Chapter 6
Port case studies:
Gladstone Harbour and Abbot Point
6.1
This chapter examines evidence received in relation to port developments
at Gladstone Harbour and Abbot Point.
Gladstone Harbour
6.2
The Port of Gladstone is approximately 100 years old. It is located
within the World Heritage Area boundary, and adjacent to the Marine Park. The
port is the largest multi-cargo port in Queensland (in terms of tonnage) and
the fourth largest in Australia.[1]
6.3
The submission from the Australian and Queensland Governments specified
that the Minister for the Environment, the Hon Greg Hunt MP, approved projects
in Gladstone Harbour in December 2013.[2]
These were:
-
Arrow Liquefied Natural Gas Facility, Curtis Island, Gladstone;[3]
and
-
Arrow Gas Transmission Pipeline, Gladstone to Curtis Island.[4]
6.4
However, the committee notes that these approvals were only the latest
in a series of projects and developments approved in the Gladstone Harbour
area. The harbour has been subject to dredging activities since the late 1960s.
More extensive projects started around 2011 and included the Gladstone Ports
Corporation's Western Basin Dredging and Disposal Project in Gladstone Harbour
of 2011 (Gladstone Western Basin project)[5]
and the development of three LNG processing facilities on Curtis Island,
approved in 2010 and 2011.[6]
The Gladstone Western Basin project
6.5
The Gladstone Western Basin project approval allowed for a total maximum
of 46 million cubic metres of dredge spoil to be removed and disposed of
both offshore and within a constructed reclamation area behind a 'bund wall'.[7]
The project commenced in late 2010 and the reclamation area was completed in
July 2011. The committee received conflicting evidence about the commencement
of dredging in the harbour. According to the Gladstone Ports Corporation,
dredging for the project commenced on 20 May 2011.[8]
The Bund Wall Review states that dredging and deposition of dredge spoil behind
the bund wall commenced in September 2011.[9]
Dr Matthew Landos, of the University of Sydney's Faculty of Veterinary
Science, submitted that 'the dredging commenced in October 2010, not September
2011'.[10]
The first stage of the project has been completed and involved around 25
million cubic metres of dredging over two years.[11]
6.6
The Bund Wall review noted that from September 2011 increased turbidity
was reported around Gladstone Harbour.[12]
There were also reports of disease in fish and crabs, and the harbour was
closed to all fishing in that month.[13]
In October 2011, GBRMPA reported a 'significant increase in the number of
dugong and turtle deaths in the southern Great Barrier Reef', including in the
Gladstone area.[14]
Monitoring of seagrass from 2009 to 2012 showed 'significant declines in
seagrass abundance' at all sites in the Gladstone area.[15]
6.7
As Mr Simon Whittingham of Gladstone Fish Markets told the committee:
Not only was something clearly wrong with the commercial
[fish] product being exposed to what was in the water; turtles, dolphins and
dugongs were washing up dead. Fish kills were occurring throughout the harbour.
Something was terribly wrong...[16]
6.8
The impacts on the fisheries were significant, with Mr Ted Whittingham
of Gladstone Fish Markets explaining that his company has lost 90 per cent of
its business since 2011 as a result of the outbreak of fish disease and the
loss of suppliers.[17]
The committee heard that they received no compensation for this loss. The
committee notes that the problem appears to be that the conditions relating to
compensation under the Queensland approval only required Gladstone Ports
Corporation to mitigate financial losses to commercial fishing operators to
cover loss of access to fishing areas and marine fish habitat.[18]
While Gladstone Ports Corporation submitted that claims for compensation from
the seafood industry failed in court 'because of an inability to provide
evidence which substantiated their case'.[19]
In at least one case, the committee notes that the relevant applicant was
considered a recreational fisher, rather than a commercial fishing operator.[20]
6.9
Dr Landos described the scale of the problem affecting Gladstone
Harbour:
In Gladstone harbour more than 1,500 hectares of seagrass
have been eradicated and have not recovered, large numbers of turtles, dolphins
and dugongs have died and a commercial fishery has been virtually eradicated...[21]
6.10
Ms Ginny Gerlach of the Keppel and Fitzroy Delta Alliance gave evidence
to the effect that the tourist industry, in particular the charter boat
industry, was also negatively affected by the exclusion zones and shipping
traffic that resulted from Gladstone Port developments.[22]
6.11
Many submitters and witnesses argued that these problems with turbidity
and disease and death of marine animals and fish were as a result of dredging
project.[23]
WWF-Australia and the Australian Marine Conservation Society submitted that
'dredging, dumping and bund wall construction in Gladstone Harbour coincided
with massive fish kills, sick and dead turtles and dugongs, and the closure of
fishing in the Harbour for three weeks'.[24]
6.12
Mr Michael McCabe of the Capricorn Conservation Council described
Gladstone Harbour prior to 2011 as 'a big marine area' that was sometimes
'clear' and sometimes 'a bit murky in big tides' and it has since become 'a
very messy harbour'. He went on to note that, after dredging had commenced,
corals and marine megafauna, including fish in and around the harbour, had
shown signs of illness and disease and had started dying off.[25]
6.13
Save the Reef described these impacts as tantamount to 'ecocide' and Ms Suzanne
Arnold of Australians for Animals described Gladstone Harbour as 'an
environmental disaster'.[26]
6.14
However, the Queensland Ports Association submitted that 'accusations
and claims that dredging-related activities were responsible are not supported
by available evidence'. They stated that:
As noted in reports published in 2012 following scientific
investigations conducted by the Queensland Department of Environment and
Heritage Protection, Queensland Department of Agriculture, Fisheries and Forestry,
CSIRO, the University of Tasmania and also in the Independent Review of the
Port of Gladstone (2013), the fish health issues in Gladstone Harbour during
2011 were the most likely the result of extreme weather events, freshwater
influxes and associated overcrowding from fish that moved into the area after
overspilling from Awoonga Dam.[27]
6.15
Ports Australia, in its report on dredging and Australian ports,
acknowledged that the impacts of the project on water turbidity were
significantly greater than initially approved or predicted. Ports Australia
noted that:
This apparently was the result of a number of factors
including the influence of large spring tides, major flood events, unexpected
seepage of fine sediments from a reclamation area until a remedial bund sealing
operation was complete, hydrodynamic changes, and a major increase in boating
traffic (over 20,000 movements per month) with associated wash effects.[28]
6.16
The report noted that the Independent Review of the Port of Gladstone
(Independent Review 2013) accepted that dredged sediments were compliant with
the requirements of the National Assessment Guidelines for Dredging 2009
in relation to ocean disposal.[29]
The Independent Review 2013 stated that water and sediment quality testing
demonstrated that dredged sediments were not contaminated to levels that would
lead to toxicological effects.[30]
6.17
Dr Landos rebutted these claims, arguing:
...the project allowed the release of very large volumes of
sediment from excavation from the seafloor and it was stirred up by boat
activity. A lot of that material contained toxic levels of metals...A lot of
the material was also dumped at sea, triggering toxic algal blooms...The
combination of events seriously stressed the animals that were exposed to
elevated metals. We know they had high metals because we measured turtle blood
and it showed very high levels of metals...there is a myriad of data showing that
metals were involved; toxic algae were involved; and massive amounts of noise
from the increase in boat traffic...[31]
6.18
However, Gladstone Ports Corporation queried much of Dr Landos's
evidence. For example, they submitted that they would 'welcome the opportunity
to view and review any evidence that supports the claim that algal blooms
occurred around the offshore disposal site', as well as the claim that dredged
material contained 'metal concentrations at levels likely to cause toxic
impacts on the ecosystem'.[32]
Investigations and reviews
6.19
As noted in Chapter 2, in response to community concerns, and concerns
of the World Heritage Committee, there have been a number of recent
investigations and reviews into Gladstone Harbour.[33]
These include the Independent Review 2013, commissioned as part of the
Australian Government's response to the 2012 decision of the World Heritage
Committee.[34]
After that review reported on its findings, information came to light that the
reclamation bund wall at the Port of Gladstone was leaking. This sparked
another separate review: the Independent Review of the Bund Wall at the Port
of Gladstone released in April 2014 (the Bund Wall Review).[35]
6.20
WWF-Australia and the Australian Marine Conservation Society noted that
initial investigations suggested that the cause of the decline in the health of
the Gladstone Harbour ecosystem could not be determined conclusively, but there
was significant emphasis placed on the role of concurrent flood events.[36]
However, some submitters and witnesses were concerned that information relevant
to the earlier investigations was available but not provided.[37]
6.21
The Independent Review 2013 found that the fish-health issues and other
environmental impacts in 2011 were:
...likely to be the result of multiple pressures, including
extreme weather events[38]
and associated overcrowding from fish that moved into the area after
overspilling from Awoonga Dam. These conditions have improved since 2011.[39]
6.22
However, the Independent Review 2013 found that 'community confidence in
the environmental performance of approved developments within the port is
generally low'.[40]
6.23
The most recent Bund Wall Review found that 'aspects of the design and
construction of the bund wall were not consistent with industry best practice',
which 'contributed to changes in turbidity in the vicinity of the bund wall'.
It also found deficiencies in Australian Government decision-making processes,
compliance, monitoring and recordkeeping practices, which are discussed further
below.[41]
6.24
However, the terms of reference for the Bund Wall Review did 'not
mandate the examination of issues pertaining to the ecological consequences of
the construction and performance of the bund wall, including possible impacts
on ecosystem health'.[42]
6.25
As such, some submitters and witnesses were critical of both reviews.
For example, Ms Suzanne Arnold of Australians for Animals suggested that 'there
has been no proper independent inquiry as requested by the World Heritage
secretariat'. She noted that the Bund Wall Review did not have public hearings
and did not call witnesses. Ms Arnold also argued that the appointment of CSIRO
scientists as members of the relevant inquiry panels undermined the
independence of those panels and she called for a commission of inquiry or a
royal commission to be set up to examine the development of Gladstone Port. Ms
Arnold told the committee that she knew of some 'whistleblowers' who 'will not
come forward unless they have the protection of a royal commission'.[43]
The call for a royal commission was also voiced by Dr Landos.[44]
6.26
The situation was summed up by Ms Wishart of the Australian Marine
Conservation Society, who described the issues affecting Gladstone Harbour as a
'travesty':
There has been a whole series of different studies,
reports—you name it—into what occurred there, and yet we are still not at the
bottom of that mire...There has clearly been massive failure in the existing
regulation....[45]
6.27
Dr Landos stated the legislation did not appear to be the problem.
Rather, he suggested it was subverted through poor process. He added that this
was evident at every level:
...poor process in the assessment stage; poor process in the
writing and drafting of conditions; poor process in compliance activities, and
response to very serious harm; and poor process, finally, and that is
continuing, in the review and assessment of what the problem was, meaning that
future applications which should have learnt from the problems in Gladstone
have not learnt at all what is going on.[46]
Issues with the approvals process
6.28
The committee received evidence alleging that port development in
Gladstone Harbour was poorly managed and that there were deficiencies in the approval
process.
6.29
As noted by WWF-Australia and the Australian Marine Conservation
Society, the Bund Wall Review identified serious deficiencies in both the
approval process (the environmental conditions attached to the development
approval were vague) and follow-up compliance monitoring of the Gladstone
Western Basin project. The submission stated that the project had been plagued
by poor practice due to the actions of Gladstone Ports Corporation and Australian
and Queensland Government officials. Therefore, WWF-Australia and the
Australian Marine Conservation Society contended that there was a need for a
'thorough shake-up of all decision-making processes for development approvals,
and the need for ongoing vigilance by regulators during the life-time of any
project'.[47]
6.30
It was also suggested that the consultation process was inadequate, because,
for example, the concerns of the fishing industry had been ignored. Mr Simon
Whittingham Gladstone Fish Market gave evidence about a meeting attended by
fishing stakeholders in 2009 which exemplified these concerns:
There was a lot of animosity at this meeting due to the
importance identified by fishers of the grounds that were going to be reclaimed
and the integral role it played to stock recruitment for following seasons of
fish, mud crabs and prawns. It must be said that even after all the banging of
fingers and fists on the charts, the plan, which was being vigorously contested
by local fishermen, was eventually implemented.[48]
6.31
Save the Reef called for 'genuine, open and transparent consultation
with the Australian community, affected industries and relevant scientific
experts, and genuine consideration of the broader community's views in final
decisions'. It was noted that Gladstone Harbour provides a good example of 'how
difficult it was to get the balance right'.[49]
Issues relating to compliance with
conditions
6.32
Others noted that compliance and monitoring was inadequate. Mr McCabe
cited the Bund Wall Review, which noted that most of the environmental
conditions in relation to the development of Gladstone Port were satisfied, but
companies, port corporations and government officials failed to properly
communicate that to the general public, contributing to mistrust amongst
community and non-government organisations.[50]
Ports Australia acknowledged the advantages of better communication, using an
improved information management system which would include the results of
required monitoring programs, as this 'could help to improve public confidence
that dredging projects are managed effectively and have not resulted in
unanticipated impacts'.[51]
6.33
However, Mr McCabe suggested that the main compliance-related issue was
not poor communication but 'that the conditions set were inadequate in the
first place'. He went on to argue that 'if you are simply complying with an
inadequate condition and not reporting on it, that is not good enough'.[52]
6.34
Dr Landos agreed that the conditions were poor, noting that although
there were many conditions placed on the project they 'were hastily prepared without
all the information from the proponent'. He went on to say:
Unfortunately, having conditions drawn up to manage these
large projects does not in itself prevent harm occurring, and Gladstone serves
as a perfect example of this problem.[53]
6.35
A further problem outlined by Dr Landos was the failure by the
Department of the Environment to monitor compliance with conditions. He argued
that this was because the conditions that were set were 'too weak to take
action on', citing an example of where the department:
...demonstrably approved ongoing dredging during the 2013 flood
conditions, further adding to the turbidity loads in the harbour, which were
already stressing quite stressed out seagrass. [The department] failed to take
any notes on the limited site visits they undertook for compliance.[54]
6.36
Indeed, the committee notes that the Bund Wall Review also found that
the Department of the Environment was faced with a number of problems relating
to the monitoring of compliance with conditions. In particular, the report of
the review noted that 'the large number of approved projects across Australia
(currently around 1200) means that departmental monitoring officers cannot
confirm project compliance on the ground in real time, but depend on desktop
checks'. The report recommended that resource levels within the department
should be bolstered to ensure adequate monitoring capacity. The report also
noted that, since June 2012, there has been a significant increase in
monitoring capacity (now around 30 staff), which allows greater oversight of
more projects. Finally, the report recommended that this increased resourcing
should be maintained as a matter of priority.[55]
6.37
The committee also notes that the Australian National Audit Office
(ANAO) recently conducted an audit of monitoring of compliance with approval
conditions under the EPBC Act, published in June 2014. The ANAO's report
identified a number of concerns with the Department of the Environment's
compliance-monitoring activities and made a number of recommendations to address
these shortcomings.[56]
6.38
A representative of the Department of the Environment told the committee
that it has stepped up its compliance and monitoring processes in recent years.
This has included the implementation of a comprehensive business-improvement program
since 2012, to improve its monitoring compliance procedures, including doubling
the number of staff in the compliance and enforcement branch, and putting in
place a range of standard operating procedures.[57]
6.39
Mr McCombe from the Minerals Council of Australia suggested that the
deficiencies in the Australian Government's monitoring and compliance processes
identified in the Gladstone Harbour reviews were an illustration of the need
for a more efficient and streamlined regulatory process:
...regulatory processes should be more efficient and more
streamlined and that those resources should be consolidated. We believe that
regulations should be appropriately resourced. We think at the moment the
duplication between the Commonwealth and states is a misuse of those
Commonwealth resources and we can see how stretched the Commonwealth perhaps
have been in recent years in ensuring their compliance activities were
completely and wholly undertaken.[58]
6.40
However, Ms Arnold of Australians for Animals told the committee that
the compliance monitoring problems in Gladstone actually stemmed from the
assessment bilateral agreement between the Commonwealth and Queensland:
The bottom line, the foundational problem, was the bilateral
agreement. There were never any proper clear instructions, in spite of what was
written in the bilateral agreement, about who would monitor, when they would
monitor, how they would monitor and what would be done in terms of compliance
issues...complaints of noncompliance that we put to Canberra were basically
disregarded...[and] no [Commonwealth environment officials] were allowed to go on
site unless they had permission from the Gladstone Ports Corporation.[59]
6.41
Ms Arnold suggested that, to avoid self-regulation, the approvals
process needs to include third-party independent audits of compliance with
conditions of approval.[60]
6.42
Other witnesses identified an inherent conflict of interest in the
situation at Gladstone. For example, Mr Brodie, of the ARC Centre of Excellence
for Coral Reef Studies at James Cook University, cited Gladstone as an example
of the need for the Commonwealth to retain its environmental powers:
The Queensland government is both the proponent of the port
development and the regulator, and it did not work. It cannot possibly work
ever. So, while that is the case, you cannot expect the Queensland government
to manage the coastal environment, much less the land environment, at all.[61]
6.43
In the same vein, Dr Landos stated:
...there is a clear issue of conflict of interest where we have
a government body who stands to make a profit from the operation. For instance,
in Gladstone, Gladstone Ports Corporation is a wholly owned government
corporation, so there is a flow of income to the government there as well as
from the promotion of the mining industry which will export out of that area—in
royalty flows to the government. Where there is a financial benefit that flows
to the state government, the state government should not be the body
responsible for approving these types of developments.[62]
6.44
The 'one stop shop proposal' and proposed approval bilateral agreement
is discussed further in Chapter 8.
Gladstone Healthy Harbour
Partnership
6.45
In response to community concern and the World Heritage Committee
concerns over the health of Gladstone Harbour, the Queensland Government has
developed the 'Gladstone Healthy Harbour Partnership' as a forum to bring
together parties and to maintain and, where necessary, to improve the health of
Gladstone Harbour. The guiding principles of the partnership were based in
open, honest and accountable management; annual reporting of the health of
Gladstone Harbour; and management recommendations and actions based on rigorous
science and strong stakeholder engagement.[63]
6.46
The Gladstone Healthy Harbour Partnership was launched in November 2013
with partners across community, government, industry and research
organisations. Each partner signed a memorandum of understanding reflecting the
guiding principles.[64]
The Queensland Government has invested $3 million into the partnership over a
two-year period and this has been matched by industry, community, research and
local government. The Australian Government is also supporting the Gladstone
Healthy Harbour Partnership by committing up to $1 million to the programme
over the next two years.[65]
6.47
The Australian and Queensland Governments submitted that the Gladstone
Healthy Harbour Partnership has developed a report card program which will
report on 'the community's vision of a healthy harbour across environmental,
social, economic and cultural dimensions'. The program will be conducted in
partnership with government, research, community and industry and the report
card will be guided by recommendations of an independent science panel. The
first pilot report card will be developed in 2014, with the first full report
card scheduled for 2015.[66]
6.48
In principle, WWF-Australia and the Australian Marine Conservation
Society supported the establishment of the Gladstone Healthy Harbour
Partnership but at the same time noted that:
...the Queensland government also announced plans to continue
development at Gladstone and duplicate the main shipping channel at Gladstone
which will involve 12 million m3 of dredging. In December 2013
approval was given for the fourth LNG Facility on Curtis Island and a Gas
Transmission Pipeline to Curtis Island...[67]
6.49
In contrast, Ms Arnold of Australians for Animals suggested that the
creation of the Gladstone Healthy Harbour Partnership 'sets a most alarming
precedent'. She was concerned that there is no representation from
non-government organisations, and suggested that 'we cannot have agencies and
partnerships put together to monitor state and federal regulations'.[68]
6.50
The Capricorn Conservation Council expressed the view that the Gladstone
Healthy Harbour Partnership would not be enough to win back public confidence
in the environmental decision-making processes, stating:
While the Gladstone Healthy Harbour Partnership's first
report card is expected late in 2014, the public trust in the oversight of the
harbour is almost beyond repair. Reasonable requests and recommendations in EIS
submissions were generally ignored or dismissed. Most independent reviews
simplistically looked at whether or not the project had met with environmental
conditions, but not at the adequacy of those conditions.[69]
Abbot Point
6.51
The Port of Abbot Point commenced operations in 1984 and is currently a
coal export port. It is located 25 kilometres north of Bowen, and is in the
vicinity of the Galilee and Bowen coal basins. The port is located within an
exclusion area and therefore, although it is within the Great Barrier Reef
World Heritage Area, it remains outside the Marine Park.[70]
The port is also adjacent to the Kaili (Caley) Valley Wetland, a large coastal
wetland system covering an area of approximately 5,154 hectares and listed
under the Directory of Important Wetlands in Australia. The wetland represents
one of the largest intact wetland systems between Townsville and Bowen.[71]
6.52
The Queensland Ports Association commented on the development of Abbot
Point:
The port is strategically located to provide export capacity
from the northern Bowen basin and potentially in the future the Galilee basin.
There are a number of projects currently proposed at the port that if realised
will result in an expansion of infrastructure and export capacity. Currently
two new terminals are in advanced stages of planning, while market demand and
interest is being examined to determine what further expansion may be required
in the medium to longer term.[72]
6.53
The issue of dredging and dumping of dredge spoil for port development
at Abbot Point, including perceived flaws in the associated decision-making
process, was raised repeatedly during the committee's inquiry.
Abbot Point expansion proposals and
approvals
6.54
There are a number of proposals, both approved and under consideration,
for expansions at the Port of Abbot Point. These include:
-
capital dredging program for the proposed terminals 0, 2 and 3 (approved
on 10 December 2013 by the Hon. Greg Hunt MP, Minister for the Environment);[73]
-
Adani Abbot Point Coal Terminal 0 (approved on 10 December 2013
by the Minister for the Environment);[74]
-
a proposal by BHP Billiton to construct and operate the T2 coal
terminal expansion (withdrawn in October 2013);[75]
-
a proposal by Waratah Coal, referred in January 2012, to
construct and operate a new coal terminal at Abbot Point (still active under
consideration);[76]
-
Abbot Point Coal Terminal 3, Hancock Coal Infrastructure Pty Ltd
(approved on 4 October 2012);[77]
and
-
Abbot Point expansion project, known as the AP-X Project, proposed
by the Queensland Government (still in the tendering process, no application
for environmental approval has been lodged).[78]
6.55
The committee received a considerable amount of evidence during its
inquiry in relation to the capital dredging program and in particular the approval
of the disposal of the three million cubic metres dredge spoil from the
dredging program in the Great Barrier Reef World Heritage Area.
Capital dredging program for the
proposed terminals 0, 2 and 3[79]
6.56
The dredging is for six new berth pockets and the associated ship apron
areas for three coal export terminals (terminals 0, 2 and 3) at the existing
Port of Abbot Point. The sediment will be removed from a 185 hectare dredge
area within port limits, to a maximum depth of five metres. The proposed spoil
disposal site is located 24 kilometres north-east of Abbot Point. The
Australian and Queensland Governments advised that:
An offshore option was found to have better results as the
silt to be disposed is not toxic and will be disposed on similar material on
the sea bed. The proposed disposal site is 20 kilometres from the closest
significant areas of seagrass and 40 kilometres from the closet mid-shelf coral
reef.[80]
6.57
The original proposal requested approval for the disposal of 38 million
cubic metres of dredge spoil. The final approval to the expansion project was
granted subject to 95 conditions on 10 December 2013 by the Australian
Government and only allowed for the disposal of three million cubic metres of
dredge spoil.[81]
6.58
On 31 January 2014, the Great Barrier Reef Marine Park Authority
(GBRMPA) approved a permit application by North Queensland Bulk Ports
Corporation to dispose of dredge spoil at a deepwater location offshore of
Abbot Point. The Australian and Queensland Governments advised that 'the permit
was assessed in accordance with the GBRMP Act and is subject to strict
environmental conditions'.[82]
6.59
The approval by GBRMPA to dispose of dredge spoil included conditions
requiring:
-
that no more than 1.3 million cubic metres of sediment be dredged
or disposed of in a year, unless the proponent can demonstrate that increased
dredging will not compromise water quality;
-
that dredging and disposal activities only be undertaken between
1 March and 30 June each year to protect water quality during critical times
for seagrass growth and coral spawning; and
-
an offsets plan to address any loss and potential loss of
seagrass. The plan will provide a net benefit outcome to the Outstanding
Universal Value of the Great Barrier Reef World Heritage Area. It will offset
any fine sediments resulting from the dredging and dredge spoil disposal
activities and available for re‑suspension by an equivalent 150 per cent
reduction in the load of fine sediments entering the marine environment from
the Burdekin and Don catchments.[83]
Legal challenges to the Abbot Point
decisions
6.60
The committee notes that the Minister's approval decision is being
challenged in the Federal Court under the Administrative Decisions (Judicial
Review) Act 1977 (Cth). The case has been set down for trial in October
2014.[84]
6.61
The North Queensland Conservation Council (NQCC), a party to the case,
submitted that it will 'focus on the inadequacy of the research undertaken by
the proponent and the failure to take into account adequately the London
Protocol to which Australia is a signatory'.[85]
6.62
The Administrative Appeals Tribunal is also hearing a challenge to
GBRMPA's approval of a permit under the Sea Dumping Act.[86]
World Heritage Committee concerns
about Abbot Point
6.63
As set out in Chapter 2, the World Heritage Committee expressly
mentioned the Abbot Point approval in its recent June 2014 decision, noting
with concern and regret Australia's approval for dumping three million cubic
metres of dredge material inside the property prior to having undertaken a
comprehensive assessment of alternative and potentially less impacting
development and disposal options. The World Heritage Committee further
requested that Australia ensure that the option selected does not impact Outstanding
Universal Values, and is the 'least damaging option available'.[87]
6.64
As Mr Richard Leck of WWF-Australia observed, expressing concern and
regret is 'very strong language' when used by an agency of the United Nations.[88]
6.65
However, Mr Roche from the Queensland Resources Council told the
committee that:
We felt that the World Heritage Committee misunderstood the
rigour of the assessment processes that went into the Abbot Point coal
terminal—the multiple assessments, the cumulative impact assessment, the
comprehensive scientific studies. We thought that was a misplaced observation.[89]
Other concerns
6.66
Many submitters and witnesses expressed grave concerns or were highly
critical of the decision to allow disposal of the dredge spoil from the Abbot
Point dredging program in the Great Barrier Reef Marine Park.[90]
For example, the Whitsunday Charter Boat Industry Association submitted that:
Given water quality has been identified as one of the
greatest threats to the GBR, recent decisions by the Minister for the
Environment, Mr Greg Hunt, to dump 3,000,000 m3 of dredging spoils
from the Abbot Point expansion into GBRMPA waters is inconsistent with solving
the problem of declining water quality within the GBRMPA, and with the World
Heritage Committee recommendations.[91]
Location of dredge disposal site
6.67
The committee heard that the Minister's approval decision 'indicated a
disposal site', but that the 'conditions also allowed for the proponents to
investigate other sites if they choose to', and that they have not yet
identified any alternative sites.[92]
A representative of the Department stated:
They have an approval for a particular location. If they want
to find a different location, that is in their hands to consider and have
assessed a different location.[93]
6.68
Representatives of the Department of the Environment told the committee
that the proposed site is '25 kilometres from the nearest seagrass beds and 40
kilometres from the nearest coral'.[94]
6.69
In response to evidence that there may be some coral isolates in the
area of the proposed disposal site,[95]
Dr Reichelt told the committee that 'I would not say there is no coral; I would
say there are no emergent platform coral reefs within a long distance'.[96]
6.70
In answers to questions on notice, GBRMPA advised that 'the approved
dredge material disposal area is approximately 45 kilometres from the nearest
offshore reef (Old Reef)'.[97]
The Queensland Government stated that 'while there may be some examples of
inshore corals around Abbot Bay, it is important to note that the Abbot Point
approval is subject to strict conditions to prevent impacts'.[98]
Possible impacts
6.71
Concerns were expressed about the potential impacts of the Abbot Point
expansion and associated dredging and dumping on the Whitsundays, the tourism
industry of the area[99]
and on fishing-related businesses in the area.[100]
6.72
Mr Terry Must of Arabon Seafoods noted that, although the dredging site is
only 12 square kilometres in size, by the time the shipping comes in, its footprint
will be hundreds of square miles, with the whole area becoming a 'no-go zone
for trawlers and fishermen'. This will have devastating impacts on the fishing
industry in the area.[101]
6.73
Mr Jon Brodie told the committee that 'dredging has large effects on
coral and fish...none of which were properly taken into account in the decision
at Abbot Point'.[102]
6.74
The Whitsunday Charter Boat Industry Association stated that they were
'extremely concerned' about the Abbot Point decision, particularly because the
dredging and dumping would add to the water quality problems already being
observed in the Whitsundays area.[103]
6.75
Mr McKenzie of the Association of Marine Park Tourism Operators told the
committee that, given that the Outlook Report 2014 identified that the
reef is in poor condition and declining, there is 'no logic' to the decision to
approve permits for dredging and dumping more silt in the reef area.[104]
Submitters also suggested that the decision to allow for the disposal of the
dredge spoil had rendered the considerable efforts of the agricultural sector
to reduce sediment and nutrient run-off as 'useless'.[105]
This issue was discussed at a more general level in Chapter 5.
6.76
In contrast, the Queensland Resources Council submitted:
All dredging and at sea placement activities are subject to
detailed environmental assessments and management to ensure impacts are
effectively reduced and managed to avoid environmental harm. In addition to
sediment plume modelling, each proposed dredging project must undertake a
rigorous analysis of the sediment to ensure it is not contaminated or toxic;
and also a thorough investigation of disposal options. All dredged material
that is placed offshore is placed in designated areas following a detailed
environmental assessment and approval process. These seabed areas are generally
free of vegetation, distant from major coral reefs and many have been used for
decades. Dredged material is never placed on coral reefs or other areas of high
conservation value.[106]
Composition of dredge material
6.77
The Queensland Government stated that the dredge material to be disposed
of in the Marine Park is 'a mixture of sand, silt and clay'.[107]
GBRMPA confirmed this by stating that the composition of dredge material is on
average 7 per cent gravel, 54 per cent sand, 19 per cent silt and 20 per cent
clay. It was noted that the material is unlikely to contain garnet, and any
heavy metals or polynuclear aromatic hydrocarbons that may be present were
below the relevant screening levels in the National Assessment
Guidelines for Dredging 2009.[108]
6.78
However, Dr Landos told the committee that acid sulphate soils 'may well
be present at Abbot Point'.[109]
As noted in the previous chapter, there is also an issue of the potential resuspension
of sediments and how far they travel. For example, Mr Brown of the Whitsunday
Charter Boat Industry Association told the committee that:
...we have a long way to go. The reason we are all on the back
foot, and I think the marine park authority would agree with this, is that
dredging and sea disposal is just part of business as usual and no-one had
really thought about it impacts in any great manner. Now that this has
happened, Abbot Point has become this lightning rod and so science is trying to
catch up. That is why things keep coming out slowly as our understanding
catches up and as more people put more energy into understanding the impacts,
if there are impacts. We would be the first to agree that we do not understand
fully, and that is our concern.[110]
Modelling and research
6.79
Several submissions and witnesses expressed concern about the modelling of
dredge material dispersion used in Environmental Impact Statements for dredging
projects.[111]
6.80
As noted in the previous chapter, the Whitsunday Charter Boat Industry
Association pointed to inconsistencies in modelling of sediment drift plumes from
dredging near Hay Point in 2006, which they submitted reached the Whitsundays
(80 kilometres away) and queried whether the Hay Point dredging and dumping has
had an influence on the increased sediment in the Whitsundays.[112]
Mr Tager pointed to modelling of deep ocean currents 'which showed that
sediment was transported further and that dump spoil was resuspended more often
than previously believed'.[113]
Mrs Janice Claxton of the Whitsunday Charter Boat Industry Association told the
committee:
The problem, I believe, is that there is no science—GBRMPA
have told us there is no science—that actually measures the movement of
sediment once it has been dumped. To a point there is science, but it is
targeted. They have admitted to us that there have never been any tests to see
whether the impacts actually reached the Whitsunday islands.[114]
6.81
Ports Australia acknowledged the deficiencies in the modelling systems
applied to the Hay Point and Gladstone Port activities. However, it was noted
that 'improved predictive modelling techniques have enabled environmental risk
to be more effectively managed'.[115]
6.82
However, Dr Oliver of AIMS told the committee that it had provided
advice to GBRMPA 'on a number of occasions' in relation to the modelling used
for the Abbot Point decision:
We did find that there were deficiencies in the overall
modelling that had been done and we pointed them out very clearly to the marine
park authority in assisting them with their final assessment. I am not sure to
what extent those problems have been addressed, but we certainly did agree that
there could be areas where the modelling could be significantly improved.[116]
6.83
Mr Jon Brodie suggested that documents released under freedom of
information requests revealed that the review of the modelling done by AIMS was
a 'damning indictment of the sediment transport modelling at Abbot Point, which
was found to be inadequate—basically, they were standards of modelling we were
able to do 20 years ago, not today'.[117]
6.84
Mr Black of the Queensland Government advised that 25 per cent of the
sediment dredged at Abbot Point could possibly resuspend.[118]
However, Mr Jon Brodie expressed concern that the entirety of the sediment
could be 'completed resuspended, especially in cyclonic conditions'.[119]
6.85
In response to a recent study undertaken in Western Australia which
found that dredging and dumping increases the risk of coral disease, Ms Story
of the Queensland Resources Council suggested that the Abbot Point proposal is
quite different to the subject of that research. In particular, she told the
committee that:
That was a study of seven million cubic metres of spoil that
was conducted over an 18-month period. The impacts were highly localised...the
impact from the dredge locations had the greatest impact...the placement area had
even less impact. So it is about the dredging area rather than the placement
area...Comparing that to the Great Barrier Reef and the Abbot Point proposal: the
coral reefs there are 40 kilometres away, the dredging projects are 1.3 million
cubic metres at any one time and the project limit is three to four weeks
rather than 18 months.[120]
6.86
Similarly, an officer of the Department of the Environment told the
committee that:
...with the volumes and the intensity of the dredging campaign
and the length of the dredging campaign and its proximity to coral...there were
important findings with respect to impacts on coral health which would not seem
to apply in the space of Abbot Point.[121]
Offsets
6.87
In June this year, this committee examined the proposed environmental
offsets for the North Queensland Bulk Ports Corporation's capital dredging
project as Appendix 6 to the Senate Environment and Communications References
Committee report into Environmental Offsets. That case study outlined many of
the issues related to the proposed offsets plans.[122]
During this inquiry, the committee heard from the Department of the Environment
that the actual offsets plans have not yet been submitted for the three
projects approved at Abbot Point (the dredging project, and Terminal 0 and
Terminal 3). The Department noted that:
When submitted, the plans are to include a marine offset
strategy to compensate for any residual impacts on Green and Flat back Turtles.
They are also required to achieve a net benefit to the outstanding universal
value of the Great Barrier Reef World Heritage Area and an offsets plan to
address any loss of seagrass from dredging actions.[123]
6.88
The committee notes that the offsets conditions in relation to Abbot
Point were widely criticised in evidence to this inquiry and to its previous
inquiry into environmental offsets.[124]
A particular issue was the feasibility of the offset condition requiring 150
per cent of fine sediments to be offset by a reduction in the load of fine
sediments entering the marine environment from the Burdekin and Don catchments.
6.89
The committee notes that evidence received in its inquiry into
environmental offsets showed that around 1.62 million tonnes of fine sediments
would need to be offset. According to information provided by the Department of
the Environment to this inquiry, the average cost of reducing one tonne of sediment
through the Reef Rescue program would cost approximately $140. The committee
notes that the total cost of this offset would therefore be in the order of
$226.8 million.[125]
6.90
Mr Brodie described the offsets to reduce sediments from the Burdekin
and Don catchments as a 'farce' and 'technically and financially impossible to
implement'.[126]
Consideration of alternatives
6.91
Several submissions queried why alternative options to dumping, such as
land-based disposal, or the use of trestles, were not taken.[127]
For example, Mr Jeremy Tager submitted that 'there were viable land based
alternatives' but that the ports authority claimed that land based disposal
would involve 'disproportionate costs'. He argued against this claim, stating
that:
...the cost of dumping on land as a proportion of the total
coast of the project and the total revenue of the project—which is a
multibillion dollar project—is not disproportionate at all.[128]
6.92
Mr Richard Leck of WWF-Australia similarly told the committee:
The proposal that was put forward was done because it was
cheap. If you were to develop Abbot Point, it is possible to do it to minimise
the amount of dredging and dumping that occurs at Abbot Point...I would argue
vehemently that an additional $500 million is a perfectly reasonable price to
pay to operate alongside one of the world's premier World Heritage areas.[129]
6.93
Mr Brodie also confirmed the availability of more environmentally sound
options by telling the committee:
Abbot Point could have gone ahead with a better option and a
better process to get to an option that would have allowed the port to go ahead
with limited damage to the Great Barrier Reef.[130]
6.94
Mr Brodie suggested that there were five options:
-
building a very long jetty where there is no dredging involved at
all;
-
building a medium-length jetty where there is only a very small
amount of dredging;
-
dredging three million cubic metres and dumping offshore;
-
dredging three million cubic metres and putting it behind a small
bunded area; and
-
dredging three million cubic metres and putting it on the land.
6.95
Mr Brodie examined the pros and cons of these options and was of the
opinion that the long jetty with no dredging was the most environmentally
friendly, particularly as it involved no dredging. In his view the second best
option was to dredge and place the spoil behind a small bunded area.[131]
6.96
Mr Brodie went on to comment that 'there was no consideration of some of
the more feasible options or options that caused less damage to the Great
Barrier Reef than the one that has now been chosen—for instance, a small bund
wall was never considered'. He concluded that:
...we got a result out of that process that was the quickest,
cheapest and dirtiest option for the Great Barrier Reef, designed specifically,
really, to cause most damage to the Great Barrier Reef of all the possible
options.[132]
6.97
Submitters and witnesses noted, for example, that GBRMPA had suggested
that best environmental practice, and their preferred option, would have been to
minimise dredging through extending trestles into deeper water.[133]
However, this advice was not followed. It was suggested that the reason for
this was that the proponent rejected this option as being unfeasible 'due to
uncertainty in approval requirements and timeframes and significant additional
costs'.[134]
The Whitsunday Charter Boat Industry Association referred to the GBRMPA risk
assessment, which identified extended trestles as GBRMPA's preferred option,
disposal on-shore as the second best option, and disposal in the Marine Park as
the least favoured option.[135]
6.98
However, in response to questioning on this issue, a representative of
the Department of the Environment told the committee that 'there was an
extremely comprehensive assessment of the propositions that were put to us around
Abbot Point'.[136]
In response to a question on notice, the Department stated that a 'multi-criteria
analysis concluded that offshore disposal of dredged sediment was the best
option for disposal on environmental grounds, prior to consideration of costs'.[137]
6.99
Mr Elliot from GBRMPA told the committee that GBRMPA's decision in
relation to the disposal of dredge spoil in the Great Barrier Reef Marine Park
'was independently taken from the minister's' decision about dredging.[138]
He said:
Under our legislation, a decision under the Great Barrier
Reef Marine Park Act cannot occur before a decision under the EPBC Act. So the
minister must make his decision first and then there is a statutory time frame
under which we have to make a decision...[139]
6.100
Mr Elliot explained that 'alternatives were investigated', including
'land disposal and trestles':
Those alternatives were investigated, in particular in the
supplementary public environment report that was done by the proponent, and
that was after we had actually engaged with them to request additional work to
be done on a number of alternatives. So they were considered as part of the
process.[140]
6.101
In terms of the change in advice, Mr Elliot explained that GBRMPA:
...worked with the proponent throughout the process to try to
shape that proposal and we required them to investigate alternatives as well.
But when we got to the end of the process, the proposal we were making a
decision on was for offshore disposal not for any other option.[141]
6.102
He noted that GBRMPA's preferred options were set out in a document in
2013, released during the approval process:
When we were examining alternatives such as trestles and land-based
options, we were providing feedback to the proponent and to the department to
suggest that we believed there were alternatives that would have a better
environmental outcome for the marine park. That does not mean that they were
engineeringly feasible or that there were not other issues associated...
The other thing to note of course is that the proposal we
were making a decision on was for an offshore disposal...We could not provide a
permit for something other than what was applied for. So we could not say, 'We
are going to give you a permit to dispose it on land.'[142]
6.103
In response to questioning, Mr Elliot told the committee that the
accusation that GBRMPA had been 'leaned on' to change its position was not
correct.[143]
Dr Reichelt noted that an 'alternative disposal site analysis' was done as
part of the conditions of approval, with 'much improved modelling'.[144]
6.104
One land-based disposal option that was offered in January 2014 by Mr
Kevin Murphy of Bowen Land Development Corporation was that the dredge material
from the Abbot Point expansion be pumped into the old Cheetam salt works, 17
kilometres from Abbot Point. Mr Murphy explained that the salt works is divided
into 27 sealed ponds covering a site of 300 hectares. The ponds have a capacity
to accommodate over six million cubic metres of fill.[145]
When questioned about why the salt works were not considered, GBRMPA and the
Department of the Environment stated:
We are advised that Mr Murphy's salt works was not available
as an alternative at the time the assessments were completed.
North Queensland Bulk Ports have not submitted a proposal for
the assessment of the disposal of dredged material at the salt works site to
date.[146]
6.105
GBRMPA also explained that land-based disposal of dredge material is
generally more expensive than off-shore disposal 'due to the de-watering
process...which involves the storage of the dredge material, as well as the de-watering,
stabilisation and separation of the material'.[147]
However, Mr Murphy explained that the proposed salt works site could act as 'a
giant filtration system', initially allowing for the treatment of potential
acid sulphate soil and for the water to be flocculated. Then, the clear surface
water would naturally flow through the ponds into the ocean.[148]
In response to this option, Mr George Christensen MP, the Federal Member for
Dawson, has asked North Queensland Bulk Ports Corporation to exhaustively
investigate every land-based option and has stated 'if a viable option emerges
I will ensure that the spoil is dumped on land, not at sea'.[149]
The committee notes reports that North Queensland Bulk Ports Corporation is
considering altering its plans to dispose of dredge spoil material at sea.[150]
The committee further notes that the Minister for the Environment recently
stated that he would welcome and consider alternative options to offshore
disposal.[151]
Capacity at Abbot Point
6.106
As discussed in the previous chapter, there was some discussion as to
whether port expansions, including the expansion at Abbot Point, are even
necessary, and whether existing ports are operating at full capacity.
6.107
Mr Anderson from Ports Australia told the committee that Abbot Point 'is
pretty much close to capacity at the moment'.[152]
Nevertheless, the committee notes that the North Queensland Bulk Ports
Corporation website, the website of the company responsible for the Port of
Abbot Point, states that the current export capacity of Abbot Point Terminal 1
(T1) is 50 Mtpa and, last year, the annual throughput was around 22.9 Mtpa.[153]
6.108
However, Mr Roche from the Queensland Resources Council explained that
at Abbot Point T1 'there is one ship loader that is not functional at the
moment'. He further stated that 'the current port capacity of that operation is
33 million tonnes', and that the port will 'go close to capacity' by the end of
next financial year.[154]
6.109
As noted in the previous chapter, the Queensland Government explained
that the listed capacity of a port is often given in terms of its theoretical
maximum throughput and this figure does not take into account factors such as
maintenance shutdowns and adverse weather. It was noted that the entire present
capacity of the Port of Abbot Point has already been allocated to resource
companies, meaning that new capacity will be required for new and expanding
coal producers.[155]
Process for approval
6.110
Mr McKenzie of AMPTO explained that they were surprised that the permit
was granted before the Strategic Assessment was finalised:
...we did not expect to see any of the permits being granted
until such a time as we understood the full cumulative impact of all the
proposed port development. The real issue is that then they turned around, six
months before the finalisation of that document, and issued permits. Quite
frankly, our industry felt betrayed in the trust that we had given to the
federal government on that document and that process.[156]
6.111
Based on documents received under freedom of information requests, it
was claimed that experts in GBRMPA had initially recommended that the dumping
permit not be issued.[157]
For example, Mr Coates of CAFNEC told the committee that 'internally the advice
seems to have been quite different to what has gone to the minister in the
end'.[158]
6.112
It was suggested that, as the Department of the Environment gave its
approval first, before GBRMPA had made a decision about the sea dumping permit,
GBRMPA was then left in a politically difficult position.[159]
Mr Jeremy Tager told the committee that 'despite really clear evidence that the
staff at GBRMPA were not recommending approval of either the dredging or the
dumping, approval was given, which seems to me to be a clearly political
decision'.[160]
He also noted that a change occurred in GBRMPA after a change in the delegated
decision‑maker and 'it is hard to conclude anything except that there was
political interference'.[161]
Impact on GBRMPA
6.113
It was submitted that the Abbot Point decision has undermined community
confidence in GBRMPA and its independence.[162]
For example, the North Queensland Conservation Council submitted that:
Having been involved in public education in relation to
marine issues in Townsville, we can attest to the fact that very, very many in
the community feel let down by the action of GBRMPA in providing permits to
allow the dumping of dredge spoil in the GBRMP at Abbot Point. The agency that
was seen as 'the good guys' 'on the side of the Reef' is now, sadly, regarded
as an agency that can be swayed by the government of the day.[163]
6.114
They further submitted that they are aware that many GBRMPA staff also
'did not agree with the dumping decision and are sad, mortified and angry that
their expert advice was not accepted'.[164]
6.115
The Cairns Local Marine Advisory Committee submitted that it wants 'a
strong and trusted advocate' for the Great Barrier Reef and that 'the
reputation of the Authority has been badly damaged'.[165]
Similarly, CAFNEC submitted that:
Community confidence in decision making around GBR protection
is at a low point and huge improvements in consultation, research and policy
will be required to ensure that problems that have come to light around the
Abbot Point decision are not repeated.[166]
6.116
Ms Felicity Wishart of the Australian Marine Conservation Society told the
committee that:
There was clear advice from the marine park authority experts
that dumping should not occur, and yet approval was given by the marine park
authority. That raises serious questions about whether that organisation is
fulfilling its mission.[167]
6.117
In response to further questioning on this issue, Ms Wishart further
explained:
...there were serious concerns by the experts about the impact
particularly of dumping in the marine park. They were strongly recommending
that this was not the preferred option, that other options should have been
taken first. In the case of Abbott Point, in my opinion, the Marine Park
authority has been put in an invidious position where the minister approved the
dredging and a dumpsite within the marine park, even though he anticipated it
would not be the final dump site, which then put inordinate pressure on the
Marine Park Authority to then have to issue the permit...we saw politics
overriding science in that particular circumstance.[168]
Other process issues
6.118
It was also suggested that there was a 'lack of transparent consultation
and provision of timely information' in relation to the Abbot Point decision.[169]
The Whitsunday Charter Boat Industry Association submitted that it was:
...never consulted by NQBP or the GBRMPA which we would expect
as our operators have permits to operate at Holbourne Island only 6 km from the
catalina dump site.[170]
6.119
It was also suggested that, on the basis of the precautionary principle,
the disposal should not have been approved, and the permit should not have been
issued, since there is insufficient information on the impacts of dumping.[171]
6.120
However, industry groups such as the Queensland Ports Association
pointed to the Abbot Point 'Cumulative Impact Assessment' as a 'comprehensive
evaluation of the combined effects of port development'.[172]
The Queensland Ports Association submitted that this cumulative impact
assessment, combined with the environmental assessment Public Environment
Report:
...highlight that port development, including a 3 million m3
capital dredging campaign, can occur in a sustainable manner and deliver
conservation objectives that maintain or improve the current environmental
situation. Further, the studies also showed that the marine values of the area
could be protected and that the Outstanding Universal Value (OUV) of the GBR
preserved through appropriate design, management, monitoring and offsetting
residual impacts.[173]
6.121
In contrast, WWF-Australia and AMCS submitted that:
...the environmental impact assessments undertaken for the
recent Abbot Point dredging and dumping approvals do not take into account
cumulative impacts and were done prior to the establishment of an
evidence-based framework for assessing impacts at a regional scale on the
Outstanding Universal Value of the Great Barrier Reef.[174]
6.122
Furthermore, Mr Tager noted that the 2012 dredging guidelines, which
took into account the effects of deep ocean currents on sediment
transportation, were not imposed on the Abbot Point development. He went on to
infer:
...because the Abbot Point development application went in
before the guidelines took effect, GBRMPA decided they could not impose them on
the ports authority. The ports authority, although they certainly could have
modelled based on deep ocean currents and the current knowledge that was
available about deep ocean currents, simply stuck to the legal requirements
rather than best practice and allowed themselves to do work that did not
reflect the reality on the ground.[175]
Lessons from Gladstone Harbour
6.123
Arabon Seafoods was concerned that the issues that have occurred in
Gladstone Harbour will occur again in the Abbot Point area.[176]
Arabon Seafoods suggested that there are clear lessons to learnt from the
issues in Gladstone Harbour:
There is potential for considerable environmental harm by
maritime developments in Abbot Point—such
environmental concerns evident from the port developments in Gladstone. The
Gladstone Port outcomes cannot be ignored for Abbot Point.[177]
6.124
Similarly, Mr Jon Brodie told the committee that the:
...at Abbot Point now it is meant to be all okay because we are
going to have stringent conditions. I do not believe it for a moment. We saw
what the stringent conditions did at Gladstone: they did nothing. So there is
no way we could ever trust the conditions[178]
Navigation: Previous Page | Contents | Next Page