Chapter 3
Issues relating to program design and administration
3.1
This chapter discusses how aspects of the program design, administration
and risk management contributed to the serious problems that arose during the
Home Insulation Program (HIP). It considers:
- the design and implementation timeframe;
- the adequacy of DEWHA's administration and resources;
- the adequacy of DEWHA's risk management;
- in particular, the adequacy of training and competency standards
for installing insulation;
- the effect of the maximum rebate and the Medicare billing model.
Design and implementation timeframe
3.2
The HIP was developed in the limited timeframe between the Prime Minister's
announcement on 3 February 2009 and the start of the fully developed program on
1 July 2009. The HIP was part of the $42 billion Nation Building and Jobs
Plan stimulus measure. A dominant, if not overriding instruction to the
Commonwealth Coordinator General (within the Department of the Prime Minister
and Cabinet), who oversaw the Nation Building and Jobs Plan, was to 'break red
tape and get work happening on the ground as quickly as possible'.[1]
3.3
This short time frame created significant and arguably insurmountable risks.
A risk assessment prepared by Minter Ellison for DEWHA in April 2009 (the Risk
Register) noted that the 'scale' of the task was 'new' to the Department. It advised
of risks of 'delays or total non-delivery; substantial increased costs;
increases in other risks including fraud and political fallout'.[2]
3.4
The Risk Register identified a number of mitigating actions – for
example, 'simplify business model where possible to reduce time constraints'.
However it regarded the effectiveness of the proposed mitigating actions as 'weak',
and the residual risk value after mitigating actions as 'extreme'. It suggested
as an additional action 'extend rebate scheme to 30 September [2009]'.[3] The Risk
Register is discussed further from paragraph 3.39.
3.5
There is evidence that much of the pressure to roll out the program
quickly came from the Department of the Prime Minister and Cabinet. According
to the minutes of an industry consultation meeting on 18 February 2009, a
representative of the Office of the Coordinator General informed the meeting that
'$2.7 billion worth of funding is in part structured around the Government
going into deficit for a short period of time. Clear statements from Treasurer
and the Prime Minister state that funding is required to be spent within 2.5 years
with a cap of $1600 per household.'[4]
3.6
Mr Mrdak (former Coordinator General) said in evidence:
The government had clearly set out a very ambitious program
for the rollout of a number of these infrastructure initiatives... The time
frames were set out in the National Partnership Agreement, which was agreed by
COAG... There certainly was a strong view by government and by senior officials
that we should continue to press on to meet the time frames that had been set
out by the government.[5]
3.7
The tight time frame was a significant factor in the choice to use a demand
driven model in which installers would register for the program, contract
directly with householders, and claim payment through Medicare.[6]
3.8
On Minter Ellison's suggestion to defer the start of the program by
three months, DEWHA commented:
[deferring the start date] was considered only in the context
of the risk which was put on the table by Minter Ellison. We addressed those
risks and, as a result, given the model which we adopted, there was no need to make
a deferral.[7]
3.9
Dr Hawke's review commented that 'while the model was delivered,
implementation of the audit and compliance framework lagged behind...'
...The opportunity to step back from the day to day management
of the program, ask hard questions and test assumptions was not taken until
late in proceedings. Resources were tied up with crisis management.[8]
Committee comment
3.10
The haste in rolling out the full program by 1 July 2009 was a major
cause of problems that subsequently arose. The government had clear and
unambiguous warnings of this in Minter Ellison's suggestion that the interim
(reimbursement) program should be extended by three months, in order to allow
more time to properly address the identified program risks.
3.11
It is clear that the Office of the Co-ordinator General, operating
within the Department of the Prime Minister and Cabinet with direct and regular
reporting to the then Prime Minister, Minister Arbib and the relevant
sub-committee of the Cabinet applied pressure to roll out the program quickly,
in spite of the forecast risks.
3.12
By and large, federal bureaucrats do their professional best to
implement the will of the government of the day.
3.13
Due to a failure to comply with requests for the release of all
briefings and relevant information, coupled with understandable hesitancy of
lower ranking public servants to speak 'on the record', the committee could not
sufficiently test allegations that junior to middle‑ranking departmental
officers issued early, repeated warnings to senior departmental ranks. Nor
could the committee satisfactorily test allegations such as those aired on the Four
Corners program[9]
that such warnings went unheeded by senior departmental officers, swept aside
by government‑dictated exigencies of haste to get taxpayer dollars out the
door.
3.14
In the absence of such 'testing', and in any event, responsibility for
any bureaucratic shortcomings properly falls at the feet of respective
Ministers and Prime Ministers.
3.15
In the committee's view, then Prime Minister, the Hon Kevin Rudd, then
Deputy Prime Minister Gillard who was responsible for workplace training, and
the Minister Assisting the Prime Minister for Government Service Delivery,
Senator Arbib (who had oversight of fiscal stimulus spending), bear significant
responsibility for the consequences of the HIP, particularly due to their
apparent role in placing speed of delivery before the safety of implementation.
3.16
This is in addition to the responsibility borne by Minister Garrett, and
the responsibilities Minister Combet now has to neutralise the negative
consequences of the HIP. Regrettably in rejecting invitations to appear before
the committee, these Ministers failed to avail themselves of opportunities to
provide evidence to the contrary.
Adequacy of DEWHA's experience, administration and resources
3.17
DEWHA very quickly began to experience the management, capability and
capacity risks identified by the Risk Register for DEWHA’s looming role in the
management of the HIP.[10]
3.18
In short, the government tasked a bureaucracy better experienced and
equipped for policy development than program implementation, with defying
forecast risks to implement an unprecedented and ambitious demand-driven
program largely on the run and across the states.
3.19
The tight time frame for developing the full program exacerbated problems
DEWHA already faced. Before the HIP, DEWHA had little to no experience in
running a program of this size and nature. It did not have staff with any detailed
knowledge of the insulation industry. Management of the program was undertaken
in a division with significant other responsibilities (the Renewables and
Energy Efficiency Division). The relevant Deputy Secretary was also responsible
for other major portfolio activities including the Antarctic Division, the
Marine Division, the Land and Coasts Division, and Parks Australia Division.
3.20
A management structure more suitable to the size of the program, with reduced
responsibilities for the Deputy Secretary, was established only in November 2009,
by which time the HIP had run for about three quarters of its ultimate duration.[11]
3.21
While measures were taken to second staff both internally and from other
agencies with at least some relevant experience (eg the Australian Tax Office),
capacity issues remained significant throughout the program. Staffing numbers
ramped up during the period, but there was a heavy reliance on contracted
staff.
3.22
According to Dr Hawke 'internal project management infrastructure and
departmental experience were insufficient to support the (at times
unanticipated) demands placed on them.'[12]
3.23
The frequent changes to the program details during the second half of
2009 created ongoing difficulties:
The program developed incrementally and reactively through
this period... These frequent changes increased complexity and often involved
transitional arrangements...that absorbed additional effort and resources,
leaving DEWHA with more 'catch up' on top of day to day work and process
improvement.[13]
DEWHA consultations
3.24
DEWHA consulted with stakeholder groups and with state/territory
governments in the first half of 2009 during the development of the 'phase 2'
program.[14]
Not all groups were happy with the level of consultation. ICANZ appeared to be
satisfied,[15]
but some of the smaller players were less satisfied. The Polyester Insulation
Manufacturers Association of Australia thought that the program was 'rushed and
needed greater consultation.'[16]
Mr Tikey of the Aluminium Foil Insulation Association said:
We were never consulted right at the start. Had we been consulted
and had some of the areas we raised concerns about been taken on board, we
would not be where we are today.[17]
3.25
Autex, a manufacturer of polyester insulation, in its submission argued
that 'until it was highlighted that ICANZ only represented the interests of the
fibreglass and rockwool industries, statements from this organisation were
regarded by government as representative of the industry as a whole.'[18]
3.26
Dr Hawke reported that the states/territories felt they had had minimal
input during the development of the program, and they would have preferred more
engagement and a better flow of information.[19]
Committee comment
3.27
The government's move to commission an independent review of the HIP (the
Hawke Review) was too little, too late and should have been undertaken earlier
so that the findings could be used to improve the HIP. Such a comprehensive,
independent assessment of the program structure and the capacity to deliver it
should have been undertaken at the beginning and used to inform the development
of such a large and untested program.
Communications with ministers
3.28
DEWHA briefed Minister Garrett on the Home Insulation Program 62 times
between 6 February 2009 and 25 February 2010. The Department of Climate Change
and Energy Efficiency (DCCEE), which has taken over responsibility for the
program, refused to provide these briefs to the committee. In relation to ten
briefs, DCCEE claimed various public interests reasons for withholding the
information. In relation to the remaining 52 briefs, DCCEE gave no reason for
refusing to provide them.[20]
The department referred the 52 briefs to Minister Combet for his consideration
of these matters. In relation to the 52 briefs the minister advised the
committee that:
It is my view that they should not be released. I have come
to this view on the following two grounds. Firstly, as the Secretary of the
Department of Climate Change and Energy Efficiency noted in his letter of 1
April 2010 to the Committee, there is a level of ambiguity about whether their
release would be in the public interest. In view of the Secretary's opinion, I
have decided that it would not be in the public interest to release documents
about which there is doubt. Secondly, it is my view that the documents are
deliberative in nature, and therefore pertain to the deliberative processes
involved in the functions of Government. Disclosure would therefore be contrary
to the public interest.[21]
3.29
Neither of these claims meets the standard of past Senate practice. In
response to his claims, Clerk of the Senate, Dr Rosemary Laing provided advice
to the committee which states that:
Against this background, it is clear that the responses
provided by Minister Combet do not meet the standards set by past Senate
practice. Ambiguity about whether the disclosure of a document would be in the
public interest has never been accepted by the Senate as a ground for
non-disclosure. Paragraph (c)(4) of the Senate’s resolution of 13 May 2009
requires a minister to consider whether the harm that may result from the
public disclosure of a document would also result from its provision to a
committee in camera. If there is ambiguity about this matter then the
committee may wish to press the Minister further and ask whether the ambiguity
could be addressed by provision of the documents to the committee in camera.
The second ground that has been advanced by the Minister for
non‑disclosure of the documents, namely, that they are deliberative in
nature and pertain to the deliberative processes involved in the functions of
government has also not been accepted by the Senate as a “just and proper” claim of privilege.[22]
3.30
According to evidence from DEWHA, Minister Garrett did not ask for, and
was not given, the Minter Ellison Risk Register until February 2010.[23]
DEWHA explained that:
The standard practice is for departments to actually look
into risk assessment as part of good program design. By contracting Minter
Ellison I do not think we necessarily indicated to the minister’s office who we
were actually contracting but we certainly indicated we were undertaking
appropriate risk assessments and seeking the appropriate expertise in this area
to help us.[24]
[The minister] would have been advised, as I think he has
indicated, that there were risks in the program and that mitigation strategies
would have been put in place to deal with those risks.[25]
3.31
The extent of ministerial awareness of the early risks identified in
documents, such as the Risk Register, or of the problems that rapidly emerged
with the program are difficult to deduce given the refusal of the government to
reveal contents of briefings. However the committee does note that both DEWHA
and the Office of the Co-ordinator General acknowledged the provision of
regular briefings about the HIP to Ministers Garrett and Arbib respectively.[26]
Communication between ministers
3.32
Four letters from Minister Garrett to the Prime Minister concerning
planned changes to the program were mentioned in evidence. The letters, dated
14 August, 27 August, 28 October and 30 October 2009, had been first
mentioned by the Prime Minister in the House of Representatives. The committee
sought further information about the letters. DCCEE replied that they were 'of
a Cabinet-in-Confidence nature'.[27]
On 12 May 2010 the Senate ordered production of the letters.[28]
3.33
On 27 May 2010 the government released the letters of 27 August,
28 October and 30 October 2009, claiming that because much of the
information was already in the public domain, no public immunity interest was
claimed. These letters brief the Prime Minister about planned changes to the
program conditions.[29]
3.34
The government continues to withhold the fourth letter (14 August 2009),
claiming that it formed an under the line submission to cabinet and therefore
its release would be contrary to the public interest, in keeping with the
convention of cabinet confidentiality.[30]
3.35
In the absence of evidence to the contrary, the committee is entitled to
deduce that the government considers that this letter contains information not
yet in the public domain. Given the extent of public concern about this program
the committee again urges the government, in the name of transparency and
accountability to release this letter and all other briefings, reports or
correspondence relevant to the HIP.
Committee comment
3.36
It appears that the management structures needed within DEWHA to handle
such a large and complex program were not instituted until far too late. The
committee endorses Dr Hawke's comments which it reiterates:
The opportunity to step back from the day to day management
of the program, ask hard questions and test assumptions was not taken until
late in proceedings. Resources were tied up with crisis management. DEWHA is
not unique in this regard, but it is a lesson that is not easily learned by
busy departments under pressure to deliver large programs.[31]
3.37
In relation to briefs from the DEWHA to Minister Garrett, which the
committee requested, the committee records its strong dissatisfaction that
DEWHA has not provided these without giving adequate reasons. On 9 June 2010,
pursuant to a Senate Procedural Order, the committee sought the referral of
these and other related matters to relevant ministers.[32]
3.38
In the absence of evidence to the contrary, the committee can only
conclude a level of negligence on the part of ministers or senior officials
that detailed information on risks (including Minter Ellison's recommendation
to defer the starting date) were either never communicated to or never acted on
by the highest levels of the government.
Adequacy of DEWHA's risk management
Minter Ellison's Risk Register
3.39
In mid-March 2009 DEWHA commissioned from Minter Ellison a risk
assessment of the program. The key outcome of this was a 'Risk Register and
Management Plan' which was received by the department in early April 2009.[33]
It listed many extreme and serious risks, and recommended mitigation measures to
minimise the probability that the unwanted outcome would occur. To take one
example:
Risk 5: Fraud: inadequate controls may allow fraudulent
or inappropriate behaviours:
- Ineligible
people accessing the program
- Industry
quoting above actual cost of job
- Households
double dipping between Commonwealth, State and Territory Programs above out of
pocket costs
- Applicant
accessing both SHWR and HIP programs
- Installer
theft/ vandalism/ professionalism
- Internal/
staff member process integrity
Recommended
Management Plan:
- Develop
specific fraud strategy based on a capacity to outsource the risk
- Review
processes to test specifically for control over possible fraud/incorrect
payments... [and five other dotpoints: see Appendix 6][34]
3.40
The Risk Register listed 19 individual risks, which in summary were:[35]
- Extremely limited time to determine and implement
effective project methodology and delivery/business model post 1 July 2009.
- Procurement processes/timeframes; 1 July 2009 deadline for
full program; scale of task is new to Department.
- Time available to develop and implement the program in a
properly controlled way may be inadequate.
- Quality of installation/ control by installers and
compliance structures may be inadequate.
- Inadequate controls may allow fraudulent or inappropriate
behaviours
- Multiple policy goals, vested commercial interests may
hamper the efficient delivery of the program.
- A variety of failures in the process, system, project
deliverables etc may have significant indirect political/ public confidence
impact.
- Inadequate planning and communication may create poor
delivery of communications strategy (internal and external).
- Complex legal issues associated with the program may not
be fully understood or dealt with.
- Capacity to develop, staff, control and deliver the
program on time may be insufficient.
- The existing regulatory framework may not adequately
support the program's goals.
- Industry's capacity to produce and deliver sufficient
quality materials and installations may be inadequate.
- Actual outcomes (eg number of households included, long
term savings), may not eventuate.
- Delivery structure may result in overcentralisation, poor
allocation and political/economic fallout.
- Program may not achieve its objectives through poor
uptake/program awareness.
- Training mechanisms: capacity/control over installer
network skills may be inadequate.
- Risk of focussing on specific tasks and pressure groups
may result in inadequate attention to all stakeholders and their interests.
- Structure of program may impact on capacity of the
industry both in the short and longer term.
- Product quality may not be of adequate standard.
3.41
The Risk Register also listed relevant current activities, and gave an
estimate of how serious each risk was; how effective mitigation steps were
likely to be; and additional suggestions.
3.42
For example, in relation to risk 3 in the list above—the time to develop
the program may be inadequate for a desired 1 July 2009 rollout—the risk was
estimated as 'extreme', the effectiveness of mitigating actions was regarded as
'weak'; the residual risk after mitigating action was regarded as 'extreme';
and the suggested 'additional action plan' was 'extend rebate scheme to 30
September'.[36]
3.43
Minter Ellison advised that even after mitigating actions, six matters
had a 'high' or 'extreme' residual risk, as follows:
Table
2—Extracts of the Minter Ellison Risk Register of 9 April 2009
No.
|
Risk description[37]
|
Risk today
|
Effectiveness of mitigators
|
Residual risk value
|
Is residual risk value
tolerable
|
Additional action plan
|
2
|
Procurement/licensing: needs
for entire program duration to be determined and fulfilled by 1/7/09
|
Extreme
|
Weak
|
Extreme
|
No
|
Extend rebate scheme to 30
September 2009...
|
3
|
Time: time available to
develop and deliver the program in a properly controlled way may be
inadequate
|
Extreme
|
Adequate
|
Extreme
|
No
|
Extend rebate scheme to 30
September 2009...
|
5
|
Fraud: inadequate controls
may allow fraudulent or inappropriate behaviour
|
Extreme
|
Adequate
|
High
|
Yes
|
|
7
|
Political: a variety of
failures in the process, system, project deliverables etc may have
significant political fallout
|
Extreme
|
Adequate
|
Extreme
|
No
|
High level political/
stakeholder coordination and monitoring required
|
10
|
Internal capacity: capacity
to develop, staff, control and deliver the program on time may be
insufficient
|
Extreme
|
Adequate
|
High
|
Yes
|
|
11
|
Regulation: the existing
regulatory framework may not adequately support the program's goals
|
Extreme
|
Weak
|
High
|
Yes
|
|
3.44
The risks to the safety of persons and property, subsequently one of the
program's key shortfalls, are covered in the Risk Register under the heading
'installation quality and compliance':
[Risk 4] Risk
description: Installation quality and compliance: quality of installation/
control by installers and compliance structure may be inadequate:
- poor quality installations
- compliance
cost (to department or industry) may be excessive and process may be
ineffective
- safety – house
fire/damage
- insufficient
number of auditors
Risk today: Extreme
Recommended management plan:
- Consider
these issues in developing the business model
- Ensure
business model transfers fraud risk from Commonwealth to providers where
possible and allows effective monitoring
- Develop
effective processes for registration of installers. Cover both financial
viability and technical capacity in registration process
- Alternatively
let third party contracts to do this; set up monitoring and reporting processes
to identify emerging provider stress
- Ensure
contract structure provide capacity to monitor and take action on poor
performing providers
- Ensure
installers are properly insured and consider requiring installers to indemnify
the Commonwealth against claims/loss arising from installers' actions
- Review
mitigation strategies in light of the agreed business model.
Effectiveness of mitigators: Strong
Residual risk value: Medium
Is residual risk value tolerable: Yes[38]
3.45
DEWHA advised that the April 2009 Risk Register was updated over time.[39]
Later versions of the Risk Register used by the interdepartmental Project
Control Group in July, September and October 2009 noted the risk of 'unsafe or
incorrectly installed product leads to fire/damage, injury or death', and
listed various 'ongoing' mitigating actions, including:
- Additional compliance audit activity
- Enhance compliance education activity including proactive
communications to educate installers on compliance requirements
- DEWHA
communication tools (guidelines, website, installer packs, call centre) clearly
explain policy requirements. Communications through public relations is
consistent and includes info about the quality of materials.
- Mandatory
training competency checking in desktop audits
- Liaise
closely with DEEWR on management of installer skills...
- All companies
to be responsible for ensuring supervision of staff in their employ (liaison)...[40]
3.46
The Risk Assessment and the Risk Register (at 9 April 2009) are at
Appendix 6.
3.47
It is noteworthy that at the relevant item 4 in the April 2009 Minter
Ellison Risk Register the fire risk is dismissed with four words ('safety -
house fire/damage') and the electrocution risk is not mentioned at all (see
paragraph 3.44).[41]
The recommended risk management actions depended strongly on uncertain future
conditions (for example 'review mitigation strategies in light of the agreed
business model'), and they had a strong focus on minimising the Commonwealth's
responsibility, rather than actually ensuring safe outcomes.
3.48
Training needs are mentioned elsewhere in the Risk Register;[42]
but the most obvious action to mitigate risks to personal safety—'ensure adequate
training of all personnel'—is not mentioned at item 4. This suggests that at
this time risks to personal safety were not being adequately considered.
DEWHA's management of risk
3.49
In April 2009, DEWHA established a Project Control Group with
representatives of the Commonwealth agencies involved. They were DEWHA;
Department of Education, Employment and Workplace Relations; and Department of
the Prime Minister and Cabinet; Medicare Australia; and the Australian Taxation
Office. The Department of the Prime Minister and Cabinet was involved in the
form of the Office of the Coordinator General which was responsible for
monitoring stimulus spending projects.[43]
3.50
The Project Control Group met generally weekly from April to December
2009, with standing agenda items including the project's schedule, monitoring
and reporting, risk management, stakeholder management, communications and
compliance.[44]
3.51
Commenting on risk management in evidence, DEWHA emphasised that the
risk assessment was not a prediction of what would happen (with implication
that the government would be negligent for persevering over its strong
warnings), but rather a prudent hypothetical of what might happen in the
absence of preventative action.[45]
DEWHA argued that as the program rolled out 'significant measures were put in
place systematically and progressively in an effort to manage those risks'—for
example, in using the Medicare system for payments.[46]
DEWHA admitted that the short timeframe for implementing the program (which
Minter Ellison had flagged as creating an 'extreme' risk) was 'challenging':
It was an ambitious program. Basically, the issue was to use
a range of strategies to minimise that risk...the risks of the program were
consistently discussed with the minister. The time frame in which it was being
rolled out was one component of those and that was actually quite influential
in the selection of the business model that was ultimately rolled out, as I
indicated in relation to Medicare.[47]
3.52
Commenting recently on DEWHA's risk management strategy, Minister Combet
argued that 'the level of demand created significant difficulties not only for
the administration of the program but also for the management of audit and
compliance...'
...During the program design process, potential risks were canvassed
in the Minter Ellison report received by the department in April 2009. Attached
to each of the risks identified in the report were proposed mitigation actions.
The risk register tracked these actions. I am advised that this information,
along with other inputs, informed the overall program design. Notwithstanding
the best endeavours of those responsible for the program design, the behaviour
of unscrupulous operators led to the realisation of a number of these risks in the
delivery of the program—most notably concerning the quality of installations
and fraud.[48]
3.53
Dr Hawke's recent review of the HIP, commenting on the 'high' and
'extreme' residual risks, said:
The first two of these risks and the last ['needs for entire
program duration to be determined and fulfilled by 1/7/09'; 'time available to
develop and deliver the program in a properly controlled way may be
inadequate'; 'the existing regulatory framework may not adequately support the
program's goals' - see paragraph 3.43] were addressed by the revised delivery
model, but the remainder were risks that had to be managed through the life of
the HIP.[49]
3.54
Dr Hawke commented generally on DEWHA's risk management:
DEWHA established a strong risk management framework and then
had in place a number of mechanisms to address and mitigate the risks...When
issue arose, DEWHA and the Minister worked quickly to address them...Warnings
were heeded; however this was largely reactive. Internal management structures,
particularly early in the program, did not provide the necessary senior
management oversight or allow for considered review at appropriate times. A
program of the profile and significance of the HIP involving an industry that had
minimal regulation warranted very close attention. It is acknowledged, however,
that some of the issues flowing from the extreme level of demand could not be
anticipated.[50]
Committee comment
3.55
For a program of the HIP's nature, Minister Garrett should have
requested the conduct of a risk assessment, a copy of it once done, and an
action plan identifying how each risk was being addressed, when and by whom. The
Risk Register should have been provided to Minister Garrett earlier than
February 2010 for his consideration and government action. The extent to which
important information was allegedly not shown to the minister appears
reflective of a 'don't show–don't tell' culture.
3.56
In the committee's view the government's risk management activities through
DEWHA fell breathtakingly short. It failed to anticipate or respond with
sufficient urgency to the extremely high risks created by the haste, scale,
demand-driven and national roll-out of an ambitious program involving an
industry with standards and rules, simply inadequate for a program for which
the government's overriding goal was to drive demand and rapidly rollout such a
large program.
3.57
These risks were sufficiently flagged in Minter Ellison's April 2009 Risk
Register and had been raised with the government by various industry
stakeholders as early as February 2009.
3.58
The committee comments particularly on the electrical and fire risks
which have since become a critical concern. Industry associations had raised
these risks as early as February 2009. For example concerns were raised:
- by the National Electrical and Communications Association (NECA),
February 2009: 'There is a significant risk of electrical equipment overheating
especially in the event of downlights in ceilings being covered if insulation
is installed inappropriately';[51]
-
at stakeholder meeting, 18 February 2009: '...in New Zealand...a
similar program had to be suspended because three people electrocuted
themselves';[52]
- by NECA to Minister Garrett, March 2009: 'Whilst not the only
safety issue by far the most dangerous is the risk of fire associated with
installing thermal insulation over or in close proximity to recess luminaires';[53]
- by Master Electricians Australia in May 2009: '...incorrectly
installed insulation created a very serious fire risk, especially in older
homes'.[54]
3.59
From the evidence presented to the committee it is clear that DEWHA and government
ministers received various written and oral warnings of the serious risks posed
by the program prior to its large-scale deployment in July 2009. It is also
clear that these warnings were either ignored or not taken sufficiently
seriously at the Cabinet or departmental level, in the rush to commence this
flawed and ill-conceived stimulus measure.
Adequacy of training and installation standards
3.60
The required training and work standards in the program are summarised at
paragraphs 2.25ff. DEWHA submitted that comprehensive safety requirements were
always fundamental to the program:
- Supervisors were required to have training (this had never before
been required in the retrofit insulation business), and to comply with
state/territory occupational health and safety laws.[55]
- Training materials were developed with the advice of industry
stakeholders.
- Training materials covered the full range of hazards. For example,
the installers pocket book issued in August 2009 gave detailed warnings in
relation to electrical and fire safety. Safety warnings were upgraded in a new
edition of the pocket book released in November 2009.
- Installations had to comply with the relevant Australian
Standards for insulation materials and installation. The standards included
requirements for clearances around downlights.[56],
[57]
Submissions on training and competency
standards for installing insulation
3.61
Submissions generally approved of the new training standards and
training materials, and stressed that they were an advance in a business which
had previously not had any training or licensing requirements (except in South
Australia, which has licensing requirements for insulation installers).[58]
3.62
South Australia was the only state that had a requirement for installers
to be licensed, but still had to deal with 'fly-by-nighter' installers who worked
illegally.[59]
3.63
A key issue was how well any trade-related competencies were actually
transferred to workers in the roof cavity. Some witnesses thought the main
concern was that all personnel involved in installation, not only supervisors,
should have been required to demonstrate trade-related competencies. For
example:
It [was] not mandatory for all installers to have insulation‐specific competencies
(only for the supervisor). In practice, this [meant] that a supervisor [could]
have a large crew of untrained people performing the installations and just
‘swing by’ each installation to sign off on the form.[60]
While in the past the industry had always relied on staff
learning how to work safely on the job, it appears that this was no longer good
enough with so many new staff – and, more importantly, new companies – in the
system.[61]
3.64
Witnesses suggested that brief formal training could not adequately
replace supervised experience:
What we should have was a condition such that, every time a
worker goes in a roof, there should be at least one person there who is either
a tradesperson, or who has at least six months experience in the industry, who
has danger sense. You cannot teach that in six hours or in two days... Youngsters
do not know that.[62]
Most of us in the insulation industry would not have allowed
our installers to go out only having been on a two-day course.[63]
Up until this stage [October 2009] the training was scant to
non-existent for most installers, and as there were many new entrants into the
market very few had experience to fall back on.[64]
3.65
At the same time, exemptions from competency requirements defied logic
and were seen to give a 'free pass' to a number of trades which seem to have limited
direct dealings with insulation:
Stupid thing is if you have a trade, ie; brick layer, you are
exempt. What does a brick layer know about installing insulation materials???[65]
3.66
There was criticism of 'tick and flick' forms, such as the mandatory
risk assessment template that was used from 2 December 2009:
The latest tick-and-flick sheet is too large, too
black-and-white and too technical... More likely as they are paid by the job,
they would tick and flick without checking – take the risk, as they knew no-one
would ever check.[66]
3.67
There was implied criticism of training materials as likely to be too
complicated for the intended readership:
The Government did accept recommendations from industry and
training experts in the revision of the training materials and associated risk assessment
forms, to include visual aids to assist those without a firm grasp on the
English language. It is unfortunate that these changes appear to be a case of
too little, too late.[67]
3.68
In relation to installation standards, particular criticisms or
suggestions included:
- there should have been a mandatory requirement to turn off the
power before entering the roof;[68]
- plastic staples should have been mandated;[69]
and
- there should have been an electrical inspection before
installation.[70]
3.69
The National Electrical and Communications Association (NECA)
recommended in February 2009 that a licensed electrician should check wiring
before installation. NECA suggested this again at an industry consultation
meeting on 12 November 2009, after the first death linked with the program,
but told the committee that 'the response to this suggestion was that there was
not enough money available'.[71]
3.70
On the other hand, ICANZ did not support compulsory electrical
inspections, as 'experienced insulation installers know what to do and have
managed this safely over the years'.[72]
Committee comment
3.71
The committee acknowledges DEWHA's efforts to establish some training
standards in an industry which had not had them previously but finds these
efforts to be grossly inadequate given the scale of inexperienced start-up
operations that were anticipated under the HIP.
3.72
Shortcomings in the detail of formal training and competency
requirements were exacerbated by a systematic failure to adequately implement,
enforce and communicate to the industry and workforce.
3.73
In the committee's view DEWHA did not adequately respond to the high
risk created by the huge influx of inexperienced workers. As submissions
commented:
Master Electricians Australia knew from its more than 70
years representing the electrical contracting industry that if you combined
unskilled labour with electrical cabling then tragedy would not be far away.[73]
The competency based training that was implemented should
have been satisfactory, however the inconsistent delivery of this training, and
the large amount of exemptions, meant that the training was not enough.[74]
3.74
Arguably the key mistake was failing to ensure from the outset that all personnel
involved in installation (not only supervisors) were properly trained.[75]
It was not adequate to allow a trained/qualified registered installer to oversee
what could be an unlimited number of untrained workers. In this situation it was
unreasonable and irresponsible to assume that written warnings about fire and
electrical safety would effectively reach the actual workers in the roof.
3.75
It was counter-intuitive to exempt from training requirements a number
of building trades which had little direct experience with insulation yet were
now likely to interface with it.
3.76
Stakeholders gave both DEWHA and the government strong warnings of these
risks from as early as February 2009. Similar warnings were expressed in a
stakeholder consultation meeting on 18 February 2009.[76]
Neither DEWHA nor the government paid enough attention to these warnings.
Making the standards more stringent in the last few months of the program was
too little, too late.
3.77
The fact that the authorities felt the need to amend the installers'
pocket book extensively after the first program-related fatality in October
2009, to upgrade the warnings on electrical and fire risks, does not inspire
confidence in the adequacy of the earlier edition.
3.78
The committee expresses its deep concern and disappointment about
DEWHA's and the government's failure to adequately minimise risks or respond
effectively to the first tragic fatality in October 2009. It was not until
February 2010 that the training requirement for all installers took effect.[77]
It appears that the option of mandating safety switches as a condition of
participation was never considered. Similarly, despite the best endeavours of
the Fuller family, the simple step of requiring the household's power to be
switched off during installation was never mandated.[78]
Steps along these lines may have helped avoid at least one of the subsequent
fatalities. The committee finds this both tragic and deplorable.
3.79
The committee is not expert in insulation or electricity. However, it considers
it incumbent upon the government to counter criticism that the government
should have mandated:
a. turning
off the power before entering the roof;[79]
b. the
use of plastic staples with foil, as had been recommended in New Zealand since
2007;[80]
and
c a
condition of HIP insulation that a house had a safety switch (residual current
detector).[81]
3.80
In the committee's view, by October 2009, DEWHA and the government had
received sufficient written and oral warnings of the serious risks posed by the
program that it should have been suspended immediately following the first
fatality. However, disturbingly, these warnings were either ignored or not
taken sufficiently seriously. Again, the desired speed of spending appears to
have superseded safety considerations.
The maximum rebate and the Medicare billing model
3.81
According to DEWHA, industry estimates at the time of the announcement
of the HIP indicated the cost of installation could range between $660 and $1600
per dwelling.[82]
When the program was launched the maximum rebate was set at the upper end of
this range, that is $1600.
3.82
DEWHA said that this provided 'the greatest scope for strong take-up by
eligible households. This was designed to achieve maximum impact in line with the
economic stimulus and employment objectives of the program.'[83]
DEWHA advised that a study commissioned by ICANZ had estimated that the average
cost of insulating a home would be $1200; and subsidies at the lower end of the
spectrum (ie towards $660) would not be likely to create enough demand for the
program to achieve its goal of insulating enough houses in the two year time
frame.[84]
3.83
ICANZ estimated in 2007 that an average home would cost from $1200 to $1500
to have ceiling insulation professionally installed, and a $500 rebate could
achieve a 28 per cent uptake over 3 years. ICANZ submitted that 'in order for
the government to achieve a high initial take up, and the objectives of
creating jobs and insulating all uninsulated housing stock, a rebate of up to
$1600 was necessary to get full participation.' ICANZ submitted that with a $1600
maximum most people would have paid nothing.[85]
3.84
After extensive allegations of profiteering and abuse, the rebate was
reduced to $1200 from 2 November 2009. DEWHA said that this 'recalibrated the
level of assistance in line with increasing consumer confidence'. The average
claim between 1 July and 6 December 2009 was $1389.[86]
3.85
The evidence suggests that the scheme in which installers claimed the
rebate directly through Medicare was chosen primarily to facilitate rolling out
the program in a tight time frame. However it had the effect that householders,
as well as paying nothing if the cost was below the maximum rebate, would not
be out of pocket at any time. This was probably a significant driver of the
huge increase in demand once this system started on 1 July 2009 (see Figure 1
at paragraph 2.50).
3.86
Many submissions argued that the excessive emphasis on 'free insulation'
was detrimental. For example United Bonded, submitted that:
The EEHP has had an enormous take up because it offers "free" insulation rather than necessarily because of the utility or
efficacy of the program as a nation building tool or as a mechanism to reduce
energy consumption and greenhouse gas emissions.[87]
3.87
The Polyester Insulation Manufacturers Association of Australia
suggested that requiring a co-payment would have encouraged 'buy-in' by
householders:
Introduce the requirement for a co-payment within the scheme
requiring the householder to, say, pay the first 25 per cent of the cost of
insulation (less than 12 months payback, and which could be funded by the green
loans scheme) so that there is a return to rational decision making behaviour
of consumers and some “buy-in” from them in the outcome.[88]
3.88
Dr Hawke's review commented that 'the lack of an upfront payment and no
requirement for quotes (between June and November 2009) meant there was little
incentive for householders to take the normal level of responsibility for the
quality and performance of the installers.'[89]
Committee comment
3.89
Arguably many of the problems of the program resulted from the government's
role, in and quest for, driving demand, culminating in an overwhelming deluge in
the second half of 2009. In terms of market-place drivers, it seems to have
been driven more by marketing by installers, taking advantage of the fact that installations
were free for most dwellings, than by the initiative of householders.
3.90
As householders had no motivation (and almost certainly no expertise) to
check the quality of the work, it left the way open to program abuses by
unscrupulous newcomers to the industry who encouraged a large influx of
inexperienced installers. This in turn was a contributor to the deaths, safety
risks and other poor program outcomes described in more detail in chapter 4.
3.91
The committee considers it incumbent on government to explain why it did
not spread the program over a considerably longer time frame and promote 'buy-in'
by householders by:
- reducing the level of the subsidy offered;
- requiring a co-payment, that is the householder pays some part of
the price; and/or
- requiring the householder to pay the price of installation
upfront and then be reimbursed a portion of the price.
3.92
The committee finds that the excessive value of the initial $1600 rebate
(above the industry average at the time) was always going to promote
profiteering and, with it, bring about the low standards, short cuts and shonks
that inevitably come from those solely attracted by a 'quick buck'.
3.93
The committee further finds that effectively making insulation 'free'
for a period of time was never likely to provide lasting benefits to the
industry as it was structured to create a boom-bust cycle, without leaving
consumers with any understanding or appreciation of the real 'value equation'
that underlies the installation of insulation.
3.94
A reimbursement or co-payment scheme might have moderated demand and may
have helped to deliver some longer term sustainability. However, it is unlikely
of itself to have seen improved long term environmental effects or to have
reduced risks to installers and householders without commensurate higher
standards.