Chapter 6 - Conclusions
6.1
In conclusion, the Committee stresses its main
findings on ‘what lessons have been learnt and what can be done to prevent
problems like this occurring in the future’ (terms of reference 5):
Unsatisfactory environmental assessment procedures at Port Hinchinbrook
6.2
The Port Hinchinbrook dispute was caused by the
regrettable lack of a thorough up-front environmental impact assessment of this
major development proposal before approval. The most important question
- ‘Having considered environmental impacts, should the development be
approved or refused?’ - was never asked. This omission has left the field wide
open for ongoing argument about what the environmental impacts will be. It is
at the root of claims by environment groups that all subsequent environmental
management actions are prejudiced by the political need to justify the initial
approval decision.
6.3
The Committee hopes that all will agree that the
resulting conflict has been unsatisfactory for all concerned - unsatisfactory
to the developer who has suffered uncertainty and delay, to the environment
groups who believe that the post-approval environmental management has been
inadequate, and to the authorities who have had to handle the matter with
vastly more trouble and expense (both administrative and political) than if the
job had been done properly in the first place. As the Great Barrier Reef Marine
Park Authority said:
‘... it would have been desirable that a comprehensive
Environmental Impact Statement (EIS) be prepared for the Port Hinchinbrook
development at the time this project was initially proposed in 1993.’ (GBRMPA,
Submission 157a, p 1)
6.4
The same comment applies equally validly back to
1988, when the local council of the day, in spite of the concerns of
environment groups at that time, exercised its discretion not to demand
environmental impact assessment of this major development adjacent to a World
Heritage Area.
Need for upfront environmental impact assessment
6.5
There is a fundamental difference between
monitoring and mitigating environmental impacts of a development already
approved, and upfront environmental impact assessment as an input to deciding
whether to approve a development. The purpose of upfront environmental
assessment is to ensure that decisions are based on the best possible
information, so that decision-makers can weigh in the balance all the costs,
benefits and risks involved. In the Port Hinchinbrook case there was never an
upfront environmental impact assessment. The controls of the Deed of Agreement
are focussed on monitoring and mitigating, because the Queensland government in
1993-94 and the Commonwealth in 1996 were clearly unwilling to contemplate the
possibility that the development should not go ahead (and perhaps because they
felt bound by the history of the 1988 approval and the degraded site). But the
‘monitor and mitigate’ approach disregards the possibility that some
environmental impacts may prove intractable, suggesting with the wisdom of
hindsight that the development should not have been approved.
6.6
In the case of Port Hinchinbrook, if the various
ad hoc controls in the Deed of Agreement succeed in preventing
environmental harm, this would be coincidental: it does not
retrospectively justify the lack of upfront environmental assessment. In
important respects the Committee doubts that the controls will be able to
prevent harm - we refer to the risks to dugongs from increased boat traffic,
the obvious impact of the waterfront development on the aesthetic values of the
renowned natural landscape of the Hinchinbrook Channel, and the likely long
term impacts from pressure of increased tourism in the island national parks.
6.7
Planning authorities must commit to thorough,
independent, up-front environmental impact assessment of significant
development proposals. Environmental impact assessment of important aspects of
proposals after the approval has been given instead of before should have no
place in environmental management. This is particularly the case in management
of World Heritage, where the highest standards, and the most cautious
application of the precautionary principle, should apply. In the Committee’s
view the history of Port Hinchinbrook approvals is very far from best practice
World Heritage management.
6.8
As well, there is a need for better processes to
ensure the independence and impartiality of environmental impact statements.
For example, instead of proponents engaging consultants directly, it would be
possible for planning authorities to choose a consultant by lot from a short
list of tenderers with the necessary expertise. Then consultants would know
that they could not be discriminated against in future tenders if they reach
unwelcome conclusions. The thoroughness of the authorities in setting the terms
of reference for environmental impact studies is also most important.
Need for transparent rules for public input
6.9
Environmental impact assessment alone, no matter
how expert, cannot objectively decide whether a development should be approved.
That decision must take into account all factors, environmental, economic, and
social. Where there are conflicting interests the decision is usually a
compromise which - hopefully - reflects broad community values. The purpose of
environmental impact assessment is not itself to decide the question, but to ensure
that decision-makers can decide the question on full information. The
precautionary principle should apply: lack of scientific certainty should not
be an excuse for allowing development that may have serious or irreversible
environmental impacts.
6.10
Since decisions on development applications must
often mediate between conflicting interests, it is all the more important that
their processes are fair and are seen to be fair. In the Port
Hinchinbrook debate a chief complaint of environmental groups concerned the
lack of public process. The Deed of Agreement was an ad hoc one-off
response to the situation - a private contract which contained no public input
and no possibility for interest groups to initiate prosecution of breaches.
6.11
A transparent public consultation process, set
out for all to see in development control law, is important for at least three
reasons. It is most likely to elicit all the relevant information, as different
interests compete to put their cases on the record most persuasively. It is
less likely to be captured by one interest group. Above all, it is necessary to
promote trust in the fairness of the decision. Due process will not stop people
from having conflicting interests, and in the individual case it will not stop
some from being unhappy; but it will, hopefully, encourage all to respect each
other’s differences and to respect the fairness of the system.
‘A public assessment process
often goes a long way towards reducing the level of dispute, because at least
you have a more agreed foundation of scientific fact upon which to base debate
and to move on from.’ (J Johnson, Environmental Defender’s Office of NSW Ltd,
Evidence 10 August 1998, p 289)
6.12
In the case of
Port Hinchinbrook, the Committee notes the considerable evidence that objectors
to the development, and scientists who have given unwelcome advice on it, have
been harassed and intimidated. In a society that values free speech, this is
most regrettable and unacceptable.
Need for regional planning
6.13
Many witnesses on both sides of the Port
Hinchinbrook debate stressed the need for better regional planning policies to
give clear ground rules to developers about what sort of developments will or
will not be acceptable.
6.14
The Committee agrees. Regional plans are most important to prevent future Port-Hinchinbrook
style disputes, by giving more certainty to developers and giving more
confidence to environmental groups that regional environmental issues have been
adequately considered. A plan cannot always prevent case by case dispute, but at
least, when dispute occurs, one side or the other should be able to point
clearly to the plan as supporting their position, which should allow the
question to be decided more quickly and with less acrimony than we saw at Port
Hinchinbrook. Prof. Marsh commented:
‘I was very struck by the
polarisation in the submissions, particularly the polarisation from ordinary
Australians, on both sides of the debate ... I would really hate to see this very
alienating situation repeated up and down the coast. We need to have good
processes in place so that we can move forward and strike the right balance
between development and conservation.’ (Prof. H Marsh, Evidence 31 July 1999, p
169)
6.15
As well, a key purpose of regional planning is
to set out a long-term vision that can be followed from the start, so that the
environment is not unintentionally degraded by the accumulation of small
changes. Incremental changes may seem
innocuous when viewed from day to day, but over time may add up to a situation
which no-one has planned or wanted and which might be very hard to undo later.
It is not hard to think of places around the world where incremental tourist
developments over many years have spoilt the thing that the tourists came to
see. No one would want that fate to befall the Hinchinbrook region. A threat
may seem far-off now; but by the time it seems close, it may already be too
late to act. The purpose of strategic planning is to prevent the threat getting
that close.
6.16
However, regional
planning is only purposeful if the plan represents a real commitment by all
concerned, flowing through to individual development control decisions. Long
term goals are always at risk from the temptations of short-term expediency.
The prospect of more Port Hinchinbrook-style disputes up and down the coast
should be enough motive for decision-makers to resist the temptation.
Conclusion
6.17
The Committee is confident all would agree that
we do not want to see the Port Hinchinbrook debate repeated up and down the
Australian coast. Local councils, as well as State and Commonwealth governments
when they are involved, must commit to thorough, independent environmental
impact assessments for significant developments, which should be made available
for public scrutiny and comment. All must commit to Regional Coastal Management
Plans. Upfront independent environmental impact assessment, transparent
procedures, clear rules about public consultation, Freedom of Information as
the backstop, wide standing for interested parties to challenge administrative
decisions - these things are all part of a package the purpose of which is both
to get fully informed decisions and to encourage public confidence in
the fairness of decisions. They are essential to repair trust among interest
groups of all stripes, and will hopefully take a lot of the heat out of Port
Hinchinbrook-type disputes. They will give community groups the confidence that
their voice will be heard, and they will give developers confidence that when
they propose developments they will get clear answers and upfront certainty.
Navigation: Previous Page | Contents | Next Page