Chapter 4 - Environmental impact assessment - the issues
The approvals process has been designed to facilitate
development rather than examine the nature of that development in any adequate
way.[1]
4.1
This chapter discusses the environmental impact
assessment process followed for the Jabiluka project, analysing problems and
uncertainties that the Committee has identified in relation to radiological
protection, run-off containment, tailings disposal, and in the identification
and mitigation of negative social and cultural impacts on Aboriginal people.
Further problems include a lack of scope for public comment and examination of
the proposals, particularly by Aboriginal communities, and an inappropriate
level of assessment of outstanding tailings disposal and mine design issues.
The chapter argues that ministerial approvals for the mine’s construction have
been premature, and that administrative arrangements for the monitoring and
regulation of uranium mining in Kakadu National Park are inadequate.
The Jabiluka EIA Process: Flaws and Uncertainties
Overview
4.2
Many submissions to the Committee expressed the
view that a significant flaw in the EIA process was that the proponent of the
mine developed the environmental impact statement or public environment report.
For example, the Gundjehmi Aboriginal Corporation argued that both the EIS and
PER were ‘clearly mining advocacy documents which make little or no attempt to
examine the impact of mining from an Aboriginal perspective ... The entire
purpose of these documents is to achieve an economic objective for a publicly
listed mining company.’[2]
4.3
They also argued that:
The EIS/PER process is one in which proponents develop a project
advocacy document which plays down or deliberately ignores detrimental aspects
of their proposal. The ‘burden of proof’ is then on others, including
illiterate Traditional Aboriginal people, to show that the position advocated
by the proponent is flawed. In this way the proponent sets the parameters of
debate in a way which greatly disadvantages those affected by the proposal.[3]
4.4
No submissions made definite suggestions about
how this arrangement should be reformed. In the Committee’s view, there are
both advantages and drawbacks in having the company develop the original EIS.
It demonstrates the technological and design competence of the company in
relation to environmental protection, and provides an overview of the measures
the company is willing to implement, which can then be evaluated by experts.
However, if the proposed environmental protection measures are found wanting in
substantial ways, the company’s willingness and ability to comply with
recommended modifications, particularly if they involve substantial project
redesign or additional cost, may be the subject of some uncertainty. Similarly,
the current regulatory regime under which these recommendations can be enforced
is also inadequate.
4.5
A very real test of this process is the quality
of the environmental impact assessments that ERA actually produced, and the
extent of project modification that was subsequently required. The assessment
of the Ranger Mill Alternative EIS resulted in approval being given subject to
77 conditions. The assessment of the Jabiluka Mill Alternative PER resulted in
approval being ventured subject to a further 17 conditions, substantial project
redesign and further assessment. The large number and scope of these conditions
suggest that the EIS and PER were deficient in a range of crucial areas, and
bring the adequacy of the proponent’s role in the EIA process into question.
4.6
In the case of the Jabiluka Mill Alternative,
which remains the only viable option given the Traditional Landowners’
opposition to the RMA, the Government has required substantial project redesign
and further assessment, and there remains considerable scientific uncertainty
about whether it can be made environmentally acceptable and therefore approved.
Meanwhile, mine construction costing hundreds of millions of dollars has
already progressed. Given these problems, the Committee believes that there are
grounds for further inquiry into the current EIA process, including the
question of whether the proponent should prepare the EIS. These grounds are
discussed further in the final part of this chapter.
4.7
In addition, a group of scientists from the
Australian National University, in a 1998 submission to the World Heritage
Committee, exposed serious deficiencies in both the EIS/PER and its assessment
by the NT and the Commonwealth in relation to run-off and waste containment and
groundwater hydrology and rainfall, and in assessing the impact of the mine in
a Kakadu–wide context.[4]
Only after the report of the WHC Mission did the Supervising Scientist conduct
further study and assessment which confirmed many of the ANU scientists’
concerns, and make a further series of recommendations for project redesign.[5] It remains unclear whether
these will be incorporated as binding conditions on the mine’s further
development.
4.8
As indicated above, submissions also detailed a
range of concerns about the EIA process, which are dealt with individually
below.
Run-off Containment and Management
4.9
Apart from the disposal of tailings, the linked
problem of run-off from the mine site is one of the most serious potential
threats to the surrounding environment. Water from tailings can leach
radionuclides, sulfates and other contaminants into the ecosystem, and stored
rock can cause acid mine drainage, threatening the survival of flora and fauna.
The assessment and management of these threats requires attention to the design
of the mine site, measures for water containment, recycling and channelling,
and extensive knowledge of weather patterns such as rates of evaporation and
levels of rainfall. In the case of a project which involves the surface storage
of radioactive tailings, these rainfall and evaporation statistics must be
known so that containment measures can be designed to preserve the surrounding
environment for thousands of years.
4.10
In an effort to manage these threats, ERA
devised a series of measures to contain run-off. These essentially involved the
division of the mine-site into three zones:
- A ‘catchment run-off zone’ in which clean run-off will be
diverted away from mine facilities to undisturbed catchment in the project
area;
- A ‘sediment control zone’, in which turbid run-off from roads and
surface facilities is treated before release to the catchment; and
- A ‘total containment zone’ (TCZ) in which all waters are directed
to a retention pond and permanently segregated from the catchment. At Jabiluka
this includes any area where rock containing more than 0.02% uranium is mined,
stockpiled, stored or handled.[6]
4.11
The retention pond was designed for a
theoretical extreme wet season that would occur once in ten thousand years.
However dispute has arisen about the models that were used to calculate weather
probabilities and evaporation rates, and which governed the design of
containment facilities.
4.12
In 1998, a group of scientists from the
Australian National University (ANU) made a submission to the World Heritage
Committee questioning the assumptions used for these factors in the EIS and
PER. They argued that:
- The design of water containment structures was flawed because of
the use of a design method which was based on the assumption of statistical
stationarity in rainfall, which over 10,000 years would be negated by
greenhouse-driven climate change;
- Other inadequacies in calculations and modelling generated an
underestimation of maximum run-off and flaws in the construction of surface
retention ponds. They stated that ‘the recent 1998 extreme rainfall event at
Katherine, 100 kilometres south of Jabiluka, probably exceeded the
calculated extreme rainfall at Jabiluka.
- Evaporation calculations, both from the retention pond and from
the mine air stream, were seriously in error; all these factors would require
new calculations and a redesign of the containment ponds.[7]
4.13
The World Heritage Committee considered these
issues of such importance that it requested the Supervising Scientist to
prepare a report responding to the concerns put by Professor Wasson and his
colleagues. The Supervising Scientists report supported the analysis of the ANU
scientists in the area of evaporation and rainfall. The report recommended that
Bureau of Meteorology estimates and records from Oenpelli be used in the estimation
of rainfall, and that either a humidifier system be installed in the mine to
assist evaporation or the retention pond be expanded in area from 9 hectares to
13 hectares.[8]
4.14
The Committee concurs with the view of Professor
Wasson and his colleagues, who praised the overall quality of the Supervising
Scientist report but argued that these issues should have been resolved at the
EIS stage, rather than be resolved after the mine’s approval, if at all.[9]
Tailings Disposal and Hydrology
4.15
Many submissions to the Committee, and both
assessment reports on the Jabiluka Mill Alternative, by Environment Australia
(EA) and the Northern Territory Department of Lands, Planning and Environment
(NTDLPE), identified serious problems with ERA’s proposals for tailings management.
In the Committee’s view, this in turn raises concerns about the precipitate
approval of the project by the Minister and the inadequate level of further
assessment of new proposals.
The Jabiluka Mill Alternative – ERA’s preferred option
4.16
One key recommendation, No 2, of the NTDLPE was
that ERA should ‘demonstrate to the supervising authority that the cement paste
technology and location of the tailings pits constitutes Best Practice
Technology for the management of uranium tailings and potential leachate ...
prior to the grant of an export licence’. Recommendation 9 also stated that
research into the chemical stability and local suitability of the process was
to be presented ‘to the supervising authority prior to approval of tailings
disposal operations’.[10]
4.17
In its assessment report, Environment Australia
also identified significant flaws and uncertainties in the PER. It identified
the need for further hydro-geological investigation of the area proposed for
the tailings pits, and sought further research to resolve scientific
uncertainties about ERA’s preferred method of tailings disposal. These latter
concerns included:
- The newness of the proposed paste-fill technology, with ERA
indicating there was no previous experience of its use with uranium or in tropical
climates;
- Uncertainty as to how acid levels would affect the curing and
integrity of cement paste fill, with further test work being required; and
- Problems with the design and location of the pits. ERA had no
plans to line the pits (which raised concerns about possible seepage), while
the proposed site of one pit was in an area with fractured and weathered
material and possible faults and joint planes (which raised concerns about
possible contamination of Swift Creek and groundwater within 10-50 years). EA
stated that the PER had failed to consider that the fractures in the sandstone
might form potential contaminant pathways.[11]
4.18
EA also cast doubt on ERA’s proposal to manage
possible seepage in the below ground pits by blocking cracks in the pit walls
with a cement-based grout: ‘Whilst this might provide a suitable physical
barrier in the short term, it would be relatively brittle and will be subject
to chemical reactions potentially allowing mobilisations of contaminants.’ In
addition, EA expressed doubts about ‘the long-term chemical integrity of the
cement-hardened tailings mass’ which was ‘unknown’. This raised the danger of
radionuclides being released into groundwater.[12]
4.19
Environment Australia thus argued for a
‘precautionary approach’ to be taken, and for ‘the risk posed by these
contaminants to be more adequately assessed before the Government commits to a
decision.’ This was important because ‘once the project is under way corrective
action may be difficult’. EA considered the paste fill technology to be
‘somewhat experimental for the Kakadu region. We do not regard this as best
practice nor believe that it should be trialed in such an environmentally
significant area.’ The report concluded that it was ‘a matter of judgement as
to the seriousness of environmental harm and degree of irreversibility of
potential harm involved in allowing the JMA to proceed at this time.’[13]
4.20
In response to this uncertainty, the Minister
for the Environment commissioned an independent review of the tailings
management proposals from scientists at Unisearch Ltd. Their report argued that
the proposed location of Pit No 2 was unsuitable and identified additional
assessment and design work that was needed.
4.21
In particular, they found that the high
concentrations of sulfate and magnesium in the tailings water might degrade the
curing, strength and impermeability of the cement paste. Possible measures to
avoid this included the investigation of alternative binding agents or, if that
proved unsuccessful, the minimisation of the use of sulfate in ore processing
and the removal of contaminants from the tailings water prior to paste
formation and cement addition. They commented that both of these latter
strategies ‘would impose significant cost and technological challenges’.[14]
4.22
Other problems with the tailings paste involved
the ‘critical’ dewatering step prior to cement addition, which they thought
could be prone to failure; and the proposed method of underwater emplacement of
the cemented tailings mass which could ‘create problems with segregation of
paste components and insufficient compression’. Because scientific literature
was not definitive in relation to the likelihood of the paste immobilising
contaminants, further mineralogical and microscopic investigations were
required.[15]
Thus, it appears that significant scientific (and technological) uncertainties
remain about the environmental safety of the cement paste technology when used
with Jabiluka ore tailings.
4.23
The Unisearch team also identified significant
uncertainties in regards to the proposed tailings pits. While they stated that
the permeability of the Kombolgie sandstone in which the pits would be dug was
‘low to negligible’, they added that ‘extensive and persistent jointing,
faulting and weathering has resulted in secondary porosity in the form of
fissures which allow water to flow through the rock mass’. They stated that the
location of Pit 1 was unsuitable because it was in a zone affected by faulting
and deep weathering, would suffer pit slope stability problems and allow excessively
high water flow past the tailings. While the location of Pit 2 might be
suitable, they stated that ‘relatively high permeable rock can be expected in
the upper 30m highly weathered zone and in fracture zones in the rock at
depth’.[16]
4.24
They recommended further extensive drilling and
testing and possible changes to the dimensions and shapes of the pits in order
to avoid joints, faults and shear zones. They concluded that:
It is essential that a monitoring system and program
commensurate with the level of assurance normally expected of the uranium
industry be established as soon as possible to collect baseline data, assist
with the design, construction and operation of tailings disposal pits and
monitor developing conditions around the pits as they are filled, capped and
subsequently left to interact with the groundwater system.[17]
4.25
At this time ERA also made reference to a third
tailings management option which would involve returning all tailings paste
underground to the mined-out underground stopes. This would in turn require the
excavation of underground silos in unmineralised rock adjacent to the decline
and the indefinite storage of that rock on the surface as artificial landforms.
The Jabiluka Mill Alternative – The Government’s preferred option
4.26
Reflecting the obvious scientific and
technological uncertainties attending the 50-50 option, Senator Hill wrote to
the Minister for Resources and Energy, saying that there was insufficient
information to decide whether ERA’s preferred option for the JMA was environmentally
acceptable, but that if 100 per cent of tailings were placed underground in the
mine void, and a further series of recommendations were complied with, ‘the
milling of uranium ore at Jabiluka will be environmentally acceptable’. The
Minister wrote that Environment Australia had advised him that ‘this option
would avoid the uncertainties associated with ERA’s preferred option’ and told
Senator Parer that the JMA could proceed and export licences be granted if ERA
prepared an amended proposal for the underground tailings disposal, and if that
proposal was approved by the Supervising Scientist and the Supervising
Authority (the Northern Territory Government).[18]
4.27
The Committee shares the concerns of many
witnesses that this decision was premature, given that ERA had supplied
virtually no detail to the Government about the 100 per cent option and that it
had not been the subject of any further environmental impact assessment. Doubts
remained about the cement paste process, and the hydrology of the rocks
surrounding the mine stopes was unknown. Similarly, the placement of vast
amounts of waste rock on the surface would create impacts which needed further
assessment. The ANU scientists have also argued that the construction of
artificial landforms with this rock could have substantial cultural effects,
given that the mine is located in an area of enormous cultural significance.[19]
4.28
The basis for the Minister’s advice to Senator
Parer appears to be the August 1998 ERA paper, Jabiluka Mill Alternative:
Synopsis of Key Issues and Processes, which included a paragraph discussing
the possibility of returning 100 per cent of tailings into the mine void, but
indicated that this would be an expensive and less desirable option. No
further information about this proposal, nor any technical detail, was
included.[20]
Apparently on the basis of this information, Environment Australia advised the
Minister that this alternative ‘would completely avoid the uncertainties
associated with the previous proposal to use open cut pits in the Kombolgie
sandstone.’[21]
4.29
In evidence to the Committee, Government
witnesses insisted that the option of storing all tailings underground is the
only one that ERA will pursue. Supervising Scientist Dr Arthur Johnston relied
on this claim to dismiss the concerns expressed in 1998 by Professor Wasson and
his ANU colleagues.[22]
Secretary of the Department of Environment and Heritage, Mr Roger Beale, also
sought to discredit the ANU scientists by insisting that returning all tailings
underground ‘is, in fact, the only approved process. That is why the long-run
climate change effects were not relevant’.[23]
In response to questioning from the Committee, Dr Johnson reiterated his view:
we have not said that we are assuming that 100 per cent of
tailings is going into the ground. We are saying that that is precisely what
has been required by the Government in giving its approval, and therefore, yes,
that is what has been approved, and that is what will happen.[24]
4.30
Clearly, Dr Johnston and Mr Beale are confident
that this option will be pursued. However the Committee does not share that
confidence, having received evidence which raises serious doubts about ERA’s
intention to pursue this option. It seems clear that the Company’s preferred
options remain firstly, the Ranger Mill Alternative and secondly, the earlier
JMA option using surface pits.[25]
The Committee’s visit to the mine on 15 June 1999 also confirmed that the
constructed layout of the mine portal, rock stockpiles, storage tanks and
retention pond exactly conforms with the design of the Ranger Mill Alternative
as presented in the EIS. A great deal of reconstruction of the area will have
to occur if the JMA has to proceed.[26]
4.31
The possibility of resubmitting the preferred
JMA option for approval was specifically left open by Senator Parer. On 27
August 1998, he wrote to ERA Chief Executive Philip Shirvington indicating
conditional approval for the Jabiluka Mill Alternative, subject to the
conditions recommended by Senator Hill. That is, approval would be given for
the final option of complete disposal of tailings into the mined-out shafts or,
if ERA wished to continue with the 50-50 preferred option, it could submit a
new assessment to the Environment Minister for consideration, with guidelines
to be developed in consultation with the Commonwealth and NT, to address the
identified inadequacies.[27]
He commented that:
I note that the Minister for the Environment believes,
nevertheless, that there is every prospect that further assessment can identify
design amendments to your preferred option which ensures tailings can be
adequately managed and disposed of in this way.[28]
4.32
The Committee possesses a copy of the advice
provided to the Environment Minister in relation to these options, and has
formed the view that his confidence in a successful redesign of the 50-50
proposal was premature. Environment Australia told the Minister that ERA had
presented three possible revised options which could be assessed in a
‘fallback’ approach:
- Proving up an unlined pit option as proposed in the PER;
- A pit option with clay lining and other barriers to be
determined; and
- 100 per cent of the tailings going back into the ground ... with a
new barren waste rock strategy to be developed.[29]
4.33
The EA minute continues by saying that the 100
per cent underground option would ‘be an expensive option and there would still
be a small risk to the surrounding environment related mainly to the disposal
of the excavated material and its subsequent rehabilitation. However, it
appears superior to in-ground pit disposal in terms of isolation of
radionuclides.’[30]
These unknowns did not prevent EA from suggesting that this proposal ‘would
completely avoid the uncertainties associated with the previous proposal’.[31] The Committee believes that
the Department’s confidence in an option which had been the subject of no
scientific assessment was premature.
4.34
At no point did EA suggest that successfully
redesigning the 50-50 option (or a 70 per cent underground option also put
forward by ERA) would be easy; they continued to suggest that if ERA wanted to
pursue either of these options the concerns of EA and the Unisearch scientists
would have to be addressed and that: ‘should the additional studies and
investigations fail to define a technology which, in the opinion of the
Supervising Scientist, is likely to adequately protect the environment, then
ERA must commit to 100 per cent disposal of tailings back underground in the
mine voids’.[32]
4.35
The Committee is concerned that this revised
50-50 option, when resubmitted, will be subject to the minimum level of
assessment allowed under the EPIP Act or its equivalent; there is to be no
higher level environmental impact assessment or public consultation. More
detailed consideration of this decision-making process is continued later in
this chapter (4.147-4.181).
4.36
The Supervising Scientist’s report to the World
Heritage Committee did make further assessment of the likely movement of
tailings contaminants from the mine voids using existing hydro-geological data.
The OSS recommended that new silos be dug in the Kombolgie sandstone to the
east of the ore body and found that the quality of groundwaters in the vicinity
of the Jabiluka ore body was high, indicating that ‘there is very little
movement of radionuclides into the groundwater aquifer from the orebody’.
Modelling of the dispersion of contaminants in groundwater indicated that the
maximum distance uranium could move east under the most extreme conditions was
300 metres in 1,000 years, but was more likely to be 50 metres. Movement of
solutes west through the schists would be faster, some 500 metres in 200 years.[33]
4.37
However, this was of little concern given the
presence of clays underneath the Magela floodplain which would limit upward
migration of groundwater, and the continual dilution of solutes to levels less
than naturally occurring concentrations in the region. The OSS concluded that:
‘the wetlands of Kakadu will not be harmed as a result of the dispersal of
tailings constituents in groundwater,’ a conclusion which the ANU scientists
accepted. However, the OSS did state that a full risk assessment has not been
carried out and would require further analysis and hydro-geological data
collection.[34]
4.38
Despite endorsing the OSS analysis, the ANU
scientists expressed a range of other concerns about both JMA options.
Professor Wasson expressed doubts about the likelihood of ERA implementing the
100 per cent underground option. He stated that he and his colleagues continued
to disagree with the OSS about:
whether or not above-ground storage of tailings is likely ... We
remain sceptical of blanket promises. This country is littered with abandoned
mine sites. This is a World Heritage property, I repeat, not just any old mine.[35]
4.39
Their submission also drew the attention of the
Committee to the possibility that:
in the future, this approved plan may be changed. Over the 30
year lifespan of the mine there will be ample opportunity for new plans to be
approved, including the storage of tailings on the surface. If this possibility
can be ruled out with complete confidence ... then our concerns about the
calculation of risk for the stability of surface storages vanish. If the
possibility of a renegotiated disposal plan cannot be ruled out, then we remain
concerned that the actual extremes of rainfall and run-off may substantially
differ from those modelled and calculated.[36]
4.40
The ANU’s Professor Ian White also cited the
failure of the BHP mine at Beenup where the cost and technological challenge of
dewatering tailings (as ERA proposes in forming the cement paste) caused the
mine to be abandoned. Professor Wasson stated that the uncertainties identified
in regards to the 50-50 option suggested that it could not be successfully
redesigned:
Storing tailings at the surface is really not an environmentally
sound option.[37]
4.41
The ANU scientists’ submission also expressed
dissatisfaction with the lack of public scrutiny of the proposal, associated
with the 100 per cent underground option, to excavate inert rock from the mass
adjacent to the decline to create room for the extra tailings: ‘Again the
Supervising Scientist asks us to trust the details of this procedure, the
details of which remain unclear.’[38]
Radiological Protection
4.42
Radiological protection challenges arise in two
main areas:
- The exposure of mine workers to radiation, particularly given
that the operating environment is underground and that much of the uranium ore
is of a very high grade, from 0.2 per cent U3O8 to 0.65
per cent;
- The possible exposure of nearby populations, particularly the
Aboriginal settlement at Mudginberri, to airborne radiation.
4.43
Environment Australia appeared to endorse the
radiation limits used by ERA, which accorded with the then published limits
from the International Commission on Radiological Protection (ICRP). These
were:
- Doses to designated workers to be limited to 100 millisieverts
(mSv) in a 5-year period, which is an average of 20 mSv per annum, with a
subsidiary limit of 50 mSv in any one year;
-
Doses to members of the public to be limited to less than 1 mSv
per annum during mine operation and after its closure.
4.44
The EIS and the PER modelled the dose rates
predicted in the mine and public environments and outlined a range of measures
to protect workers and minimise levels. These models and techniques were
reviewed by the Supervising Scientist, Australian Radiation Laboratories (ARL)
and by other specialist consultants.
4.45
The evaluations conducted by Environment
Australia appear to demonstrate that the modelling and measures initially
outlined by ERA were inadequate. Its EIS and PER assessment reports include
very extensive and detailed recommendations in relation to the collection of
further baseline data about pre-mining background levels, the monitoring of
radiation levels and forms in the mine workings, new modelling, and the
redesign and reassessment of shielding equipment for workers and of the mine
ventilation system.[39]
4.46
Concerns about the ventilation system and its
assumptions were confirmed by analysis of Dr M J Howes, an internationally
recognised expert in uranium mine ventilation. The Environment Australia
assessment said that workers would be exposed to doses of 9.4 mSv to 14 mSv per
annum, which approach legislated maximum levels, and remarked that it was
essential that underground workers be protected. According to Environment
Australia, comparison with the underground uranium mine currently operating at
Olympic Dam:
indicates that the dose estimated from modelling is less than
might be expected from actual operation ... given that the largest predicted
annual radiation doses approach the annual dose limit, it is essential that an
exhaustive radiation protection program be planned and implemented to verify
the methodologies employed to estimate effective doses to mine workers, and to
accurately quantify the radiation doses incurred as a result of each work
function at the mine.[40]
4.47
Dr Alan Roberts of Monash University stated in
his submission that the richness of the uranium ore at Jabiluka was of
particular concern. It contains about six times more uranium than the ore from
Olympic Dam; in other words, there is six times the amount of radiation source
for each ton of ore mined, which could produce a greatly increased dose for
workers. Dr Roberts said that while the EIS had dealt with this issue, it did
not do so in sufficient detail and left important questions unanswered.[41]
4.48
Also of serious concern to the Committee are the
predicted effects of airborne radiation (through the inhalation of radon
progeny) on the surrounding public area – that is, on Mirrar lands. Environment
Australia’s assessment stated that, depending on the calculations used,
exposure rates at Mudginberri could vary from 0.12 mSv pa (12 per cent of
the current ICRP dose limit) to as high as 49 per cent of the dose limit.
Environment Australia commented that:
It should be noted that, even if these dose rates at Mudginberri
are below the public dose limit, there will be regions in the vicinity of
Jabiluka at which restrictions on permanent occupancy might have to be placed
(e.g. Ja Ja) – that is, the annual radiation dose to occupants in some areas
near to the mine may be over the 1 mSv limit.
The potential for members of the public to be exposed to levels
above the recommended dose is viewed as an unacceptable impact and would be of
particular concern to Traditional Owners.[42]
4.49
When the PER assessment report was prepared,
these uncertainties still remained. The Office of the Supervising Scientist and
the ARL both stated that while they did not expect doses to people at
Mudginberri to exceed the legal limits, they had significant questions about
the modelling used by ERA to predict doses, which they thought produced
‘unexpectedly low dose rates’. Environment Australia thus recommended further
research and monitoring of airborne radiation, with the results to be submitted
to the Supervising Scientist and the NT prior to the mining and
processing of ore.[43]
4.50
Many submissions to the Committee argued that
there is no actual ‘safe’ level of radiation exposure, and that dose levels as
set by bodies like the ICRP are a trade-off between possible casualty rates and
the perceived economic benefits of mining employment and access to the products
of the nuclear industry. The Jabiluka Action Group (QLD) submitted that the
ICRP has steadily been revising downwards safe permitted levels of exposure to
radiation as more information emerges over time. It cited a 1997 article in the
New Scientist in which:
The ICRP now admits there is no safe lower limit of radiation
exposure. Low levels of exposure over a period of time are as dangerous to
health as high dose levels.[44]
4.51
The Jabiluka Action Group also told the
Committee that the ICRP revised its limits for exposures to uranium workers
from 50 mSv pa to the current 20 mSv pa in 1990. Other countries have far lower
dose limits for the public than the current ICRP and Australian level of 1 mSv
per year. The US limit is 0.25 mSv, Germany 0.30 mSv and the UK 0.30 mSv.[45] The Committee notes that
Environment Australia’s EIS assessment speculated that annual doses to the
residents of Mudginberri could be between 0.25 and 0.49 mSv per annum, well
over the overseas limits.[46]
The Australian Conservation Foundation put the question as to ‘how, over time,
the [Jabiluka] project would be able to come in under what are bound to be an
ever increasing tightening of ICRP standards’.[47]
4.52
The Committee has three major concerns about
radiological protection at Jabiluka:
- Environment Australia’s analysis indicates that significant
uncertainties remained at the time of the EIS about the modelling used to
predict radiation doses on the mine workers and that the design of crucial
control measures, such as the mine ventilation system, was unresolved. These
uncertainties combine, over time, with the likelihood of ICRP limits falling.
In the Committee’s view, this raises serious questions about the ministerial
approvals given to the Ranger Mill Alternative in June 1998.
- The regulatory regime relies on the Northern Territory Government
to enforce Government recommendations about radiological monitoring and
protection, given that they must be completed before mining begins.
While the Supervising Scientist has the skills to assess the studies it is
unclear whether further scientific peer review would be involved. Should the
Northern Territory’s oversight be inadequate, the Commonwealth has no direct
power to intervene until ERA applies for an export licence for its first
yellowcake shipments. The Committee heard serious concerns about the regulatory
record of the NT, which are detailed below (4.125-4.134).
- The potential for public access to areas around the mine to be
banned is of grave concern. If ICRP recommendations about permissible levels
fall further this is more likely to occur. This possibility needs to be
considered in relation to the very serious potential social and cultural
impacts of the mine on Aboriginal people, whose culture and tradition may
suffer if they are discouraged, through anxiety or regulation, from visiting
and using their lands for traditional purposes. This concern, in its broader
context, is discussed further below (4.60-4.115). The Committee feels that
these concerns were not given adequate consideration by the Government in its
decision-making, and should have contributed to a decision to delay, rather
than approve, the mine’s construction.
The Scope for Public and Aboriginal Input to the EIA Process
4.53
The Committee acknowledges that formal
requirements for public comment and participation in the EIA process have
generally been met. However, submissions raised substantial concerns with some
elements of the process. Of most concern to the Committee was the lack of scope
for Aboriginal people to understand and comment on the assessments.
4.54
Concerns were raised that opportunities for
public comment on the Jabiluka Mill Alternative were compromised by the level
of assessment of the PER. According to Environment Australia, a majority of
submissions expressed unhappiness with the level of the assessment. These
submissions argued that ‘for a project of this nature with potential impacts on
an area of international significance, at least an EIS with its enhanced
opportunities for public input was warranted’. A substantial number of others
argued that the assessment of the JMA warranted a Commission of Inquiry. A
great majority, including ATSIC and the NLC, also argued that the period of
public consultation (four weeks) was insufficient, and did not allow for
‘appropriate consultation with key indigenous stakeholders’.[48]
4.55
The level of assessment required by the Minister
for Resources and Energy of the final proposal for the disposal of tailings
under the Jabiluka Mill Alternative has was also raised in many submissions.
Further assessment of the proposal for the disposal of all tailings
underground, which involves the excavation of massive amounts of waste rock
which will need to be permanently stored on the surface, is limited to the
Supervising Scientist, who will report to the Commonwealth and the Northern
Territory. There will be no public consideration of this proposal. Similarly,
the further assessment of ERA’s preferred Jabiluka Mill Alternative option,
which involves the partial disposal of tailings in surface pits and about which
there remains significant scientific uncertainty, will receive no public
consideration.
4.56
The Committee believes that this level of
assessment is inadequate, and also that at the very least the proposals should
be subject to a new PER and be open to scientific peer review.
4.57
In its submission to the EIS the Northern Land
Council stated that it had made its comments under protest because of the
inadequate consideration of Aboriginal concerns. The NLC’s concerns took two
forms:
- The Mirrar had refused to participate in consultations about the
mine until their concerns about the unfairness of the 1982 Agreement and the
company’s refusal to reopen negotiations were addressed; and
- The EIS guidelines were flawed in that they did not require the
company to produce the EIS in a format accessible to the Aboriginal community.
The documents were neither produced in the Gundjehmi language nor plain
English. ERA released a plain English version, ‘The Jabiluka Project – The
Project in Pictures,’ which was only made available to the community a month
before comment was due. The NLC requested an audio tape of the plain English
version, which was not supplied before comments were due.[49]
4.58
The Gundjehmi Corporation argued that the entire
approach of the EIS and PER to Aboriginal socio-cultural issues was flawed
because, as a process, it entrenched the original denial of the rights of
Traditional Owners to make fundamental decisions about their land. They
expressed concern that ‘there were no Aboriginal contributors to either the EIS
or PER’, and argued that:
The entire purpose of the documents is to achieve an economic
objective for a publicly listed mining company. This objective is to develop a
uranium mine on Mirrar land. The Mirrar are fundamentally opposed to this
objective. To this end, the EIS and PER processes have disempowered the Mirrar
from the outset ... as soon as the Mirrar engage in the process of correcting or
providing new information to the EIS or PER the Mirrar are effectively
legitimising and contributing to this appropriation.
The EIS and PER processes are not about whether the
project should proceed but how it should proceed.[50]
4.59
The Committee acknowledges and sympathises with
these concerns. It is a mark of the way in which the basic conflict with the
Mirrar over the mining of their land has coloured the whole Jabiluka assessment
process. Bearing these concerns in mind, the Committee has nonetheless sought
to conduct a careful assessment of the totality of the EIA process in relation
to the project. It is of major concern to the Committee that an appearance that
the process has functioned not to decide whether the project should proceed but
how it should proceed, has been created. This is a concern that relates to
issues considered throughout this chapter, and has some legitimacy. The process
of Government decision-making which has provoked this concern is discussed
further later in this chapter (4.147-4.181).
Cultural Heritage and Sacred Sites
4.60
Requirements to assess and report on the
potential cultural impacts of the Jabiluka mine for Aboriginal communities were
given high priority in the draft guidelines for both the EIS and PER. The EIS
guidelines required ERA to develop baseline descriptions of Aboriginal land
uses, food gathering and ceremonies, of sites of significance to Aboriginal
population and culture, and of Kakadu as a cultural landscape.[51] The PER guidelines involved
even more detailed requirements to assess the impacts of the JMA on:
- Traditional Owners’ use of the land after the proposed mill has
been completed;
- The social and cultural lifestyle of Traditional Owners and the
broader Aboriginal community, including customary practices, resource sharing
and food gathering; and
- Impacts of milling activity upon Aboriginal values of the region,
sites of significance and Aboriginal culture (including the views of
Traditional Owners on impacts).[52]
4.61
In the two years since the EIS was prepared,
attention has fallen on the requirement of ERA to develop a comprehensive
cultural heritage management plan in consultation with Traditional Owners, and
on disputes about how the extraction of ore will affect the Boiwek-Almudj
sacred site complex (which the Traditional Owners believe to overlay and
include the orebody).[53]
The Australian Government and ERA are disputing the claims of the Senior
Traditional Owner about the extent and significance of the site, and ERA has
refused to cease construction of the mine in order to complete the cultural heritage
management plan. These disputes have become particularly bitter and have soured
relations between the Mirrar and ERA.
4.62
The EIS identified a need for further
archaeological surveys of the project area and conceded that the project layout
may need to be reviewed in the light of those studies. Environment Australia’s
assessment report on the EIS specifically recommended that:
ERA must develop a cultural heritage management plan in
consultation with Traditional Owners, and Environment Australia and relevant NT
authorities, prior to project construction commencing.[54]
4.63
The Northern Land Council confirmed to the
Committee that it received an interim cultural heritage management plan six
months after construction had started. A completed plan, it told the Committee,
‘would have served to clarify a number of issues, including the extent of sites
in the lease area ahead of development being undertaken’.[55]
4.64
The Committee views the fact that the cultural
heritage management plan has not been completed with great concern. It believes
that the Government’s approval for construction of elements ‘common’ to the
Ranger Mill Alternative and Jabiluka Mill Alternative was premature, given that
the plan had not been completed. Concerned about the damage construction could
do to the Boiwek-Almudj sites, the Mirrar have refused to cooperate with the
development of the plan until construction was suspended for a period of
between four and six months.[56]
Such a suspension could have allowed for the credible cultural mapping of the
area in consultation with Traditional Owners.
4.65
The Environment Australia assessment report also
identified the Boiwek (knob-tailed gecko) site, a ‘soak’ on the edge of the
Magela wetlands across the Oenpelli road, as ‘of particular concern and was
raised as such in a submission by the NLC. This site would appear to be a
“danger” site which could be compromised if development proceeds’. The
assessment report felt that the proposal to draw groundwater for mine workings
may affect the site, and recommended that if a program to monitor its impact
could not be established, alternative water sources would need to be sought.[57]
4.66
Both the EIS and the assessment report failed to
document the further information which was now being revealed about the site by
the Senior Traditional Owner and other custodians. Presumably under the
pressure of the mine’s imminent construction, they had revealed that the site
was linked easterly through the mine valley to the Almudj (Dreaming Serpent)
site by a dreaming track to form a single complex. This site was djang
andjamun (dangerous and restricted) and had sub-surface manifestations.
4.67
In its response to the Report of the World
Heritage Committee mission, the Australian Government argued that it was not
aware of claims that the Boiwek site had an ‘extended area’ or underground
manifestations. It stated that: ‘The recent claims are not consistent with
anthropological records or the previous statements and permissions given
between 1976 and 1997 by Traditional Owners’. These instances were said to
include the 1982 Jabiluka agreement, the 1977 Fox Inquiry, the claim book for
the Stage II Alligators Rivers stage two land claim, and research for the
registration of sites on the National Estate. In all of these instances, the
Government claims, Boiwek was defined as a small discrete soakage or swamp and
was not classified as ‘dangerous’.[58]
4.68
Professor John Mulvaney, an eminent
archaeologist and former Australian Heritage Commissioner, told the Committee
that the site complex had, in fact, been identified as early as 1978 in the
course of a study by George Chaloupka and other anthropologists.[59] Chaloupka’s report includes
extracts from a survey of the Jabiluka area that was undertaken by Dr Ian Keen,
who recorded the Boiwek and Almudj sites and the dreaming track extending
between them. His notes state that at Almudj was a series of paintings,
including a design of the Buyweg figure: ‘Almudj is said to have made the place
and travelled to Buyweg where it made permanent freshwater springs’. He quotes
the traditional custodian who accompanied him as saying:
That one went right through to Buyweg – where that Buyweg are –
that’s dreaming. I don’t reckon – spring water is that bit of ground there.
Buyweg make it that way.[60]
4.69
Intimating the underground manifestations denied
by the Government, Keen then noted:
These springs associated with Buyweg and Almudj are located in
the Pancontinental deposits, and test drillings have been made immediately
beside it.[61]
4.70
Chaloupka’s notes accompanying a photograph of
Boiwek add further weight to the Mirrar Senior Traditional Owner’s account of
the site. He writes:
Plate 10. This is Bojweg Bagolu, djang, a dreaming site
of Bojweg, a knob-tailed gecko ... an actual animal, but also a dangerous
mythological being. The soak never dries up, even when during extreme drought
the wetlands dry out. This is believed to be because Almudj, the Rainbow Snake,
is below the ground here.[62]
4.71
Legalists might point to the reference to the
site as djang, which indicates that it is sacred, rather than to a
specific reference to it as djang andjamun, or sacred and dangerous.
However, there is also reference to the Bojweg creature as ‘a dangerous
mythological being’ and that the Almudj figure exists below ground. Keen’s
notes also suggest that the Almudj figure, which created and perpetuates the
springs, exists in a location generally coterminous with the ore body.
4.72
This statement alone, from one of the most
widely respected anthropologists to have worked in the region, should be
sufficient to dispel any doubt about the nature of the site and to cause the
Government to reassess its approach to the issue and to the current mine
proposal. The Committee believes that this record strongly suggests that the
current Senior Traditional Owner, Yvonne Margarula, is not engaging in wilful
fabrication in her recent accounts of the site and its location, as the
Government appears to be suggesting. In evidence to the Committee she stated
that:
What I will tell you today will be the same thing which I have
been talking about for years. I want to assure you that when we talk about
these things, we don’t make them up; we don’t change them from time to time to
suit the occasion. It is something we always talk about in the same way. When
Aboriginal people talk about sacred sites, it is a historical thing which goes
back into our ancestral past ...
this particular site we are talking about here [Boiwek-Almudj]
is a dangerous site. We just don’t go there and sing out any old way or call
out any old thing or behave in any sort of informal fashion ...
those of us today know and understand what our ancestors
explained to us. We hold that knowledge and know it to be true.[63]
4.73
Professor Mulvaney told the Committee that it
was not unusual for new details about sacred sites to emerge over time. In
fact, he argued, it was quite normal and in accordance with the rules in
Aboriginal law which govern the transmission and revelation of secret
knowledge:
It is essential to acknowledge that Aboriginal practice and
European legal understanding differ. While company officials might assume that
all details have been revealed [to Pancontinental for the purposes of the 1982
Jabiluka Agreement], elders would not have felt any obligation to disclose all
esoteric details. Indeed, the reverse is the case. In Aboriginal law only
appropriate persons may be told details, and those are revealed progressively
through their life cycles at specified rituals. It should neither surprise nor
anger industry and government when new attributions emerge in the face of dire
actions which force revelations.
Access to stories by non-indigenous people is severely
restricted and may become public only when every other course of action proves
impossible.[64]
4.74
In defence of its argument about the site, the
Government has cited the actions of the Northern Territory’s Aboriginal Areas
Protection Authority (AAPA), which declined to register the site formally after
an application was made by the Northern Land Council in 1997. The AAPA’s Chief
Executive Officer, Dr David Ritchie, told the Committee that it declined to
register the site because:
What emerged ... was that, while there is no doubt that Boyweg and
Almudj are very significant sites, and clearly sacred sites within the meaning
of the Land Rights Act and hence the Sacred Sites Act, there was considerable
disagreement – and by considerable I mean a large range of views – over how big
the sites are, what features comprise and the stories associated with, those
particular sites ... So the authority resolved that it could not enter the Boyweg-Almudj
site as requested on the register of sacred sites; but it made the point – this
is again a legal point – that it in no way was a statement that the area was
not a sacred site.[65]
4.75
In the Committee’s view this last statement
discredits the Government’s attempt to use the AAPA decision to defend its
position. Dr Ritchie also told the Committee that similar levels of
uncertainty, this time working in the opposite direction, influenced its
decision at the same time to refuse an application by ERA for an authority
certificate to carry out works in the mine valley:
The Sacred Sites Act says that the Authority, before issuing an
approval, must be satisfied that the proposed works do not pose a substantial
threat of damage to interference with sites on or in the vicinity of the
application – so again, there was substantial doubt.[66]
4.76
It appears to the Committee that Ms Margarula’s
claims about Boiwek-Almudj were sufficiently credible for the AAPA to refuse an
Authority to ERA to undertake underground works in the mine valley,
which included the construction of ventilation shafts from the mine tunnels.
However, the disagreement among custodians did not provide enough legal
certainty for the site to be registered.
4.77
Of some interest to the Committee is the test the
AAPA uses to evaluate the knowledge and standing of custodians it consults. If
Professor Mulvaney’s evidence about the rules governing what custodians may
know and reveal is to be taken seriously, it is possible that some were not in
possession of the full ‘story’ about the sites. The Gundjehmi Corporation
states that in 1980 the then Senior Traditional Owner identified Mr Jimmy
WogWog as the elder responsible for sacred sites in the area. On a survey with
George Chaloupka in 1992, he had identified the Boiwek-Almudj area as a
‘dangerous proximity’. They also claim that the evidence of five senior Mirrar
custodians to the AAPA was contradicted ‘by a person not considered to be a
custodian for the Jabiluka land’.[67]
Unfortunately, the Committee was unable to pursue these points with Dr Ritchie.
4.78
The Gundjehmi Corporation has assembled a
history of the recording of sacred sites in the Jabiluka area which clarifies
many of the statements which the Government has made about existing site
records. It makes the following points:
- It is true that George Chaloupka’s research for the Fox Inquiry
identified only one site in the entire Jabiluka project area. However Chaloupka
attributes this to the fact that the Fox Inquiry was focussed on Ranger which
threatened sites in the southern part of Mirrar land.
- In 1976 Chaloupka did further cultural mapping with two
custodians for an application to have the Djawumbu-Madjawarnja site complex
listed on the National Estate. The custodians referred to the Boiwek-Bagaloi
soak and the Almudj rock art site as sacred and dangerous places, along with
the dreaming track which connected them. Chaloupka included the Boiwek-Almudj
site complex in the listing application, but after representations from the
mining company the Heritage Commission excised the extent of Jabiluka mining
activity from the area to be protected, which was listed in 1980.
- In 1978 Chaloupka made representations to the Australian
Government that Pancontinental’s claim – in an EIS for the proposed Arnhem
highway extension – that there were no known sites in the area of the proposed
road was misleading. Dr Keen’s studies at this time, referred to above (4.68),
specifically refuted the company’s claims.
- Dr Keen included the full reference to the Boiwek-Almudj complex
and dreaming track in the Alligator Rivers Stage II land claim, in explicit
contradiction of the Australian Government’s recent claims. The hearings
however incorrectly recorded the sites, noting that Boiwek stood alone and
recording a non-existent site called ‘Berewuk’.
- In 1982, following serious desecration of sacred sites attributed
to Pancontinental personnel, including the theft of human remains, local
Aboriginal people requested at 18 separate meetings that sacred sites not
be identified in the 1982 Jabiluka agreement. Despite this, and the fact that
no project-specific anthropological work was carried out during the
negotiations, a highly erroneous sites map appeared in the Agreement,
transcribing the mistakes made in the record of the 1980 land claim.
-
In early 1982 a well-known anthropologist wrote to Pancontinental
to warn the company of serious concerns within the Aboriginal community that
appropriate custodians had not been consulted about sacred sites in the
Jabiluka area and that sites underground could be disturbed by mining
activities with severe consequences.[68]
4.79
This is an extensive and compelling record when
one considers the claims made by the Government and ERA in relation to the
Boiwek-Almudj sites. The Committee believes that for the Australian Government
to use an obviously flawed process, which included the desecration of sacred
sites and the wilful disregard of known information, in an attempt to discredit
the claims of custodians about the Boiwek-Almudj complex, is grossly
disrespectful. Whatever the legal uncertainties surrounding the site complex,
the Committee believes that the claim of the Australian Government that the
extent and meaning of the sites has recently been changed cannot be sustained.
4.80
Widespread evidence exists to show that a
recorded description of the sites as sacred and dangerous and linked by a
dreaming track, had appeared as early as 1978 and has been repeated on many
occasions since. The rules governing the revelation and transmission of secret
knowledge, and caution about revealing knowledge to non-Aboriginals until
absolutely necessary, explains the absence of the site from the 1982 Agreement
and the public statements about its nature since the Jabiluka development was
revived in 1996. The Committee believes that it is a matter of respect for
traditional law and culture that this information be accepted. The Committee
calls on ERA to enter into new negotiations with the Mirrar with the aim of
protecting the site from the impacts of mining.
4.81
Ms Margarula told the Committee, in response to
a question citing the assurances of ERA about the eventual rehabilitation and
return of the mine site to the Traditional Owners, of the irreversible damage
already wrought by the mine’s construction:
That idea [rehabilitation] is no good. They will interfere with
the integrity of the site, they will take parts of it away, deposits in the
ground made by the dreaming ancestor will be removed, they will do all sorts of
explosions and crush the ground with forces of all description and then cover
up all the dangerous things and leave it alone and go away. It is too late ...
Once you destroy a sacred site that is the end of it.
We Aboriginal people believe that the wet seasons are intimately
connected to this site and we do not know what bad things are going to happen
with respect to the weather or the water. This will affect other Aboriginal
people in the area as well.[69]
Recommendation 3
The Committee
recommends that all further construction of the Jabiluka mine be suspended
until cultural mapping of the site area can be conducted in cooperation with
the Traditional Owners and recognised custodians of the Jabiluka area.
The Social Impacts of Uranium Mining
Overview
4.82
Requirements for ERA to address the broader
social impacts of the Jabiluka mine were included in the guidelines for both
the EIS and PER. These included:
- The effects on employment, education, health and health services,
safety, law and order;
- Possible adverse impacts upon Traditional Owners’ social and
cultural lifestyle, including customary practices and resource sharing; and
- Cumulative impacts, including the combined impacts of the Ranger
and Jabiluka mines upon the Kakadu region.[70]
4.83
The Committee heard a great deal of evidence
about whether or not ERA, and the Commonwealth and Northern Territory
Governments, had adequately assessed and attempted to mitigate these potential
impacts both in the EIS and PER and in later initiatives.
4.84
Possible social impacts were thought to arise
from a variety of causes:
- The influx of a large number of non-Aboriginal people during the
mine life. The EIS stated that operation of the mine would result in an
approximate ten to fifteen per cent increase in the population of the region,
with a total possible mining workforce of over 200;
- The replacement of Government funding for basic services and
programs with mining royalties;
- Adverse effects on food gathering and land usage through real or
perceived contamination of the environment;
- The encroachment of non-Aboriginals onto restricted Aboriginal
land;
-
The pressure of participating in meetings and administrative
arrangements; and
-
Aboriginal perceptions of marginalisation, as a result of either
the increasing numbers of non-Aboriginal people in the area or the denial of
sovereignty over land and development. The extension of the life of the Ranger
mine and of the town of Jabiru were important considerations here.
4.85
From the outset, the question of social impacts
and their consideration within the EIA process has been coloured by the
opposition of the Mirrar to the mine and the company’s determination to hold
them to the terms of the 1982 Agreement between Pancontinental and the NLC. The
NLC, on behalf of Traditional Owners, restricted access to the lease area by
the company, which ERA claims prevented the EIS from presenting sufficient or
reliable information on social impacts on Aboriginal people.
4.86
Ms Jacqui Katona, Executive Officer of the
Gundjehmi Aboriginal Corporation which represents the Mirrar, told the
Committee that the dispute over the 1982 Agreement already had powerful social
effects:
The most fundamental impact ... is the fact that their decisions
were ignored by Government, that governments totally overrode Aboriginal
people’s opposition to uranium mining ... It has set up a power relationship
where Aboriginal people are powerless and all the rest are powerful.
The poverty is phenomenal and all the other social and economic
symptoms of that – like alcoholism, poor health and domestic violence – are
just that: symptoms.[71]
4.87
The Senior Traditional Owner, Yvonne Margarula,
was asked by the Committee whether the mine had brought any benefits to her
community:
I can’t think of anything good. I would like to think of
something but I really can’t.
Just look at the history of what has happened here with the
mining. In the beginning when mining negotiations actually started and when
mining first started, there was money coming out everywhere. There were houses
built for people – promises of this, that and the other thing. But look what
came with all this development – the alcohol, all sorts of unhappiness. We
stand to lose our sacred sites but get a lot of money.[72]
Time demands, cultural stress and administration
4.88
The Northern Territory’s EIS assessment report
stated that the process of negotiation, and the pressure and complexity
surrounding development, also had powerful social effects:
Aboriginal people, individually and in communities, have become
subject to increasing pressures to change and to information overload so there
is often sufficient stress to cause social disruption. The people are currently
receiving complex information on many topics from a variety of sources, but the
information they receive is often incomplete and conflicting. Added to this are
time pressures to make rapid decisions in a manner not consistent with
Aboriginal approaches, which require a high degree of consensus arising from
considered discussion from all parties concerned.[73]
4.89
Environment Australia’s EIS assessment also
commented that dealing with mining companies, Park management and participation
in Aboriginal organisations produced added stresses for Aboriginal people.
Environment Australia noted that if the Commonwealth approved the project such
pressures could increase.[74]
Access to country and risk perception
4.90
Environment Australia’s EIS assessment noted
that the Ranger operation and Jabiru already took up a large part of Mirrar
land. ‘While access to most of the lease will remain,’ they stated, ‘it will
potentially be less attractive. Even after rehabilitation, the land may have
reduced value because of perceived association with radioactivity. While ERA’s
commitments to consultation ... would reduce this impact, the impact may remain
significant.’[75]
4.91
Echoing the NT’s assessment, Environment
Australia also noted that:
perception of risk may exist after an issue has been
demonstrably dealt with to the satisfaction of the company and regulatory
agencies. Risk perceptions may be due to issues of trust in scientific data
collection and in the company ...
The impacts of these fears have not been well documented, other
than reports (including in the NLC submission) of reduced usage of the Magela
floodplain. Possible social impacts of these fears can include the
psychological and health effects of suffering fear, reduced use of the area
concerned and of species normally hunted from it. Over a very long period there
is a risk of gradual attrition of knowledge of these areas if they become less
frequented and children are taken there less often for socialisation into
traditional ecological knowledge.[76]
4.92
The Committee applauds the acuteness and
sensitivity of this analysis. However, it is also concerned that such a
profound series of potential impacts, which affect the very survival of
Aboriginal tradition and are compounded by the Mirrar’s fears for the integrity
of the Boiwek-Almudj complex, were not reflected in a stronger recommendation.
The Department merely recommended that ERA and the Supervising Scientist aim
for better levels of communication about and participation in environmental
monitoring, including providing data in forms which assist Aboriginal people to
evaluate it for themselves.[77]
4.93
This recommendation is laudable in itself, but
will be counteracted by the growing pattern of distrust and hostility which
marks relations between the Mirrar and ERA. This has only been exacerbated by
the arrest and prosecution of Yvonne Margarula for trespassing on the mine site
in May 1998, which marked a new low in relations with the Mirrar, and by ERA’s
refusal to respond to the concerns about Boiwek-Almudj. Environment Australia
stated that, ERA’s commitment to cooperate and communicate with community
groups in order to increase mutual trust and cooperation:
may reduce perceptions of perceived risk, [but] if such
perceptions continue to exist so long after the commencement of mining at
Ranger, it is unlikely that they could be easily banished.[78]
4.94
It is the Committee’s view that such impacts
cannot be adequately dealt with in discrete measures arising from the EIA
process. They must be addressed in the context of broader issues about
sovereignty, consent and justice in relation to the approvals process and the
legal rights of Traditional Owners.
Recommendation 4
The Committee recommends that the issues of Aboriginal
people’s access to, and perception of, country as a result of development
projects, be addressed in a holistic process which links environmental impact
assessment with questions of Aboriginal land rights, sovereignty and cultural
survival.
Marginalisation and disempowerment
4.95
Environment Australia’s assessment acknowledges
this aspect of the social impacts of mining. It commented that marginalisation
occurred through unequal power relations and the alienating daily experience of
being a minority among non-Aboriginal people:
It affects people’s ability and sense of effectiveness to pursue
their own planning and development agendas (including visions of their country
and futures) rather than be forced to adapt to the agendas of others.[79]
4.96
Environment Australia stated that evidence
dating from the Fox Inquiry confirmed the high level of Aboriginal
marginalisation and that ‘approval of the Jabiluka project would continue this
degree of marginalisation over a far longer period (46-48 years post-1977). It
stated that while approval would cause ‘additional pain’, non-approval ‘would
simplify the stakeholding relationships in the region after Ranger ceases
operation around 2008, leaving Aboriginal people in a more influential position
overall.’[80]
4.97
The Gundjehmi Corporation’s Jacqui Katona told
the Committee that the impact of such enduring marginalisation was cultural
genocide:
We live our culture. So when parts of our culture are being
eroded, it is our identity which is being attacked and undermined. It is the
future of our children that is being undermined. We might still be living after
all this, but there will still have been an act of cultural genocide because
the instability caused to our families will mean that the integrity of our
culture has been severely affected. We will not have the ability to act as
traditional owners.
In the same way that previous policies removed children from
their families, that is exactly what is happening here. There is a definite
break occurring in the ability that Aboriginal people have to exercise their
identity.[81]
4.98
The Committee is concerned that neither ERA nor
the Australian Government has been able to respond to these concerns with
sensitivity. Environment Australia conceded that ‘the manner in which the
Commonwealth decision-making process is concluded has the potential to influence
the extent of marginalisation that may be felt.’[82] Environment Australia was
particularly critical of ERA, saying that ERA’s commitments to employment,
training and business opportunities for Aboriginal people would be undermined
by conflict with the Mirrar. It cited ERA’s contention that ‘many other
Traditional Owners of the region have given strong support to mining and the
benefits of mining to the community’, and commented:
Given that no formal consultation has taken place, it is
difficult to assign any credibility to this statement. It is also important to
note that the final EIS does not acknowledge the possibility that, because
there has been no formal canvassing of other Aboriginal people with cultural
responsibility for the project area, it is equally possible that further
opposition to the mine and support for the Senior Traditional Owner’s position
may be found there.[83]
4.99
The assessment concluded with the grim statement
that, if the opposition of the Mirrar continued, ‘a decision to proceed with the
project will increase marginalisation and social impact no matter what other
measures are put in place.’ It is telling, in the Committee’s view, that this
discussion did not give rise to any formal recommendations. The attitudes and
decisions of the Minister also indicate that it has been ignored in the
Commonwealth approvals process.
The Kakadu Region Social Impact Study
4.100
Both Environment Australia’s assessment and the
EIS refer issues such as the distribution of royalties, alcohol and substance
abuse, and cumulative impacts to the Kakadu Region Social Impact Study (KRSIS).
KRSIS has been the subject of some controversy and bitterness, particularly
over its implementation.
4.101
The Northern Land Council complained that
because it was conducted in parallel with the EIS, the KRSIS study had little
opportunity to determine outcomes in the EIS process. For this reason, in
addition to the fact that the EIS was undertaken before the concerns of
Traditional Owners about social impacts had been given consideration, the NLC
argued that the EIS was ‘fundamentally flawed’.[84]
4.102
The KRSIS took place over an eight month period
in two components. The first, the Aboriginal Project Committee (APC), conducted
research among Aboriginal Communities and developed the analytical basis on
which recommendations and an action plan could be developed. The Study Advisory
Group (SAG), which was chaired by Mr Mick Dodson and included representatives
of the NLC, ERA, the Northern Territory Government, Environment Australia, and
the Office of the Supervising Scientist, oversaw the project and drafted its
recommendations.
4.103
The introduction to the APC’s report states that
the KRSIS has ‘been a project oriented less towards past impact causation than
to identification of problems and issues that need to be addressed in an action
plan for community development.’ These included: analysis of servicing regimes,
including support for efforts to transmit and strengthen traditional knowledge;
the structure and operation of Aboriginal organisations set up to manage the
material benefits of mining; and Aboriginal critiques of organisations in the
region, such as ERA, ERISS, the NLC, Parks Australia North and the Jabiru Town
Council.[85]
4.104
The Committee acknowledges the quality and
importance of the APC’s report, which was compiled in a short time and created
welcome scope for Aboriginal voices to be heard on the future of Kakadu.
However, the opening comment about its scope also indicates the enforced
limitations which governed its work. Despite being invoked as a necessary
accompaniment to the EIA process, the study was not focused on assessing the
impact of uranium mining on the region. In particular, it was specifically
prevented from examining the potential social impact of the Jabiluka mine. The
issues of mining-related disempowerment and sovereignty discussed in the NTDLPE
and Environment Australia assessment reports were not discussed in the Kakadu
Region Social Impact Study.
4.105
Many submissions to this Committee criticised
the lack of specific attention in the Kakadu Region Social Impact Study to the
social impacts of Jabiluka, particularly given its establishment in parallel
to, but not necessarily as a part of, the EIA process. Thus it possesses an
ambivalent status where it is both invoked and disavowed as an element of the
Jabiluka EIA process. In the Committee’s view, this has been counterproductive
in the task of assuring Aborigines that their longstanding concerns about the
impact of uranium mining were being addressed.
4.106
Many submissions to the Committee voiced
concerns that the KRSIS recommendations were not being implemented. In its
submission to the PER, the Northern Land Council said that: ‘there continues to
be no perceptible movement by the Commonwealth and Northern Territory
Governments towards the implementation of its recommendations’.[86] Environment Australia, in its
July 1998 PER assessment, acknowledged that: ‘the Commonwealth and NT
Governments have not as yet announced any decisions on implementing the
recommendations of KRSIS’. [87]
4.107
In its April 1999 reply to the World Heritage
Committee mission’s report, the Australian Government claimed that it ‘has
commenced action to implement the recommendations’ of the Kakadu Regional
Social Impact Study:
In late 1998 the Australian and Northern Territory Governments
announced their formal response to the recommendations of the KRSIS Community
Action Plan and the appointment of the Honourable Bob Collins as the
independent Chair of the KRSIS implementation team. Mr Collins is a well
respected former Senator for the Northern Territory with a strong record of
working to progress Aboriginal people’s interests.[88]
4.108
The Government did not say what that response by
the two governments had been, and stated that Mr Collins was still in the
process of developing a draft KRSIS Action Plan in consultation with
Commonwealth and NT Governments, Aboriginal organisations and individuals in
the Kakadu region. Yvonne Margarula was asked by the Committee whether Mr
Collins had visited her or her community:
He has been here to do something with the Aboriginal community.
I do not understand fully what he is supposed to be doing. I do not know ... he
came here once.[89]
4.109
The Gundjehmi Corporation asked why the impact
of Jabiluka was specifically excluded from the study, and why the local Aboriginal
community was not allowed to decide the study’s recommendations.[90] They have also asked why the
Commonwealth and Northern Territory Governments have ‘vehemently opposed the
primary recommendation of KRSIS that Jabiru become Aboriginal land’. The APC report
argued that:
All of Kakadu, including Jabiru, should be legally Aboriginal
land. If the Aboriginal political position is to be sustained and enhanced, it
must be underwritten by that legal recognition. Indeed that legal recognition
would probably be seen itself as an act of respect from the non-Aboriginal
polity to the Aboriginal culture of Kakadu. It is also seen as a necessary act
of empowerment.[91]
4.110
The Kakadu Region Social Impact Study contained
two recommendations which dealt with mining. One recommended that the
definition of the ‘area affected’ by the Ranger mine for the purpose of the
distribution of royalties be widened. The second went to the heart of the
dispute over Jabiluka, and appears to have fallen on deaf ears since. It
stated, in part, that:
Recognition be given to the special interests of the traditional
owners of a mine area. In particular the Traditional Owners should have primacy
over decision-making that may impact on their land, while recognising this is
different to decisions on area affected moneys which are directed to the whole
community.[92]
4.111
The KRSIS also made reference to the problem of
the substitution by Governments of service and welfare funding for royalty
payments, by recommending further investigation of and action on the issue. At
its hearing in Darwin the Committee was told by a member of the SAG, Mr Stephen
Roeger, that the NLC believed that Kakadu communities received less from
Government because of a perceived wealth in royalties, but that:
There has not been an objective study of it. The Aboriginal
Project Committee in the Kakadu Region Social Impact Study sought to engage in
an investigation of that nature. They were encouraged not to do so by the Study
Advisory Group – I will not attempt to explain their reasoning ...
One of the most telling findings of the social impact study was
that conditions in Kakadu are no better than they are anywhere else in the
Territory. Indeed, many would argue that they are considerably worse in many
respects.[93]
4.112
The Committee notes with concern that Mr Collins
and the KRSIS implementation team are still in the process of developing a plan
to implement the KRSIS recommendations nearly two years after its findings were
released. It is also concerned that his consultation with key stakeholders,
such as the Mirrar, appears to have been so limited. Given the roles played by
the Commonwealth and the Northern Territory in this process to date, the
Committee has serious doubts that full implementation of the KRSIS
recommendations will ever occur.
The cumulative impact of mining
4.113
Perhaps the most profound impact of the Jabiluka
project will be the cumulative effect of the mine developments. In its
submission to the World Heritage Committee the Northern Land Council said that:
The approval of Jabiluka means that the affected land will not
be returned to the ‘Aboriginal domain’ for the quiet enjoyment of its
traditional owners until about 2035. The mining project will have an impact on
a generation who were never intended to be saddled with the impacts of mining.[94]
4.114
The Gundjehmi Corporation’s Mr Matt Fagan also
outlined this impact, particularly if ERA’s preferred option, the Ranger Mill
Alternative, proceeds:
If the Ranger alternative goes ahead, Yvonne Margarula, most of
her sisters and most people in her family will never see the Ranger project
area rehabilitated. It will not be rehabilitated until 2035 or 2040.
Unfortunately, with the life expectancy of Aboriginal people in
this area, it is highly unlikely that Yvonne Margarula will ever see that area rehabilitated.
That has to be a tremendous concern. Talk about a bigger environmental
footprint, if you like, with a JMA; what about the fact that that area will not
be rehabilitated?[95]
4.115
The Committee feels that the potential social
impacts of mining have only been partially understood and addressed within the
EIA process. In particular, they have been inadequately addressed in formal
recommendations arising from either the EIS/PER and the Kakadu Region Social
Impact Study, and have been disregarded in ministerial decision-making about
the mine.
Recommendation 5
The Committee recommends that a new inquiry be conducted
to assess the specific social and cultural impacts of the Jabiluka project on
the Aboriginal communities of the Alligator Rivers Region. The Committee also
recommends that the social and cultural impacts of mining be given greater
attention in ministerial decision-making.
World Heritage Protection
4.116
Injunctions for the company to address the
potential impacts on the surrounding World Heritage values of Kakadu National
Park were contained in the Guidelines to both the EIS and PER. With the report
of the World Heritage Committee mission to Australia in November, and the
imminent meeting of the World Heritage Committee in Paris to decide whether to list
Kakadu as In Danger, these issues have clearly been of concern to the
Australian Government as well.
4.117
A detailed discussion of the Jabiluka project
and the World Heritage values of Kakadu National Park is contained in Chapter 6
of this Committee’s report. That chapter outlines the legislative and
administrative arrangements in Australian law which provide for World Heritage
protection, and summarises the Government’s defence of its record in relation
to Jabiluka. The chapter also discusses the many submissions to this Committee
which expressed concern about the possible impact of the project on the World
Heritage values of the Park. For this reason the Committee refers readers to
Chapter 6 for further detail, and makes some brief comments below.
4.118
The World Heritage Committee mission’s report
already suggests that the company and the Australian Government have failed to
protect the World Heritage values of Kakadu National Park adequately throughout
the Jabiluka process. It is the view of this Committee that much of the
evidence discussed above supports the views of the mission. While the
Supervising Scientist’s report to the World Heritage Committee has been rightly
praised, it does not conclusively dispel uncertainties about the project.
4.119
As the above discussion (4.9-4.41) of the
outstanding run-off and tailings management issues shows, substantive
scientific and technological uncertainties remain in relation to the cement
paste process and the method of tailings disposal. These uncertainties have
been compounded by the continuing uncertainty about the option ERA intends to
pursue and the inappropriate level of assessment to be accorded the revised
proposals. For these reasons it was premature for the Supervising Scientist to
argue that ‘the natural values of Kakadu National Park are not threatened by
the mine and the degree of scientific certainty that applies to this assessment
is very high’.[96]
4.120
The Committee also makes the point that the
protection of natural values – in this case by no means certain – is only a
part of the task of protecting World Heritage values. The World Heritage
Committee, in particular, has firmly stated that its consideration of World
Heritage protection also takes in the cultural and social protection of living
cultures, and must take into account developments in international human rights
law regarding the right of indigenous peoples to determine their own futures.[97] The adequate protection of
World Heritage values requires a holistic framework in which environmental
protection, the recognition of indigenous rights and the protection of living
culture are given equal weight.
The Regulation and Oversight of Uranium Mining in Kakadu
4.121
A number of submissions expressed concern about
the regulatory structure for the environmental oversight of both the Ranger
mine and the Jabiluka development. Of particular concern were:
- The shift in responsibility for day-to-day regulation from the
Office of the Supervising Scientist (OSS) to the Northern Territory Government
(NTG);
-
The erosion of funding and resources within the OSS; and
-
Concerns about the independence of the OSS.
The Office of the Supervising Scientist (OSS) and the Regulatory Regime
4.122
Section 5 of the Environment Protection
(Alligator Rivers Region) Act 1978 specifically established the Office of
the Supervising Scientist with the responsibility of ensuring that the region’s
uranium mines do not damage the environment of Kakadu. From its establishment
until recently the OSS has maintained offices in Jabiru and manages an
environmental research institute (ERISS). It is required to advise the Minister
on matters of environmental protection in relation to uranium mining, and to
‘devise and develop’ standards and practices for environmental protection.
Section 5(d) specifically empowers the OSS to:
coordinate, and supervise the implementation, in relation to
uranium mining operations in the region, of requirements of, or having effect
under, prescribed instruments in so far as those requirements relate to any
matter affecting the environment of the region.[98]
4.123
In its submission to the Committee, the
Australian Conservation Foundation (ACF) argued that there have been long
standing problems, dating from the establishment of the OSS, ‘with the
functioning of the OSS and the complicated accountability lines between the
Commonwealth, the NT Government, ERA and the Northern Land Council’. They cited
the 1988-89 Annual Report of the OSS as stating that the level of cooperation
between the OSS and ERA was low and that ERA was seeking to make the role of the
OSS in the region redundant.[99]
The ACF also alleged that:
There was also evidence that ERA and the Northern Territory
Government were also colluding to reduce the extent to which OSS was directly
involved in decision-making processes concerning the operation of uranium
mining in the region.[100]
4.124
The 1988-89 Annual Report of the OSS complained
that:
Ranger has, by increasingly ignoring OSS advice on environmental
issues, appeared to wish to establish that OSS performs no useful function ... it
has attempted to impugn the scientific credibility of the office, and has
lobbied for its disbandment’.[101]
The Northern Territory Government as the Supervising Authority
4.125
In 1995 a Memorandum of Understanding between
the Commonwealth and the Northern Territory redefined the respective regulatory
roles of the NT and the OSS. The MOU shifted primary responsibility for the
day-to-day supervision and regulation of uranium mining from the OSS to the NT,
which would henceforth rely on the UMEC Act.[102]
4.126
The ACF identified two problems with this new
arrangement. First, it stated that the terms of the MOU are not legally
binding. Second, it argued that this involved delegating responsibility
‘without enforceable controls or accountability mechanisms’ to a government
with a poor track record in the environmental regulation of mining. In the
ACF’s view:
This delegation of Commonwealth powers to the NT Minister for
Mines directly places environment management of Kakadu at risk. The NT
Department of Mines is not an independent body. It is a department which is
directly involved in the promotion of mining in the NT. This is a direct
conflict of interest and means that environmental management considerations
will be subject to distortions caused by the prevailing economic and political
aspirations of the NT government.[103]
4.127
As early as 1988-89 the Annual Report of the OSS
had identified problems with the Northern Territory as a regulator. In
identifying a range of breaches of the Ranger Environmental Requirements (ERs)
that year, the OSS said:
These matters are of concern, not so much because of any
immediate risk to the environment, but because by slow attrition of the ERs,
and the accumulation of numerous uncoordinated small impacts, environmental
control of the operation could be compromised. These actions by Ranger [are]
too readily accepted by the NT...
The OSS has expressed its concerns a number of times over the
years, that the formulation of NT authorisations has been too imprecise to
allow them to be enforced.[104]
4.128
The ACF and the Environment Centre of the Northern
Territory (ECNT) pointed out that the NT Government has a poor record in the
environmental management of mines. In particular, the ECNT told the 1996 Senate
Inquiry into Uranium Mining and Milling of pollution episodes at Groote
Eylandt, McArthur River, Nabalco and Pine Creek which the NT Government had
failed to monitor or prevent.[105]
4.129
In 1996 BHP was fined $45,000 by the NT
Government for allowing more than 2 million litres of diesel to leak into
Groote Eylandt’s water table from stores held at its manganese mine. The NT
Government had been warned of this possibility as early as 1991 but had failed
to investigate. At the Renison gold mine, local residents detected the
pollution of Copperfield and Pine Creeks which the NT had failed to notice; at
Mount Isa Mines’ lead and zinc mine near Booroloola, the NTDME failed to ensure
that proper safeguards were in place to prevent a large spill of ore into the
McArthur River when it was being loaded onto barges; and only after a 1989
study found high levels of heavy metals in oysters at Gove Harbour did the NT
institute a tighter environmental regime at the Nabalco mine, despite Justice
Fox expressing disquiet about the refusal of Governments to reveal their
knowledge of pollution problems.[106]
4.130
The ECNT also cited a Northern Territory News
report of a leaked internal memo drafted by an officer of the NTDME’s
Environmental Directorate. The officer criticised the Department’s lack of
preparedness to cope with potential environmental problems arising from the discharges
from mine sites, and complained that:
my efforts to implement these [data collection] initiatives in a
timely manner have been continually frustrated by internal wrangling,
complacency and poorly defined responsibilities ... I am disappointed that approaches
designed to develop standardised techniques for environmental protection in the
NT have been stymied by the inability of policymakers to make timely decisions.[107]
4.131
The ECNT also expressed concern to the 1996
Inquiry about the ‘club’ which had developed between mining companies and NT
regulators:
There is a revolving door by which staff move from company to
supervisory bodies and reverse with alarming regularity. Independent assessment
is impossible in these circumstances. [108]
4.132
The ACF argued that the 17 August 1998
correspondence from the former Minister for Resources and Energy, Senator
Parer, to ERA confirmed the marginalisation of the OSS. Senator Parer told ERA
that the Northern Territory Government held responsibility for regulation and
monitoring of mining as the ‘supervisory authority’, whereas the Commonwealth,
through the OSS, merely provided advice on matters relating to environmental
protection. The ACF commented that:
Previously ERA had to convince the OSS that there would be no
environmental damage. Now all they have to do is convince the Supervising
Authority – the NTG – that there will be no environmental damage. An altogether
easier task as the NTG only needs to be convinced that ERA is seeking to
protect the environment to an extent that is reasonably practicable.[109]
4.133
However, the Minister put the view in his letter
that:
Where my requirements relate to regulatory arrangements, I have
only referred to the Supervising Authority as the regulator, but this should
not be interpreted as minimising the role of the Supervising Scientist in
providing relevant advice consistent with working arrangements argued between
the Commonwealth and Northern Territory.[110]
4.134
In the Committee’s view this argument confirms
the fact of the transferral of regulatory authority about which the ACF has
expressed concern, but attempts to cast it in a different light. The Committee
welcomes the vote of confidence placed in the OSS but shares the ACF’s broader
concern about the shift in regulatory authority from the OSS to the NTDME,
which has a proven record of failing to act on environmental breaches.
Recommendation 6
The Committee recommends that powers of
day-to-day regulation of uranium mining in the Alligator Rivers Region be
removed from the Northern Territory Department of Mining and Energy and
restored to the Office of the Supervising Scientist.
The Funding and Operation of the OSS
4.135
The Northern Land Council, in discussing the
standards required in relation to radiological protection, expressed concern
about the erosion of funding from the OSS:
There is a continuing need for an effective independent
monitoring authority to ensure compliance with national and international
standards. The progressive weakening of the role of [the OSS] has reduced the
level of independent assessment of environmental protection within Kakadu ...
Australia could better demonstrate its commitment to such protection by
strengthening the role of OSS within Environment Australia.[111]
4.136
The NLC also expressed its concern, at the way
the NT assumed the role of regulator and also at a steady withdrawal of
resources from the OSS:
We see [the assumption of regulation by the NT] as a substantial
reduction in the Supervising Scientist’s role and that, from there on forward,
the Supervising Scientist’s funding and resources have been systematically
reduced – and substantially so in 1995, when the organisation was subject to a
major review.[112]
4.137
The ACF’s Mr Dave Sweeney told the Committee
that:
the OSS has experienced a major series of financial cutbacks and
a major decline in both its autonomy and its resource base. The other thing ...
is that the on-the-ground presence is moving away. There are currently detailed
negotiations to move the bulk of OSS and ERA offices away from Jabiru and into
Darwin. OSS has increasingly moved away from a field presence to a lab or
laptop presence where now, instead of collecting its own data, it largely
monitors company provided data.[113]
How Independent is the OSS?
4.138
Some witnesses also felt that in addition to
losing resources and having its permanent monitoring presence scaled back, the
OSS had become less independent. Mr John Hallam suggested that:
the annual reports of the [OSS] have become more glossy, thinner
and less detailed, and there has been progressively less honest assessment in
those reports, particularly over the last ten years. You would have seen a
progression from reports that were at times highly critical of the Ranger
operation to a tick-a-box exercise where all the boxes are pre-ticked.[114]
4.139
Legal and Policy Adviser to the Gundjehmi
Aboriginal Corporation, Mr Matt Fagan, told the Committee that:
Any notion that the Office of the Supervising Scientist is
independent is clearly ludicrous. It takes direction from the Minister.
Materials that are produced by [ERISS] are vetted by Environment Australia. The
Supervising Scientist has acted as a lobbyist at World Heritage Committee
meetings for the Australian Government on the Jabiluka proposal.[115]
4.140
In contrast the Supervising Scientist, Dr Arthur
Johnston, strongly defended the independence of the OSS. While he acknowledged
that under Section 7 of the Environment Protection (Alligator Rivers Region)
Act 1978 (EPARR) the OSS reports to the Minister for the Environment and is
subject to the direction of the Minister, he stated that the Act also required
that the OSS report to Parliament any direction given by the Minister and that
any report that results from that direction must be tabled in Parliament.
‘This,’ he said, ‘is a safeguard that essentially ensures the independence of
the advice given by the Supervising Scientist.’[116]
4.141
In relation to the Supervising Scientist’s April
1999 report to the World Heritage Committee, Dr Johnston also assured the
Committee that:
This report was finalised by the Supervising Scientist without
it being seen by the Minister or his staff; and significantly, no request was
received by the Supervising Scientist from the Minister or his office to see
the report prior to its being submitted to the [World Heritage] Committee.[117]
4.142
This Committee accepts the assurances of the
Supervising Scientist about his statutory independence and the requirement in
Section 36 of the EPARR Act for Ministerial directions to be reported to
Parliament. It also accepts the assurances that his report to the World
Heritage Committee incorporated no material at the request of the Minister.
Professor Wasson has also praised the scientific quality of the bulk of that
report.[118]
However, these assurances do not mitigate broader concerns about the decline in
the power, resources and independence of the OSS.
4.143
While it would seem proper (and valuable) that
the OSS should be required to conduct studies and suggest measures for
environmental protection at the recommendation of government, the Committee
believes that it is highly inappropriate that the OSS remain an office within
the Commonwealth Department of Environment and Heritage, or that it work
closely with government in campaigning for, or promoting, policy decisions.
4.144
A broad range of evidence to the Committee has
shown that the numerous statements by the OSS about the environmental safety of
the mine conflicts with known scientific and project uncertainties. For
example, its comment in the April 1999 report that there was a ‘very high’
degree of scientific certainty that the natural values of Kakadu National Park
were not threatened, was based on the assumption that ERA will develop an
option (100 per cent underground disposal of tailings) which the company has,
in fact, expressed considerable reluctance to pursue.[119] Further scientific investigation
of the proposed tailings treatment method and disposal remains outstanding, and
final approval of the JMA remains contingent on the submission and assessment
of these studies. Broad political assertions in the face of such uncertainties
dramatically erode the credibility of the Office of the Supervising Scientist.
4.145
Similarly, the Committee feels that the OSS, in
arguing that many outstanding environmental issues (as identified by Wasson et
al and the WHC mission) could be resolved at the later design stage rather than
prior to approval, is taking on an inappropriate role which compromises its
independence. The OSS further contended, to the WHC, that this deferral of
design and investigation did not prevent it from reaching a conclusion that
‘there were no insurmountable obstacles that would prevent a design being
achieved that would ensure the highest level of environmental protection in
Kakadu National Park’.[120]
4.146
These are highly tendentious policy arguments
which have been strongly criticised by many witnesses, and should properly
remain for executive government to defend. Making such arguments draws the OSS
into defending an incremental approvals process which has been strongly
criticised, and which disregarded the continuing possibility that there might
never be an environmentally acceptable JMA option proposed by ERA.
Recommendation 7
The Committee recommends that the Office
of the Supervising Scientist be removed from the corporate structure of the
Department of Environment and Heritage and reconstituted as an independent
regulatory authority of uranium mining in the Alligator Rivers Region. It
should retain a carefully defined capacity to receive references from, and
provide advice to, the Environment Minister and make recommendations. The
funding of the Office of the Supervising Scientist should be increased so that
it is able to conduct its own monitoring and research.
The Government’s Decision-Making
4.147
Serious concerns were expressed to the Committee
about the quality, timing and appropriateness of Government decisions to assess
and approve various stages of the Jabiluka project. These concerns included:
- Inappropriate levels of assessment applied to the various
Jabiluka Mill Alternative proposals;
- Whether Ministerial decisions reflected environmental
assessments;
- The precipitate approval of mine construction before the Jabiluka
Mill Alternative had been assessed and approved;
- The politicisation of decision-making to avoid a change of
government blocking the project’s development; and
- Whether Government conditions placed on the mine’s construction
and operation can be adequately enforced.
Level of Assessment
4.148
Many of the submissions to the Committee
identified problems with the level of assessment applied to the Jabiluka Mill
Alternative and, in particular, to the resubmission by ERA of proposals to
either put 100 per cent of the tailings underground or a portion in surface
built pits. These concerns appeared in submissions by The Wilderness Society,
ACF, Friends of the Earth, the ANU scientists, the NLC and the Gundjehmi
Corporation.
4.149
The insistence of the former Supervising
Scientist, Dr Peter Bridgewater, that the JMA be subject to a full EIS has been
cited above (3.23). In evidence, Dr Johnston explained that Dr Bridgewater had
used ‘a loose phraseology’ and that his desire was for ‘a public process ...When
[the assessment] was a PER rather than an EIS, that in his view was
sufficiently a public process, and that was the advice he subsequently gave to
the Minister’.[121]
4.150
However, some witnesses put the view that the
requirement for an assessment of the JMA as a PER, in isolation from the RMA,
fractured the process of assessment to the detriment of the EIA process. The
Environment Centre of the Northern Territory (ECNT) submitted that the JMA
required a full EIS because it involved the consideration of issues wider than
those established in administrative guidelines for a PER, which was to be used
‘where impacts are expected to be focused on a restricted number of specific
issues’. It cited the author of Environmental Law in Australia,
G. M. Bates, as saying that ‘a PER would be directed where it is
considered that ... the issues or impacts are likely to be limited ... An EIS would
be expected where the issues are more wide ranging, the impacts potentially
great, and the issues themselves requiring clarification.’[122]
4.151
The Committee accepts this view. It is clear
that the JMA will have a far greater impact on the Jabiluka site and
surrounding area than the RMA. Similarly, the large number and scope of the
requirements following the RMA EIS suggest that many issues remained to be
clarified. In the Committee’s view, a new proposal involving the construction
of milling facilities and tailings disposal on site, located inside a World
Heritage Area and adjacent to an identified sacred site complex, and which has
potentially significant social impacts given the hostility and bitterness of
Traditional Landowners, meets the definition of a project requiring a full EIS.
The Public Environment Report demonstrates that the surface disruption is far
greater, with long-term ore stockpiles and tailings disposal plans creating far
greater challenges for managing run-off containment and rehabilitation
strategies.
4.152
A further concern about the reduced level of
assessment for the JMA is that it creates a further tendency and rationale for
the downgrading of subsequent assessments as new options are proposed. This in
particular occurred with the requirements for further assessment of the JMA
tailings disposal options. ERA is required both to conduct further studies of
the cement paste technology before the 100 per cent option can be implemented,
or, if it wishes to pursue its preferred 50‑50 option, to seek new
guidelines for further assessment of that proposal. Further redesign and
scientific study is to be assessed by the Supervising Scientist and the
Northern Territory Government.
4.153
While the ANU scientists did express their
confidence in the abilities of the Supervising Scientist, evidence cited above
(4.138-4.146) also reflected concerns about the independence of the OSS and the
regulatory record of the Northern Territory Government. Statements by the OSS
to the World Heritage Committee, to the effect that there are ‘no
insurmountable obstacles that would prevent a design being achieved that would
ensure the highest level of environmental protection’, appear to have prejudged
the issues they are being relied on to adjudicate.[123] The Committee believes that,
at the very least, any further assessment of the tailings disposal options at
Jabiluka should be a public process. It should enable expert peer review by
scientists, and also require an assessment of the cultural impacts of creating
new landforms with excavated waste rock.
Recommendation 8
The Committee recommends that should the project proceed,
further assessment of Jabiluka tailings management, waste rock disposal,
run-off containment and radiological protection measures be subject to a public
process at the level at least of a Public Environment Report, and that such
revised proposals be subject to peer review by scientists.
The Timing and Appropriateness of Approvals
4.154
In evidence to the Committee, Professor Wasson
complained that ‘the assessment of the entire Jabiluka project has been
piecemeal and very difficult for non-specialists to understand. I think this is
a dreadful outcome for such an important area ... we remain concerned, therefore,
that possible damage to Kakadu is a reality because a complete risk assessment
has not been completed’.[124]
He continued that:
there was a lot of change on the run. A lot of policy decisions
seemed to be being made on the run – for example, the below ground disposal
requirement by Senator Hill was made only two weeks before the last federal
election. We are concerned that there appears to have been somewhat indecent
haste in some of the these matters before the evidence was in.[125]
4.155
In his submission to the Committee, Professor
John Mulvaney argued that the decisions of the Environment Minister to approve
the Ranger Mill Alternative and Jabiluka Mill Alternative were ‘premature and
counter to the provisions of Section 30 of the Australian Heritage
Commission Act 1975’ because:
[he] did not have before him, a complete database of the
cultural features of the Jabiluka area, or the consequences of dust or vibration
upon the art and cultural sites in the mine vicinity ... A cultural management
plan, and scientific tests re dust and vibration should have preceded not
followed mining impact under the provisions of the heritage legislation.[126]
4.156
Under Section 30(3) of the Act the Minister is
required to obtain the advice of the Heritage Commission prior to taking any
actions affecting places registered on the National Estate. The Secretary of
the Department of the Environment and Heritage told the Committee that that
advice had been sought but could not undertake to provide a copy of that advice
to this Committee.[127]
The problem of incremental decision-making
4.157
The Australian Conservation Foundation (ACF)
expressed serious concerns about the ‘incremental’ nature of the approvals
given by the Commonwealth:
This is perhaps the most insidious of the ways the approvals
process has been manipulated. In theory the final approval for the Jabiluka
mine has not been given, yet we have extensive underground works – right to the
edge of a known sacred site – and extensive surface works and industrial
infrastructure. All have been sanctioned by a series of Ministerial decisions a
number of which are the subject of ongoing legal action in the Federal Court.[128]
4.158
The ACF argued that precipitate approvals were
being given from the earliest stages of the project. When the Traditional
Owners refused permission for the Ranger Mill Alternative, ERA was forced to
submit a ‘change in scope’ application to the Northern Land Council (NLC) for
approval to proceed with the JMA. Even after that was refused by the NLC on
behalf of the Mirrar, and the NLC was forced into adjudication under Section
3.2(h) of the 1982 Agreement, the Northern Territory Government approved the
construction of a security compound around the mine site.[129]
4.159
Of great concern to many witnesses, including
the ACF, Friends of the Earth, The Wilderness Society, the Northern Land
Council, the ANU scientists and the Gundjehmi Corporation, were the subsequent
approvals given by the Northern Territory Government to the construction of the
access portal, decline and other works before the JMA assessment process had
even been concluded. This decision flowed from the indications given by Senator
Parer and Senator Hill that aspects of the project allegedly ‘common’ to the
RMA and JMA could proceed. The ACF commented that:
At this stage ERA had no legal mining project because the
remote mill option had been rejected and the on site milling at Jabiluka had
not been approved under the Environmental Protection (Impact of Proposals) Act.[130]
4.160
The Committee notes that this concern remains
current. A final milling and tailings disposal option at Jabiluka has still not
been finally developed or approved, and is the subject of continuing scientific
uncertainty. Meanwhile the construction of the decline has been completed and
ERA is proceeding with further drilling and exploration of the ore body prior
to mining.
The politicisation of decision-making
4.161
The ACF further argued that the timing of
Government decisions has been deliberately aimed at thwarting possible future
courses of action:
Decisions related to the disposal of tailings were being made in
the lead-up to the 1998 federal election. There was therefore considerable
pressure being exerted on the Government to make a decision about the mine.
There was evidence that the Liberal Government could lose power and that the
Labor Party had a no new mines policy. Therefore if the approvals for Jabiluka
were made prior to the election and if Labor won they could be bound to allow
the mine to continue ... The approvals process has been based on political
expediency and blatant moves to facilitate a timetable being set by the mining
company.[131]
4.162
It is obviously difficult to prove such an
allegation conclusively. However the Committee concurs with the views of
witnesses such as Professor Wasson that the 100 per cent underground tailings
option had not been fully assessed before conditional approval for the JMA was
given. That the mere appearance of ‘political expediency’ was allowed to occur
indicates a serious failure of decision-making. The facts of this issue will
probably remain in dispute, but if the allegation were to be true it would
indicate a gross perversion of the EIA process.
4.163
The ACF concluded by describing how this ‘incremental’
approach to approvals has damaged the integrity of the EIA process:
Incremental decision-making has a number of impacts. It places
the Traditional Owners under increasing pressure as they see their demands
regarding the proposal overridden and ignored. Incremental decision-making also
strengthens the resolve of the proponents of the mine as it gives them a legal
basis to challenge future decisions to prevent the mine or seek compensation
for work already carried out, even if that work has been done with the full
knowledge that they do not have final approvals.[132]
Did assessments support approvals?
4.164
Many witnesses raised the problem of whether the
environmental impact assessments provided adequate scientific certainty and
assurances to support the extension of Government approvals. These concerns
have been particularly acute regarding the approvals ventured for the JMA.
4.165
This report has already discussed the
substantial scientific uncertainties which attended the JMA proposals for the
manufacture of cement tailings paste and its disposal partly in the surface
pits. Departmental recommendations would also then have to take into account
other objectives of the assessment, such as the discussion of potential social,
cultural and World Heritage impacts.
4.166
In its assessment of the Jabiluka Mill
Alternative PER, Environment Australia expressed considerable caution about
allowing the project to proceed. It is significant that its view took account
of the all the major issues – environmental, social, and cultural - raised
during the EIA process:
it could be reasonably argued that these key aspects of the
proposal [milling and tailings disposal] are not sufficiently advanced or
justified to allow either of the JMA proposals to proceed at this time. Such a
position is based on the importance and sensitivity of the area within which
the Jabiluka lease is located and a conservative precautionary approach in the
face of the scientific uncertainty associated with important aspects of the
JMA, including the degree of social and cultural impact on the Traditional
Owners and other Aboriginal people, whose perception of harmful impacts of
uranium mining on the biophysical environment may be as significant as any
scientifically measurable impact (or lack thereof) on these attributes.[133]
4.167
As discussed in the section above (4.15-4.41)
dealing with tailings disposal, the Committee feels that, notwithstanding the
Environment Minister’s reluctance to grant approval for the 50-50 disposal
option, it was also the case that insufficient evidence was available either to
him or to his Department to approve the JMA on the basis of a complete return
of tailings underground.
4.168
The Committee feels that it is of great
significance that Environment Australia’s caution regarding the JMA referred also
to the lack of knowledge about the ‘degree of social or cultural impact’ on
Aboriginal people in the area. The Gundjehmi Corporation, the Northern Land
Council, the ANU scientists and others have also offered the view that cultural
heritage issues had been inadequately addressed in the EIS and PER. As the
NTDLPE and Environment Australia’s EIS assessments show, concerns about the
potential social impact of the mine’s approval were profound. The Kakadu Region
Social Impact Study was an inadequate vehicle for the consideration of these
concerns and was specifically prevented from dealing with the potential impact
of Jabiluka itself. No dedicated social impact study has been commissioned. The
Committee believes that the concerns about the mine’s social and cultural
impact were alone of such significance as to prevent the mine’s approval at
that time.
4.169
In evidence, and in its recent report to the
World Heritage Committee, the Supervising Scientist put the view that many of
the outstanding run-off and tailings disposal issues did not need to have been
resolved at the EIS stage but could be deferred to the detailed design stage of
the project; that is, after formal approvals had been given:
It was our view that, while in some cases there were issues of
detail that would need to be pursued by the Supervising Scientist and by the NT
regulatory authorities at the detailed design stage, there was adequate
evidence that an appropriate final design was achievable that would ensure the
protection of the World Heritage values of Kakadu National Park.[134]
4.170
However, Professor Wasson argued that the
location of Jabiluka within a World Heritage area required that the mine’s
environmental technologies should have been fully developed at the EIS stage:
for a project with the potential to impact on a World Heritage
property the highest possible standards of assessment should be applicable at
the EIS stage, not just in the detailed design stage. Let us be very clear:
mining in the midst of a World Heritage area is not normal ... Therefore, to
apply to a mine site in the midst of a World Heritage area the same standards
of protection and process as we do to any other site seems to miss the point of
the very high values that are attributed to a World Heritage property by the
international community.[135]
4.171
The ANU scientists further contended that the
Supervising Scientist’s April 1999 report to the World Heritage Committee
confirmed their view that the previous assessments of the EIS and PER ‘included
key technical errors and omissions, principally related to hydrology, to
planned waste disposal and conservation values’. Professor Wasson argued
strongly that this pattern of decision-making had brought the key aspects of
the project into doubt:
We believe that much closer attention should have been paid to
some of these issues - that are now in the OSS report - at the EIS stage.
Personally, I find it worrying that the mine has continued to be developed
while the very important data on rainfall, flooding, the design of the tailings
disposal and all these issues to do with stability are still going on. We are
expected to believe a lot in good faith. A lot of the processes we have seen
thus far do not give us huge confidence. It is almost as if the cheque is in
the mail. Frankly, in our view, that is not good enough in a World Heritage
area.[136]
4.172
The Committee shares these concerns. It takes
the view that the manifest inadequacies in the assessments, relating not only
to the scientific uncertainties but also to the failure of the EIS and PER to
take adequate account of social and cultural impacts, ensured that ministerial
approvals were bound to be premature. The arguments of the OSS that
uncertainties would be resolved in the design stage fail to reflect the degree
of uncertainty which still attends the cement paste technology and the possible
resubmission of a 50-50 option for the disposal of tailings in surface pits and
underground at Jabiluka.
4.173
It is clear to the Committee that the serious
problems identified by the ANU scientists were only acted upon following the
concerns expressed by the World Heritage Committee’s report and the
international publicity that surrounded its mission. The Committee does not
accept the assurances that these very serious problems would have automatically
been resolved or addressed at a later stage. The Committee believes that
environmental impact assessment by government agencies should be improved to
ensure that the ‘key technical errors and omissions’ identified by the ANU
scientists do not recur.
Enforcement
4.174
Of significant concern to the Committee in this
inquiry has been the issue of whether the conditions placed on the mine’s
development and operation by the Government can be adequately enforced or,
indeed, whether the Government intends that they be enforced.
4.175
It was explained to the Committee that under the
EPIP Act and its administrative procedures, the requirements which the
Commonwealth Environment Minister wishes to be placed on the mine are forwarded
to the action minister, which at the time of the Jabiluka approvals was the
Minister for Resources and Energy, Senator Parer. The action minister must then
ensure that the suggestions or recommendations of the Environment Minister are
‘taken into account in relation to the action’.[137] This obviously creates legal
scope for the action minister to disregard or modify some or all of those
recommendations.
4.176
The Committee was also told that, under the
joint arrangement between the Northern Territory and the Commonwealth, the
recommendations would be ‘applied by the Northern Territory in the context of
its regulation of uranium mining under the UMEC Act and the NT Mining Act. They
would be enforced at a Commonwealth level by making compliance with the
requirements a condition of the grant of licences to export milled uranium (yellowcake).[138]
4.177
Friends of the Earth (FOE) pointed to the way in
which at least 22 of the original 77 conditions placed on the mine after the
EIS were ‘blunted’ by the insertion of words requiring ERA to ‘take into
account the intent of’ the recommendation, while the terms of a number of
others were altered. FOE also pointed out that the words ‘must comply with’
were used in relation to only two of the recommendations. They argued that:
‘the overall effect of the change in language between the Hill recommendations
and the Parer recommendations is undoubtedly to make the “77 stringent
requirements” less than binding and probably unenforceable.’[139]
4.178
One example is the Environment Minister’s
recommendation 56, which stated that ‘ERA must develop a cultural heritage management
plan in consultation with Traditional Owners, and EA and relevant NT
authorities, prior to project construction proceeding’. Minister Parer’s
recommendation, however, stated that: ‘In complying with Jabiluka ERs 3, 6 and
32, ERA must take into account the intent of recommendation 56’.[140] The question of the
enforceability of this recommendation has been thrown into relief by the
decision of the Northern Territory Minister for Resource Development to grant
construction permits for the decline and other works before the cultural
heritage management plan was completed. The Mirrar-Gundjehmi refused to
cooperate in the development of the plan while mine construction, including
blasting and drilling, continued. ERA refused to suspend construction in order to
complete the plan.
4.179
Evidence from representatives of the
Commonwealth Department of Industry, Science and Resources made it clear that
enforcement is dependent on ministerial discretion in the issuance of
export licences and on monitoring by the NT under the UMEC Act. The Department
told the Committee that while the Minister had written to the company advising
it of the conditions that would need to be met should it wish to export
yellowcake, ERA’s compliance remained a matter that the Minister would consider
when assessing applications for export permits. No formal legal conditions have
been or will be incorporated into an export licence.[141] In short, enforcement remains
a matter of ministerial discretion at a time far removed from the initial
construction of the mine.
4.180
The Committee was also told that the
Commonwealth did not take up the option recommended by Senator Hill (in his
letter to Senator Parer of 25 August 1998, indicating approval of the JMA) that
compliance ‘should be secured through legally binding arrangements – for
example, by requiring ERA to enter into a Deed, by implementing the
recommendations in conditions under Commonwealth or Northern Territory
legislation, or through a combination of the above’.[142] A Deed (which could have
given the Commonwealth the capacity to act on any breach) has not been sought
and reliance will instead be on the Northern Territory authorities. The effect
of this has been to remove the Commonwealth’s capacity to directly enforce the
requirements outside the ministerial discretion in the area of export licences.[143]
4.181
The Committee believes that this enforcement
regime is manifestly inadequate – far from the ‘legally binding’ regime
suggested by Senator Hill. It recommends that enforcement should be
strengthened by:
- drawing up a Deed between ERA and the Commonwealth incorporating
all those conditions so far suggested by the Minister arising from the EIS and
PER; and
- the direct attachment of conditions to the issue of export
licences to limit Ministerial discretion.
Recommendation 9
The Committee recommends that in the event
that the Jabiluka project proceeds, the enforcement regime should be
strengthened by the implementation of a deed between ERA and the Commonwealth
incorporating all the conditions put forward by the Commonwealth to this date,
along with those recommended by the Supervising Scientist following further
assessments. These conditions should also be made the explicit conditions of
the issue of export licences by the Commonwealth.
Should There be an Inquiry into the Jabiluka Project Under Section 11 of
the EPIP Act?
4.182
A key task of this Committee, as set out in
paragraph (b) of its terms of reference, has been to ascertain whether an
Inquiry under Section 11 of the Environmental Protection (Impact of
Proposals) Act 1974 is warranted in relation to the Jabiluka project.
4.183
A number of submissions to the Committee argued
strongly that the Jabiluka project, and the process of its approval, be
investigated by such an Inquiry. These included the Gundjehmi Corporation, Friends
of the Earth, the Environment Centre of the Northern Territory, the Jabiluka
Action Group, the Wilderness Society, the Australian Conservation Foundation,
and the Northern Land Council. The Committee also received over 320 submissions
from the public arguing for a Section 11 Inquiry. An Inquiry was opposed by
ERA, the Northern Territory Government, Mr Mark Sonter and the Commonwealth
Government.
4.184
The Committee has sought to make a careful and
measured assessment of the evidence available to it. It believes it has
identified serious flaws and deficiencies in the original environmental impact
statements, in the assessment process applied to the Jabiluka project, in
ministerial approvals, and in ongoing levels of assessment and regulation.
Significant uncertainties remain in relation to tailings disposal, radiological
protection and final project design. Crucial social and cultural impacts of the
mine on the Traditional Owners of the Jabiluka area have been poorly assessed
and, at worst, exacerbated by company and Government conduct. Australia has
failed to fulfil its international obligations to protect the World Heritage
values of Kakadu National Park. These problems, as they relate to both the
Jabiluka project and the legislative and policy frameworks that govern the
assessment and approvals process, require a full public Inquiry if they are to
be properly and fairly addressed.
Recommendation 10
The Committee recommends that in view of
the inadequate level of assessment applied to the Jabiluka proposals and the
premature decision-making of the Action Minister, the Minister for Environment
and Heritage establish a Commission of Inquiry into the Jabiluka project under
Section 11 of the Environment Protection (Impact of Proposals Act) 1974
(or under the equivalent provision of the Environment Protection and
Biodiversity Conservation Bill, when proclaimed).
Navigation: Previous Page | Contents | Next Page