view of the Mirrar-Gundjehmi, directly undermines the
intent of Sections 23 and 48 and prevents them from making a legal challenge to
the 1982 Jabiluka Agreement. This Section states:
Where a Land Council, in entering into an agreement under
subsection (1), fails to comply with subsection 23(3) in respect of Aboriginal
land to which the agreement relates, that failure does not invalidate the entry
by the land council into the agreement.
5.10
The possible effect of these sections of the
Land Rights Act is of great concern to the Committee. It feels that they are
highly discriminatory. They deny justice to Traditional Owners and bring
unnecessary levels of uncertainty into development agreements negotiated with
Aboriginal people. These issues are discussed in greater detail below.
Aboriginal Land Ownership and the Jabiluka Mine
5.11
The traditional Aboriginal landowners of the
land that includes the Ranger and Jabiluka lease areas are the Mirrar-Gundjehmi
people of Kakadu. Their land also includes the town of Jabiru and extends from
south of Mt Brockman northwards in a large heart-shape to the southern tip of
the Magela floodplain. The Ranger and Jabiluka lease areas take up nearly half
the area of their traditional lands. The current Senior Traditional Owner is
the Mirrar elder, Yvonne Margarula.
5.12
The Mirrar people have consistently opposed the
development of Jabiluka since the project was revived in 1996. Although Ms
Margarula’s late father, the former Senior Traditional Owner, signed the
original 1982 Jabiluka Agreement negotiated between the Northern Land Council
and Pancontinental, she maintains that his agreement was obtained under duress
and that before his death he beseeched her to prevent the mine’s development
and to protect the Boiwek-Almudj sites. She has undertaken extensive and
ongoing legal action in an effort to prevent the mine from going ahead.
5.13
The Committee heard extensive and credible
evidence to suggest that undue duress was placed on Aboriginal leaders during
the negotiation process and that their wishes were disregarded by the NLC at
crucial stages of the process. This pressure was compounded by feelings of
futility amongst Aboriginal people given the experience with the Ranger
approvals and the legal capacity of the Commonwealth to override Aboriginal
objections. The Mirrar have said that they would like to make a legal challenge
to the 1982 Agreement but feel that they would be defeated by clauses in the
Land Rights Act and by the equity protection afforded Energy Resources of
Australia because it was not the original party to the agreement.[4]
5.14
A statement issued by the Gundjehmi Aboriginal
Corporation on behalf of the Mirrar Gundjehmi, Mirrar Erre, Bunitj and
Manilakarr clan leaders, and signed by Yvonne Margarula, Jacob Nayinggul and
Bill Niedjie, outlined their concerns about the Jabiluka mine:
We do not feel that our people or country have been adequately
protected since mining came here. Government has forced us to accept mining in
the past and we are concerned that you will force mining development on us
again. Previous mining agreements have not protected us or given our
communities strength to survive the development.
A new mine will make our future worthless and destroy more of
our country. We oppose any further mining development in our country...
Our future depends on our culture remaining strong. It is
important for our obligations to each other to be recognised and our
responsibilities to country to be met. Our cultural values cannot be traded for
money...
We say no to mining at Djabulugku.[5]
5.15
In evidence to the Committee, Ms Margarula
expanded on her Clan’s opposition to the mine. She stated that the integrity of
the Boiwek-Almudj sites was under threat, and continued:
In the beginning when mining negotiations actually started and
when mining first started, there was money coming out everywhere. There were
houses built for people – promises of this, that and the other thing. But look
what came with all this development – the alcohol, all sorts of unhappiness. We
stand to lose our sacred sites but get a lot of money.[6]
Jabiluka, Ranger and Change in Kakadu
5.16
Witnesses also directed the Committee’s
attention to the coincidence of the Ranger and Jabiluka agreements with
tremendous legal, administrative and social change in Kakadu. Aspects of this
change – which include the enactment of the Land Rights Act, the establishment
of Kakadu National Park, and uranium mining and increased tourism – have been
beneficial and empowering, while others have been disempowering and corrosive
of traditional culture.
5.17
The Kakadu Region Social Impact Study (KRSIS)
describes how the impact of colonisation in Kakadu, from the late 19th Century
through to the 1920s, caused a ‘radical decline’ in the number of people living
in Kakadu, through the decimation of populations by introduced epidemic
diseases. It cites the calculations of Ian Keen that populations fell from over
2,000 pre-contact to less than 100 in 1980. Traditional Owners could not
recognise the names of some languages recorded in 1912 by Spencer, and at least
six other known languages are extinct. The Study speculates that:
Cultural disruption must ... have been serious. The failure of
individuals, and of landowning groups, to reproduce broke[n] lines of
transmission of knowledge and intimacy with country ... these historical
processes had led to a substantially reduced, disconnected and diffused
Aboriginal population.[7]
5.18
The Study then described how there was in turn a
return of Aboriginal people to Kakadu in the late 1970s and early 1980s after a
series of policy developments made the region more accessible to Aboriginal
occupation. These developments included the land claims made possible by the
enactment of the Land Rights Act. The discovery of uranium deposits in the
region led to the Ranger Uranium Environmental Inquiry (the Fox Inquiry), which
established the principle of total catchment protection of a major river that
underlay the creation of Kakadu National Park, accepted evidence of Aboriginal
traditional ownership and recommended sequential development only of uranium
mines.[8]
5.19
However, crucially, the Fox Inquiry acknowledged
strong Aboriginal opposition to uranium mining but resolved that it ‘should not
be allowed to prevail’. It also excluded the town of Jabiru from Aboriginal
ownership. Fox wrote:
The reasons for that opposition ... would extend to any uranium
mining in the Region ... the Aboriginals do not have confidence that their own
view will prevail; they feel that uranium mining development is certain to take
place at Jabiru, if not elsewhere in the region as well ... They have a
justifiable complaint that plans for mining have been allowed to develop as far
as they have without the Aboriginal people having an adequate opportunity to be
heard ... There can be no compromise with the Aboriginal position; either it is
treated as conclusive, or it is set aside ... we have formed the conclusion that
their opposition should not be allowed to prevail.[9]
5.20
As a result the Fraser Government inserted a
clause (Section 40(6), since repealed) in the Land Rights Act. This clause
exempted the company from having to seek NLC consent for the Ranger project if
it became Aboriginal land following a successful land claim. Thus, the
Commonwealth Government avoided having to invoke the national interest
provisions of the Act; it had also been party, since October 1975, to a MOU
with Peko Mines and Electrolytic Zinc of Australasia to ‘grant any necessary
authorities’ for the project.[10]
5.21
The Gundjehmi Corporation’s Executive Officer,
Ms Jacqui Katona, told the Committee how Aboriginal people had been caught up
within this change and how it had brought a profound set of impacts:
The most fundamental impact ... is the fact that their decisions
were ignored by Government, that governments totally overrode Aboriginal
people’s opposition to Uranium mining ... It has set up a power relationship
where Aboriginal people are powerless and all the rest are powerful. It means
that every non-Aboriginal agenda is successful and every Aboriginal aspiration
is ignored, trivialised or marginalised. Aboriginal people do not trust
non-Aboriginal people here because they always believe that in the end the
white man will win...
This has been borne out primarily by the way uranium mining came
here, because everything else followed. If it were not for the Ranger uranium
mine and if it were not for the Inquiry that caused such a controversy in
Australia, there would not be Kakadu National Park. There would not be the
township of Jabiru. There would not be the Office of the Supervising Scientist.
There would not be all this activity on people’s land.[11]
How Fair Was the 1982 Jabiluka Agreement?
Overview
5.22
Representatives of Pancontinental and the
Northern Land Council signed an agreement for the development of Jabiluka in
June 1982. ERA and the Australian Government have insisted that the agreement
is binding and must stand. Matters are further complicated by Clause 3.2(a) of
the original 1982 Agreement, which required the mining leaseholder, in the
event of a ‘change of scope’ in the project, to seek the approval of the NLC.
(This process is discussed further below.) However, since the revival of the
proposal in 1996, the Mirrar clan, the Traditional Owners of the area which
includes the Jabiluka lease, have opposed the mine and have undertaken
extensive lobbying and legal action to have the lease annulled and to prevent
the mine’s construction and development.
5.23
The Senior Traditional Owner, Yvonne Margarula,
has pursued legal action in the Federal Court and the High Court of Australia
in an effort to stop the mine. The Federal Court’s Justice Sackville dismissed
the case in March 1998, and her appeal was dismissed in August 1998. In
November 1998 the High Court refused Ms Margarula leave to appeal the Federal
Court decisions.[12]
5.24
This action did not challenge the substance of
the 1982 Agreement, but instead challenged the powers of the Northern Territory
Minister for Mines and Energy (as opposed to the Commonwealth) to grant a lease
to Pancontinental.[13]
An action in the NT Supreme Court to prevent the construction of the access
portal and decline also failed.[14]
The Mirrar’s legal options, at least with regard to the argument put in these
cases, appear to have been exhausted.
5.25
Action in the Federal Court, challenging the
ministerial decisions made following the environmental impact assessment
process, is continuing: on 1 June the Court granted Ms Margarula leave to
challenge the decisions of the Minister for Resources and Energy (on the basis
that he was the action minister) but not those of the Minister for Environment
and Heritage (who was deemed not to have made ‘reviewable decisions’ as defined
under the Administrative Decisions (Judicial Review) Act 1977).[15]
5.26
However, the Committee was informed of
significant questions about the process of consultation which led to the 1982
Agreement and about the adequacy of the Land Rights Act properly to allow for
the gathering and expression of traditional owners’ views. The question of the
moral and legal status of the 1982 Agreement was brought into sharp relief by
the report of the UNESCO World Heritage Committee mission to Australia, which
made a formal recommendation stating that:
It is incumbent on the Australian Government to recognise the
special relationship of the Mirrar to their land and their rights to
participate in decisions affecting them. Therefore the Mission is of the
opinion that the Australian Government, along with the other signatories,
should reconsider the status of the 1982 agreement and the 1991 transfer of
ownership to ensure maintenance of the fundamental rights of the traditional
owners.[16]
5.27
In response to this, the Government submitted to
the World Heritage Committee that ‘through the Northern Land Council,
traditional owners gave informed consent to mining in 1982 and consented to the
transfer of those mining rights to Energy Resources of Australia in 1991’. It
also argued that to set aside the Agreement as the UNESCO mission recommended,
would ‘risk creating a precedent that would unjustly privilege one set of
acquired rights over another, to the extent of allowing one party to
unilaterally revoke a contract.’[17]
5.28
In its submission to the Committee, Energy
Resources of Australia argued that:
The consultation that led up to the Mining Agreement in 1982
passes the ultimate test in that it was clearly considered to be adequate by
the traditional owners of the time, who went on to enter the agreement. Energy
Resources of Australia believes that it is vital for future associations
between Aboriginal groups and major projects that a duly negotiated agreement
is adhered to. To do otherwise would undermine a fundamental tenet of our legal
system and render any agreement made with Aboriginal people implicitly
unreliable.[18]
5.29
The Mirrar-Gundjehmi and other submitters have
raised a number of objections to these arguments. They cite:
- A systematic pattern of harassment and duress during the
negotiating process which led up to the 1982 Agreement, along with several
breaches by NLC officials of their duty properly to inform Traditional Owners
and act on their views;
- The rights accruing in traditional Aboriginal law to the Senior
Traditional Owner to make decisions about country, which in the case of the
1982 Agreement had been legally alienated to the Northern Land Council by the
provisions of the Land Rights Act. Thus, the Mirrar were in the extraordinary
position of not actually being a party to an agreement that they are now being
forced to accept;
- The lack of scope for the NLC to reject freely Energy Resources
of Australia’s application for a deed of transfer. Thus, claims that Aborigines
had freely consented to the transfer of mining rights to Energy Resources of
Australia in 1991 are misleading;
- The inconsistency between the requirement of the proponent to
submit to a new environmental impact assessment process in 1996, given the
enormous changes to the original Pancontinental proposal and the fifteen year
time lapse, but no requirement to enter new negotiations with the NLC and
Traditional Owners; and
- Discriminatory provisions in the Land Rights Act, such as the
‘national interest’ provisions of Section 40 (which added to the duress felt
during negotiations) or Section 48D (which undermines the requirement of the
NLC properly to consult Traditional Owners). A process so weighted against
Aborigines, it is suggested, gravely undermines the moral force of any contract
entered into on behalf of Traditional Owners.
The 1982 Negotiations and the History of Duress
5.30
The Committee heard a great deal of persuasive
evidence which suggested that the negotiation process leading up the 1982
Jabiluka Agreement was accompanied by an unacceptable level of duress and
deception.
5.31
In evidence to the Committee the Senior
Traditional Owner, Yvonne Margarula, described the pressures placed on her
father during the process:
In the beginning, around that time, there were lots and lots of
meetings, and people would come and collect my father to take him to the
meetings. He was the main focus of a lot of this pressure, so there were people
coming to pick him up constantly. They gave him a lot of money. He had new cars
whenever he wanted it. He was given a lot of good things. He found the pressure
overwhelming. He started drinking a lot. He became an alcoholic. They just kept
pursuing him until they got what they wanted, and then it stopped.[19]
5.32
The Gundjehmi Corporation’s Executive Officer,
Ms Jacqui Katona, also outlined the pressure Ms Margarula’s father had been
placed under:
Pancontinental ... harassed Yvonne Margarula’s father, the
senior traditional owner at that time, to the extent where, even during the
rainy season when there is limited or nil access by road, the company used
helicopters for the staff to visit him at his place of residence to the point
where he had to appeal to the Northern Land Council to in some way restrict permits
for the company to prevent them from harassing him and his family.[20]
5.33
The Gundjehmi Corporation referred the Committee
to a document, attached to its submission, in which it had compiled an account
of the consultation process that took place prior to the 1982 Agreement. This
document is entitled “We are not talking about mining”: The History of
Duress and the Jabiluka Project (the Duress Document).[21] There, and in evidence to the
Committee, they described a series of problems that combine to suggest that Aboriginal
people were denied the ability to exercise their consent freely and fairly.
5.34
Ms Katona told the Committee that at the outset
of Pancontinental’s discussions with Aboriginal people about Jabiluka, which
began in the late 1970s:
The opposition to Jabiluka was
reportedly stronger than that to Ranger. We know that influenced a train of
events which led to the Mirrar people once again being put in an invidious
position where they were left with no choice but to agree to a mine going
ahead. A land claim known as the Alligator River Stage II land claim was
triggered.
...
We believe Pancontinental made their views very well known to
the Northern Land Council: that is, they would take the steps Peko Wallsend had
taken by lobbying the Government to again create the legal circumstances where
Aboriginal people could not withhold their consent to Jabiluka going ahead.[22]
5.35
That would occur if the mine site was not on
formally recognised Aboriginal land or, if it were, only if the Government then
amended the Land Rights Act or invoked its national interest provisions. The Duress
document outlines how Peko Wallsend had made ‘detriment’ submissions to the
Land Commissioner deciding the claim, outlining the damage its mining interests
might suffer. Peko later unsuccessfully sued the Minister for Aboriginal
Affairs when the land was granted to a land trust.[23]
5.36
At the Committee’s hearing in Darwin, the
Northern Land Council confirmed the added pressure of this factor. Legal
adviser Mr Brett Midena said that:
there is no doubt that there were considerable pressures around.
That land was ... under claim under the Land Rights Act – which, at the end of
the day, is a political process because it falls to the Minister for Aboriginal
Affairs ... to decide whether to grant the land. It was anticipated in that
context that he would consider what had been said and whether an agreement had
or had not been reached in relation to the mine going ahead. So there were
undoubtedly pressures on everybody at that time.
... [the pressure] came from Pancon representatives as well as
Commonwealth Government representatives.[24]
5.37
Ms Katona told the Committee that the land claim
problems were raised by the NLC at a meeting which took place at Djarr Djarr on
26 and 27 January 1981:
At least 200 Aboriginal people were in attendance at that
meeting and they were requested by the Northern Land Council to give permission
to the NLC to discuss the opposing arguments that the mining company was
putting to the Alligators Rivers Stage II land claim. It was feared by the Northern
Land Council that the opposition put by the Pancontinental mining company,
along with Peko Wallsend and the Northern Territory Legislative Assembly, could
threaten the success of that land claim.
They received permission from Aboriginal people to approach the
company and talk about that document of opposition, known as a detriment.[25]
5.38
Transcripts of the meeting repeatedly show NLC
representatives at the meeting assuring the Aborigines present that they were
arguing for discussions with Pancontinental only to discuss the land
claim:
It’s important for everyone to remember. Yesterday and today we
are not talking about the mining. We are not talking about whether that mine
starts, whether it stops, nothing about that mine. So everyone should feel very
strongly that we are not talking about that mining.[26]
5.39
However, the following day the NLC’s legal
officer, Philip Tietzel, wrote to Pancontinental’s solicitors stating that a
meeting with landowners at Djarr Djarr on 26-27 January 1981 had authorised
them to ‘commence and conduct formal negotiations ... on all aspects of the
Jabiluka project’.[27]
Ms Katona stated that:
from that point on Traditional Owners were in a legal process.
Every meeting that they attended contributed to the negotiation of the
agreement. There was precious little they could do to halt the process.[28]
5.40
The process then moved through the negotiation
of a draft mining agreement, a round of consultations with Aborigines, and a
second round of negotiations and consultations. During this time the Commonwealth
Government made a ‘conditional’ approval for export licences (which allowed the
company to begin negotiating sales contracts) before an agreement
between Pancontinental and the NLC had been signed. Deputy Prime Minister Doug
Anthony stated that: ‘In making this decision I have taken account of the views
of the Northern Land Council which has indicated its support for market entry.’
The Duress document argues that this raised the spectre of the national
interest provisions of the Act being invoked to override Aboriginal opposition
and ‘put considerable pressure on the Aboriginal landowners to give their
consent to the project’.[29]
5.41
The Agreement was finally signed on 29 June
1982. The Gundjehmi Corporation’s legal adviser, Mr Matt Fagan, told the Committee
that Department of Aboriginal Affairs records show that even on the final day
of negotiations Aboriginal people were raising concerns about sacred sites and
the appearance of the mine:
At 10.40 a.m. Traditional Owners raised concern about a sacred
site called Kungarnbu. They were told that the site would only be disturbed ‘to
the extent necessary for the Jabiluka project’. At 11.20 a.m., just forty
minutes later, the NLC chief negotiator Eric Pratt informed local Aboriginal
people that the NLC had ‘nothing to object to in the draft of the agreement’ –
that is, forty minutes after people had raised concerns about a sacred site. He
then asked whether the ‘inside group’ of people were ready to decide whether
mining should proceed.
The Aboriginal interpreter arrived for the first time that day.
Half an hour later, at 11.52 a.m., local Aboriginal people told negotiators
that they were not ready to decide. They requested more information about what
the mine would look like. Nine minutes later, after Aboriginal people had
advised the NLC that they were not ready to decide, Eric Pratt advised the
mining company that negotiations were concluded. At 12.39 p.m., half an hour
later, after receiving a brief explanation of what the mine would look like
from the road, Yvonne’s father said that he was tired and that he was not going
to object to the mine going ahead.[30]
5.42
Mr Fagan concluded that:
That is an excerpt from a very critical stage, but it gives you
an idea of the way these negotiations proceeded. Key issues which should be
triggers in any negotiator’s mind negotiating on behalf of traditional owners –
like issues about a sacred site or what the mine looks like – are pushed to one
side in the haste to see the agreement signed by a certain date – maybe the
impending election.[31]
5.43
It is clear to the Committee that negotiations
conducted under such conditions of pressure, haste, and callous disregard for
Aboriginal concerns, cannot be seen as either fair or reasonable.
5.44
The Gundjehmi Corporation argues that a major
factor in the agreement of Aboriginals to the mine was the relentless pressure
of meetings, with one participant quoted as saying that: ‘A lot of meetings
amount to pressure, out and out. It’s a long process – a blitzkrieg towards the
end. The old blokes have just been worn down.’ Records of the final meeting
showed Yvonne Margarula’s father saying, just prior to signing, that: ‘Eric,
David, Phil, I myself am tired, everybody is tired, and everybody agrees we can
go ahead.’[32]
5.45
The Committee
acknowledges the view put to it by the Northern Land Council that ‘informed
consent’ was given by Traditional Owners in 1982. The NLC stated that it
wished ‘to put on the record the strongest possible denial by the NLC or any of
its officers of any impropriety’.[33]
In response to the specific claims of the Gundjehmi Aboriginal Corporation, the
NLC stated that at the meeting at Djarr-Djarr on 26-27 January 1982, NLC
officials gave an undertaking that ‘there would be no agreement to mining
without consent’.[34]
5.46
The NLC also
stated that an extensive pattern of meetings should not be interpreted as
‘duress’, and that the Fraser Government’s approval of uranium sales
negotiations prior to the Agreement being signed, along with amendments to the
Aboriginal Land Rights Act on 18 March 1982, lent ‘little credence to any
conspiracy or duress theory which involves the NLC’.[35] The NLC
told the Committee that:
despite the existence of the
Agreement, the NLC has continued to assist the traditional Aboriginal owners in
any way it can within the legal constraints which the Agreement creates.[36]
5.47
The Committee
acknowledges and commends the strong efforts of the NLC since 1996 to represent
faithfully the views of the Traditional Owners of the Jabiluka lease. It also
acknowledges that there is considerable dispute over the interpretation of
events leading up to the signing of the 1982 Jabiluka Agreement. However, the
Committee also acknowledges that the Mirrar provided evidence, in the form of
records of the consultation process, that the Northern Land Council *failed in its obligations to Traditional Owners
under section 23(3) of the Aboriginal Land Rights Act.
5.48
While the formal pattern of meetings and
consultations create an appearance of probity, the records suggest that at
crucial points NLC officials failed to inform Aborigines adequately of the
nature and implications of Pancontinental’s proposals, that they failed to
follow the instructions provided by Traditional Owners, and that they failed to
create an atmosphere free of pressure in which Traditional Owners could provide
informed consent. Clause 48D(3) of the Land Rights Act means that these
arguments may never be tested in court. However the Committee feels that
available evidence creates a prima facie argument for a review of the 1982
Agreement.
Recommendation 11
The Committee believes that the
circumstances surrounding the negotiation of the 1982 Jabiluka Agreement, the
changes made to the proposal following its original negotiation, and the clear
opposition of the Traditional Owners to the project were extraordinary and
unfair. The Committee therefore recommends that ERA seek a new mining agreement
from the Northern Land Council and the Mirrar-Gundjehmi under Section 46 of the
Aboriginal Land Rights (Northern Territory) Act 1976 before further
construction or operation of the Jabiluka mine occurs.
The 1991 Deed of Transfer
5.49
Both the Government and Energy Resources of
Australia have claimed the NLC’s agreement to a Deed of Transfer in 1991 – of
the mining agreement from Pancontinental to ERA – as further evidence of freely
given consent by Traditional Owners to the Jabiluka Agreement.[37]
5.50
However, in its second submission to the UNESCO
World Heritage Committee, the Gundjehmi Corporation pointed out that Clause
27.1 of the 1982 Jabiluka Agreement provided that Pancontinental should seek
the consent of the NLC to any transfer but that ‘consent shall not be
unreasonably withheld’.[38]
It is clear to the Committee that this is an extremely misleading claim by the
Australian Government: Traditional Owners were in no way able to veto the
transfer and thus could not freely consent to it.
5.51
The Committee also received evidence that ERA
sought to evade obligations it had committed to under the Deed of Transfer,
that is, to seek the consent of Traditional Owners to the milling of Jabiluka
ore at Ranger. The NLC’s submission to the EIS stated that:
by the deed made on 24 December 1991 between the NLC and Energy
Resources of Australia, the latter acknowledged and agreed that for the
preferred option [the Ranger Mill Alternative] to be implemented the consent of
the NLC, to be given in accordance with the direction of the traditional
Aboriginal owners of the Ranger project area, was required and such consent may
be given with conditions.
Energy Resources of Australia has consistently, and again within
this EIS, failed to acknowledge that it is bound by the deed ... to obtain the
consent of the NLC to the milling of Jabiluka ore at Ranger.[39]
The 1997
‘change in scope’ Application
5.52
Some bitterness was also evident to the Committee
regarding the process followed in the consultation of Traditional Owners after
ERA altered the ‘scope’ of the project from that which was the subject of the
1982 Agreement with Pancontinental. Clause 3.2(a) of the 1982 Agreement
provides that if the leaseholder proposes a change in scope in concept of
design or operation of the mine, it should deliver a detailed submission to
both the NLC and the Northern Territory Minister for Mines and Energy outlining
the change in concept and its likely impact on the environment and the
Aboriginals affected.[40]
5.53
The 1982 Agreement provided for the NLC to
consider the submission and respond within 42 days. However, if the NLC’s
consent to the changes could not be obtained, the Agreement, under Clause
3.2(h), provided for the formation of a committee to determine the outcome.
This committee’s decision would be binding on the NLC and the leaseholder.[41]
5.54
In August 1997 ERA lodged an application for a
change of scope with the NLC, which included detail about both the RMA and JMA
options. After consulting with traditional landowners the NLC rejected the
change, and the issue was referred to a 3.2(h) Committee for resolution. In
evidence to the Committee the NLC stated it refused consent because:
We were then talking about an agreement which was 14 or 15 years
old. I think that, on any reasonable assessment, it needed to be reviewed – not
just the agreement but also the Commonwealth’s environmental requirements. The
so-called 3.2 process under the Jabiluka Agreement provided a very good
opportunity to do all of those things. The Commonwealth, other government
officials and ERA decided not to take that opportunity.[42]
5.55
This somewhat dry final comment referred to the
forced referral of the change in scope to the 3.2(h) Committee. The Committee
agreed by a majority to approve the change in scope, subject to ERA entering
into a Deed Poll with the NLC which incorporated offers such as additional
housing, funding of alcohol programs and a social impact monitoring program for
the life of the project.[43]
5.56
The Committee’s membership included
representatives of the Supervising Scientist, Energy Resources of Australia,
the Northern Territory Minister for Resource Development, the Commonwealth
Minister for Aboriginal and Torres Strait Islander Affairs, the Commonwealth
Environment Minister, the Northern Land Council, and the Bininj Working
Committee.[44]
Each stakeholder held a single vote. The non-Aboriginal majority of five
defeated the NLC and Bininj Working Committee representatives, who voted
against the change in scope.
The Rights of Traditional Aboriginal Owners: Debate and Conclusions
Should the 1982 Agreement Have Been Reviewed in 1996?
5.57
The arguments of the Northern Land Council for a
review of the 1982 Agreement in 1997, on the basis that it was by then 14 or 15
years old, have been cited above. This was also the view of other submitters.
The Gundjehmi Corporation pointed to the inconsistency between the automatic
triggering of a new environmental impact assessment process without a
corresponding review of the views of Traditional Owners. Ms Jacqui Katona told
the Committee that:
The lasting concern that Traditional Owners have is that,
although a process of assessment of environmental impacts was triggered, there
was no process whereby Traditional Owners had an opportunity to provide their
input into the development – no legal opportunity, and no opportunity in any
formal process, for their views to be taken on board either by the mining
company or by the Federal Government.
They made those concerns known very clearly to Senator Hill. In
fact, Yvonne Margarula travelled to Canberra to meet with Senator Hill and
discuss with him the reasons we felt the Land Rights Act particularly should be
triggered, because of the lapse of time between the negotiations which took
place in 1982 and the new proposal being put by Energy Resources of Australia
was 15 years, and because of the fact that it was a new proposal as well.[45]
5.58
Ms Katona indicated this had enforced the
marginalisation of Traditional Owners from the Jabiluka process:
Every opportunity the Traditional Owners have taken they have
been forced to take outside the process, when they are legitimate titleholders.
They are not merely stakeholders in the process. The question for Traditional
Owners and the Northern Territory Aboriginal Community is: what refuge do
Aboriginal people have in the Aboriginal Land Rights Act when we are seeing an
environmental process construed to be superior to that of title.[46]
5.59
The Committee believes that not merely this
question, but the whole of the evidence placed before it regarding the rights
of Traditional Owners in this case, raises serious concerns about the legal
framework provided by the Aboriginal Land Rights (Northern Territory) Act
1976 and the Government’s exercise of its discretion since 1996. It is
clear to this Committee that the Mirrar have been callously and systematically
marginalised and their fundamental rights ignored in the negotiation and
development of the Jabiluka project. At the very least, the revival of the
project in 1996 should have been the occasion for new consultations with
Traditional Owners which recognised their authority to make decisions about
their land. The Committee supports the view of Ms Katona that:
At a minimum Aboriginal people must have the opportunity, under
the Aboriginal Land Rights Act, to provide some input as to their consent or
otherwise for the project to go ahead if there is such a length of time between
the different processes.[47]
Can the 1982 Agreement Be Challenged?
5.60
The Australian Government has defended the
integrity of the 1982 Jabiluka Agreement by arguing that it has never been
subject to legal challenge. The Secretary of the Department of the Environment
and Heritage, Mr Roger Beale, told the Committee during Estimates hearings
that:
this agreement has never been contested as to its statutory
validity or its conscionability by anyone who has standing in relation to the
matter, and the Northern Land Council has never resiled from the applicability
of the Agreement.[48]
5.61
The Gundjehmi Corporation told the Committee
that the Mirrar had long wished to make a legal challenge to the validity of
the 1982 Agreement. They believe that they have a persuasive case, using
available records, which proves that the Jabiluka Agreement was negotiated in
unconscionable circumstances. It also believes that it has a strong case which
proves that the Northern Land Council failed to observe the provisions of
Section 23(3) of the Aboriginal Land Rights (Northern Territory) Act 1976 to
ensure that Aboriginal people affected by the Agreement understand and agree to
the Land Council’s actions, and have been consulted and had an adequate
opportunity to express their view.
5.62
The Gundjehmi Corporation told the Committee,
however, that the Mirrar are prevented from successfully pursuing an action
against the 1982 Agreement for two reasons. The first is that under the
principles of equity, Energy Resources of Australia would be protected by
having purchased an agreement negotiated by another party. The second is an
amendment to the Land Rights Act, Section 48D(3), which in their view negates
the obligations incumbent upon land councils under Section 23(3) to properly
represent the views of Traditional Owners.[49]
This section states:
Where a Land Council, in entering into an agreement under
Subsection (1), fails to comply with subsection 23(3) in respect of Aboriginal
land to which the agreement relates, that failure does not invalidate the entry
by the land council into the agreement.[50]
5.63
Jacqui Katona argued that the result of this was
that:
The Aboriginal Land Rights Act is now structured in such a way
that, although there are explicit provisions about discussions being required
with traditional owners, and therefore consent being withheld or consent given
to the Northern Land Council to allow projects to go ahead, there are other
provisions which really negate that happening at all.[51]
5.64
The Committee believes that this is an
extraordinary situation which gravely undermines the credibility of the Aboriginal
Land Rights (Northern Territory) Act 1976 as a vehicle for the exercise and
protection of the rights of Traditional Owners. It believes that this provision
undermines not only the obligations of land councils under the Act, but the
whole intent, purpose and credibility of the Land Rights Act itself. This
provision undermines the force of contracts entered into by land councils on
behalf of Traditional Owners, endangers the rights of Traditional Owners when
negotiating with developers and introduces unacceptable levels of uncertainty
into agreements made with Aboriginal people. This ought to be of concern as
much to industry and government as to indigenous people. The Committee
recommends that this provision be removed from the Act.
Recommendation 12
The Committee recommends that consideration be given to repealing
Section 48D(3) of the Aboriginal Land Rights (Northern Territory) Act 1976.
How Binding Should the 1982 Agreement Be?
5.65
Other witnesses to the Committee put the view
that to review the 1982 Agreement, as suggested by the World Heritage Committee
mission and by the Mirrar, would undermine the principles of contract law. At
its hearing in Darwin, the Committee asked the Gundjehmi Corporation why the
1982 Agreement was different to any other contract which was binding on its
signatories. Mr Fagan replied:
Because agreements reached under the
Land Rights Act are extraordinarily strange agreements. The people who own the
land are not parties to the Agreement. That, for a start, is a very strange
circumstance in regular contract law.
...
another circumstance of the 1982 Agreement ... was that it was the
first agreement reached under Section 43 of the Land Rights Act – the very
first one ... it came on top of a very manipulated set of circumstances relating
to the Ranger agreement. It is a peculiar situation.[52]
5.66
The submission of the Aboriginal and Torres
Strait Islander Commission (ATSIC) commented that:
[consent] was obtained under unusual circumstances that need
further investigation. It appears to have taken less than a year to obtain
consent from Aboriginal people who spoke little English, in comparison to other
more recent agreements that have taken four times as long.[53]
5.67
The Australian Government and ERA maintain that
the contract is binding and must stand. Their views are cited below.
- Professor Jon Altman and Dr Roy Green, members of the World
Heritage Committee mission to Kakadu:
reconsidering the status of the 1982
agreement would overturn the principles of property law in Australia,
establishing a precedent that a changing oral consent could over-rule a written
contract, thereby privileging the property rights of one group over another,
and would jeopardise Aboriginal economic opportunities based on mining futures
and, possibly, the credibility of Aboriginal land rights law.[54]
- The Australian Government:
To set the agreement aside would
risk creating a precedent that would unjustly privilege one set of acquired
rights over another, to the extent of allowing one party to unilaterally revoke
a contract, which was freely given and accompanied by payments, at a later
date. [55]
- Energy Resources of Australia:
it is vital for future associations
between Aboriginal groups and major projects that a duly negotiated agreement
is adhered to. To do otherwise would undermine a fundamental tenet of our legal
system and render any agreement made with Aboriginal people implicitly
unreliable.[56]
5.68
The Mirrar-Gundjehmi told the Committee that
since 1996, they have refused to accept payments due to them on the start of
construction. A sum of $1 million has been paid to the NLC and remains in an
NLC bank account.[57]
5.69
The Committee notes that the substance of the
Government and ERA objections is that they believe that to review the agreement
would bring uncertainty into contracts negotiated with Aboriginal people,
jeopardise the credibility of land rights law, and unjustly privilege one set
of acquired property rights over another. In response the Committee makes the
following points:
- The ‘acquired rights’ of Aboriginal people derive from an ancient
and irrefutable interconnection with the land, a fact which is only imperfectly
recognised in Australian law. The provisions of the Land Rights Act, in which
Traditional Owners are not parties to contracts negotiated on their behalf,
already create scope for those rights to be unfairly alienated within contracts
which otherwise appear legal; and
- The ‘national interest’ clauses of the Land Rights Act, along
with Section 48D(3), unfairly prejudice in law the rights of Traditional
Owners, and could be argued to ‘unjustly privilege’ the ‘property rights of one
group over another’ – that is, of developers over Aboriginals. The Mirrar have
already seen those rights alienated in the case of the Ranger mine, and the
latent threat of the national interest provisions remained present throughout
the Jabiluka negotiations. It is these provisions, not demands to review the
1982 Agreement, which undermine both the credibility of the Land Rights Act and
of agreements reached with Aboriginal people under that Act.
5.70
The Committee agrees that certainty in
agreements reached with Aboriginal people is an important goal, and that it is
important that contract law should evolve to ensure consistency. However, it
believes that it is the very framework in which those agreements are reached which
undermines those principles. Certainty cannot be guaranteed without fairness.
5.71
The highly prejudicial arrangements of the Land
Rights Act, and the sorry history of negotiation and consultation with
Aboriginal people in the Jabiluka case, ensured that the historic rights
accruing to Traditional Owners under Aboriginal Law and kinship could easily be
ignored. This has been compounded by provisions of the 1982 Agreement, such as
clause 3.2, which thwarted the opposition of later generations of Traditional
Owners after the project was changed.
5.72
The Committee believes that the Land Rights Act
should be reformed to ensure that:
- Traditional Owners are fully consulted and informed about
developments on their land (in forms they can understand, such as plain English
and local language);
- Their agreement to significant changes in scope is also required.
5.73
At the very least, the ‘national interest’
provisions of the Act should be removed, and consideration should also be given
to deeper reform which makes the contracts accord more closely with traditional
law and authority.
5.74
This might involve the designated party being
Traditional Owners themselves rather than the Land Council, although there will
be a continuing need to ensure that other Aboriginals affected be consulted.
Independent observers, perhaps from the Human Rights and Equal Opportunity
Commission, should also be present at all stages of negotiations to monitor
their fairness. The Committee believes that such reforms would restore
certainty to agreements entered with Aboriginal people and remove any questions
about the underlying credibility of the Land Rights Act.
5.75
During the course of its inquiry the Committee
became aware of a significant gulf of understanding between the Government and
ERA and Kakadu Aboriginals about legitimate lines of authority and ownership.
For example, ERA Chief Executive Philip Shirvington told the Committee that:
A group of the Aboriginals affected have indicated that they
oppose milling of Jabiluka ore at Ranger. The sole purpose of this group’s
opposition is to attempt to frustrate the Jabiluka project. It is ERA’s view
that the decision to proceed with that option does not rest with a single clan
to the exclusion of other stakeholders, including in particular other
Aboriginals affected.[58]
5.76
Such views misunderstand the rights accruing to
Traditional Owners under traditional law. The statement released by the
Gundjehmi Corporation, quoted above, and signed by leaders of the Mirrar
Gundjehmi, Mirrar Erre, Bunitj and Malikarr clans, stated that:
We recognise and affirm the responsibility of the senior
traditional owner, Yvonne Margarula, to decide on the future of Mirrar lands
and we support her opposition to mining.[59]
5.77
In evidence to the Committee, the Northern Land
Council also affirmed these rights:
Our experience has been that, whilst there may be some different
views within the Aboriginal community of Kakadu, if you like, the overriding
consideration is support for the Gundjehmi clan’s rights over that area and
their right to assert their stance on the development.[60]
5.78
In the Committee’s view it is important that, if
a credible Aboriginal Land Rights regime is to be developed, one that provides
for both fairness and certainty, the rights of Aborigines under
traditional law be more clearly recognised in the legal frameworks which shape
the development process. That has yet to occur.
Recommendation 13
The Committee
recommends that Section 40(b) of the Aboriginal Land Rights (Northern
Territory) Act 1976 be repealed.
Recommendation 14
The Committee recommends that
consideration should be given to further reform of the Aboriginal Land
Rights (Northern Territory) Act 1976 in order to ensure that the rights of
Traditional Owners are protected during negotiations, and to ensure that their
agreement to substantial changes in the nature and scope of projects be
required.
The Ranger Mill Alternative
5.79
A final, and particularly urgent, concern of the
Committee is the indications it has received from Energy Resources of Australia
that a new round of pressures are to be placed on the Traditional Owners to
obtain their agreement to the Ranger Mill Alternative. In evidence to the
Committee, ERA’s Chief Executive stated that:
The Ranger Milling Option is ERA’s preferred development, and
has always been so since we purchased the project from Pancontinental ... ERA has
vigorously pursued this preference ... we are now intensifying our focus on
finalising outstanding approvals for this option.[61]
5.80
In answer to questions from the Committee about
how far ERA would go in pursuit of this option, Mr Shirvington stated that ERA
hoped to have approval for the Ranger Mill Alternative by 2001, ‘but, if it is
not, then we will take as much time as is needed.’ He further stated that:
Prior to 1992 ... the Northern Land Council took a broad view of
the consultation process with traditional owners and consulted them as a group
... that focus by the Northern Land Council since 1992 has since narrowed down to
just the Mirrar clan. Our contention is that is not the obligation of the
Northern Land Council and we believe that the process should be opened up to
the whole of the Aboriginal community in that region.[62]
5.81
The Committee finds the implications of this
statement disturbing. While it does not dispute that there may be other views
about mining to those of the Mirrar, the statement appears to hint at the
possibility, either that the Mirrar could be swayed by these views, or that the
NLC could give consent to the Ranger Mill Alternative against the express
wishes of the Mirrar. This would involve the NLC in the contravention of
Section 23(3) of the Land Rights Act and could provoke legal action. It would
certainly lead to the further embitterment of relations between the Mirrar and
the NLC.
5.82
Yvonne Margarula was adamant about the Mirrar’s
opposition to the Ranger Mill Alternative:
We feel as though we have made our decision quite clear to
everybody. With respect to the mill where they want to go and crush the ore at
Ranger, we have had meetings about that a number of times. We have clearly
said, ‘No we don’t agree to that proposal,’ and still people keep coming back
to us and putting pressure on us. [Translator’s comment: The term used to ‘put
pressure’ literally means to apply the finger to the nose and push backwards] ...
Our feeling is that the mining company wants to divide us into two sides, go
down the middle, and entice people with large amounts of money and promises of
good things.[63]
5.83
During its inquiry the Committee was informed of
the divisive social effects of such pressures, which also place pressure on the
traditional structures of Aboriginal law and culture. In the Committee’s view,
for ERA to pursue so aggressively a renewed consent to the Ranger Mill
Alternative – especially over an extended period of time – would be an
unwelcome return to the practices of the past that have already caused so much
resentment and unhappiness.
5.84
Ms Jacqui Katona told the Committee that this
renewed pressure was symptomatic of the saying amongst Aboriginal people in
Kakadu, ‘You know white people – they just can’t listen’. She reminded the
Committee of the deeper social and cultural issues that were at stake in the
recognition of fundamental Aboriginal rights – sentiments the Committee
endorses:
The poverty is phenomenal and all the other social and economic
symptoms of that – like alcoholism, poor health and domestic violence – are
just that: symptoms. The Mirrar firmly believe that, until jurisdictionally
they have the ability to exercise the rights which they are fully entitled to –
not only in Aboriginal law but in non-Aboriginal law – and the Government
accepts that and implements that, there will not be any fundamental change
here.[64]
5.85
The Committee believes that it is crucial that
the linkages between the continuing dispossession of Aboriginal people, as represented
by the 1982 Agreement and its aftermath, and their deep social distress and
demoralisation, be understood. These processes are inextricably interlinked.
Aboriginal people see their basic rights in relation to land, the protection of
sacred cultural heritage, and the survival of their living culture, as parts of
a seamless continuum. By disregarding these rights and this interconnection the
Jabiluka process has placed the survival of the Mirrar’s culture and tradition,
and perhaps of the Mirrar themselves, in grave danger. The Committee believes
that until the fundamental human and cultural rights of Aboriginal people are
recognised, in law, in political and administrative structures, and in the
Jabiluka process, there will not be any fundamental change, and the conditions
of Aboriginal people may well deteriorate further.
Recommendation 15
The Committee recommends that in view of the inadequate
recognition of Aboriginal rights in Australian law, the Australian Government
recognise the fundamental human and cultural rights of Aboriginal people in all
laws applying to their lands and cultures.
Navigation: Previous Page | Contents | Next Page