Chapter 1 - Eastlink proposal
Background
1.1 Although the potential benefits of interconnecting
New South Wales and Queensland electricity grids had been discussed for several decades, it was not
until December 1993 that the State Governments of NSW and Queensland, along with the Commonwealth Government, signed a
Memorandum of Understanding to proceed with interconnection. This had been
preceded by an agreement in principle, at the Adelaide Premier's Conference of
1991, to work towards the establishment of a national electricity grid, and a
1993 Council of Australian Government (COAG) agreement to the establishment of
an interstate transmission network and a competitive national electricity
market.
General Concept
1.2 The Eastlink proposal would connect the Queensland electricity grid with that of the south eastern
states via a high voltage dual transmission line from Springdale near Gatton in Queensland, to Armidale in northern NSW (Figure 1.1).
The line would be a 330kV double circuit steel tower transmission line having a
length of about 380-40Okm, depending on the final route selected, and
capable of carrying 50Ornw in either direction.
Project
Rationale
1.3 Projections indicate that Qpeensland will require
around 280 megawatts (mw) of new capacity in 1998 and between 200 and 30Omw
each year thereafter to meet projected growth rates. NSW currently has surplus
generating capacity and forecasts suggest that it will.not require additional
capacity until about 2003. Connecting Queensland to the
south-eastern grid would allow other states, and in particular NSW, to
bid competitively to supply Queensland's future requirements.
1.4 Queensland's energy strategy for the period 1998-2006
is contained in its April 1995 Energy Policy Statement, a document based on the
Government's Future Supply Consultative Electricity Task Force report of
September 1994. The strategy includes: 'demand-side management, renewable
energy, refurbishing and recommissioning power stations which had been closed
and inter-State connection with NSW, as well as more conventional options
for new generating capacity.
1.5 To allow Queensland to
include interconnection among its options for extra supply in 1998, it is
necessary to carry out initial feasibility studies for Eastlink now. These preparatory
studies include completion of engineering and operational studies, the
identification of a transmission line route and acquisition of property
easements for the line.
Benefits of
Interconnection
1.6 Connection of Queensland to the already connected electricity grids of southern Australia is an important element in the establishment of a
competitive national electricity market. The specific benefits expected to be
gained from interconnection through Eastlink are that:
- it will offer
operational efficiencies as it will allow lower cost power generation in one
system to replace higher cost generation in others;
-
it will allow the
deferral of new power station construction through increased reserve sharing
across four states; and
- it will lead to greater
efficiencies by increasing competition between power generators through trading
in electricity between states (power interchange).
The Authorities
1.7 When the Memorandum of Understanding was
signed in December 1993 the two state power authorities involved in Eastlink
were Pacific Power (NSW) and the Queensland Electricity Commission (QEC). Since
that time, both authorities have undergone major restructuring to separate the
functions of electricity generation from transmission.
1.8 On 1 January 1995, the Queensland Electricity Transmission Corporation
(QETC) was formed to assume responsibility for the bulk electricity
transmission functions of the former QEC. It trades under the business name of Powerlink
and is a subsidiary corporation of the newly formed Queensland Transmission
and Supply Corporation (QTSC) which also has responsibility for all the former
regional distribution Boards (now also Corporations). The general functions of
the former QEC are now undertaken by Austa Electric, the trading name of
the Queensland generating corporation. All corporations
are Queensland Government owned and Powerlink has responsibility for Eastlink.
1.9 On 1 February 1995, the NSW Electricity Transmission Authority was
formed as a separate NSW Government Statutory Authority to assume
responsibility for the bulk electricity transmission functions of Pacific
Power, with the latter continuing to discharge all the remaining functions
associated with electricity generation. The transmission authority operates
under the business name Transgrid and has responsibility for Eastlink .
Commonwealth
Involvement
1.10 The Commonwealth strongly supports the
extension of electricity transmission links between the states on the
basis of increasing the level of competitiveness among power authorities.
1.11 Under the 1993 Memorandum of Understanding, the
Commonwealth agreed to pay one third of the cost of the work undertaken bly NSW
and Queensland to assess technical feasibility, route selection and environmental
impact up to a maximum of $7 million, with no more than $3.5 million going to
each state. The contributions of the Commonwealth will be limited to $1 million
in 1993/94 and $3 million in 1994/95 and 1995/96.
Technical
Specifications
1.12 The transmission line proposed is to be a 330 000
volt (330kV) single transmission, high voltage alternating current line
carrying two circuits with a firm transfer capacity in either direction of
50Ornw. The line must be capable of carrying 50Omw when one of its circuits is
temporarily out of service for maintenance, or due to a fault. Connection
points must meet several essential technical criteria and site selection has
been narrowed down to one site in NSW (an existing high voltage substation near
Armidale) and a green-field site in Queensland (a future high voltage substation at Springdale near Gatton). The transmission line would be similar to other 330kV
lines around Australia, suspended from towers approximately 40-45
meters high and 400-450 metres apart in flat to undulating country. Other
designs are being investigated for visually sensitive areas. The line would be
able to transmit up to 50Omw of power between the two states.
1.13 The works
required for Eastlink are:
- one double circuit
330kV transmission line between Armidale and Springdale;
- substation works at the
existing Armidale 330kV substation;
- construction of Springdale 330kV Substation by QETC;
- minor substation works
at a number of other sites in Queensland and NSW; and
- the construction of a double
circuit 275kV transmission line between Springdale and Blackwall in Queensland. (This line, and some other small
substation works would have been constructed at some later time anyway, so only
advancement costs are attributed to Eastlink.
Costs
1.14 The
present cost estimate for Eastlink is about $300 million. This includes all survey and engineering
costs, installation costs of the line and substations at Armidale and Springdale, casement acquisition and compensation costs, an
appropriate level of contingency cost and interest incurred during
construction of the project.s
1.15 Operation
and maintenance costs associated with Eastlink have been included in the
evaluation and are estimated at nil for the first two years after establishment
of the interconnection and conservatively at 1% of the c 1 cost per annum from
the third year onwards.
Route Selection
Process
Three different
terms are used in describing the line taken by Eastlink:
Corridor: A
general area or broad of land in which a transmission route may be located. The
width of the corridor depends on land constraints. It may be as narrow as
several hundred metres in critical areas or as wide as 10 kilometres in other
areas.
Easement: A strip of land wide enough to construct,
operate and maintain the transmission line. Easements required for Eastlink
will generally be about 60 metres wide but may increase to 110 metres in some
areas.
Route: The specific alignment on which a
transmission line is built.
1.17 The
process used to determine the ultimate path of the transmission line will have
six stages:
- the identification of
preliminary corridor concepts;
- the refinement of those
concepts, with the aid of the community, into viable corridor options;
- the presentation to the
community, for formal comment, of those corridors in a Corridor Selection
Report;
- an evaluation of all
community comment and environmental and other studies leading to the selection
of a preferred corridor;
- the production and
presentation of environmental impact assessment documents for the proposed
transmission line within the preferred corridor in accordance with state
legislation;
- the selection of a
final route within the preferred corridor on the basis of the environmental
impact assessment and community submissions, technical considerations and
following consultations with property owners.
1.18
As shown in Figure 1.
1, two major corridors (Eastern and Western) with a series of link options
(Western
Alternative, Central Corridor, Link 1, Link 2 and Link
3) were initially identified. Prior to the selection of a preferred corridor,
the power authorities stated: 'At this stage, the Eastlink team has no
preferred option and all corridors are being treated equally. The preferred
corridor will be selected on an assessment of the relative impact of each of
the corridors; the community submissions and the technical requirement for the
line.
Figure 1.1 - Corridor an link
options for Eastlilnk (Map available in hard copy report)
Western
Corridor Selected
1.19 After extensive consideration of submissions to
the selection process and after an assessment of the relative impact of each of
the corridor options, notice was given in February 1995 that the Western
Corridor (Corridor A in the Selection Process Report) had been chosen for
refinement of an exact route. The project team is currently contacting
landowners along the preferred corridor to have further discussions aimed at
identifying an alignment of the transmission line so as to minimise impact.
During the course of the environmental impact statement the corridor will be
refined to an casement.
Easement
Acquisition
1.20 When a transmission line is constructed across
a property, the electricity authority does not normally purchase the affected
land but acquires an casement. This allows the authority to maintain and
operate the line while most normal farming and grazing activities remain
unrestricted. Guidelines are provided which outline activities which are
allowed, those which are restricted, and those which are prohibited along
casements.
1.21 Ownership of the casement remains with the
property owner but, by acquiring the right of casement, the authority is
able to use the defined area for a specific purpose. In exchange, the property
owner is entitled to compensation based on the impact of the casement, as it effects
the market value of the property. However, neighbouring property owners, who
may be affected by the visual impact of the line, are not eligible for any
compensation.
1.22 The route acquisition process differs in each
state: in Queensland the target date for approval of the line
route is October 1995 following which line casements will be acquired; in NSW
the target date for determination of the Environmental Impact Statement is June
1996, following which line casements will be acquired.
Work Program
and Commissioning
1.23 According to
the Powerlink Submission' the proposed timetable for Eastlink is:
-
Preliminary
Environmental Impact Study February 1996
-
Environmental Impact
Study Complete August 1996
- Field Construction
Commences April 1997
- Commissioning December
1998
Role of the
Committee
1.24 Although the Commonwealth has actively
promoted and supported the concept of an integrated south-eastern
electricity grid through interconnection, the Commonwealth's role in the
specific matter of the Eastlink transmission line is only one of providing a
contribution towards the funding of feasibility studies.
1.25 This Committee is similarly limited in its
jurisdiction and thus limited in the recommendations it can make. It is not
within the Committee's power to prevent or place a moratorium on the
construction of Eastlink. That is a matter that can be decided only by the two
states involved, NSW and Queensland.
1.26 However, having received a considerable amount
of evidence from the communities affected by the proposal, and having conducted
lengthy inspections and discussions with people in those regions, the Committee
believes that it has a responsibility to report on the process leading to the
selection of the western corridor. A large part of this report details many of
the concerns that were raised in evidence about the location of the line, the
consultation process, the social impact and local economic impact and the
potential health effects. In this regard, the main role of the Committee has
been to provide an opportunity for these and other matters to be fully
disclosed.
Navigation: Previous Page | Contents | Next Page