Chapter 4
Application and operation of the Bill
Introduction
4.1
The focus of this chapter is on the second of the two key areas of
debate raised during the committee's consultation process, namely, the
application and operation of the Bill's requirements that fibre-related
infrastructure be installed in specified developments.
Key matters raised
4.2
The key matters raised by submitters concerning the application and
operation of the Bill were:
- the scope of the Bill, specifically to what types of developments
it will apply, and how it will affect projects for which planning, development
and/or construction processes have already commenced;
- the content and implications for fixed-line telecommunications
service provision generally of the requirements to deploy fibre and/or install
fibre‑ready facilities; and
- ownership of the infrastructure, the intended access regime, and
integration of the infrastructure with the NBN.
4.3
To some extent, the grounds for discussion shifted between the time at
which written submissions were received and the committee's public hearing. The
Bill provides that the detail of the application and operation of the Bill's
requirements is to be provided for in subordinate legislation. This includes,
but is not limited to, the threshold 'triggers' at which developments will be
exempted from requirements to deploy fibre, and the stage of development to
which the Bill will apply. The committee's deadline for written submissions was
6 April 2010. On Friday, 16 April 2010, a Position Paper outlining the
substantive approach expected to be taken in the subordinate legislation was
released by the minister for Broadband, Communications and the Digital Economy
(the minister) and circulated by the Department.[1]
The committee conducted its hearing on the following Monday, 19 April
2010.
4.4
As a result of the timing of these events, at the public hearing, the
committee invited witnesses to subsequently submit additional information
outlining their response to the Position Paper.
The scope of the Bill's application
The role of subordinate legislation
4.5
The Bill is drafted broadly as framework legislation. It provides that
detailed subordinate legislation will provide for the application and operation
of Proposed Part 20A.[2]
It gives the minister the authority to specify the property developments or
classes of developments in which:
- Fixed lines which are installed to building lots and/or units
must be optical fibre; and
- fixed-line facilities (e.g. passive infrastructure like conduits
and pits) which are installed to building lots and/or units must be fibre-ready
facilities.
4.6
For example, the requirement in proposed section 372B(2) that any fixed
line deployed to a project area be a fibre line, applies only to projects
'specified in, or ascertained in accordance with, a legislative instrument made
by the minister'[3]
and where no exemption under a legislative instrument provided for in
subsection 372B(4) applies.
4.7
At the time of making written submissions, in the absence of the
subordinate legislation, many submitters were concerned that the details of how
the Bill would operate in practice were unknown. The Urban Development
Institute of Australia, for example, stated that:
...under the current available legislation, it is uncertain
which developments will be required to adhere to the FTTP provision and which
are exempt.[4]
4.8
However it was also clear at the committee's hearing that the attitude
of most witnesses was that their concern was not that the detail of the
requirements be in the primary Act itself, but that it be contained somewhere.
The following statement of Master Builders Australia to this effect was
representative of the attitude of a number of submitters:
What we are saying is that we do not mind where the detail
lies so long as it is open, transparent and readily communicable to our members...
The problem to be solved is getting the detail of those rules that can be
implemented and having them in a comprehensive form that we can then distil and
then provide to our members in terms of education. The detail of how that is
achieved in the legislative process—it is always better the more it is
transparent, open and upfront, but if the process renders clear rules that our
members can follow, that is our credible criterion.[5]
4.9
Optus indicated that although its policy preference is that all fibre be
deployed (or at least its deployment co-ordinated by) NBN Co, if the Bill is to
be the mechanism for servicing new developments, then it is sufficient that the
detail be contained in subordinate legislation:
[T]he broad principle in our submission... is that logically
we think it would be preferable for NBN Co. to deploy fibre, and that in many
senses would obviate the need for these further detailed rules around
deployment of fibre and the characteristics of that particular fibre. However,
if [the detailed rules for new developments] is a path that we need to go down
then certainly the subordinate instruments are an appropriate place for that
information to be set out—but we would need to look at the detail.[6]
4.10
The Department emphasised that in the circumstances of this Bill,
extensive use of subordinate legislation to provide the operating detail was in
the interests of flexibility and more appropriate targeting of its application:
The bill makes extensive use of subordinate legislation to
have operational effect. The use of subordinate legislation is to ensure
requirements can be specified in sufficient detail and to provide flexibility,
particularly to allow for the targeting and phasing in of requirements.[7]
The content of the proposed
subordinate legislation
4.11
The Position Paper now sets out the substantive approach to be taken in
the subordinate legislation.[8]
It clarified the geographic application of the Bill, the types of developments
to be captured (assessed according to size of development and price of fibre
deployment thresholds), the content of exemptions for certain conduct, and the
practical date of effect for the Bill to apply to developments already at
various stages of development (the trigger event).
4.12
In summary, the approach outlined in the Position Paper is as follows:
- Geographic application of Bill: the subordinate
legislation will seek to target those parts of Australia where services are
expected to be provided over a fibre access network, and to provide for the possible
expansion of the fibre footprint over time. To this end, it is proposed that
the subordinate legislation apply in areas of Australia where an urban utility
such as reticulated water, sewerage or mains electricity is installed.[9]
- Application of fibre-ready requirement: it is envisaged
that any development caught by the geographic coverage criteria would be
subject to the fibre‑ready requirement. That general rule would be
subject to certain exemptions. One exemption envisaged is that the rule would
not apply if, at the time of installation, the development was in an area
specified in a plan published by NBN Co as being a non-fibre area or where NBN
Co otherwise gave an explicit exemption in writing prior to the installation of
relevant infrastructure. Consideration is also being given to allowing a party
to apply to ACMA to exempt a development, in writing, from the fibre-ready
requirement.[10]
Further qualification of the rule will apply to in-fill and urban renewal
developments so that the fibre-ready requirement would generally be limited to
facilities within the property boundary and existing passive infrastructure in
the street not otherwise being touched would not need to be replaced.[11]
- Fibre connection requirement: the requirement to actually deploy
fibre will build on the fibre-ready requirement. It will apply where:
- (a) the development meets the fibre-ready threshold criteria,
and:
- (b) the development over its life is to be equal to or greater
than 200 building lots and/or units (the size threshold); and
- (c) fibre could be installed at a price of $3,000 or less
(including GST), which includes the price of backhaul (the price threshold).[12]
The Position Paper
additionally provides the following clarifications:
- the number of lots or units refers to the whole of the
development;[13]
- the price figure refers to the price payable by the party
acquiring the fibre facilities, not to the total cost to the provider of
providing the infrastructure and services.[14]
- the price figure would cover all relevant equipment and
installation for providing FTTP services, including the provision from the
network to the property boundary and to the premises of trenches, passive
infrastructure, fibre cabling and associated distribution facilities, backhaul
capacity, an optical network terminal and cabinet at the premises, and basic
internal wiring.[15]
- Practical date of effect on the ground: the legislative
framework is proposed to commence on 1 July 2010 (proposed clause 2 of the
Bill). However, the regulations are to provide that in terms of practical
effect on the ground, the fibre and fibre-ready requirements will apply to
fixed-line facilities and fixed lines that are to be installed in relation to a
development for which a Stage 3 planning application (infrastructure planning)
is lodged on or after 1 July 2010. 'Stage 3' is broadly defined as a
stage occurring 3¼–8 years prior to premises construction and being one of
'negotiation of infrastructure levies and detailed structure planning' in which
'more detailed site planning, possible determination of developer
contributions' occurs, and agencies such as roads, water, electricity, sewer
and public transport are involved.[16]
Appendix 3 reproduces the Department's table of the 'Six Stage Generic
Development Pipeline for Greenfield Development and Major Brownfield
Redevelopment' which was used in the Position Paper.
Application and operation of the
Bill: views expressed
4.13
The approach taken in the Position Paper had the effect that a number of
concerns raised in written submissions about the operation or application of
the Bill were not pursued at the hearing. For example, concerns that property
developers might be financially disadvantaged by requirements to invest
substantial sums deploying expensive optical fibre lines and backhaul infrastructure
to project areas, were largely circumvented by the articulation in the Position
Paper of the envisaged $3000 price threshold and 200 lot size threshold.
Similarly, previously voiced concerns that the requirements to deploy fibre or
install fibre-ready facilities would cause significant cost blow-outs for
projects substantially commenced and constructed, were to a great degree
rendered moot by the Position Paper's proposal that the Bill take practical
effect on the ground only to projects lodging a Stage 3 application after 1
July 2010.
4.14
At the public hearing, most witnesses did not comment on the financial
implications for project developers whose projects will be subject to either a
fibre‑ready or fibre-deployment requirement.
4.15
To the extent that opinions were expressed at the hearing on the
application and operation of the Bill, the primary matter raised related to the
policy of new developments being subject to a requirement to pay for, or
contribute at all to, the installation of fibre-ready facilities or the
deployment of fibre lines.[17]
This was generally described as the 'inequity' argument and particularly
propounded by property developers. The argument was explained by one member of
the Urban Development Institute of Australia as follows:
What we see as the inequity in this from day one is that, in
effect, you are capitalising upfront costs for fibre to the premises for a
person purchasing and then paying that as a lump sum upfront, because it is
built into the cost of the land that they are purchasing, and then you are
going to tax them. There is inequity in that that it is important to address.[18]
4.16
Master Builders Australia were also dissatisfied with the application of
any fibre deployment or 'fibre-ready' requirement funded in any way through
developer contributions, regardless of whether a price cap or size threshold
applies:
As a general rule, we are of the view that the developer
should only be responsible for the provision of pit and pipe reticulation for
fibre within the development that would allow future fibre installation when
the super-fast broadband service is available. All other costs should become
the responsibility of the Service Provider and/or Government...
The proposed legislation and the Paper are highly likely to
adversely affect the commerciality of affordable and low-income housing
developments.[19]
4.17
Mr Aaron Gadiel, Chief Executive Officer of the Urban Taskforce
Australia, expressed his organisation's attitude to the perceived inequities
underlying the Bill and the government's fibre in greenfields policy as
follows:
To some extent the federal government has accepted that there
is some inequity in [providing different arrangements for the deployment of
fibre infrastructure to new developments compared with those for existing premises]
and the proposal now is for the cost to new development projects to be capped
at $3,000, I assume per residential lot or unit, although the paper does not
make this clear. There is also a restriction saying that the obligation to put
optic fibre in, as opposed to fibre ready, would only apply to developments of
200 building lots or units and larger. This does raise a couple of issues.
Firstly, there is still an expectation from the federal government that some
development projects will carry the cost of backhaul, backhaul being the
network infrastructure that is not located on a development site but might be
necessary to integrate new homes or business premises effectively into a
national broadband network. We appreciate the financial costs of backhaul or
head end are to be taken into account in this $3,000 cap, but we still are of
the view that it is inconsistent for new home owners and businesses to be
required to make a direct contribution to off-site network infrastructure
through their own property’s purchase price, whilst existing home owners and
businesses do not face these costs, although they are funding it through the
taxes that everyone pays.[20]
4.18
Further, Mr Gadiel explained that his organisation dissents from the
government's view that a size threshold trigger is appropriate in any case:
We have never been fond of the suggestion that there should
be a size threshold, as such. To us the more relevant consideration should be
what is the likely pace of the rollout of an optic fibre network, including
head end and so forth, in the community or area concerned. It seems to us
illogical that a developer might be compelled to introduce fibre to a 200
dwelling unit development in an infill location in the absence of any clear
plan to roll out the connecting network to that unit development in the
foreseeable future. It seems to us the obligation should not exist in isolation
from clear concrete plans from whatever authorities will be responsible for
rolling out this network to existing areas as well as new communities.[21]
4.19
The Department's evidence to the committee indicated that the premise of
the inequity arguments (that new developments will have to pay for fibre
infrastructure while existing premises will get it free from NBN Co at a later
date) may be incorrect. The Department responded to the inequity argument by
saying:
It was noted in the Second Reading Speech that the cost
recovery arrangements that may ultimately apply in greenfields will depend on
the commercial arrangements that emerge between all relevant parties as fibre‑to-the-premises
is deployed more widely. How roll-out costs will be recovered in both
brownfields and greenfields will depend on a range of factors and it cannot
simply be assumed that stakeholders in greenfields will have to meet costs in
one way while those in brownfields are expected to meet them in another. In all
instances, NBN Co is expected to operate on a commercial basis and to recover
its costs.[22]
4.20
In contrast to the submissions made by property developers, carriers
appeared to be in broad support for the proposed operation and application of
the Bill, subject to their concerns that the price threshold may be too low,
and the size threshold too high, to capture sufficient developments with the
requirement to deploy fibre. Mr Roger McArthur, General Manager of the
Universal Communications Group, explained his concern that, as drafted, the
Position Paper will see subordinate legislation created that has loopholes enabling
developers to side-step fibre connection requirements:
[T]he bill, it defines a framework, but there is a level of
detail. Some of those elements are covered off in the Position Paper—for
example, setting the 200 [lots size threshold] and the financial frameworks [of
the price threshold] and so on—and that goes a long way to actually providing
some degree of certainty. I do feel that in its current form it does provide
leverage or capability for developers to sidestep by creating development lots
which actually fall below a threshold, so they might have to be forced to meet
the fibre-ready requirement but not be forced to build the fibre requirements.[23]
4.21
In light of that concern, Mr McArthur and Mr Ralf Luna, Chief Executive
Officer of the Universal Communications Group, put forward a proposal that
local governments aggregate FTTH Greenfield developments in local development
plans so as to ensure the cost of backhaul could not be used to manipulate the
application of the price cap or the size threshold:
[W]e believe the most likely claim for a development to be exempt
under the proposed Bill will be that it is too small to cover the common
development costs, and this will push up the cost per lot to an unacceptable
level. To avoid developers sidestepping the legislation, we believe
consideration should be given to requiring local councils, maybe under the
direction of NBN Co., to aggregate fibre to the home greenfield developments in
the local development plans. The aggregation of multiple developments in the
same geographic area would allow much smaller developments to be added to the
fibre to the home plans of existing greenfield developments in the future...
[The aggregation element] would prevent individual developers from creating lot
sizes which would simply mean that they could avoid admitting the intent of the
bill.[24]
4.22
Telstra also submitted that the size threshold will operate as an
artificial constraint on the deployment of fibre to new developments:
Telstra has consistently advocated for a singular monetary
cap as the threshold for the fibre requirement. In our view, the 200 lot size
threshold is an artificial constraint on the deployment of fibre. There may
well be many smaller developments that could be fibred for less than $3000 per
lot, especially once the policy and the market dynamics are established.
But if the 200 lot threshold is to remain, it should be
closely monitored and adjusted downwards as the regulation and the market
matures.[25]
4.23
In addition, while broadly supportive of the $3000 price threshold, Telstra
raised a number of concerns as to its particular detail. Amongst other concerns
and recommendations, Telstra suggested the price cap should be drafted so as
not to enable a developer to claim the full value of trenching costs that would
be incurred by the developer anyway in order to provide water, sewerage and
electricity to the development.[26]
4.24
As to the timing of the Bill's application, a number of views were
expressed. Most witnesses agreed that discussions about telecommunications
infrastructure occur at around a time corresponding with the 'stage 3' outlined
in the Position Paper. Mr Paul Granville of Telstra explained that:
[g]enerally the negotiations occur before the developers
finalise the financing. They need to understand all of their costs reasonably
early in the process, so they go out and seek negotiations with various
suppliers so that they have clarity about their total costs before they
actually go through to get approvals. So it would be quite early on, probably
at around stage 3. Those stages do vary from state to state, but it would be
roughly in that sort of time frame. It could be several years before they
actually turn the first sod.[27]
4.25
Property developers and organisations suggested that there is some
fusion between stage 2, 3 and 4 for the purposes of determining when telecommunications
infrastructure decisions are made, and that this would complicate the merit of
the proposal in the Position Paper as to the timing of the Bill's requirements
taking effect:
The government in its paper on Friday had a very neat table
with the six stages of development. That has been reproduced by the National
Housing Supply Council. That table rather oversimplifies a process that most
developers and planners cannot get their heads around. There is no clear, neat
stage 3. The government suggests that all developments that have progressed to
the stage 3 point at 1 July would be subject to these new rules. Trying to work
out whether a development is at stage 3 is a challenge because stage 3 is not a
statutory process. It is a non-statutory process that can be as long or as
short as a piece of string, if it exists at all. Sometimes what is described as
stage 3 would actually happen before stage 2 and sometimes what is described as
stage 3 would happen after stage 4.[28]
4.26
Telstra was the only organisation to submit that stage 3 may be too
early in the development process with the result that there will be
'significant delay in the government's fibre objectives being achieved':
[U]sing Stage 3 as the trigger point means that there will be
a significant 'tail' or real estate developments constructed after 1 July 2010
to which the fibre/fibre-ready requirements do not apply–even though the
deployment of fibre in those real estate developments may well be feasible.[29]
Application and operation of the
Bill: committee view
4.27
The committee supports the general principle adopted by the Bill and the
Position Paper which will create a default fibre-ready requirement
applying broadly wherever other utilities services are reticulated, and a more
limited fibre‑deployment requirement additionally applying where the 200
lots size threshold and $3000 price cap threshold are satisfied.
4.28
The committee also supports the intention that the subordinate
legislation will result in the Bill's requirements to deploy optical fibre or
install fibre-ready facilities taking practical effect for developments which
lodge a Stage 3 application after 1 July 2010. The committee believes
that, given Telstra's decision to no longer deploy copper to new developments,
if fibre deployment is feasible (logistically and financially) in projects
which are not captured by the cut-off date, then property developers may very
well enter into commercial arrangements to deploy fibre so as to provide
fixed-line infrastructure to end users. The committee does not believe it is
necessary to bring forward the cut-off requirement so as to apply to projects
which, on 1 July 2010, will be classified as having reached, a later stage.
4.29
The committee believes that the price and size thresholds are
appropriately targeted to ensure that, wherever possible, new developments are
serviced with fibre technologies and are not left with outdated infrastructure.
The committee believes that, in combination, the Bill and the Position Paper
represent a reasonable balance between the competing considerations of
financial cost to developers, the interests of end users and the community in
the provision of modern telecommunications infrastructure to new developments,
and government policy, which all need to be taken into account. The committee
agrees with the Universal Communications Group that local government could play
an important planning role in the aggregation of new developments for the
purposes of backhaul costs, but considers that this is a matter for local
governments and that, as a first step, the size threshold remains an
appropriate mechanism.
4.30
The committee acknowledges that not having the final version of the
proposed subordinate legislation prior to undertaking the inquiry to some
extent affected the ability of witnesses to evaluate all the relevant material
and to articulate their positions to the committee. The committee appreciates
the final version of the subordinate legislation has not yet been settled and
that the Position Paper is subject to a consultation process.
Content and implications of the fibre / fibre-ready requirements
4.31
As drafted, the Bill does not mandate or compel the provision of fibre
lines or fibre-ready facilities to specified developments. Rather, it prohibits
a person from installing a fixed line or telecommunications facilities unless
it is a fibre line or they are fibre-ready facilities.
4.32
However, in answer to a question taken on notice, the Department
indicated that the intention is that the effect of complementary state and territory
planning arrangements currently being negotiated will be to require that fixed
telecommunications facilities be provided in new developments. The Department
explained:
The particular measures will vary because state and territory
planning arrangements vary in their structure, but it is envisaged that there
would be a requirement that fixed telecommunications facilities be provided in
new developments, and that those facilities meet relevant Commonwealth
requirements, thereby interlinking state, territory and Commonwealth
arrangements...
In general...it appears that the approach most states and
Territories would take is to add fixed telecommunications to the list of
utilities which have to be provided for before a planning application is
approved.[30]
4.33
It should be noted that some reservations were expressed, for example by
Master Builders Australia, concerning the fragmentation of fibre connection and
fibre-ready facilities installation standards and regulations into a myriad of
different state and local government requirements.[31]
4.34
However, the Department did indicate that proposals to legislatively
mandate the deployment of fibre infrastructure at a Commonwealth level had been
canvassed but rejected for a number of reasons:
[T]he Bill conditions what is to be done rather than directly
requiring the installation of such facilities.
[The Department] canvassed the possibility of legislating
directly to require developers to ensure pit, pipe and FTTP infrastructure and
services are available to consumers in its Discussion Paper in May 2009. It
found that this could be done using the Commonwealth's corporations power under
the Constitution but would be limited to corporations and would have to be
enforced by prohibiting the trading of land where the requirement was breached.
This was strongly opposed by developers and was considered to be intrusive and
disproportionate. Developers also put the view their developments would need to
include fixed line infrastructure to be marketable.[32]
4.35
In relation to the issue, it is necessary to bear in mind Telstra's
decision to no longer deploy copper to new developments regardless of whether
those developments are subject to a legislative prohibition on the installation
of non-fibre fixed-line telecommunications infrastructure. A number of
submitters, including the Urban Development Institute of Australia, stressed
that the decision may have profound effects on the financing, infrastructure
deployment arrangements, and end-user satisfaction with new developments.[33]
Mr Paul Budde, Managing Director of Paul Budde Communication Pty Ltd,
explained his assessment of the implications of Telstra's conduct as follows:
Perhaps the most disruptive development has been not the Bill
itself but the subsequent announcement from Telstra that it will no longer
deploy its copper-based infrastructure in greenfield developments.
This action, of course, makes the government’s proposition in
the legislation to be ‘fibre-ready’ a non-issue. There is no longer an
alternative. And this, then, places a large question mark on how the developers
will enable the provisioning of a telephone service. In most situations they
will simply not get planning approval unless they can prove that such a fibre
based service will be made available.
At the same time customers will not expect just a telephone
connection – they will demand broadband – but, legally at least, nobody will be
required to provide such a service since broadband is not a declared
telecommunications service.[34]
4.36
Mr Budde went on to elaborate what he believes is likely to happen to
fill the vacuum created:
The reality remains – as it always has been – that Telstra is
the only organisation capable of dealing with the smaller sites (1–500
dwellings), as it is uneconomical to provide site space, backhaul and a FTTH
network for these small sites, since the end cost of all this has to be
recovered from the sale price of the product (a house or piece of land).
For these small sites a developer would have to rely on a
solution that goes back to Telstra’s exchange, as this is the only location
they can physically connect back to without massive backhaul costs. And so as a
result of this policy Telstra, by default, wins that entire segment of the
market, which is significant in terms of the overall number of sites.[35]
4.37
However, the committee did receive evidence that there is a competitive
market for the supply of fibre services to new developments. In addition to
Telstra and the Universal Communications Group, several other companies which
currently offer to install fibre for new estates are listed in the EM. They
include Arise, Clubcom, OPENetworks, Opticomm, and TransACT.[36]
4.38
It was also pointed out by the Department that although the Bill
supports the continued existence of the competitive market for the supply of
fibre-related infrastructure, nothing in the legislation would prevent NBN Co
from supplying fibre or installing fibre-ready facilities in the future if it
chose to do so.[37]
4.39
A number of submitters suggested that they believed it would be
preferable that all fibre deployment and installation be managed by NBN Co. One
of the most vocal proponents of that proposal was Optus:
In our submission we have argued that NBN Co. should deploy
fibre in greenfield sites. If it were to do so then the cost of that deployment
would be taken up as part of the general costs of running the network and
therefore it would be recovered through access fees to wholesale customers such
as Optus and Telstra and ultimately passed on to end users—in exactly the same
way as the costs of NBN Co. deploying fibre into brownfield locations would be.[38]
4.40
The Implementation Study into the NBN was released subsequent to the
committee's public consultation process. A key finding of the implementation
study was that the 'fibre component of the NBN should be extended from 90 to 93
per cent and cover the 1.3 million new premises expected to be built by 2017–18.[39]
4.41
Recommendation 13 of the Implementation Study is that NBN Co be the
provider of last resort for premises within or adjacent to NBN's fibre access
network and that developers be required to cover the costs of trenching and the
duct, pit and pipe network and that NBN Co would be responsible for the cost of
installing all other fibre infrastructure up to the network boundary.[40]
4.42
Recommendation 14 is that fibre design standards be developed that align
with those being applied by NBN Co across its network. Recommendation 16 is
that fibre networks that do not comply with the standards be overbuilt by NBN
Co. Recommendation 17 is that all new developments where fixed line
infrastructure is deployed be required to provide a duct, pit and pipe network
to allow for later fibre deployment by NBN Co.[41]
4.43
If accepted by the government, these recommendations still leave open
the possibility that other providers, besides NBN Co, will provide fibre
facilities to new developments provided they meet the necessary standards. As
such, the recommendations are not inconsistent with this Bill.
Committee view
4.44
The approach adopted in the Bill is that, if fixed-line infrastructure
is installed in specified development projects, then that infrastructure must
be fibre-related infrastructure. The committee believes this legislative
approach is appropriate for the policy end sought. That is, the committee does
not believe that it is necessary for the Bill to actually mandate that
fixed-line infrastructure be installed in those specified developments. As the
Department foreshadowed in its evidence to the committee, it is most likely
that any such mandatory requirement will be supplied by state and/or local
government planning policies.
4.45
The committee notes the concerns expressed regarding the potential for
cross‑border fragmentation of standards and planning requirements to
arise due to the different requirements and obligations of different local
government areas. The different standards could relate both to whether it is
mandatory to install fixed-line telecommunications infrastructure in a new
development in order to get planning approval, and also to the standards and
specifications required for any installation work. However, the committee
considers that concern about uniformity of standards and specifications is
largely misplaced given the government's clear intention to establish national
standards about technical matters and a national accreditation scheme for
providers.
4.46
The committee believes there is significant scope for the government to continue
to lead discussions between state and local government planning organisations
to ensure that there is a nationally integrated and consistent set of
requirements for the deployment of telecommunications infrastructure in new
developments.
Recommendation 1
4.47
The committee recommends that the government continue its work with state
and local government planning authorities to ensure a nationally integrated and
consistent approach to requirements for telecommunications infrastructure in
new developments.
4.48
As to the role of NBN Co, the committee notes that there is nothing in
the explanatory material for the Bill or in the Position Paper that would
preclude NBN Co from participating in new estates. However, the committee
believes the government should make it clear in its response to the
Implementation Study its expectations for the involvement of NBN Co in
servicing new developments with fibre-related infrastructure.
Recommendation 2
4.49
The committee recommends that the government clarify, as soon as
possible, the role of NBN Co in servicing new development projects.
Ownership, access arrangements, and integration with the NBN
4.50
The matters of who will own the fibre infrastructure once installed, how
access to the infrastructure will be regulated, and how standards of service
installation will be sufficiently regulated were all prominent concerns in
written submissions to the committee.
4.51
A number of submitters merely noted that, in advance of sighting the
proposed subordinate legislation, these were matters yet to be resolved.[42]
Others were more descriptive of the topography of the issues.[43]
Ownership of infrastructure
4.52
The committee asked the Department to clarify who will own any fibre
deployed to a project area (including backhaul), any fibre installed in it, and
the fibre‑ready infrastructure installed or constructed as part of the
project. The Department responded that:
A range of ownership and management arrangements already
exist when it comes to the operation of telecommunications infrastructure in
new developments. The government has not seen any reason why these arrangements
cannot be left to the market. The government is concerned to ensure, however,
that quality facilities are installed in new development and are operated to
provide quality services. To a large extent this will be achieved through the
setting of appropriate technical specifications and competitive forces. As a
further safeguard, [the Department] is working with stakeholders on the
development of a process for accrediting fibre providers and certifying the
infrastructure they install.
While legislation is not prescriptive as to who can own,
manage or operate infrastructure in new developments, under section 47 of the Telecommunications
Act 1997, a network unit (which would include fibre lines...) must not be
used without the owner having a carrier licence or a nominated carrier
declaration.[44]
4.53
While it may be the case that fibre cannot be owned by a person not
holding a carrier licence or a nominated carrier declaration, the Department's
answer does not necessarily address the uncertainty expressed by LandCorp as to
ownership of all the fibre infrastructure and assets. LandCorp wrote to the
committee that:
As a condition of subdivision LandCorp is required to build
the infrastructure (roads, power, water and drainage) to meet a prescribed set
of specifications. The infrastructure within the estate would be build,
inspected and certified as meeting the technical design specification and after
testing, the infrastructure would be transferred to the appropriate body, with
that subdivision infrastructure becoming part of that utilities network. It is
presently unclear who LandCorp will transfer fibre infrastructure to once it
has been constructed.[45]
Committee view
4.54
The committee believes there is a need for the Department to clarify
with industry and future stakeholders who can own the relevant fibre-related
infrastructure. It may be that allowing for a diversity of ownership
arrangements provides scope for the development of innovative cost-sharing
arrangements.
Recommendation 3
4.55
The committee recommends that the Department of Broadband,
Communications and the Digital Economy give consideration to the variety of
ownership arrangements that exist, or might arise, and whether there are good
reasons for the government to intervene in these arrangements.
Access arrangements
4.56
A number of submitters raised concerns about the lack of detail
currently available as to the content of the regulations providing for access
to fibre lines and fibre-ready infrastructure deployed in new estates. Optus
and Telstra both submitted substantial comment on the importance of the matter
to the committee.[46]
4.57
Proposed subsections 372CA(4) and 372CB(4) provide a high-level
framework for regulations to establish a regime for third party access to a
fixed-line facility.
4.58
The Position Paper provides little additional detail about the
government's intentions for an access regime. It states:
The government envisages that fibre networks in new
developments will operate on an open access basis, and that wholesale services
like those available on the NBN will be offered. There is scope for the
Australian Competition and Consumer Commission (ACCC) under Part XIC of the Trade
Practices Act 1974 to declare access to services and regulate access
pricing. The government will also consider more direct forms of regulation, if
necessary, to ensure consistency of outcomes for service providers and
end-users.[47]
4.59
In response to a question on notice raising the concerns of submitters,
particularly carriers such as Telstra, as to the likely arrangements for an
access regime, the Department stated:
The regulations will provide all the appropriate guidance and
will be developed with regard to existing and proposed telecommunications
access arrangements and in consultation with stakeholders. The [EM] to the Bill
notes that one possible model for the regulations is Part 5 of Schedule 1 to
the Telecommunications Act 1997 [the telecommunications access regime
provisions].
The Department recognises that the regulations will need to
have due regard to carriers' obligations under Part 5 of Schedule 1 so as not
to create conflicting obligations on carriers.[48]
Committee view
4.60
The committee acknowledges the critical importance of an effective and
open access regime to fibre-related infrastructure for the provision of
telecommunications services to the eventual end users in project areas.
4.61
The committee also notes the access arrangements in place under Part XIC
of the Trade Practices Act 1974 will apply to greenfield sites
and the government has another Bill in the Senate, (the Telecommunications
Legislation Amendment (Competition and Consumer Safeguards) Bill 2009), to
strengthen current arrangements. The committee urges the government to clarify
its intentions in this regard. The committee notes the government's assurances that
the-soon-to-be-released regulations will provide 'all the appropriate guidance'
on the proposed telecommunications access arrangements.
Recommendation 4
4.62
The committee recommends that the government ensure that access
arrangements, including the genuine equivalence of access of a kind contemplated
for the NBN, operate in new developments consistently with those in the rest of
the country.
Integration with the NBN
4.63
The chief concern of submitters regarding the integration of new fibre
lines and fibre‑related facilities with the broader NBN related to the
clarity of network standards and specifications, and the extent to which
further regulation and oversight of industry operators may be necessary.
4.64
Most submitters who addressed the matter were supportive of NBN Co
having a clear role in setting industry standards.
4.65
The Urban Development Institute of Australia submitted that planning
decisions will be hampered by there not being:
- a public document detailing NBN Co's deployment plans, that is,
when they will be deploying to certain areas;
- a public document detailing NBN Co's technical design solution
which will affect spatial planning requirements of a site to be 'fibre-ready';
- a publicly available NBN Implementation Study;[49]
and
- an agreed industry standard on compliance thresholds.[50]
4.66
Mr Paul Budde expressed strong concern that, in the absence of clear
guidance and co-ordinated policies, sub-standard work may otherwise be
undertaken which will compromise the potential of the NBN:
This is a recipe for a patchwork outcome – different cabling
topologies, different technologies, different construction standards, different
services and service pricing, different ownership and operation models. Now
that NBN Co is operational there is an obvious role for it to play in this;
but, in the current documentation at least, there is no indication as to
whether it is to play a role or what its role will be.[51]
4.67
Mr Budde recognised that there are a number of potential ways in which
adequate supervision and installation practices may be regulated:
NBN Co doesn’t have to take over all of this work, it could
also, of course, work very closely with existing bona fide greenfield operators
and work out a plan with them. A positive industry policy could see these
companies working together with NBN Co to achieve a truly national outcome,
whereby the greenfield operators can concentrate on new innovative services.[52]
4.68
The Position Paper outlines an intention that 'networks in new
developments be subject to clear technical specifications to maximise
consistency with the end-use experience to be enjoyed on NBN Co's fibre
network'. It also explains that the ministerial power to specify conditions for
the deployment of fibre lines and the installation of fibre-ready facilities[53]
enable the minister to set technical specifications and develop network
standards.[54]
The Position Paper explains that technical specifications to be applied in new
developments would be contained in one or more of the following documents:
- A document published by NBN Co for this purpose;
- An industry code published by the Communications Alliance and
registered by ACMA for this purpose; or
- Any industry standard that may be prepared by ACMA from time to
time for this purpose.
4.69
The Position Paper also notes that Part 6 of the Telecommunications
Act 1997 provides a framework for the development of industry codes and
standards and that proposed amendments to Part 6 contained in the Bill will
'make it simpler' to make relevant industry codes and standards for optical
fibre facilities and services. The Department indicates in the Position Paper
that it is currently working with the Communications Alliance on draft
guidelines for the deployment of FTTP in new developments and has also
consulted the Stakeholder Reference Group with early drafts of this work. NBN
Co has also been developing its own specifications and these have been provided
to the Communications Alliance for consideration.[55]
4.70
Telstra was the only submitter to query the desirability of network
standards being made as proposed by the Bill. Telstra argued that the categories
for which the Communications Alliance and ACMA may make codes and standards are
'very broad and in particular would allow [the Communications Alliance] and
ACMA to determine the characteristics and quality of services provided over
Telstra and competitor business fibre networks.'[56]
Telstra submitted this would be inappropriate because:
Direct fibre for businesses is already a highly competitive
and dynamic market. There is no case for Government intervention to prescribe
specifications in this market, and the prospect of Ministerial proclamation
could discourage investment and innovation in this already competitive market.[57]
Committee view
4.71
The committee believes that nationally consistent network standards and
specifications are integral components to ensuring that fibre deployed, and
fibre-ready facilities installed, in new developments, are properly designed
and adapted to eventual integration with the NBN. The committee acknowledges
the significant work and consultation process the Department is continuing to
undertake with relevant stakeholders to ensure that appropriately adapted and
targeted standards and specifications are developed.
4.72
The committee did not receive evidence indicating whether the network
standards and specifications being developed will also deal with safety and
training requirements for the deployment and/or installation of relevant
infrastructure. To the extent that they do not, the committee believes that
such matters ought to be specified as a condition of installation, and should be
specified in an appropriate legislative instrument made by the minister
pursuant to his or her power to specify conditions for the deployment of fibre
lines and the installation of fibre-ready facilities.[58]
Recommendation 5
4.73
The committee recommends that the minister, by legislative instrument,
specify that a condition[59]
of installation of a line or fibre-ready facility in a project area is that the
installation be undertaken in compliance with nationally consistent network
safety and training standards.
Recommendation 6
4.74
The committee recommends that the Bill be passed.
Senator Anne McEwen
Chair
Navigation: Previous Page | Contents | Next Page