Regulatory issues
3.1
This chapter examines concerns raised by submitters regarding the
transparency and independence of the regulatory regime, the adequacy of
community consultation during project development, and the provision of
information to interested stakeholders.
Ministerial oversight and decision-making expertise
3.2
As previously noted, prior to 2014 all proposed offshore oil and gas
projects in Commonwealth waters were required to be referred to the Minister
for the Environment for assessment and approval under the EPBC Act if they were
likely to have a significant impact on a Matter of National Environmental
Significance (MNES). Following the development of the 'one-stop-shop' model for
the approval of offshore oil and gas projects, this responsibility was
transferred to the National Offshore Petroleum Safety and Environment Authority
(NOPSEMA).[1]
3.3
The industry supported the oil and gas regulatory framework with Chevron
stating that it welcomed NOPSEMA's regulatory regime as 'it adds independence
and rigour to the process'.[2]
3.4
Several submitters raised issues with the removal of departmental and
ministerial oversight of the approval process. The International Fund for
Animal Welfare (IFAW) expressed concern that 'there is no longer any
ministerial accountability for such decisions now that sole assessment and
approval powers have been given to an unaccountable arms-length body'. Further,
it stated that 'it is not appropriate that decisions about proposals that could
have catastrophic impacts...are taken without proper political accountability'.[3]
3.5
The Humane Society International (HSI) also stated that it has
'consistently opposed the devolution of responsibility for the environmental
assessment and approval of offshore oil drilling projects in Commonwealth
waters'. It considered that 'ministerial accountability and in particular
confirmation of the role of the Federal Environment Minister with regard to
threatened species must be restored.'[4]
Similarly, the Australian Marine Conservation Society (AMCS) stated that it:
...is concerned about the lack of ministerial accountability
regarding threatened species impacts and other impacts and the lack of full
public access and consultation in the approvals process. NOPSEMA has been the
sole assessor and approver of offshore oil and gas activities since March 2014,
[and] there is no longer any ministerial accountability for such decisions and
public access and transparency has been lost in the system.[5]
3.6
Dr David Ellis, an environmental consultant, expressed concern that 'with
no Commonwealth Government ministerial oversight and the establishment of a relatively
new regulator NOPSEMA, the Australian public and international community are
yet to see how this regulatory body begins to attempt to seriously and
scientifically assess the potential impacts of BP’s proposed project'.[6]
3.7
Mr Lyndon Schneider, The Wilderness Society, commented that the US
National Commission which investigated the Deepwater Horizon disaster 'spoke...damningly
about the poor level of political oversight and a failure by, if you like, the
political class to properly regulate and manage the risks around this industry.
They talked a lot about a national interest'. Mr Schneider went on to note
that:
A national interest in this instance involves both the
national interest around the use of resources, which is the more traditional
one, but a national interest also involves the idea of making decisions that
are to the benefit of the wider community and managing risk. I think an
argument that would say, 'Leave this to the experts,' when we are dealing with
Commonwealth of Australia waters, we are dealing with a resource that is owned
by the Australian people, and we are dealing with an environment that is
fragile—of course there needs to be political oversight. The needs to be very
direct political oversight. These decisions are being made around resources
owned by the Australian community.[7]
3.8
Mr Stuart Smith, Chief Executive Office, NOPSEMA, in acknowledging
concerns raised, stated that:
The idea of having a minister making the decision on environmental
factors has some merit, but I also recognise that that sort of approach brings
with it the possibility that factors other than economic conditions would be
taken into account, and I do not think that is appropriate for determining
environmental impacts and the subsequent decisions arising from that. I think
an independent statutory authority is the appropriate way to go. Having said
that, I do see there being a role for elected officials in determining whether
an activity should proceed, and there is in the current process. The decision
to award acreage, for instance, is a decision made by the elected officials in
the federal government and the state and territory governments, and I think
that is quite appropriate. But, when it comes to decisions around the
environmental impacts and how those impacts should be managed, I think those
decisions should be made by an independent statutory authority such as NOPSEMA.[8]
3.9
In addition to concerns regarding the lack of ministerial and
departmental oversight, some submitters were concerned that the streamlining of
the approvals process could 'lead to a lowering of environmental standards' and
a failure to meet the standards of the Environment Protection and
Biodiversity Conservation Act 1999 (EPBC Act). [9]
Some submitters also raised concerns that NOPSEMA staff lack the expertise to
make assessments which support the objectives of the EPBC Act. For example, The
Wilderness Society stated that the 'devolution of environmental decision-making
powers to NOPSEMA is highly inappropriate' and that there is not the
appropriate EPBC Act expertise within NOPSEMA.[10]
It particularly noted that it had been advised by Mr Stuart Smith, Chief
Executive Officer of NOPSEMA that as at December 2015 there had not been a
transfer of staff experienced in making EPBC Act assessments from the
Department of Environment to NOPSEMA.[11]
3.10
However, Mr Cameron Grebe, Head of Division, Environment, NOPSEMA, told
the committee that NOPSEMA employs appropriately qualified staff including:
...28 environment specialists in the environment division, and
many of them have been there since we started in 2012—so for quite some time.
They cover a range of expertise. There are eight PhDs covering marine science,
eco-toxicology and cetacean biology—whales, dolphins and so on—and we have
arrangements in place and we do seek external advice if we do not have the
skills and experience necessary in-house.[12]
3.11
NOPSEMA submitted that its staff 'includes former Department of the
Environment employees, regulatory experts and other Australian and
international technical scientific experts with extensive knowledge of the
OPGGS Act and the EPBC Act regimes' which ensures that 'it has the capacity to
implement the necessary environmental safeguards'.[13]
NOPSEMA also noted that it has 'systems in place to ensure that regulatory
staff obtain and maintain relevant competencies and that these competencies are
demonstrated prior to staff undertaking lead regulatory roles'.[14]
3.12
In addition, Mr Smith commented that the 'current arrangements have some
substantial strengths, and I think it can be argued that it is actually
superior to many other environmental approvals processes'.[15]
NOPSEMA's environmental standards
3.13
Prior to the endorsement of NOPSEMA's environmental authorisation
program by the Minister for the Environment in 2014, a number of environmental
groups participating in the consultation process[16]
expressed their concerns with the streamlined process. HSI stated in its
submission to this inquiry that their concerns, initially expressed during that
consultation, remain relevant. Specifically that 'the decision to allow NOPSEMA
to assess environmental impact has enshrined a less rigorous process for
assessment and approval of offshore activities that impact nationally
significant matters of environmental significance into law'.[17]
3.14
Similarly, EDOs of Australia provided the committee with its original
2013 submission provided during the consultation process[18]
and noted that it remains concerned that the NOPSEMA assessment and approval processes
do not equate to the regulatory requirements under the EPBC Act.[19]
In particular, it is concerned that the OPGGS Environment Regulations 'do not
mirror key components of the EPBC Act and are therefore unlikely to adequately
regulate impacts associated with offshore petroleum activities on Matters of
National Environmental Significance'.[20]
3.15
The Wilderness Society submitted that NOPSEMA's objective-based
regulatory approach is 'an entirely inappropriate framework for the protection
of environmental values'. It stated that 'even if risks and impacts can be
managed to ALARP ("as low as reasonably practical") levels, this will
not necessarily represent an appropriate protection of MNES as defined under
the EPBC Act'.[21]
It also submitted that the OPGGS Regulations are 'inadequate to enable an
assessment of cumulative impacts and risks' arising from multiple offshore
petroleum ventures in the Great Australian Bight.[22]
3.16
The Wilderness Society further criticised NOPSEMA's regulatory approach
by stating that the OPGGS Regulations 'do not provide an appropriate range of
assessment process options of complex and controversial' offshore proposals. In
particular, it noted that under the EPBC Act, the Minister for the Environment
'could decide to assess projects under a Public Environment Report or Public
Inquiry assessment process' however under the OPGGS Regulations, a
'non-transparent process of one-size-fits-all appears to be the only assessment
option'.[23]
3.17
In responding to criticisms of its environmental approvals process, NOPSEMA
noted that it is subject to a range of governance controls including
parliamentary scrutiny, ministerial policy direction and independent statutory
review.[24]
In particular, it stated that it has been:
...subject to an independent operational review of its
regulatory performance every three years. It has also been subject to a review
of its environmental management performance under the endorsed EPBC Act Program
after the first 12 months of operating under this arrangement. Both reviews
were most recently completed in 2015 and the reports from these reviews are
public documents.[25]
3.18
The 2015 Operational Review found that NOPSEMA is delivering the levels
of environmental protection required under the EPBC Act, and that it will
continue to do so into the future. Though it did not make recommendations, it
identified a range of opportunities to improve communication and information
sharing between NOPSEMA and the Department of the Environment and Energy.
NOPSEMA stated that it has implemented or is implementing a number of measures
to facilitate the continuous improvement of the EPBC Act Program.[26]
3.19
NOPSEMA also explained that its environmental and approval processes
contain the same essential elements as those of the EPBC Act. The key point of
difference being that NOPSEMA is required to evaluate all environmental impacts
and risks (including those to matters protected by the EPBC Act), and identify
appropriate control measures to manage and monitor those impacts.[27]
Mr Smith told the committee that:
...the environmental regulations we administer do not just
focus on matters protected under EPBC Act, the national environmental
significance. It is all impacts and risks. If they are not protected and if
there are unacceptable impacts or risks to those parts of the environment, they
will not proceed, and that includes social and economic features in the
environment as well.[28]
3.20
NOPSEMA rejected suggestions[29]
that its standards do not enshrine in legislation the same protections offered
by the EPBC Act. Mr Grebe told the committee that a range of legislative
amendments made in 2014 as part of the streamlining process 'actually enshrined
things such as the principles of ecologically sustainable development, the
precautionary principle and the protection of matters protected under Part 3 of
the EPBC Act into our legislation'.[30]
Mr Grebe concluded that:
The differences that appear in the process...are that, unlike
the EPBC Act, the proponent does not get a choice as to whether they need to
seek our approval or not. Under the EPBC Act there is a requirement for the
proponent to refer if they believe, as it is a self-identification process,
that it is likely to have a significant impact on a matter of NES, national
environmental significance, as defined under the EPBC Act. Under our system,
the simple fact is that they do not get a choice. Every single activity that is
defined as a petroleum activity must get our approval before it can proceed.[31]
3.21
In response to suggestions that the approvals process should be amended
to require the approval of the Department of the Environment, the South
Australian Government submitted that re-introducing overlapping powers for the
approval of offshore petroleum activities:
...would be a retrograde step for the efficiency of
objective-based legislation in Australia, as it would inevitably add
unnecessary duplicative steps within the approvals process. Indeed, it is the
South Australian Government's view that NOPSEMA has the necessary capabilities
to be the nation’s trusted regulator and approval authority for upstream
petroleum operations in Commonwealth waters.[32]
3.22
Likewise, Santos Ltd, as a leading oil and gas producer regularly
engaged with NOPSEMA's approvals process, told the committee that it:
...is of the view that this streamlining has removed
unnecessary duplication between two sets of legislation without compromising
environmental outcomes. Streamlining does not mean the requirements of the EPBC
Act are disregarded, but rather that the Environment Minister has determined
that NOPSEMA processes, through the Environment Plan assessment procedure, satisfies
the rigorous EPBC Act requirements. The titleholder is still required to
demonstrate, within its Environment Plan, how it will address (among other
things) the potential impacts and risks to matters of national environmental
significance, just as it was obliged to do before streamlining.[33]
Adequacy of consultation processes
3.23
The success of a regulatory regime in part, relies on the regulator
having the confidence of both stakeholders, and the public. Public consultation
is an integral part of many regulatory regimes, including the NOPSEMA approvals
process for offshore petroleum ventures. Though there are many models for
public consultation—including regulator-led public consultation, and
proponent-led public consultation, it is generally intended to improve
transparency, increase efficiency, and promote public involvement in policy
making.
3.24
As noted earlier, offshore oil and gas proponents are required to
identify and consult with relevant persons in the course of preparing an
Environment Plan. In relation to the EPBC Act and consultation, the Department
of the Environment and Energy noted that:
When the minister endorsed the NOPSEMA program the
consultation requirements as mandated in that program were deemed to be
sufficient in order to undertake a strategic assessment in relation to NOPSEMA...basically
the requirement is as long as the consultation requirements set out in that
document are met then for the purposes of the EPBC Act that would be called
compliance.[34]
3.25
A number of submitters were generally critical of the NOPSEMA's
proponent-led stakeholder consultation model while others were more
specifically critical of the consultation carried about by BP in the course of
preparing its Environment Plan. The following sections canvass submitters'
concerns.
Consultation—general concerns
3.26
Submitters raised a range of concerns with the level and type of
consultation required under NOPSEMA's approvals process. These included
concerns that proponent-led consultation is inadequate or inappropriate, and
that insufficient information is provided to the public and interested
stakeholder groups as well as difficulties of stakeholders in accessing and
understanding the system. In this regard, the South Australian Oyster Growers
Association (SAOGA) provided the committee with evidence of its interactions
with regulatory process.
3.27
SAOGA commented that it had been involved BP approval process for two
years and that:
We became very frustrated with the process for a couple of
reasons. Firstly, we found the consultation process frustrating from the point
of view that we did meet with BP on a number of occasions, however we did not
feel that the points that we thought were important to consider were being
considered. It took quite a long time to get feedback and information back. The
second point was that we also struggled with the NOPSEMA process. We found it
difficult to work out how that worked when you were always directed to ask your
questions to the drilling party of BP, and they could say, 'No, we're not going
to provide that information,' and we kind of had nowhere to go. So we did not
really understand how that worked.[35]
3.28
IFAW pointed to concerns about public consultation and submitted that:
...the new system leaves consultation to be dictated by the
proponent oil and gas companies and has no direct mechanism for public
consultation, with information supplied under the new system frequently very
scant and mostly supplied after a decision has been made and even then only in
summary form.[36]
3.29
IFAW also expressed disquiet with the apparent 'limited public access to
important information determining decisions'.[37]
This sentiment was echoed by the AMCS which stated that:
The NOPSEMA system abdicates the consultation process to
proponent oil and gas companies and has no direct mechanism for public
consultation. The system also fails in transparency in that little or no
information is provided by NOPSEMA about the decisions it makes i.e. approvals
are given or rejected without any reasoning/justification provided to the
public. Similarly little information is provided publically prior to decisions
being made to facilitate public interest input.[38]
3.30
The Wilderness Society submitted that 'no clear minimum requirements
[for consultation] are outlined or properly enforced under the NOPSEMA
regulation'. It went on to describe consultation processes as 'deeply flawed'.[39]
Similarly, the Conservation Council of South Australia stated that:
The nature of the consultation process is that NOPSEMA tell
BP to do 'sufficient consultation'. So what is defined as sufficient? We are
telling the Australian public and this Senate committee that we believe this
consultation is insufficient.[40]
3.31
The Environmental Defenders Office SA (EDO SA) was concerned that there
are limitations on participation placed on both the public and environmental
advocacy organisations. EDO SA noted that NOPSEMA's guidelines provide for a
broad interpretation of the concept of a 'relevant person' for titleholders,
and guidance on how people and organisations may assert their relevance.
However, it submitted that 'it is unjust that the titleholder determines the
relevancy status of members of the public, as opposed to members of the public
having an unfettered right to information as is the case under the EPBC Act'.[41]
3.32
EDO SA stated that it is concerned that by allowing titleholders to
determine relevancy, affected people and organisations may not be involved in
the consultation process. It submitted that 'any person should be allowed to
comment' as this would improve accountability.[42]
3.33
In addition, EDO SA raised concerns that relevant persons are only
required to be provided with 'sufficient information', rather than the
Environment Plan, to make an assessment of the potential impact on their
interests. EDO SA submitted that:
Given the scale of some offshore projects and possible
serious environmental and other impacts, it is clearly in the public interest
that full and complete information about such projects is disseminated as
occurs with proposals assessed under the EPBC Act.[43]
3.34
NOPSEMA, in responding to concerns regarding the adequacy of
consultation requirements, assured the committee that all Environment Plans
submitted for assessment and approval 'must demonstrate that appropriate
consultation with relevant state, territory and Commonwealth agencies and
person or organisations whose functions, interests or activities could be
affected by the proposed activity has been undertaken by the titleholder'. This
demonstration includes a range of criteria such as the provision of a report of
any objections or claims made about adverse impacts, and a statement responding
to each objection and claim. The Environment Plan must also include provisions
for ongoing consultation with affected persons.[44]
3.35
Mr Grebe told the committee that in contrast under the EPBC Act, there
is no specific requirement or prescription about the type or degree of
consultation a proponent must engage in, prior to making an application. Mr
Grebe further noted that under the NOPSEMA process, 'the regulations set out
detailed requirements about who must be consulted with and how that
consultation at a principle level should be conducted. That is quite a unique
feature of an environmental approvals process'.[45]
Adequacy of BP's stakeholder engagement
3.36
As noted earlier, criticisms of inadequate consultation were both
general, and specifically directed against BP. Submitters who were concerned
with BP's consultation process raised a number of issues including that BP
did not consult with all stakeholders. Concerns were also raised regarding BP's
failure to release sufficient information to allow for informed public
consultation. In particular, BP was criticised for not releasing its oil spill
modelling prior to, or during its public consultation phase, and for not
releasing its complete Environment Plan.
Release of information
3.37
Access to information is important in ensuring open, accountable and
transparent governance. Further, public access to information is an
internationally recognised procedural right in environmental and planning law.
This right manifests in a variety of ways including: the right to be notified
of an opportunity to participate in in decision-making processes; and the right
to access and comment on proposals. Access to information is a critical
pre-cursor to exercising other rights such as the right to challenge government
decisions in court.[46]
3.38
Submitters highlighted the importance of information being available to
the public in order to make an informed assessment of the risks associated with
offshore ventures. Mr Peter Owen from The Wilderness Society told the committee
that 'consultation is...about being open and transparent with the community as to
the magnitude of the risk that is potentially being imposed on that community and
how that risk is being dealt with'.[47]
However, submitters stated that in the case of BP's consultation process,
stakeholders were not provided with sufficient information to make an informed
view of the potential risk.
3.39
Ms Jessica Lerch from The Wilderness Society commented that her
organisation had faced difficulties in obtaining 'basic information' from BP
which would be required in order to fulfil their function as relevant persons
under consultation guidelines. Ms Lerch stated:
...it is very hard to form any kind of legitimate and credible
opinion on how a project might affect your organisation and your members'—in
our case—functions and interests in the absence of information like the worst
credible potential impact of an oil spill in the region, which we were unable
to get from BP until, somewhat strangely, it was suddenly provided in
retrospect almost at the eleventh hour of their latest assessment process.[48]
3.40
Similarly, the Clean Bight Alliance Australia (CBAA) told the
committee that it has 'been advocating for full public disclosure of industry
commissioned oil spill modelling and emergency response information' since its
inception in 2014. It stated that as a 'small local group based in a remote
area we only have access to information made readily available within the
public record' and as such, the 'lack of transparency provided to the public'
has an impact on their ability to adequately assess the risks associated with
offshore petroleum ventures.[49]
3.41
CBAA went on to acknowledge that though BP was prepared to meet
with several members of its organisation, it concluded that 'overall the
information provided has been inadequate and our requests for BP's full
environmental plan and oil spill modelling and emergency plan [were] declined'.[50]
3.42
Mr Lyndon Schneiders, The Wilderness Society, stated that in order for
BP to operate in the Great Australian Bight, it needed to do so 'with the
maximum confidence from the regional and local communities, and the Australian
community, that something will not go wrong'. Further:
...an environment that is clouded with secrecy, where core
documents are not on the public record and are inaccessible to the public
record through things like FOI, is just bad communications management...The
issues around transparency are fundamental here. Getting all the information on
the table is going to be critical, not just for decision makers, but also for
communities potentially affected by these developments and what happens.[51]
3.43
Ms Warhurst from the Conservation Council of South Australia also commented
that it had requested 'in the earliest consultation meetings' oil spill
modelling but that 'BP have consistently refused to release the basic oil spill
modelling'.[52]
Similarly, The Wilderness Society submitted that since January 2014 it had
repeatedly asked BP to release detailed worst case oil spill modelling for its
proposed exploration program. It stated that:
This modelling is necessary for a full assessment of the
potential impacts a catastrophic oil spill in the Great Australian Bight could
have on the threatened and migratory species, the values of the marine
environment and the social and economic values of the region.[53]
3.44
In its April 2016 submission, The Wilderness Society stated that BP
failed the 'transparency test' because 'there is little relevant public
information available regarding the potential worst case spill risk' arising
from BP's proposed drilling program. The Wilderness Society submitted that this
relevant information included:
...the proposed location of the four wells, the total well
depths (both the water depth and further well depth into the seabed), the
potential well pressures, and potential well flow rates or times when each well
is expected to be drilled.[54]
3.45
As noted above, when BP submitted its Environment Plan to NOPSEMA for approval
in 2015, it had not yet released any oil spill modelling to stakeholders or the
public. As a result, 'The Wilderness Society commissioned independent, expert
oil spill modelling to enable an understanding of the likely impacts of a
significant oil spill from BP’s Great Australian Bight drilling area'.[55]
Many submitters made reference to this oil spill modelling, and utilised it in
formulating their concerns regarding the potential impacts associated with BP's
proposed drilling.[56]
3.46
BP released its oil spill modelling in September 2016. Submitters raised
a number of concerns regarding BP's timing, and the details provided in the
modelling. For example, The Wilderness Society questioned:
-
why BP, after receiving numerous requests for this information
during public consultation, only chose to release its modelling and oil spill
response strategy at 'the eleventh hour of the assessment of its latest
Environment Plan';
-
how BP could have appropriately identified key stakeholders and
relevant persons in the absence of oil spill modelling. Further, how members of
the community could have self-identified as having interests which could
potentially be impacted, without this information being publicly available; and
-
why BP's 15 page publicly available response plan was lacking in
detail, especially when compared to similar documents provided by proponents
operating in the Arctic, which are over 400 pages in length.[57]
3.47
The Kangaroo Island Council submitted that in order to understand BP's
oil spill modelling conclusions, the data inputs for the modelling would be
required. As BP had not released these data inputs, the Kangaroo Island Council
stated that it 'therefore cannot accept the accuracy of the information
provided by BP'.[58]
3.48
Similarly, The Wilderness Society was critical of BP's decision to
withhold the assumed worst case flow rate used in its oil spill modelling
released in September 2016, and stated that this information is:
...critical to enable stakeholders, relevant experts and the
public to assess the adequacy of modelling. It is also needed to enable an
informed assessment of the full potential impact of a worst-case oil spill from
the Great Australian Bight - a critical factor in any assessment of the risk of
the proposal to the Australian community.[59]
3.49
BP, in its Environment Plan Summary agreed that the conclusions of oil
spill modelling and the response plans derived from it are important matters of
public consideration. It stated that it had provided information to
stakeholders regarding how the modelling was conducted, such as the thresholds used
and scenarios modelled. BP also submitted that it discussed key modelling
results with stakeholders.[60]
3.50
BP stated that the details of how the proposed drilling program would
incorporate lessons learned from the Deepwater Horizon incident were also
discussed during consultation meetings. Specifically, information regarding
prevention of loss of well control and technical solutions to a loss of well
control event, such as capping and containment and relief well planning were
provided.[61]
3.51
However, BP noted that due to the commercial sensitivities, model
inputs, which are of commercially competitive significance (including
hydrocarbon phase, volume and reservoir quality assumptions) would not be
released.[62]
Adequacy of consultation with
stakeholders
3.52
A number of submitters noted that not all affected stakeholders had been
consulted by BP. For example, Ms Kerry Colbung, Chief Executive of the
Aboriginal Lands Trust, stated that the Trust was concerned that there had been
a lack of consultation as it had not been identified as one of the key
Aboriginal stakeholders.[63]
3.53
Ms Colbung noted that three groups—the Far West Coast Aboriginal
Corporation, Yalata Aboriginal Community, and the Alinytjara Wilurara Natural
Resources Management Board—had been identified as stakeholders during
consultation. However, Ms Colbung stated that:
...anecdotally people have indicated that they are not aware of
the consultation that has taken place. Some groups have indicated that there
have been public forums. They serve their purpose, but I think, specifically,
when we deal with Aboriginal people we have to acknowledge that there needs to
be Aboriginal space and there needs to be Aboriginal-specific forums. It would
be great if there was the opportunity to allow Aboriginal space for Aboriginal
people to talk about the issues that impact on them, particularly given the
significance of this and the relevance to the responsibility that Aboriginal
people hold for all those knowledge systems and structures, as well.[64]
3.54
Ms Viriginia Leek, Outposted Solicitor from the Crown Solicitor's
Office, South Australia noted that despite the Aboriginal Lands Trust being the
land owner of the land adjacent to the Head of the Bight, there had not been a
direct approach for consultation from BP. Ms Leek stated:
There has not actually been an approach from BP as far as we
know to the lands trust itself. We looked back at all of the documents...What we
saw from the early identification of stakeholders was that there were
Aboriginal stakeholders identified but not specifically the Aboriginal Lands
Trust. I think there may be some misunderstanding about the role of the trust
in this space because it is actually the land owner of that land adjacent to
the Head of the Bight.[65]
3.55
The Aboriginal Lands Trust expressed its disappointment that it had not
been included in consultation during the environmental approvals process. It
concluded that:
Whilst BP identified Aboriginal stakeholders in the
consultation phase, it has failed to identify the Trust as a key stakeholder
for consultation and in doing so overlooked a major land holding body with a
mandate to foster the economic, social, environmental, cultural heritage
interests of all Aboriginal South Australians.[66]
3.56
The Australian Youth Climate Coalition and the Seed Youth Indigenous
Climate Network also submitted that:
Through independent consultation, we have determined that the
affected Traditional Owner groups have not been consulted by any company
wishing to drill or explore within the Great Australian Bight in any form.[67]
3.57
BP in its submission to the committee, provided the list of
organisations, including Indigenous, business and commercial, non-government
and community based organisations, it had consulted.[68]
Mr Matthew Doman, APPEA, provided a response to comments received relating to
BP's consultation process provided by witnesses at the committee's hearing of
16 November 2016. Mr Doman stated:
Frankly, I think there has been some misrepresentation of the
stakeholder engagement that BP has undertaken in relation to this project. I
understand that they consulted over 70 community groups in that process. In
fact, that consultation is detailed in their submission to this very inquiry.
So some of the discussion that occurred earlier today missed the mark on that.
However...we operate in an environment of increasing interest in the activities
of our industry whether it be onshore or offshore in South Australia, the
Northern Territory or anywhere else in the country. We have to stay on top of
our engagement with the community and make sure that the information flow is
there. We also face the task of countering misinformation wilfully spread by
many of the opponents of development. That gives us an increasing task. It is
something we are focused on and determined to do a better job of.[69]
Transparency of decision making
3.58
NOPSEMA, as the industry regulator was criticised by a number of
submitters for failing to release information provided to it by BP, and for
failing to publish the reasons for its decisions. The AMCS submitted that the
approvals system:
...fails in transparency in that little or no information is
provided by NOPSEMA about the decisions it makes i.e. approvals are given or
rejected without any reasoning/justification provided to the public. Similarly
little information is provided publically prior to decisions being made to
facilitate public interest input.[70]
3.59
Similarly, Mr Lyndon Schneiders, The Wilderness Society, told the
committee that:
The key thing we would want to see is the release of all of
BP's documentation between it and the regulator. It should be released to this
committee, at a minimum, and made public. The magnitude of the risk associated
with what has been proposed here is potentially huge, so the Australian public
deserves to see this documentation. They deserve to know and understand what
that magnitude of the risk is.[71]
3.60
NOPSEMA explained to the committee that, with the exception of
information it is required to release by law, it does not typically publicly
release information that has been provided to it as part of the deliberative
process.[72]
3.61
Mr Stuart Smith, Chief Executive Officer, NOPSEMA explained that NOPSEMA
is bound by legislation, including the Freedom of Information Act 1982
(FOI Act). Mr Smith noted that individuals or organisations can seek
information from NOPSEMA under the FOI Act, and that NOPSEMA is required to
abide by any decisions made in accordance with that Act. Mr Smith reiterated
that while information can be released, it is a matter of course that NOPSEMA
does not release proponents' proposals 'up-front' or during the deliberative
process. He explained that such a release:
...could influence the nature of the information that companies
provide and therefore diminish our capability to make an assessment. However, the
companies are required to release an environment plan summary at the end of the
process, and we will also release information about our deliberative process.[73]
Enhancements to the regulatory framework
3.62
In 2015, NOPSEMA identified that poor consultation practices in the
offshore petroleum industry can lead to negative impacts on individuals,
communities and organisations. Further, it identified that at the time, the
transparency of its decision-making processes did not meet community
expectations. The 2015 Operation Review, while endorsing NOPSEMA as an
effective regulator, also found that there was a need for NOPSEMA to continue
to build a social license to regulate by improving its capacity to engage with
stakeholders. The Review made two recommendations:
-
to develop a mechanism to provide greater transparency of
decision making and assessment to stakeholders; and
-
to continue to identify and implement cost effective and
tailored/targeted education activities that improve its capacity to engage with
stakeholders in order to share lessons, provide guidance and share new
information.[74]
3.63
In August 2015, NOPSEMA announced a Stakeholder engagement and
transparency work program to address these issues. In November 2016, it
published its official guideline on consultation requirements. This document
identifies NOPSEMA's position on key regulatory requirements for consultation
and identifies the factors that influence its decision-making.[75]
3.64
As part of the Stakeholder engagement and transparency work program,
it was also agreed that APPEA would prepare and publish a methodology for the
effective consultation with relevant persons.[76]
Dr Malcolm Roberts, Chief Executive Officer of APPEA, told the committee that
he agreed that the obligation for effective consultation rests on oil and gas
proponents but noted that the oil and gas industry is working with NOPSEMA to
'ensure that there is greater transparency', and in order to meet expectations
around public consultation.[77]
Dr Roberts informed the committee that APPEA, in conjunction with its members
is developing a:
...best practice framework which we expect will promote
effective, transparent and consistent consultation with the community. We will
soon be consulting with stakeholders on that framework, including some
important principles such as publishing the intent to commence environmental
plan preparation and related consultations as soon as possible, providing
clearer information to stakeholders about industry activities and the possible
impacts, ensuring sufficient time for stakeholders to review the information
and provide their thoughts, following a consistent approach to assessing the
merit of claims and objections made, and ensuring that assessment is provided
to stakeholders and included in environmental plans and submissions to NOPSEMA.
These practices are already being widely used across the industry, but we think
explicitly setting higher, more rigorous standards will ensure better
performance and continuous improvement.[78]
3.65
However, The Wilderness Society submitted that it considers it 'entirely
inappropriate' to contract APPEA to deliver revised consultation guidelines. It
noted that APPEA is 'behind on agreed timelines to undertake this work for its
industry regulator'. The Wilderness Society concluded that it:
...does not understand why NOPSEMA and/or the Department are
not sufficiently resourced or experienced to undertake this work and considers
NOPSEMA's outsourcing of such important guidelines to the peak body of the
industry it is supposed to be regulating completely unacceptable.[79]
3.66
NOPSEMA also identified two enhancements to the current regulatory
regime which would improve transparency and public consultation practices. The
first enhancement would be to include a public comment period at the point
where a company has completed its environment plan and the consultation for
that environment plan. Mr Smith, NOPSEMA, noted that this would go beyond the
existing arrangements and provide an opportunity for any parties which felt
they had not been consulted appropriately, to voice their interests and have
those interests addressed. Secondly, environment plans could be released
up-front, that is before a decision is made to the extent that those
environment plans would be released under the FOI process. Mr Smith stated:
We recognise that there is some very specific information
which may be confidential, may have commercial sensitivity, so there may be
some specific things that do not get released. But we think, in general,
releasing the environment plans that are submitted to us would enhance the
transparency of the process and assist the community in participating further
in the process than they are able to do at the moment.[80]
3.67
The Department of Industry, Innovation and Science noted that it is
working with NOPSEMA to review transparency:
...on the basis that there is a very robust system and it would
be better for everybody if people understood what was going on. There is nothing
to hide here. It is an extremely robust system. It is clear that some
improvement in the transparency would increase the public acceptance of the
results. So we are doing some work.[81]
3.68
Mr Mike Lawson, Department of Industry, Innovation and Science, added
that the review is considering how to increase 'citizen acceptance and
awareness of the robustness of that system by making it more transparent'. He
noted that transparency imposes cost 'but we believe that is likely to be a
price that needs to be paid'.[82]
Navigation: Previous Page | Contents | Next Page