Appendix 6
Abbot Point Dredging Project
Overview of project
Introduction
6.1
On 5 December 2011, North Queensland Bulk Ports Corporation Limited
referred a proposal under the EPBC Act to undertake capital dredging of
approximately 3 million cubic metres at the Port of Abbot Point, and for the
disposal of the dredged material (including options at sea). The proposal would
facilitate the development of Terminal 0, Terminal 2 and Terminal 3 at the Port
of Abbot Point in Queensland.
Impact of the project
6.2
On 6 January 2012, the project was determined to be a controlled action
due to likely significant impacts on World Heritage properties; National
Heritage places; listed threatened species and communities; listed migratory
species; Commonwealth marine areas; and the Great Barrier Reef Marine Park.
Assessment of the proposal
6.3
The project was assessed by Public Environment Report (PER) with
103 submissions received on the draft document. The proposal was approved
on 10 December 2013 subject to 41 conditions, including requirements to
mitigate and manage impacts on the environment and for the provision of
offsets.
Offset requirements
6.4
Condition 31 of the EPBC Act approval conditions requires the proponent
to submit an Offsets Plan to the Minister for the Environment for approval
prior to commencement of dredging and disposal activities. Under the approval decision,[2]
the Offsets Plan must:
-
address the loss of seagrass from the dredge area and areas of
potential seagrass loss resulting from the dredge plume extent;
-
outline the process to undertake actions that will result in a
net benefit outcome for the World Heritage Area;
-
consider how these offsets will contribute to programs or
incentives and align with the broader strategies and programs for the Great
Barrier Reef, including Reef Trust 2050;
-
150% of the total amount of fine sediments, potentially available
for re‑suspension into the marine environment from the dredging and
disposal activities, must be offset by a reduction in the load of fine
sediments entering the marine environment from the Burdekin and Don catchments.
This can take account of information on the sedimentation of fine sediments as
it becomes available (condition 31(d));
-
monitor and report on performance of the actions undertaken in
relation to the targets required at 31(d);
-
outline the consultation process undertaken with the Great Barrier
Reef Marine Park Authority in developing the Offsets Plan;
-
publish an annual public report outlining how the actions are
achieving the targets in 31(d) for the duration of this approval; and
-
outline contingency actions and additional management measures to
address any deficiencies to meet the targets at 31(d).
6.5
Condition 32 states that 'the approved Offsets Plan must be
implemented'.
6.6
The Department's submission states that:
The offsets were considered within the framework of the EPBC
Act Environmental Offsets Policy and to demonstrate that the outcome would
result in a net benefit. In relation to the 150% offset requirement, the
proponent suggested investment in sediment reduction options in the Great
Barrier Reef catchment, and the Department put forward the quantum required to
get a meaningful improvement in water quality.[3]
6.7
The Department's submission further advises that 'an independent
technical advice panel will review the adequacy of the mitigation, monitoring,
research and offset requirements and whether they meet the conditions of
approval, before any dredging begins'.[4]
6.8
The Department's submission states that:
Overall, the implementation of the conditions of approval
will result in a net benefit to the health of the Great Barrier Reef and better
environmental protection in the long-term.[5]
Legal challenge
6.9
The committee notes that the Minister's approval decision is being
challenged by the Mackay Conservation Group in the Federal Court under the Administrative
Decisions (Judicial Review) Act 1977 (Cth). The case has been set down for
trial in October 2014.[6]
Issues with the proposed offsets
6.10
As noted in Chapter 6, the committee does not intend to comment on
particular projects. However, the committee notes that submitters and witnesses
raised a number of key issues in relation to the offsets conditions for this
project. These included:
-
the feasibility of achieving the offset condition requiring 150%
of fine sediments to be offset by a reduction in the load of fine sediments
entering the marine environment from the Burdekin and Don catchments. Submitters
described this requirement as 'undoable', 'impossible' and 'highly complex'.[7]
For example, the Mackay Conservation Group calculated that this would require around
1.62 million tonnes to be offset, and argued that in the past decade the Reef
Water Quality program only managed to reduce sediment loads from rivers flowing
into the Great Barrier Reef World Heritage marine waters by 320,000 tonnes;[8]
-
whether the offsets requirement is 'like for like' (as discussed
further in Chapter 3) due to, for example, the differences between
sedimentation from river discharges and sedimentation from dredging;[9]
-
whether it is appropriate to be offsetting impacts on a World
Heritage Area at all (see Chapter 3);[10]
-
whether the mitigation hierarchy (as discussed in Chapter 3) has
been properly followed, including whether mitigation measures and alternative
options such as the disposal of spoil on land, were adequately and fully
considered.[11]
In addition, only fine sediments 'potentially available for re‑suspension'
are covered by the offset requirement, and as such, it was suggested that not
all the residual impacts being offset;[12]
-
whether the principle of additionality (discussed further in
Chapter 3) has been met—given that the Reef Water Quality Protection Plan 2013 already
aims to improve the quality of water entering the reef from broadscale land
use. Given this objective, ANEDO argued that no water quality offset can be
'additional' in the sense required by the EPBC Act Offsets Policy;[13]
-
the capacity to measure this offset in a timely and accurate way;[14]
-
the lack of specificity in the offset conditions, for example, the
method for achieving reductions in sedimentation is not detailed, nor any
timeframes for meeting the catchment sediment reduction. Similarly, the
requirement to 'address the loss of seagrass' was described as 'loosely
framed';[15]
-
transparency issues in relation to the process for negotiating
and deciding on offsets (discussed further in Chapter 4). For example,
Greenpeace advised that they had obtained documents through freedom of
information requests, which they claimed:
...show that they [the proponent] were presenting very
different numbers to the environment department than are available in the
public documentation. The public documentation does not at all articulate what
quantity of fine sediment will be available for resuspension, so you cannot
scrutinise it.[16]
-
lack of consultation with traditional owners;[17]
-
scientific uncertainties in relation to offsetting in the marine
environment, (discussed further in Chapter 4), such as the 'fundamental
problems with rehabilitating seagrass';[18]
and
-
timing issues in relation to the approval condition requiring the
preparation of an offset plan before dredging commences. Submitters were
critical that 'no timeframe is specified for approval of the plan or
implementation of offset activities',[19]
and that there is no requirement that the actual offsets be identified or
implemented prior to the commencement of dredging.[20]
Timing issues are discussed more generally in Chapter 4.
Navigation: Previous Page | Contents | Next Page