Introduction
1.1
The inquiry into the future of Australia's naval shipbuilding industry
was conducted over the course of two Parliaments. On 11 October 2016, following
the 2016 federal election[1],
the Senate re-adopted the inquiry into naval shipbuilding from the 44th Parliament
in the 45th Parliament. In re-referring the inquiry, the Senate agreed to an
amended terms of reference to reflect advances in the inquiry:
The future sustainability of Australia’s strategically vital
naval shipbuilding industry, including:
- the development of contracts
relating to naval ship and submarine building;
- the design, management and
implementation of naval shipbuilding and submarine defence procurement projects
in Australia;
- the utilisation of local
content and supply chains;
- the integration of offshore design
work and supply chains in Australia;
- opportunities for flow on
benefits to local jobs and the economy; and
- any related matters.
1.2
On 27 November 2017, the Senate granted the committee an extension to
report from 1 December 2017 to 27 June 2018.
Submissions and public hearings
1.3
The committee received 21 submissions following the re-referral in the
45th Parliament, as well as additional information, including answers
to questions on notice, listed at Appendix 1.
1.4
The committee held six public hearings:
-
3 April 2017 in Perth;
-
4 April 2017 in Adelaide;
-
20 June 2017 in Canberra;
-
8 September 2017;
-
13 October 2017; and
-
7 June 2018.
1.5
Concurrently, the Joint Standing Committee on Treaties (JSCOT) conducted
an inquiry into the Framework Agreement between the Government of Australia and
the Government of the French Republic concerning Cooperation on the Future
Submarine Program. Public hearings were held in Adelaide and Canberra on 8,
14 and 20 March 2017. The JSCOT tabled Report 169 on 13 April 2017.
1.6
Evidence received at several Senate Estimates hearings in 2017 and 2018
is directly relevant to this inquiry and has been used throughout this report.
The Finance and Public Administration Legislation Committee held Senate
Estimates hearings with the Australian Submarine Corporation (ASC) on:
-
28 February 2017;
-
24 May 2017;
-
24 October 2017;
-
23 February 2018; and
-
27 February 2018.
1.7
The Foreign Affairs, Defence and Trade Legislation Committee held Senate
Estimate hearings with the Department of Defence on:
-
30 March 2017;
-
29 May 2017;
-
30 May 2017;
-
25 October 2017;
-
28 February 2018; and a
-
29 May 2018.
Background
1.8
During the 44th Parliament, the overall terms of reference
for the inquiry was first referred to the Senate Economics References Committee
on 25 June 2014. The terms of reference was straightforward yet comprehensive
in its coverage—the future
sustainability of Australia's strategically vital naval shipbuilding industry.
The inquiry contained several parts, including a more narrow terms of reference
adopted by the committee on 10 July 2014 for Part I of the inquiry—examining
the tender process for the Royal Australian Navy's new supply ships and any
related matters given its significant impact on the Australian shipbuilding
industry.
1.9
The previous terms
of reference is contained in the committee's first report[2]
and is also available on the committee's webpage.
1.10
The committee tabled three substantive reports on Australia's naval
shipbuilding industry:
-
Part I - the tender process for the new supply ships, tabled on
27 August 2014;
-
Part II - the future submarines, tabled on 17 November 2014;
-
Part III - long-term planning, tabled on 1 July 2015.[3]
First report, Part 1— Tender
process for the navy's new supply ships
1.11
On 10 July 2014, as part of its broader inquiry into Australia's naval
shipbuilding industry, the committee resolved to inquire into the tender
process for the Royal Australian Navy's (RAN) new supply ships as its
first order of business. This decision was prompted by the government's
announcement on 6 June 2014 that it had given approval for Defence to conduct a
limited competitive tender between Navantia of Spain and Daewoo Shipbuilding
and Marine Engineering of South Korea for the construction of ships.
1.12
During this inquiry, the committee considered the strategic importance
of the replenishment of supply ships to the Australian Navy; the capacity of
Australian industry to build the ships; and the contribution that such
construction could make to sustaining Australia's naval shipbuilding industry.
The committee tabled this report on 27 August 2014. The committee
recommended that the tender process for the two supply ships be opened up to
allow all companies, including Australian companies, to compete in the tender.
It further recommended that tender documents should clearly note that a high
value would be placed on Australian content in the project. The report's
recommendations are reproduced at Appendix 2.
1.13
On 11 May 2015, the government's response was tabled responding to the
report's four recommendations.[4]
The government disagreed with three of the four recommendations, and agreed in
principle with the recommendation that Defence should become actively involved
in encouraging and to supporting Australian industry to explore opportunities
to become involved in the replenishment ship project.
Second report, Part II—Future
submarines
1.14
In the second report tabled 17 November 2014, the committee recognised
the immense national importance of the future submarine project and of every
decision relating to the project. The committee highlighted the vital
importance of having ideas and proposals thoroughly tested and assumptions
about the future submarines objectively and critically assessed by competent
personnel in order to provide government with the best possible advice. In the
committee's view, open and informed debate would confer much needed
transparency on government decisions; it would allow genuine scrutiny of
government decisions; and provoke robust and informed analysis.
1.15
Such a process, the committee reasoned, would also enable public,
industry and multi-partisan political support for the proposed acquisition to
be obtained. The committee asserted that the decision to acquire future
submarines was a decision in the national interest and should be owned by Australians.
The report's recommendations are reproduced at Appendix 3.
1.16
On 21 March 2017, the government's response was tabled responding to the
report's five recommendations. The government agreed in part with
recommendation 5, and noted the remainder.
Third report, Part III—Long-term
planning
1.17
The committee's third report tabled in July 2015, developed and expanded
on the findings of the first and second reports noting concern with the limited
tender process used for the acquisition of the new supply ships. In particular,
the committee expressed concern that to select just one contender at this early
juncture may be premature and that the government should consider proceeding
with two tenderers who could then further refine their proposals and develop
their design to a more mature stage. As part of the report's six
recommendations, the committee recommended that the government adopt a specific
procurement process to acquire the 12 future submarines.
1.18
The report also examined the competitive evaluation process for
Australia's future submarines, the independent audit of the Air Warfare
Destroyers project, the continuous build of vessels, the development of an
enterprise-level naval shipbuilding plan, and industry investment. All six of
the report's recommendations are reproduced at Appendix 4.
1.19
On 21 March 2017, the government's response was tabled responding to the
report's six recommendations. The government disagreed with recommendation 3,
agreed in principle with recommendations 5 and 6 and noted the remainder.
Significantly, the government rejected a recommendation, also contained in the
committee's first report, that the tender process for the two replacement
replenishment ships be opened up to allow Australian companies to compete and
place a high value on Australian content. The government awarded the contract
to Navantia S.A. and the ships are being built in Spain.
Structure of the report
1.20
This report comprises 6 chapters including this introduction. In
summary:
-
Chapter 2 – Background
-
Chapter 3 – National long term planning
-
Chapter 4 – Workforce planning strategy
-
Chapter 5 – An Australian sovereign capability
-
Chapter 6 – Support available to small and medium-sized
enterprises
Note
1.21
References to the Hansard transcript throughout the report refer to the
official transcript, unless otherwise stated. Page numbers may vary between the
proof and official transcript.
1.22
On 28 June 2017, DCNS officially changed its name to Naval Group.[5]
All references in this report are to Naval Group Australia except where direct
quotations have been used.
Acknowledgements
1.23
The committee thanks all those who assisted with the inquiry, especially
those who made written submissions and attended the committee's public
hearings. Witnesses are listed at Appendix 5.
Navigation: Previous Page | Contents | Next Page