Chapter 9
Limited tender
9.1
When announcing the limited tender for the new supply ships, the
Minister for Defence explained that the Navy was in urgent need of large
support vessels but the government had assessed that it was beyond the capacity
of Australia to produce these ships competitively at this stage. He noted:
In this instance it would not serve anyone if we were to
provide a challenge to industry that was beyond its capabilities.[1]
9.2
In this chapter, the committee considers the government's decision to
conduct a limited tender and not to test, through an open tender process, the
various options put forward by Australian companies and, indeed, the
assumptions underpinning the DMO's advice to government at first pass.
Reasons for limited tender—cost and resources
9.3
The committee has recorded the government's arguments in favour of the
limited tender which relate to the urgent need to replace the existing vessels
and the productivity and capacity of Australian shipyards. The government made
the decision based on its belief that it would be more costly and timely to
build the ships in full or in part in Australia. Further, that an Australian
full or partial build of the supply ships would not help solve the potential
'valley of death'. Representatives of the defence industry in Australia who
gave evidence to the committee did not hold these views. Indeed, they put
forward options and proposals in support of having substantial Australian
involvement in the acquisition of the two ships and argued that the government
should have allowed builders to tender for the project on their merits.[2]
9.4
As noted in chapter 3, Mr King was the responsible authority for forming
the opinion that Defence should undertake a limited tender and advised the
government accordingly. When explaining his reasons for reaching such a view,
Mr King referred to industry's concern about Defence offering tenders that they
could not possibly win. He stated that he gets told very regularly and very
fairly:
...why are you driving companies to tender for stuff you are
never going to award them? In other words, I have to be mindful or practical.[3]
9.5
In seeking to explain further the underpinnings of his recommendation for
a restricted tender, he emphasised the fact that Australian companies would not
be able to meet Defence's requirements. He took the discussion back to the
complexity and time involved in securing the design from overseas and the major
adjustments required in an Australian shipyard to accommodate that design:
...first of all, just to get into an arrangement to bid that
job...the Australian company would have to team with a design owner. If you look
at the submission from the Royal Institution of Naval Architects, they make
exactly that point—that you would have to go to a designer. That designer, in
all instances I can think of, is also a shipbuilder. So here you are in
Australia saying, 'It is an open competition and it is an open tender. I want
to tender your design', and this designer is also a shipbuilder wanting to
tender that build of it...that design will have to be re-engineered in order to
be built in the facilities that will exist in Australia.[4]
9.6
Mr King accepted that an open tender would allow the merits or otherwise
of the various Australian proposals to be examined and assessed, but asked at
what cost to industry. In this regard, he informed that committee that the
costs for a company
to tender depended on the proposal but it could be $5 million or $6 million.[5]
He cited occasions where industry has said, 'You knew we couldn't meet that,
and we were put to this cost'.[6]
9.7
According to Mr King, the tender process would have been ineffective.
He again reiterated the impediments to an Australian build that have already
been presented throughout this report:
If we tender for an offshore supplier it typically takes...two
years. If it is a hybrid build it is three years. If it is an onshore build it
is four years. You have to get the designer, for example. I see the South
Australian government has made a submission about the facilities they could
increase. In order for that Australian company to effectively make a bid, it
would have to team with a designer that was prepared, under reasonable terms,
to release that design and it would have to do a lot of work with another
government or another backing to come up with, maybe, $200 million worth of
infrastructure. It then has to put its bid together. So even if we said, 'I'm
trying to get this ship in service by 2017'—very challenging, but as soon as we
can—that would at least add, in my opinion, two years to the tender process, to
be fair to them.[7]
9.8
He then reasoned that there was not much point in putting out a tender
that is 'not fair'.[8]
Mr King stressed that if he were to put out a tender and say, 'You must have
this solution to me in two years, they would not be able to do it'.[9]
9.9
In his view, industry, whether overseas or in Australia, requires a
reasonable prospect of winning and reasonable costs in tendering. In response
to the proposals that industry had put to Defence, he stated that for a hybrid
build alone, the unsolicited offers 'came back with a 40 per cent increased
cost and delayed delivery'.
He explained:
An unsolicited proposal is about your lowest degree of
certainty about the offer. It is somewhere between marketing and a tender, but
it is certainly not tender quality. Invariably, between the unsolicited
proposal and the tender things, whatever they may be, get worse—schedule,
price, whatever. What prospect against having to balance our budget, against
the advantages for the shipbuilding industry to do hybrid...it was not the whole
ship...What prospect of success would an Australian company have in an open
tender, even had they secured their design rights?[10]
9.10
Mr King repeated his argument that the request for tender has to be
legitimate—'to really give them a chance to bid.' He then again explained the
process; the impediments for potential Australian bidders to tender; and their
inability to meet Defence's requirements:
...we would have to do add a year to the tender process for a
hybrid build and probably another year for an onshore build. So you are going
to extend the tender period. You are then probably, from experience, extend the
contract period and then you are going to extend the build period. When we
extend the build, if we did a hybrid, somehow they [are] going to have to get
access to a design that is competitive. Secondly, we are going to take longer
to get to tender, longer to get to contract and longer to do the job. In
addition to those costs, I am going to have the additional cost of keeping Success
at sea at somewhere between $20 million and $50 million a year for every year
it continues.[11]
9.11
He concluded that he could not be honest to industry and 'satisfy
government's and taxpayer's reasonable expectations of value for money'. In
essence, according to Mr King, it would be 'misleading industry to say it
stands much prospect'.[12]
9.12
As he had done on a number of occasions during the hearing, Mr King stressed
the importance of placing the tender process for the supply ships in the
broader context of the package of decisions:
-
procurement of the AORs through a limited tender;
-
consideration of the feasibility of a replacement frigate program
continuing on from the air warfare destroyer effectively using that current
hull but with different equipment; and
-
an open tender to Australia to supply Pacific patrol boats.[13]
9.13
Mr King noted that the three decisions relating to the acquisition of
naval ships were made concurrently but with a different focus and, when taken
as a whole, made sense.[14]
He placed a heavy emphasis on the proposed future frigates as
an answer to industry's concerns about the loss of jobs and skills and the
possible demise of Australia's naval shipbuilding industry. Indeed, as noted in
the report,
Mr King envisaged the future frigate project as an opportunity to lay the
foundations for a truly strategic shipbuilding industry and to ensure the
continuity of work and retention of skills.[15]
While keenly supporting the prospect of building the frigates in Australia as a
follow-on project from the AWDs, Industry's resounding response was that the
frigate build was only 'a prospect'. Their immediate concern was ensuring that
Australian companies had the opportunity to participate in the construction of
the replenishment ships.
9.14
Industry saw Australian involvement in the supply ship build as a means
of sustaining a naval shipbuilding industrial base in Australia, thereby
bringing a range of economic and innovation benefits to the economy and protecting
the country's national security. It did not support the limited tender for the
supply vessels.[16] For example, the Adelaide Ship Construction International argued that:
...it is highly feasible that Australian industry participants
could easily have been invited to contribute to the tender process, prior to
the Government’s decision. It would have been a far better approach for the
Government, to have Australian industry plead their case to build the auxiliary
supply ships in Australia; rather than make the decision without the industry’s
input, and defend it later down the track, as they are being forced to do now.[17]
9.15
While the government has made it clear that Australian companies would
not be able to bid, Defence has indicated that there would be Australian
content, which could be as low as 10 per cent.
Recommendation 1
9.16
The committee recommends that the tender process for the two replacement
replenishment ships:
-
be opened up to allow all companies, including Australian
companies, to compete in the process; and
-
make clear that a high value will be placed on Australian
content in the project.
Recommendation 2
9.17
The committee recommends further that the government require that an
open tender process be used for any future naval acquisitions.
Recommendation 3
9.18
The committee notes that Defence has identified areas where potential exists
for Australian industry to become involved as sub contractors in the replenishment
ship project. In this regard, the committee recommends that Defence become
actively involved in encouraging and supporting Australian industry to explore such
opportunities.
Recommendation 4
9.19
The committee recommends that the government release the report of the
independent review of the AWD program undertaken by Professor Don Winter and Dr
John White.
9.20
Some themes emerged during this short inquiry that have relevance for
the committee's broader inquiry into the future sustainability of Australia's
strategically vital naval ship building industry. They go to matters such as:
-
Defence's understanding of the capacity of Australia's major
shipyards and the extent to which their facilities and infrastructure are used
for both naval and commercial activities;
-
shipyard infrastructure that is or should be regarded as a
fundamental input to capability and the need and potential for future
investment for critical infrastructure;
-
the connection between building a ship and maintaining that ship
throughout its operational life;
-
the basis for the minister's statement about poor productivity
with regard to the AWD project and its relevance to Australia's shipbuilding
industry as a whole;
-
lessons to be learnt from the AWD project and how they are and
should be applied to Australia's future acquisitions;
-
the extent to which broader economic benefits of naval
shipbuilding are understood and factored into decisions regarding the
acquisition of major naval ships;
-
current government and industry skills initiatives to mitigate
risks to upcoming naval construction project costs and schedules;
-
government and Defence strategies to identify and retain required
critical skill sets for through-life support and for future projects;
-
early engagement of industry in the life of a project and any impediments
to this engagement;
-
defence industry policy and where it should reside in Defence;
-
opportunities for Australian companies to compete for
shipbuilding and repair contracts and for increasing Australian content in major
shipbuilding projects; and
-
the importance of, and difficulties in, developing a long-term naval
strategic shipbuilding plan that can cost-effectively support the needs of the
Navy while sustaining an industrial shipbuilding base in Australia.
Conclusion
9.21
Although the committee has only started its inquiry into the future
sustainability of Australia's strategically vital naval ship building industry,
its consideration of the tender process so far for the supply ships has
highlighted a number of concerns. They relate to the lack of contestability and
competition in the limited tender, the level of industry engagement in the
process so far and the absence of long-term strategic planning that led to the
decision.
9.22
Decisions, such as the acquisition of the supply ships, are extremely
important for both Defence capability and for the sustainability of Defence
industry in Australia. They involve huge amounts of taxpayers' money and have
long-term implications stretching out for decades. Such decisions should be
well-considered and based on sound research, analysis and robust testing. The
committee is not convinced that a limited tender involving only two companies
is the best way to obtain the necessary information to proceed to second pass.
9.23
A local vibrant and sustainable industry able to support navy vessels
throughout their operational lives is critical to Australia's national
interest. In this regard, the prime contractors in Australia and the many SMEs
engaged in naval shipbuilding need to have certainty and the confidence to
continue to invest and participate in the industry. The way in which the tender
process was announced and the exclusion of Australian industry from this
process has clearly undermined this confidence. Thus, whatever the merits of
the decision to opt for a limited tender, the way in which the decision was
taken and announced conveyed an unfortunate message to Australian industry. The
lack of consultation was at odds with Defence's stated industry policy
objectives, which seek to promote a competitive, collaborative and innovative
industry.
9.24
Finally, the urgency attached to procuring these vessels highlights the
importance of government having a practical, reliable long term strategic plan
for naval acquisitions that takes account of the important contribution that
local industry has and can make to Defence capability.
Senator Sam Dastyari
Chair
Navigation: Previous Page | Contents | Next Page