Chapter 5 - Economic considerations
Term of Reference (1) (b) the overall economic impact of the
power line.
5.1 The two power
authorities involved in Eastlink, Transgrid and Powerlink, have
commenced feasibility studies on the basis that interconnection is economic and
will result in net benefits to both NSW and Queensland. The benefits that have
already accrued through the interconnection of the southern states are expected
to be extended through the connection of Queensland to the grid.
However, because Eastlink is part of a broad strategy, it is difficult to
separate it from wider economic considerations of the national grid and reforms
to the electricity industry.
5.2 The main
economic benefit expected of Eastlink is a permanent reduction in the
generating capacity held as reserve in NSW and Queensland because,
after connection, this reserve capacity can be shared. Transgrid estimates
that interconnection would allow an estimated 40Omw reduction in installed
reserves in Queensland and an
estimated 350mw reduction in the southern states. Accordingly, a total of about
750mw of new generating plant would not need to be built. Transgrid further
estimates that the financial benefits of deferring this capital investment in
power stations alone outweighs the costs of Eastlink. The net national economic
benefit of Eastlink has been quantified by Transgrid at $80 million.
5.3 Economic benefits
should also accrue from increased competitive pressures among generating
authorities. These pressures should provide an incentive for electricity
producers to find ways of reducing costs associated with electricity production
and cost reductions should ultimately be passed on to the consumer though
reduced electricity prices. Such benefits have not been quantified by
the power authorities involved because of the difficulty at this stage
of putting them into dollar terms.
Concerns Expressed In Submissions
5.4 In contrast to the
views expressed by Transgrid and Powerlink, many community groups
who made representations to the Committee argued that Eastlink was not
economic, that the benefits were questionable, that they would not flow to
small consumers and that the people of both states, but in particular
Queensland, would be better served by a mix of decentralised, renewable power
generating systems. Submissions frequently expressed the view that the
proponents of Eastlink had not adequately demonstrated any real benefits,
especially to the communities that will suffer direct disruption from the
proposal.
5.5 A detailed cost
benefit analysis of Eastlink has never been published. This has led to
suspicion that the 'hidden costs' relating to environmental and social impacts
and compensation had not been fully taken into account. 3 Some
submissions claimed that it was hard to know what the real cost would be
because statements had been made by different people, including state ministers
for energy, that the project would cost variously $280m, and somewhere between
$350m and $500m .
5.6 While the
document Eastlink Your Questions Answered (June 1995) concludes that
trading in electricity through Eastlink 'will be carried out, like any trading,
to the mutual benefit of buyer and seller', some submissions argued that there
are more stakeholders than just buyer and seller. Other parties involved
include the people affected by the power line, their communities and the
environment.
5.7 Among the many
detailed criticisms of the economics of Eastlink, the following points were
made,
- The
projected appeared to have a very high cost, compared to the relatively
insignificant supply. (The line is designed to carry 50Omw, which represents
the output of one older style turbine. Since modem power stations now have four
660mw turbines, this line will carry less than 1/4 of one power station
output.)
- If
power sharing was to occur from east to west it would be easy to understand the
potential for demand sharing, but trading electricity from south to north along
the eastern seaboard did not make sense because demand would be synchronised.
- The
construction of Eastlink undermined the value of viable, less polluting
alternatives such as gas turbines, renewable energy sources and demand side
management.
- Current
electricity prices do not adequately reflect the enviromnental, health
and social costs that are caused through pollution.
- Electricity
used by Queenslanders should be generated within their own state, and not
bought from elsewhere because it would result in increased employment in NSW
and reduced employment opportunities in Queensland.
- While
Eastlink was expected to postpone the need for construction of costly new power
generating plant in Queensland, that State has in fact announced a future
energy package that includes constructing or upgrading several new power
stations thereby increasing its installed capacity to 9840mw by 2006. 9
The Small Consumer
5.8 Many people believe
that the connection of NSW and Queensland through Eastlink will
not in fact result in any decrease in the price of electricity to them, or any
other benefits. They believe that small consumers, and
particularly those in rural areas will actually be disadvantaged by the
creation of a 'national' grid. As put in one submission: 'We simply do not
believe that a small number of wholesale entities will enter into free
and open competition in order to reduce costs to the consumer; the very nature
of free enterprise almost certainly ensure maximisation of profit, not
reduction of selling price.
5.9 The general view
presented in submissions was that the overall impact Eastlink would be to
promote big business at the expense of small business and individuals. Eastlink
is designed to allowing electricity trading between states and big cities, it
is not designed to allow delivery of electricity to people who currently lack
this service. Electricity will cease to be a service, become instead a
commodity which can be purchased more cheaply by the consumers. As pointed out
in several submissions, there is no guarantee Eastlink will result in consumer
price reductions in electricity as promised the state and federal governments.
The Fear of Privatisation
5.10 There is a strong
belief in the Eastlink community that the ultimate, of governments is, once
public utilities have been corporatised, to follow m privatisation, an action
which was opposed by many people. One submiss concluded:
This power line is not
needed, not wanted, a huge cost to taxpayers and consumers, and 1 suspect,
harbouring a hidden agenda to privatise the national grid to the detriment to
small consumers.
5.11
The Guyra Shire Council shares the concerns of its ratepayers that
privatisation could mean the loss of cross subsidisation of community service
obligations and that, in particular, the selling of power generating plants;
result in higher charges to rural and remote users. The Council stated
emphatically that because of the scattered nature of Australia's population
governments must continue to accept responsibility for supplying services rural
communities.
As a rural consumer of
electricity there is no assurance that competition policy or privatisation will
decrease or hold the price of power at its present level. We will not have the
same bargaining power as industry, so the opposite is likely to occur. That
has been the experience in other countries.
5.12 Extending from
this was the concern that once privatisation commenced, the way was open for
foreign companies to buy into Australian power authorities and control the
basic essential service of electricity supply; a scenario which was rejected in
some submissions.
The Need for Decentralisation
5.13
There
was the belief expressed in some submissions that the philosophy of increased
competition among public
utilities was wrong because it placed increasing emphasis on 'big' solutions to
economic problems and ignored environmental and social need. More specifically,
concern was expressed that competition reforms in the electricity
industry would increase Australia's reliance on large
power generation plants while what was really needed was diversification in
generation capacity with much greater emphasis on renewable and
environmentally sound systems.
5.14
The
fear was also expressed that once Eastlink was in place it would in itself
become a rationale for extending the
eastern power grid with more high voltage power lines. Its very presence would
limit options for future electricity supply in Queensland. Because it
is difficult to predict where demand would be, it would seem prudent instead to
develop regional supply options rather than relying transmitting electricity
over very long distances.
The Full Cost of Eastlink
5.15
Quite a number of submissions questioned whether the cost of Eastlink as stated
by the project's proponents took into account some of the wider, indirect costs
which they felt should be attributed to Eastlink. These included:
- fair
compensation for all people affected by property devaluation and loss of future
options for property use;
- the
cost of associated infrastructure needed to distribute the power at either end
of Eastlink;
- the
full cost of environmental impacts, in both agricultural and natural
environments;
- upheaval
in affected communities;
- the
cost of health problems associated with the project, whether direct or
indirect, short-term or long-term;
- the
cost of failing to implement or postponing the implementation of energy
efficiency programs which would ultimately save money for government, industry
and small consumers;
-
loss
of jobs that could otherwise have been created through developing, producing
and installing alternative technologies (such as solar); and
-
loss
of jobs related to the export of these technologies.
ABARE Analysis
5.16 Submission from
both TOTA in Armidale and Lockyer Valley Against Eastlink referred to an ABARE
publication which had concluded that there may be significantly greater
benefits from gas pipeline interconnection than from electricity, at a ratio
exceeding 3:1. They took this conclusion as evidence that Eastlink was
uneconomic.
5.17 The Commonwealth
Department of Primary Industries and Energy commented on this, saying:
It
is important, however, to note that the ABARE and IC studies not
designed to be able to account for the benefits flowing from
increased competition in the market as a result of grid interconnection and, to
that extent, may underestimate the benefits.
They are also broad studies with an energy system perspective rather than being
specifically designed to examine Eastlink.
5.18 TOTA further
argued that an analysis carried out by ABARE, published as Appendix E to the
Industry Commission publication, Australian Gas Industry and Markets Study, which
used the figure of 90mw transfer capacity for Eastlink in modelling exercises,
as further evidence that Eastlink was uneconomic.
5.19 When questioned
about the models used for this analysis, the Manager of the Energy Economics
Branch of ABARE, Mr Roger Stuart, stated.
ABARE conducted a broad
national level analysis of the total energy system benefits of electricity and
gas interconnections and of the extent of the substitutability between the two
types of interconnection under different scenarios. Neither this nor the
subsequent report purported to be the detailed feasibility study that would be
needed to justify investments in any particular interconnection. Indeed,
neither study reports results on individual interconnections, although
the interconnection of the Queensland and New South
Wales
systems is the major new link which the ABARE model constructs. In other words,
while the ABARE work can be used to illuminate the relative economics of
alternative options, it was not intended and should not be used as a definitive
guide to the economics of particular interconnections.
5.20 The Committee
accepts that the analysis carried out by ABARE examined the general economics
of interconnection through a high voltage power line, and was not sufficiently
detailed to draw conclusions about the specific case of Eastlink. The Committee
further accepts that the model demonstrated, in general terms, that electricity
interconnection through a high voltage power line would be economic.
Conclusions
5.21 The Senate Standing
Committee on Industry Science and Technology recommended in its report
on Gas and Electricity that any interconnection between NSW and Queensland should not
go ahead until it was proven to be economic. While
opponents of Eastlink have argued that this has still not been proven, the fact
that two state governments, with the support of the Federal Government, are
going ahead indicates that it is considered by them to be economic. Further,
the ABARE analysis has shown that, in general terms, an interconnection would
be economic. However, because a specific cost/benefit analysis for Eastlink
was not available, the Committee is unable to comment on the specific case of
this proposal.
5.22 The total cost of Eastlink
is stated by the power authorities to be in the region of $300 million.
However, information given by the two power authorities on cost does not
include a breakdown of what expenses have been included. Lack of detailed
information has contributed to public confusion and misunderstanding
about the relative costs and benefits of Eastlink and therefore to a lack of
understanding of the full economic impact.
5.23 The Committee believes that, in the
interests of good public relations, the power authorities involved should make
available to the public a more detailed cost/benefit analysis of Eastlink.
Navigation: Previous Page | Contents | Next Page