Chapter 3 - Environmental impacts
Term of Reference 1 (a) (ii) ' ... 1 the possible
impact of the power line and the accompanying land resumptions on the
vegetation and overall environment.'
Definitions
3.1 In its submission to the Committee, Powerlink Queensland states: 'It is acknowledged that a high voltage
transmission line may have an impact on the environment of the area through
which it passes. The environment refers not only to the natural
ecological values of the area, but also to the man-made environment,
social and cultural attributes and economic issues'. 2
3.2 This is a very broad definition of
'environment'. The Committee's terms of reference require it to examine, as
separate terms of reference, 'the vegetation and overall environment' and the
'social fabric and local economic viability of surrounding communities'. This
report therefore makes a distinction between impact on natural environment,
discussed in this Chapter, and social and cultural impact, including local
economic impact and impact on agricultural land, discussed in Chapter 4.
Broader economic issues are discussed in Chapter 5.
Power
Authorities' Position
Environmental
Legislation
3.3 In both NSW and Queensland, development of the Eastlink proposal is subject to statutory
requirements under environmental impact legislation. In NSW the relevant Act is
the Environmental Planning and Assessment Act 19 79 (NSW) and Eastlink
cannot proceed until all the legislative requirements of the Act have
been fulfilled and the Minister for Urban Affairs and Planning (NSW) has
approved the activity.
3.4 In Queensland, the
relevant power authority must comply by requirements of both the Electricity
Act 1994, which specifically covers environmental impact in part 2, and the
Environment Protection Act 1994.
3.5 The project's Environmental Impact Statement
(EIS) must address a comprehensive list of matters and both power authorities
must consult the Commonwealth Environmental Protection Agency during
preparation of the Environmental Impact Statement. To do this, the two State
power authorities have agreed to nominate as joint proponents under the
Commonwealth Environment Protection (Impact of Proposals) Act 1974 and
to prepare one Environmental Impact Statement that would satisfy both NSW and Queensland legislative requirements, as well as those of the
Commonwealth. It is expected that the EIS will be available for public comment
in Februa /March 1996.
Consideration
of Environmental Factors
3.6 According to the two power authorities involved,
the Eastlink project takes environmental factors into consideration at two
levels. Firstly, in selecting a preferred corridor, the environmental impact of
each option was compared so as to select the corridor with the least
environmental impact. 3 Secondly, after selecting the preferred
corridor (the Western Corridor), the exact route will be chosen having regard
to the environmental impact study of that corridor.
3.7 In the submission presented by the NSW
Transmission Authority, Transgrid, it was argued that it was not
possible for the Authority to address the Committee's terms of reference, and
in particular point 1 (a) (ii), until the EIS process had been completed.
However, on the basis of 'extensive past experience' it was possible for Transgrid
to provide 'some general comments' .
3.8 In an effort
to minimise the environmental impact of high voltage power line construction
and maintenance procedures, the power authority would seek the involvement of
landholders, the NSW National Parks and Wildlife
Service and the NSW Department of Lands and Water Conservation.
3.9 With
regard to vegetation, Transgrid noted that a necessary impact will arise
from the statutory requirement that a minimum clearance be maintained between
the power line and towers and the ground, and that there was no avoiding some
disturbance to the environment through which the line passed. 5 However, all efforts would be taken by the Authority
to reduce the damage to vegetation through the use of minimal clearing
practises. These would include the lopping of trees instead of their removal,
prudent use of topography in open terrain, replacement tree planting with more
manageable species, and restricting clearing just to tower sites in rougher
terrain, rather than clearing along the full length of the route.
3.10 The impact of the power line on the environment
would depend on the type of environment through which the route passed. The
line would have minimal physical impact in cleared agricultural land and would
have a much higher impact in areas of dense native vegetation such as national
parks, nature reserves and undeveloped crown land. The Western Corridor is
located primarily within cleared lands and largely avoids forested areas. Those
areas that are not agricultural are mainly eucalypt woodland and open forests.
3.11 With regard to the overall
environment, Transgrid noted that, in its experience: ' ... once
constructed, transmission lines become passive elements in the overall
environment surrounding them.' Further, Transgrid claimed: 'The process
under-taken to identify the preferred location for [the power lines],
followed by the detailed environmental impact assessment and the development of
comprehensive mitigation measures ensures that the resultant impact is minimal
and acceptable.'
3.12 Powerlink, in its submission, noted: 'For Eastlink, a
consideration of environmental issues started at the beginning of the corridor
selection process. The preliminary corridor concepts which were
developed in-house before public consultation commenced, were based on a
consideration of broad environmental issues. Factors such as population
density, national parks and wildlife areas, and physical topographical barriers
helped define these broad corridor concepts'.
3.13 After delineation of the broad corridors,
environmental factors were again taken into account, including
present land use, probably flora and fauna impact,
location of houses and schools, heritage and conservation areas, access
difficulties and scenic quality of areas. In the final corridor selection
process 10 primary factors were evaluated: conservation areas, impact on
tourism, visual impact, tree cover, severe soil erosion, houses within 500m,
cropping land, irrigation land, number of land parcels and technical cost
issues.
Broad Environmental Benefits
3.14 As pointed out in the submission by the
Commonwealth Department of Primary Industries and Energy,
Eastlink may result on a broad scale in some
environmental benefits. These could arise from ' the sharing of reserve
capacity, the reduced need for additional power generating plant, and the
energy saving resulting from the more efficient use of energy resources. The
submission further notes that alternatives to Eastlink would not necessarily be
environmentally benign and proposals such as the Tully Millstream Hydro
Electric Scheme has potentially adverse impacts on a World Heritage Listed
area.
Community Concerns
3.15 Considerable concern was expressed to the
Committee, both in submissions and in oral evidence, that the
construction of Eastlink would result in unacceptable
environmental impact. The types of impact sustained, it was argued, would be
soil erosion, vegetation loss and disruption to plant and animal communities
and consequent fragmentation of habitat. Of broad concern was the apparently
contradictory philosophies of governments which, on one had, promoted programs
such as Landcare and One Billion Trees while, on the other hand, allowing the
destruction of trees and associated habitat along the full length of the
proposed Eastlink route. Other specific concerns included impact on Aboriginal
and European heritage.
3.16
Landholders and conservationists argue that the environmental impact would be
much wider than just the easement zone; that once the construction damage is
done, no amount of rehabilitation will return the affected areas to their
original standard of environmental integrity; and, more importantly, that there
is no need for the intrusion in the first place because Eastlink is not necessary
and not wanted.
3.17 The construction of the Eastlink power line
will necessitate the use of heavy machinery and access to pylon sites about
every 400-500 metres along the entire length of the line. As the route
proposed would be between 380 and 400 km long, this would mean a total number
of pylons of between 760 and 1000. Although the power authorities plan to
rehabilitate any areas damaged by construction machinery, submissions argued
that in some places it would be impossible to fully rehabilitate the land. Once
the soil was disrupted, a scar would be there for ever.
This transmission line would cross farming
land that is subject to high erosion from water. With the end result being that
considerable soil conservation measures have been carried out ... Maintenance
of these control measures is an ongoing procedure and the construction of steel
towers anywhere across this land completely contradicts soil conservation
practices.
3.18 Another important aspect of construction, of
concern to property owners, is the potential for mud-laden machinery to
carry weed seeds from one place to another. This can also occur after
construction when maintenance inspections are carried out. Several people were particularly concerned about the
spread of Parthenium weed which is known to cause health problems in
central Queensland through allergic reactions to its pollen.
Its spread south is of concern to physicians.
3.19 Similarly, the contamination of heavy
machinery with soil could allow the spread of fungal diseases such as Phytophthera
cinnamonni.2 In addition, the construction of access
roads and the easement itself provides increased access for feral animals into
properties and nature reserves, and the creation of windrows of felled trees to
create habitat which favours introduced species such as foxes, rabbits and
cats.
3.20 However, as described by Powerlink, routine
procedures are carried out during the construction of power lines to curtail
the spread of weeds and fungal spores by cleaning vehicles and equipment prior
to their movement from infested to weed-free areas. Should weed infestation be established to have been
the result of power line construction, power authorities will take
responsibility for their eradication or reimburse farmers for that cost.
Soil Erosion
3.21 Particular concern was expresses about the
potential for soil erosion following the excavation of pylon sites and creation
of access roads. Once soil is disturbed in some areas, it is
very difficult to stabilise again, particularly in steep, heavily wooded
country. Although the Darling Downs has deep rich black soil in parts, it is
very unstable. Paddocks become inaccessible when wet, and the soil type is
classified as having high erosion potential. The hills and ridges in that area
are even more prone to erosion. They grow very little grass, being protected by
a combination of shrubs and trees. Following mechanical disturbance, the soil
moves easily down slope into gullies during rain.
3.22 In Traprock country, south of Warwick, the soil is highly susceptible to erosion.
Even on almost flat land (2%
slope) a bulldozer can
cause erosion that is difficult to repair. Local resident are extremely
concerned that construction of Eastlink would cause serious environmental
damage. Of particular concern is the possibility that, while local properties
have always been managed by property owners who understand the fragility of the
land, power line construction crews may not be so sensitive. In evidence to the
Committee, a representative of the Traprock Branch of SEQAE/TOTA stated: 'Due
to the steep and inaccessible nature of the corridor within the particular
reference section, it would be impossible without causing extreme erosion
danger to gain access to tower construction sites with heavy vehicles such as
cement trucks and semitrailers'.
3.23 Soil erosion affects not only the immediate
construction sites but has the potential to affect the water quality of the
river systems through siltation and increased flow of nutrients from fallen
trees. As stated in evidence to the
Committee by a representative of SEQAE: 'since the Eastlink
route crosses 350 kilometres of the headwater catchments of the Darling River
... a route more damaging to the Darling River could not be found'.' Siltation and increased nutrient deposition can cause
toxic algal blooms and destruction of aquatic habitat.
3.24 The power authorities have acknowledged that
some environmental damage will occur during construction but they believe that
minimal impact construction practices will prevent any serious damage and that,
after the construction phase is complete, rehabilitation of disturbed areas
will ensure that the impact doesn't continue.
Loss of Trees
3.25 While many farmers in the regions affected by
Eastlink have joined in collective conservation practices such as Landeare
programs and are making individually efforts on their own properties, they see
the destruction of many hundreds of trees along the power line casement to be
anathema to the cause of conservation. They see hypocrisy in governments which
legislate to ensure tree preservation and which provide funding for tree
replanting, yet allow large scale destruction of trees by power authorities.
3.26 One submission estimated that if the casement
was 60 metre wide and the power line several hundred kilometres long, then the
total area where trees would be removed was about 2000 hectares. The submission
argued: 'We should be encouraging, tree plantings not their destruction'. Another submission noted that since the 1970s farmers
have been working to link remnant vegetation with road plantings and shelter
belts, and in 1991 they were assisted with tree planting through a government
grant under the 'One Billion Trees' program. Despite the prolonged drought,
farmers have persevered with the program and have worked hard to nurture the
trees.
Fragmentation
of Habitat and Impact on Fauna & Flora
3.27 One of the likely consequences of tree
clearing along the power line route will be fragmentation of habitat. As
pointed out by the Armidale Branch of the National Parks and Wildlife
Association, the New England environment is already heavily fragmented
and any further breakup of woodland habitat should be avoided. The Branch 'is
concerned at the prospect of extensive damage to vegetation and wildlife
habitat, at a time when every effort is being made to reduce habitat loss, and
thereby species loss'.
3.28 Various submissions expressed the view that
the creation of a bare corridor through native vegetation, and revegetated
farmlands would have a negative impact on wildlife, particularly tree dwelling
mammals such as koalas, possums and gliders, and birds such as the Red Goshawk,
Squatter Pigeon and Glossy Black Cockatoo. These submissions pointed out that
habitat for such wildlife is already fragmented and any further breakup of the
integrity of the areas in which they live could threaten their viability. The
easement created by Eastlink would result in a continuous north south barrier
to the movement of tree dwelling animals, especially in areas where trees are
already scarce.
Concern for the
Lockyer Malley & Llelidon Hills Areas
3.29 The Helidon Hills area near Warwick has great scenic and botanical value. This rugged
area contains a wide diversity of fauna and flora, as it retains much of
the natural tree cover and it relatively free of weeds. It also contains
several endangered animal species and has been recommended for inclusion as a
national park. Being close to Brisbane, its location is convenient for nature-based
recreation. The Toowoomba Field Naturalist Club maintained that the Eastlink
easement will cause considerable damage to the natural vegetation of the Helidon
Hills and the Club opposes Eastlink on these grounds.
3.30 The submission from the Lockyer Valley Against Eastlink
group noted that the power line route would pass through areas of high
conservation value, including habitat of rare and endangered
species, and vegetation types which were poorly conserved in south east Queensland. These areas included
the Helidon Hills (a large area of continuous bushland), and remnant bushland
in the Paradise Falls, Dry Creek, Silky Oak and Paradise Mountain area. Some of
these areas had critical conservation status. 27
3.31 In addition, the Helidon Hills area is an
important part of the Lockyer Valley water catchment.
Because the Valley has no major rivers or prospect of a major dam it depends
totally on underground water. Residents of the Valley expressed concerns that
any disturbance to the integrity of the vegetation in the Hills will have an
impact on the ability of the area to contribute to groundwater.
Concern for the
New England Environment
3.32 Several submissions from the Armidale area
expressed concern for the fragility of the New England Environment, noting that
the soil structure is such that it is highly susceptible to erosion and that
the region has already suffered badly from tree die-back.
3.33 A
submission from this region noted:
Some years ago New England suffered what is
now known as ,severe tree die-back' where very large tracts of
trees died leaving the landscape quite bare ... The de-nuding of trees
from the landscape is well known to cause other long-term problems such
as lower rainfall, salting of the soil, wind and water erosion to name but a
few ... It would now seem that the proposed route could necessitate clearing a
large part of what is left of good trees on this property - contemptible.
3.34 The Chairman off the Guyra Landcare group
pointed out that the proposed route would disrupt the Guyra Tree
Corridor Programme, the region's major Landcare effort, both because the
easement would traverse some of the tree corridor and because the Eastlink
consultation process had caused acrimony within the community which had
hindered the process of negotiating tree corridors between properties.
Concernfor the Condamine
Catchment Area
3.35 The Condamine Catchment Coordinating Committee
was formed to bring about sustainable land management in the Condamine region,
an area of some 30,000 square kilometres centred around Warwick and part of the Murray
Darling Basin. As outlined
in the Coordinating Committee's submission, the Eastlink proposal raises a
number of land and water management issues within the catchment. Their major
concerns relate to the clearing of trees, which could lead to soil erosion and
increased stream siltation, and which will have an impact on biodiversity,
animal habitats, weed invasion, and reduction in environmental integrity.
3.36 Local Landcare groups in the Condarnine Catchment
have worked hard to involve both rural and urban people in a wide range of land
rehabilitation projects; planting trees to establish seed woodlots of local
native species, planting shelter breaks for stock and crops, integrating tree
species to local soil conditions, carrying out remedial work on salinity
problems, soil stabilisation work, and establishing wildlife corridors.
3.37 The Allora Landcare Group point out that the
proposed Western Corridor traverses an important Landcare project near Allora
along Tudor Valley Road. The project involves tree species trials aimed at
encouraging graziers to establish timber plots for multiple purposes. The Landcare
Group consider the project to be of great importance because of its location,
and because a large amount of time and money has been put in to establishing
the trials. The Allora Group argued: 'Landcare groups all over the country are
demonstrating a genuine commitment to ecologically sustainable
development and protection of biodiversity. It is time for a similar commitment
from our State Governments and public utilities.
3.38 They have been dismayed to find that power
authority attitudes have been uncaring of their enthusiasm. The Tudor Valley site lies directly along the Western
Corridor and when informed of this, representatives of the power authorities
reportedly offered to replace the project with 'bushes'. According to a member
of the Allora Landcare Group: 'Any effort to point out the potential for
serious damage to natural systems has been met with "we'll fix it, little
realising (or caring) that detrimental effects can have dramatic and far-reaching
consequences that are extremely expensive and sometimes impossible to rectify'.
Use of
Chemicals in Easements
3.39 Various methods are used to reduce vegetation
height along power line easements. These methods include tree felling and the
use of herbicides to prevent their regrowth. Concern was expressed in submissions
that because power authorities use subcontractors to carry out vegetation
control, the authorities lose control over the operations and the standard of
care taken when chemicals are used may not be as high as landholders would
like. Examples were cited of chemical mishandling by subcontractors and
accidental toxic chemical spray drift onto private properties.
A Philosophy of
Care
3.40 Landholders who have worked hard over many years
to revegetate their properties in order to improve the landscape and to
encourage wildlife are now bewildered and frustrated that their acreages will
be divided and despoiled by a cleared easement and rendered unattractive by
ugly structures. Similar comments were made by rural
landholders along the full length of the line.
3.41 Landholders who have worked to blend their own
agricultural land with neighbouring nature reserves pointed out in their
submissions that the involvement of rural landholders in wildlife conservation
has considerable benefit to all Australians. 'Conservation is being achieved in
an economic and sustainable way, instead of locking up large tracts of
land which is difficult to keep free from both animal and plant pests and at
considerable cost to the public purse'.
3.42 Indeed, for many landholders, the recent
drought has highlighted the fragility of the
environment in which they live. They have struggled to retain ground cover, to
reduce the potential for erosion, to protect their farms from the
vagaries of the weather. But while they can accept the impact of the drought,
because they have no control over the weather, they are at a loss to understand
why anyone would intentionally place stress on the environment in which
they live when there appears to be many more benign and globally desirable
alternatives.
3.43 Over recent years there has been a change in
the way rural Australians think and there is a groundswell for more responsible
land management. 36 Through observing the detrimental impact
that traditional farming practices have had on their properties, and through
the advent of Landcare programs, Coordinated Catchment programs and Whole Farm
Planning philosophies, the traditional Australian farmer has changed from user
of the land, only reaping the benefits, to concerned custodian, willing to put
back into the land as much, or more than has been taken out. There has been a
definite change in the philosophy of many rural landholders such that most
farmers now both understand the need for environmentally sustainable farm
management practices, and are keen to redress the environmental mistakes of the
past.
3.44 The Glen Innes Natural Resources Advisory
Committee Inc (GLENRAC) submitted that: 'There are in excess of thirty Landcare
groups, Catchment Management Committees and Resource Management organisations
at work in the North of NSW, all of them cooperating with Government agencies
to achieve the objective of reducing soil and water degradation. ... [However]
throughout the Landcare Groups there is a strong perception of the denial of
the value of the whole Landcare movement by a Government which plans a project
which will destroy as many trees as have been planted and cause as much soil
erosion as has been rectified by the Landcare Groups, and will in addition cut
every wildlife corridor between Armidale and Springdale'. 37
Visual Impact
3.45 Many submissions to the Committee expressed the
concern that Eastlink would result in loss of the visual integrity of the bush
in those regions through which the line traversed. Submissions pointed out that
people generally move to rural areas to enjoy the bush environment,
particularly the natural beauty of the landscape and to escape the visual
disharmony of cities.
3.46 Many submissions argued that constructing large
towers and associated power lines through picturesque farmland would spoil the
visual attractiveness of the environments in which they lived. This would
reduce the quality of life for those who live within eyesight of the chosen
route by despoiling the very beauty of the bush that they had sought by moving
to that particular place. 33
3.47 As an example, during inspections the
Committee visited the property of Mr Alexander (Jimmy) Martin; some 100
acres of land bought recently as a place for retirement. The power line would
stand between his house, set on the side of a hill, and a scenic valley,
obstructing the view. Mr Martin said he had
been offered $22,000 compensation by Transgrid for the casement which he
believed was insufficient to ameliorate the loss of the view, the main reason
why he had bought that particular property.
3.48 In fact, the whole valley in which Mr Martin lives is of high scenic and rural heritage
value. The Committee inspected several other properties in the area, all of
which had very attractive scenic outlooks, both in the near distance and far
away. These views would be considerably spoiled by the imposition of a high
voltage power line.
3.49 Other witnesses pointed out that their
properties had already been crossed by several other power lines, of lower
capacity and height. While they, had tolerated the construction of the smaller
lines, the combined impact of those lines and the much larger pylons and lines
of Eastlink would be intolerable. One submission stated: 'My small 16.3 ha. property
has been grossly devalued by the existing THREE power line constructions
through my good improved grazing paddocks. A fourth construction of the even
larger Eastlink line is OBJECTIONABLE especially when it is not justifiable'. Another submission noted: 'We already have three power
lines going through our 7 hectares hobby farm. They are nothing but an eyesore.
To have another set erected will be disastrous for us.
3.50 And, while compensation might be paid to
people over whose property the line would cross, those properties which
suffered a visual impact only would not be eligible for any compensation, even
though the line may go very close to their boundary and completely spoil the
view. People in this situation were angry that they had to suffer the visual
intrusion of an offensive structure with no prospect of compensation.
Heritage
3.51 A number of properties in the Western
Corridor region pointed out that they had special heritage values that would be
compromised by the construction of Eastlink. In addition, the general concept
of family heritage was mentioned in quite a number of submissions to the
Committee.
Aboriginal
Heritage
3.52 Mr J W Deacon submitted to the Committee that
part of his property through which Eastlink would pass was of significant
Aboriginal heritage. The area was used as a camp by Aboriginal people and many
of the trees bear marks of Aboriginals removing bark. Mr Deacon has applied to
the Heritage Commission for listing, and officers of the Commission have undertaken
to express their concerns to the power authorities. Forty-eight trees
have been recorded and it is believed that the scars are at least 130 years
old. There is also a small valley on the property which has been protected by
Mr Deacon's family since 1915 because the valley was a women's area. There is
also an Aboriginal camp site and a site of rock quarrying.
3.53 As noted
in the submission: 'there are not many sites left close to civilisation where
areas are still reasonably intact and have trees which were used by the
aborigines still standing. This shows where they lived and hunted.
For the towers and
cables of Eastlink to be in close proximity to this site would destroy much of
its significance and atmosphere' .
Heritage Property
'Olliera'
3.54 Specific concern was expressed that Eastlink
was greatly reduce the value of the heritage listed-property 'Ollera'.
This property, which is situated some 80 kilometres from Armidale near Guyra,
has been listed variously by the National Trust in 1975, the Australian
Heritage Commission National Estate of Australia in 1979 and the National Parks
and Wildlife Service (NSW) as a wildlife Refuge in 1973. The property has
considerable potential for rural tourism.
3.55 The
property's assets include:
-
a homestead built in
183 8;
-
heritage buildings,
including slab cottages, shearing shed with surrounding landscaping and trees;
- a small stone church
with stained glass windows (St. Bartholomew's Church of England), maintained at
the property's expense for 119 years but used by the public;
- a cemetery containing
380 graves (152 years old);
- a cricket field and
associated grounds, maintained by the property for 145 years and open for
public use; and
- over 130 family
journals and documents held by UNE archives.
3.56 The property is already traversed by four
other main power lines including a 132kV line.
3.57 The Committee visited 'Ollera' on the morning
on 13 October 1995 and agreed that the homestead, the church
and the outbuildings had very high value as rural heritage.
Family Heritage
3.58 Both the New England and Toowoomba regions have been settled for many years and some
properties have been in the hands of the one family for three or more
generations. Owners of these properties felt a strong pride in their family
heritage and expressed a strong desire that their property should remain in the
ownership of their family for many more generations. However, they felt that
the imposition of Eastlink has threatened future heritage: that younger generations
would not want to live on a property which had traversing through it a high
voltage power line for health reasons, for aesthetic reasons and for reasons of
privacy .
Environmental
Impact Statement
Power Authority
Position
3.59 The formal environmental impact study (EIS) is
being carried out for the power authorities by consultants Dames and Moore. The EIS will be supported by a range of specialist
studies of the social and biophysical environment, including visual, natural, agricultural
and socio-economic environment, with specific studies to cover flora and
fauna impacts, visual impacts and impacts on agriculture and land use. The fauna and flora survey was carried out by
consultants from New England University.
3.60
According to the terms
of reference of the EIS, it must cover:
- a description of the
existing environment;
- a description of the
effect of Eastlink on the environment.,
- an economic evaluation
of Eastlink;
- safeguards and
mitigation measures to be employed;
- assessment of feasible
alternatives;
- government authorities
who must be contacted; and
-
issues arising from
community consultation.
Community
Criticism of the EIS Process
3.61 Two specific criticisms were made to the
Committee regarding the Eastlink EIS. The first
related to the conduct of the fauna and fauna survey and the second related to
the extent of the EIS process.
3.62 The fieldwork for the EIS dealing with fauna
and flora was carried out for 10 weeks from mid-April until the end of June. Being autumn and winter, and following a severe and
prolonged drought, a number of submissions to the Committee noted that this
period would not have been the best time to survey flora and fauna. In evidence
a representative of the Armidale Branch of the National Parks Association argued
that the survey would not have picked up annual plants, nor some perennials
which flower in spring and which would have disappeared by autumn.
3.63 The sampling methods used during the flora and
fauna survey were also criticised. One submission noted that when a power
authority representative had been questioned as to why no survey had been
carried out in a certain area, the reply had been that the impact assessment in
that area had been done from an aeroplane. Other
submissions noted that field surveys had been conducted only on some
properties, at a spacing of about every 5 kilometres. In addition a number of
local environmental groups, such as the Condamine Catchment Coordinating
Committee, requested to be involved in the EIS process for Eastlink but no
response to their request was given by the power authorities.
3.64 On one property in the Wandsworth region of New England, a fauna survey was only carried out after a specific
request was made by that property owner. Despite spotlighting and live-trapping
for small mammals, none of three endangered species known to be present on the
property were sighted. It was assumed that this was a result of the time of
year that the sampling had been carried out.
3.65 Thus because of the timing of the fauna and
flora surveys, and because of the sampling methods used, it was the general
view of local environmentalists that the results of the biological survey were
not representative of the biota that actually exists along the Western
corridor.
3.66 Of equal concern to people living in the
Western Corridor was the fact that the Corridor was chosen before the EIS was
carried out. Inherent to EIS methodology is the principle that the
environmental impact of one option be compared against the environmental impact
of another option, or several other options. While the power authorities
involved have stated that broad environmental factors were taken into account
in choosing the Western Corridor, evidence was presented to the Committee that
the legislative requirements of carrying out an EIS are only being fulfilled
for one option.
3.67 The Armidale Branch of the National Parks
Association, in particular, expressed concern that the EIS related only to the
Western Corridor, and that environmental impacts were being assessed without
examination of feasible alternatives, both at the broad level of whether the
link itself was desirable, and at the level of which Corridor was
environmentally preferable.
3.68
In addition, the Branch
was concerned that the environmental impact of all the
developments associated with
Eastlink were not being taken into account and that
the EIS was only considering the impact of the Eastlink route itself. The
Branch submission noted that the Project Concept document: 'indicates that to
achieve maximum trading benefits the interconnection plan will involve many
more lines than the single one now being discussed' Other lines associated with
Eastlink include:
- a 78km double circuit
275kV line from Blackwall (near Ipswich) to Withcott (near Toowoomba) via
Springvale;
- a second 330kV line
from Armidale to Lismore ( the choice of this route had not been made at the
time of the Project Concept report);
- a 340km double circuit
275kV line from the Callide coalfield near Gladstone to Tarong, north of Toowoomba; and
- another line between
the Hunter Valley coalfields of
NSW and Springdale needed to upgrade interconnection and
maximise trading opportunities.
3.69 The
Branch submission stated emphatically: 'The discussion of these extra lines ...
proceeds without any apparent concern for the two-, three- or four-fold
increase in environmental and social impacts to be experienced on the ground.
We think that the cumulative effects of the total complex should be considered
now, before the first line is allowed to set a precedent for the inevitable
sequence'.
3.70 The Gatton
Shire Council argued it its submission that it had not been adequately
consulted on the future of Springdale. Had the Council been informed that up to
nine lines would converge at Springdale it would have more vigorously opposed the
location. The Council argued that the EIS should have covered the impact of all
lines and not just the one line associated directly with Eastlink, and that it
should have been consulted on the terms of reference for the EIS.
3.71 During
public hearings and inspections it was made clear to the Committee that the two
power authorities were already negotiating with landholders to determine the
exact route that Eastlink would take across their land. Yet the EIS has not
been completed. This fact, plus the criticisms of the way in which sampling for
the EIS was carried out, have led many people in the Eastlink region to
conclude that the EIS is considered by the power authorities to be a mere
formality and a farce.
3.72 The Committee is aware that on the one hand,
the power authorities have taken a pragmatic attitude and that, on the other
hand, landholders and conservationists have taken a 'worst case scenario'
approach such that the views of the two groups have become very polarised.
3.73 The Committee accepts that there will be
some direct environmental impact associated with the construction of this high
voltage power line. The primary impact will be loss of trees through clearing
of easement and resultant fragmentation of habitat. Other potential
environmental impacts include soil erosion, the introduction of noxious weeds
during construction and maintenance activities, the use of herbicides to
control vegetation regrowth along easements, the unfavourable visual impact of
the line, and impact on special heritage areas.
3.74 Of greater concern to the Committee is,
however, the actions of the power authorities in determining the preferred
corridor, then carrying out the Environmental Impact Statement. While the final
impact statement is not due to be completed until mid-1996, it is clear
that the power authorities have already chosen a specific route, if not over
the whole length of the line, certainly over parts of the line. This is
evidenced by the fact that some land holders have already been made offers of
compensation. The practice of negotiating an easement before the Environmental
Impact Statement is complete goes against recognised Environmental Impact
Statement practice.
3.75 The
Committee questions the practice of carrying out an environmental impact
assessment of a proposal when alternatives have not been included in the
detailed Environmental Impact Statement and when siting of the line is clearly
going ahead before the Environmental Impact Statement is complete.
Navigation: Previous Page | Contents | Next Page