Chapter 3
Siting and Environmental Impact of the New Reactor
3.1 The arguments advanced by the Government and ANSTO in favour of building
the new reactor at the Lucas Heights site are essentially that:
- the present site meets all the siting and safety criteria for a research
reactor;
- the proposal makes use of existing physical infrastructure and experienced
personnel at Lucas Heights;
- existing distribution arrangements for radiopharmaceuticals will not
be disrupted; and
- building a new reactor at a greenfields site would involve a very
large additional cost. [1]
3.2 However, this site is opposed by a number of local residents and
community groups concerned with the environmental impact of continued
nuclear activity in their neighbourhood and perceived shortcomings in
the management of nuclear waste.
3.3 Representatives of both ANSTO and the Commonwealth Department of
Industry, Science and Resources (DISR) [2] advised the Committee that various sites across
Australia had been considered and evaluated against specific criteria.
Based on international guidelines, and endorsed by the 1993 RRR, the criteria
encompass:
- Accessibility: within one hour's road travel of a major international
airport; same day travel from major centres of research; proximity for
staff to residential and research centres;
- Health and safety: area of low seismic activity and stable
geology; low cyclonic activity and low flood potential; favourable airborne
dispersion characteristics and low potential for waterborne pathways;
not affected by other hazardous or incompatible land use; feasible emergency
response capability;
- Environmental protection: not in unique ecological or conservation
areas; without potential for significant adverse impact on the physical
or cultural environment;
- Availability of resources: adequate and reliable power and
water supplies; proximity to reliable service providers and contractors;
- Cost factors: cost of site-related construction, infrastructure
and land acquisition (including a suitable buffer zone); operating costs.
[3]
3.4 In accordance with these criteria, possible sites were identified
in the vicinity of Canberra, Sydney, Melbourne, Brisbane, Adelaide, Perth
and some regional centres. However, primarily on the grounds of cost and
confidence in the lack of health and safety risks associated with reactor
operations, the Government has chosen to maintain the Lucas Heights Science
and Technology Centre as the site of Australia's nuclear research activities.
Siting options
3.5 Originally in 1955, Lucas Heights was chosen as the site for establishment
of HIFAR, Australia's first and current research reactor. Situated in
the local government area of Sutherland Shire, approximately 30 kilometres
south-west of Sydney's central business district, the Lucas Heights Science
and Technology Centre is largely surrounded by the Heathcote National
Park, the Holsworthy Military Reserve, the Waste Management Centre, Lucas
Heights and bushland. Initially a 4.8 kilometre buffer zone encompassed
the centre, but based on overseas experience, the buffer was reduced to
1.6 kilometres [4].
3.6 In the 1950s, the combination of sparse regional population and development,
together with proximity to Sydney, were key factors in the choice of Lucas
Heights as the site for Australia's research reactor. Since that time,
however, significant population growth and urban expansion has transformed
the region into what this Senate inquiry's terms of reference describe
as`
a densely populated suburban area of Sydney'. Indeed, in 1993
the RRR described the Sutherland Shire as among the fastest growing local
government areas in New South Wales, with many more people moving in than
out. [5]
3.7 Population growth in the Sutherland Shire therefore raises two major
questions in respect of the siting of the new reactor at Lucas Heights.
First, given the ongoing debate concerning the possible health and safety
risks associated with a nuclear research reactor, it would seem expedient
and good public policy to distance such a facility from highly urbanised
areas. Many local residents would support the view of the Liverpool City
Council, which neighbours the Sutherland Shire, that:
it is completely unacceptable for a potentially dangerous facility
such as this to be built in the midst of a rapidly growing residential
suburb, within Sydney's most populous suburb. [6]
3.8 Given the population now in the Sutherland Shire, it is inconceivable
that Lucas Heights would be chosen now as a greenfields site for a new
reactor. One could anticipate huge community reaction similar to the proposed
(since abandoned) Holsworthy airport proposal.
3.9 On the other hand, population growth in the Sutherland Shire has
increased dramatically, despite the presence of HIFAR, indicating that
it is not a significant deterrent in the eyes of new Shire residents.
In support of this, the RRR noted that the Sutherland Shire Council has
a requirement that prospective land purchasers be informed of the reactor's
presence in the district, therefore ensuring an informed decision to live
in proximity to a nuclear facility. [7]
3.10 Taken together with the RRR's endorsement of HIFAR safety standards
and the siting criteria identified, this would suggest the validity of
Lucas Heights as a possible site for the new reactor. However, despite
indicating qualified support for a new reactor per se, it is important
to note the RRR did not commit itself to recommending Lucas Heights as
the appropriate site. Rather, the Review advises:
If a decision were to be made to construct a new reactor, it would
not necessarily best be placed at Lucas Heights. An appropriate site
would best be decided after exhaustive search, taking into account community
views. [8]
3.11 The Sutherland Shire Environment Centre argued that the decision
to site the new reactor at Lucas Heights is not in accordance with community
views. The Centre told the Committee that community views canvassed in
a 1996 public opinion poll, show that 83 per cent of Sutherland Shire
residents thought that a new reactor should be in a `remote location'.
[9]
3.12 It must be acknowledged that this survey was subject to markedly
different interpretations by different groups. ANSTO, for example, told
the Committee that when asked whether they would be supportive of a new
reactor being built at the existing Lucas Heights site, 57 per cent of
Sutherland Shire residents responded positively. [10]
3.13 The Committee considers that it would have been preferable if a
more detailed, extensive survey of community views had been conducted.
3.14 In light of the RRR's observation and concerns from within
the Sutherland Shire community, DISR undertook an investigation of various
alternative sites for the new reactor. The study has not been released
for public examination on the grounds that it is a cabinet-in-confidence
submission. Government officers did inform the Committee that suitable
sites had been identified in the vicinity of Canberra, Sydney, Melbourne,
Brisbane, Adelaide, Perth and some regional centres. However, specific
details of each location, together with the site selection criteria used
to evaluate these sites, have not been disclosed.
3.15 The Committee believes that such information should have been made
available to the Committee particularly having regard to the recommendations
of the Research Reactor Review.
3.16 While acknowledging that various suitable sites for the new reactor
do exist, the significant costs associated with developing a greenfields
site is the Government's key argument in favour of the Lucas Heights option.
Remaining at Lucas Heights avoids the expense of duplicating nuclear infrastructure
elsewhere. As highlighted in the joint ANSTO/DISR submission to the Committee,
the location also:
meets all siting and safety criteria, makes use of the existing
physical infrastructure and experienced personnel at Lucas Heights,
and will not disrupt the existing, very effective distribution arrangements
for radiopharmaceuticals. [11]
3.17 Furthermore, without revealing the detail of the Government's site
study, Dr Paul Wellings, Head of DISR's Science and Technology Division,
defended the study's methodology and conclusions in the following terms:
The methodology was evaluated by the Department of Finance as a robust
method for arriving at the costing procedures that would have been incurred
had we moved the reactor to a greenfield location. At the end of the
day those criteria, which include health and safety issues, showed that
the minimum additional cost of moving to a greenfield site would have
more than doubled the cost of the project. There was also the issue
that this would have had us maintaining two nuclear sites in Australia.
Lucas Heights
would still have been used to handle material from
the cyclotron and would have been an active site because it would have
been going through a cooling down phase with a view to decommissioning
in 30 years time. [12]
3.18 Although opposed to a new reactor on the grounds of science and
technology funding priorities, Professor Barry Allen, a nuclear scientist
of 35 years experience, clearly endorsed Lucas Heights as the appropriate
site due to its pre-existing infrastructure.
If you are going to have a new reactor, it should be where all the
support facilities are and where all the staff are located basically,
and I think Lucas Heights is that place. If you are going to move it,
then you have to put a dollar price on controversy. How many tens of
millions of dollars extra is controversy worth?
.I have no doubt
the reactor sited at Lucas Heights would be eminently safe and managed
in the way that Lucas Heights has managed things in the past, at a very
high level of expertise. [13]
3.19 While acknowledging the strong financial arguments in favour of
Lucas Heights over a greenfield site, the Committee appreciates community
concerns regarding the non-disclosure of the site selection study. Health,
safety and nuclear waste issues are of vital concern to local residents.
These concerns are only exacerbated when information appears to be withheld.
Both the Sutherland Shire Council and the Sutherland Shire Environment
Centre questioned the adequacy of the criteria used in site evaluations,
and in particular:
whether [the locational study] took into account issues related
to nuclear waste generation and disposal, and took account of important
local information with respect to the Lucas Heights area and any other
areas in Australia relevant to the reactor siting issues. [14]
3.20 Although, in announcing Lucas Heights as the site for the new reactor,
the Government instigated an environmental impact assessment of the proposal,
this has failed to allay the concerns of many local residents. In the
first instance, opponents of the proposal saw flaws in the alternative
sites study from which Lucas Heights was selected, and thereafter with
the design and execution of the environmental impact study of this siting
option. Further, the internal departmental consideration of alternative
sites appears to have been a modelling exercise against generic criteria
rather than a detailed consideration of specific sites. The Committee
notes with concern that this internal study was conducted prior to the
preparation of the draft environmental impact study (EIS) and was not
reviewed in the EIS:
ANSTO has advised the Senate Economics References Committee that a
process involving consideration of alternative sites, subsequent to
the Research Reactor Review, was conducted by officers within
the [then] Department of Industry, Science and Tourism, with input from
ANSTO. The site selection criteria indicated that greenfield sites,
which fulfil accessibility, health and safety, environmental protection
and availability of resources criteria, are available with proximity
to Canberra, Sydney, Melbourne, Brisbane, Adelaide, Perth and some regional
centres. In addition, the costing methods comparing locating a replacement
reactor at Lucas Heights and alternative sites were reviewed by the
[then] Commonwealth Department of Finance. This process was conducted
prior to the preparation of this Draft EIS and has not been reviewed
as part of the scope of this Draft EIS. [15]
Consideration of alternative sites to the Lucas Heights Science and
Technology Centre was undertaken for several locations but without reference
to a specific site. [16]
3.21 These factors can only lead to the conclusion that alternative sites
have not been properly considered as recommended by the 1993 RRR. Certainly
there has not been an `exhaustive search' for alternative sites and the
only site subject to the EIS is Lucas Heights.
3.22 If Australia is to have a new reactor then alternative sites to
Lucas Heights must be properly considered. Such analysis should include
the potential economic benefits of locating the reactor in a less populated
regional area.
Environmental Impact Assessment process
3.23 Following the Government's announcement that a new reactor would
be built at Lucas Heights, the Minister for the Environment directed ANSTO
to prepare an environmental impact statement (EIS) pursuant to the Environment
Protection (Impact of Proposals) Act 1974 (EPIP Act). The Committee
notes that the aim of the environmental assessment process is to ensure
that all environmental matters are examined with respect to a given project
and that community groups with particular interests have the opportunity
to raise relevant issues. The EIS is not designed to make a final decision
on the merits of a proposal. Rather, it is intended to canvass and evaluate
all likely impacts of the proposal. In accordance with these parameters,
the Committee sees the authority of the EIS as hinging on three main issues:
- the breadth of its guidelines;
- the extent of its community consultation; and
- the independence of its analysis.
Preliminary stages
3.24 The environmental assessment process involved a number of stages,
which took over a year to finalise. Key developments during this phase
included the appointment of ANSTO as the `proponent' for the new reactor
proposal. A Commonwealth agency, Environment Australia, was responsible
for preparing the EIS guidelines. These were prepared following a month-long
public review of a set of draft guidelines. ANSTO appointed a company
called PPK Environment & Infrastructure Pty Ltd to prepare a draft
EIS report. PPK in turn contracted the services of another environmental
assessment and control company, NNC Ltd which has expertise in the nuclear
industry.
3.25 Despite having appointed an independent agency to conduct the EIS,
ANSTO remained the main proponent of the EIS process and continued to
provide technical input, specifically regarding the description of the
new reactor proposal, the need for the proposal and the alternatives that
have been considered.
3.26 The EIS study team comprised a steering committee and task leaders
drawn from ANSTO officers, together with PPK Environment & Infrastructure
staff and several specialist subconsultants. At least 42 highly qualified
professionals formed the PPK EIS team, representing a range of physical
and social sciences including: environmental planning; transport engineering
and economics; geotechnical and civil engineering; nuclear safety; health
physics, archaeology and community consultation.
3.27 The EIS guidelines developed by Environment Australia demanded a
very detailed study of the likely physical, biological and social impacts
of a new reactor located at the Lucas Heights Science and Technology Centre.
Reflecting these requirements, the EIS describes in great detail:
- the new reactor proposal itself, together with the perceived need
for it;
- alternative reactor types and technologies;
- the existing environment including community and socio-economic issues
and future trends over the anticipated operating life of the facility;
- environmental impacts from construction, emissions, transport and
storage of fuel elements;
- hazards and risks;
- decommissioning of both the existing and new reactor;
- the regulatory regime surrounding Australian research reactor operations;
and
- proposed environmental safeguards and monitoring programs. [17]
3.28 The key findings of the EIS in each of these areas are discussed
below, together with relevant evidence received by the Committee. Before
proceeding to this, however, two further aspects of the EIS process warrant
consideration: the extent of community consultation; and perceived independence
of the study.
The extent of community consultation in the EIS process
3.29 A preliminary stage in the EIS process involved the preparation
of guidelines to direct the study. While the EPIP Act does not require
consultation prior to the preparation of a draft EIS, in the case of the
new reactor ANSTO sought public review of the guidelines in an attempt
to encourage maximum community involvement throughout the EIS process.
The draft guidelines were released for comment between 8 November and
6 December 1997, and attracted 118 submissions. [18]Once revised, the guidelines were provided to
ANSTO as the proponent of the EIS and to all parties who had commented
on the draft version. The guidelines also were published on the internet
for the information of any other interested parties.
3.30 Community consultation was emphasised throughout the EIS evidence
gathering process, with the aim of recognising key stakeholders and understanding
their interests in the project. Some of the key consultation activities
undertaken included:
- distributing newsletters outlining the new reactor proposal, EIS process
and issues raised during the process to households in the Sutherland
Local Government Area;
- establishing an EIS website and telephone information line;
- participating in meetings with Sutherland Shire Council and a range
of community interest groups; and
- organising mobile staffed displays at local shopping centres. [19]
3.31 A similar range of community consultation activities continued following
release of the draft EIS for public comment. The release itself was widely
advertised in national, and where applicable, metropolitan and local press.
Interested individuals or groups were invited to comment on the draft
EIS, after which ANSTO prepared a supplement to the draft, responding
to all issues raised. To assist with any inquiries during the public exhibition
phase of the draft EIS, PPK undertook for selected exhibition locations
to be staffed by members of the EIS study team for most Saturdays during
the exhibition period. [20]
3.32 Notwithstanding the various consultative efforts outlined above,
the Committee notes a degree of dissatisfaction expressed by some opponents
of the new reactor proposal. In particular, the community group People
Against a Nuclear Reactor claimed that consultation throughout the
EIS process was inadequate and that citizens were treated with contempt.
People Against a Nuclear Reactor stated their case against PPK
in particularly strong terms:
(PPK) have made it abundantly clear that they will prepare their
statement without any consideration of the cumulative wisdom or wishes
of local residents, or the technical expertise of the Australian non-nuclear
scientific community. The company has also refused our repeated requests
to conduct a public meeting on the proposal. So intense has been the
uproar about PPK's lack of any attempt to engage in meaningful consultation
with residents, that another company, Twyford Consultants [sic], has
been engaged to evaluate the public participation component of the EIA
process. [21]
3.33 While appreciating community groups' concerns about the 1new reactor
proposal, the Committee notes that, in addition to the broad consultative
mechanisms already discussed, PPK specifically identified People Against
a Nuclear Reactor as a key local stakeholder group, and met with them
on at least one occasion to discuss the new reactor proposal [22].
In response to People Against a Nuclear Reactor's complaint that
PPK failed to conduct a public meeting on the proposal, PPK argued that
participation in such a forum would be contrary to its role. PPK explained
its position in the following terms:
PPK's role is to assess the environmental impacts of the (replacement
reactor) proposal and not to advocate the proposal (therefore) participating
in such a public debate would not be appropriate. PPK declined the (public
meeting) invitation and, as an alternative, proposed that representatives
of these community groups distribute their information materials expressing
their point of view at Information Days and Mobile Displays organised
by PPK throughout the EIS consultation process. [23]
3.34 In relation to Twyford Consulting's appointment to conduct an evaluation
of the community consultation process, the Committee notes that PPK undertook
this measure in response to concerns raised by Sutherland Shire Council.
Specifically, Twyford Consulting were engaged to:
Evaluate the effectiveness and appropriateness of the community consultation
strategy, including the objectives, processes and outcomes (both outcomes
during and at the conclusion of the process); and
Evaluate the implementation of the strategy, specifically how the process
was handled; how responsive it was to the needs of the community; and
what outcomes were actually achieved. [24]
3.35 Twyford Consulting evaluated PPK's consultation strategy in respect
of the preliminary stage of the EIS, that is prior to release of the draft
statement, and recommended certain measures to assist with community involvement
in the public exhibition phase of the EIS. Twyford Consulting's general
conclusion regarding consultation in the preliminary stage of the EIS
process was that it was undertaken to an `acceptable' level, however with
some shortcomings. In the area of managing potential conflict, the consultants
found that PPK's early attempts at dialogue with the group People Against
a Nuclear Reactor were adequate, but subsequently deteriorated through
a lack of flexibility and transparency, hampering ongoing, meaningful
dialogue and producing suspicion on both sides. According to Twford Consulting:
Effective dialogue and open responses to questions and requests in
Stage 2 (the public exhibition phase of the EIS process) will be critical
in managing community expectations, minimising conflict and meeting
the (managing potential conflict) standard. [25]
3.36 Transparency was an additional aspect of the preliminary consultation
process in which Twyford Consulting identified problems. According to
Twyford Consulting, transparency refers to the stakeholders' understanding
of the EIS process, in particular the consultation and decision making
occurring within it. Twyford Consulting found that generally this standard
had not been met, with many of their sample interviewees failing to understand
the consultation and EIS process. True community consultation therefore
was not achieved. Instead, a lack of trust tarnished the process, resulting
in the perception that the EIS was being undertaken to support
a pre-determined decision, rather than the decision to proceed with a
new reactor being based on the outcome of the EIS process. [26]
3.37 In the Supplement to the Draft EIS, PPK noted that Twyford Consulting
made recommendations about the consultation process and that `as a result
of the recommendations
additional community consultation activities
were conducted during the exhibition period'. [27] These activities included an information letter
mailed to several hundred local businesses, a radio debate and public
discussion groups. [28]
3.38 However, Cr Genevive Rankin of the Sutherland Shire Council told
the Committee that:
The radio debate was held
on what must be one of the lowest
rating radio stations in the country. It is our local radio station.
It was an extremely controlled environment to make sure the minimum
number of people heard. If we has had a debate on the ABC or on broad
radio that people listened to, then you might be able to say this was
public consultation. [29]
3.39 While Cr Rankin noted that the detail of the public consultation
process outlined in the Draft EIS `sounds very impressive when you write
that down' [30] she stated that in relation
to public meetings in the community:
an ad was taken out in the paper - it was buried and it did
not mention where or when the meeting would take place. In order to
get to that meeting you had to ring Environment Australia and PPK and
satisfy their criteria. They had the meeting in a tiny little room in
the library
which holds 12 people. [31]
3.40 The Supplement to the Draft EIS acknowledged that a number of submissions
expressed concerns about the process and consultation process. ANSTO,
on the other hand, claimed that `the assessment process has been in compliance
with the Environment Protection (Impact of Proposals) Act 1974
and associated Administrative Procedures'. [32]
However, Cr Rankin told the Committee that:
Even if by some technical stretch of the imagination we can say that
the legislation written in 1974 has been complied with, it is world's
worst practice in terms of community consultation, I can assure you.
[33]
3.41 The Committee believes that while PPK and ANSTO may have undertaken
an adequate process of consultation (within the limited requirements of
the EPIP Act), this should have been more extensive and intensive given
the significance of the issue. The Committee feels that public meetings
conducted along similar lines to those relating to the Holsworthy Airport
proposal should have occurred on the new reactor proposal. Such meetings,
well advertised and providing for broader community involvement, would
have assisted in overcoming the strongly held perception that ANSTO controlled
the process to its own best advantage.
Concerns regarding the adequacy and independence of the EIS process
3.42 Having been drafted 24 years ago, the legislation underpinning the
EIS process was criticised by some inquiry participants as being
out of date and inadequate. That the Government's Environment Protection
and Biodiversity Conservation Bill 1998 (now passed) was designed to supersede
the EPIP Act, to a large extent acknowledges weaknesses within the legislation.
3.43 Despite deficiencies in the standards demanded by the EPIP Act,
the Committee notes that specific measures were adopted during the new
reactor EIS process to address criticisms about the quality and independence
of the evaluation. In terms of framing the EIS guidelines, the level of
consultation throughout the study and the subsequent peer review of the
draft EIS, Environment Australia exceeded the minimum requirements of
the EPIP Act.
3.44 A number of inquiry participants, including the Sutherland Shire
Council, criticised the EPIP Act as being inconsistent with the principles
of ecologically sustainable development, as defined in the Inter-Governmental
Agreement on the Environment of 1992. [34]
While this was an issue requiring attention in the overhaul of Commonwealth
environmental legislation, the Committee notes that it has not meant that
the question of ecologically sustainable development has been ignored
in the new reactor EIS. On the contrary, the following principles of ecologically
sustainable development as set out in the NSW Environment Planning
and Assessment Regulation 1994 are considered throughout the EIS study:
- the precautionary principle. If there are threats of serious or irreversible
environmental damage, lack of full scientific certainty should not be
used as a reason for postponing measures to prevent environmental degradation;
- inter-generational equity. The present generation should ensure that
the health, diversity and productivity of the environment is maintained
or enhanced for the benefit of future generations;
- conservation of biological diversity and ecological integrity; and
- improved valuation and pricing of environmental resources. [35]
3.45 PPK acknowleded that the parameters for measuring ecological sustainability
remain widely debated, but defended the above tests, concluding that:
Achieving a sustainable development will necessarily involve negotiating
a balance between each of the principles in order for the decision maker,
in this case the Commonwealth Government, to arrive at a decision on
whether or not to proceed with the proposal. [36]
3.46 The scope for a possible conflict of interest was a further weakness
of the EPIP Act noted by a number of inquiry participants. In particular,
the fact that the legislation allowed the initiators of a project (ie,
ANSTO) to act also as the proponent of the environmental impact study
was widely condemned. Among others, the Sutherland Shire Environmental
Centre was particularly critical of ANSTO's appointment as proponent of
the new reactor EIS, on the grounds that it would impede impartial analysis:
The fact that the proponent is also the chief adviser to the government
on nuclear matters as well as being responsible for its own EIS on its
existing site is beyond reason. [37]
3.47 Similarly, the Sutherland Shire Environment Centre saw a conflict
of interest in the Minister for the Environment and Heritage being responsible
for making recommendations on the findings of the EIS:
the person responsible for the final acceptance or rejection
of the EIS is the Minister for the Environment, Senator Robert Hill.
He is a member of the same Cabinet which made the decision, in advance,
that a new reactor will be built at Lucas Heights. All this gives the
locals little confidence that there will be anything but a positive
outcome for ANSTO and a negative for the community. [38]
3.48 The extent of concern regarding both the adequacy and independence
of the EIS process prompted the Sutherland Shire Council and other community
representatives to call for an environmental auditor to oversee the EIS
process. Whilst the Minister for the Environment instigated three peer
reviews of the EIS process, this approach of using an environmental auditor
was adopted in respect of the Holsworthy and Badgery's Creek airport proposals
and serves as a good model for ensuring appropriate scrutiny of the EIS
process. The findings of the EIS peer reviews are considered at paragraphs
3.99 - 3.108 following discussion of the major environmental impacts of
the new reactor identified in both the EIS and evidence to the Committee.
3.49 There was some concern expressed that the EIS process had gone forward
in the absence of both design features for the new reactor and a waste
plan. [39] The Committee was told that Daniel
Hirsch, a US consultant for Sutherland Shire Council on the EIS, noted
in a submission to the Council that:
In the United States, environmental review and safety assessment practice
requires that the reactor must have a design before the EIS is prepared.
[40]
3.50 However, Mr Watt, an engineer at ANSTO, confirmed that:
There are no detailed plans. ANSTO is not designing the reactor; ANSTO
is simply specifying performance criteria and a number of general parameters
within which the reactor must operate. It is up to the suppliers, the
prospective vendors, to come up with designs which meet those requirements.
[41]
3.51 The Supplement to the Draft EIS responded to concerns about lack
of reactor design, stating:
The Draft EIS uses what is known as a set of `bounding conditions'
rather than a detailed design in analysing the environmental impacts
of the replacement reactor. These bounding conditions represent parameters
within which all acceptable designs must lie. This approach allows the
designer, when selected through a competitive tender process that can
only proceed following a favourable outcome from the EIS process, to
utilise the best possible design and technology whilst still ensuring
that all environmental constraints are met.
the proponent must still obtain regulatory approval to construct,
to commission and to commence routine operation. [42]
3.52 In the Committee's view, the independence of the EIS process was
satisfied within the limitations of the EPIP Act. That said, the process
would have been strengthened if an independent environmental auditor had
been appointed in an oversight role similar to the approach adopted for
the Holsworthy and Badgerys Creek airport proposals. This would have given
far greater assurance to the public, and in particular the local community,
that the EIS process was not only independent but also transparent and
accountable.
Health and environmental impacts of the new reactor
3.53 The new reactor will impact on its physical and social environment,
both in the construction phase and operationally over the longer-term.
The extent of its impact will vary across a range of issues. According
to the draft EIS, even in the most extreme cases, these impacts can be
mitigated through specific environmental management initiatives. This
view is shared by the Australian Radiation Laboratory, the agency currently
responsible for independent verification of radioactive discharges measured
by ANSTO:
we have no doubt that with a proper waste management policy
and environmental controls in place, a new reactor can be operated at
the site without causing any significant environmental harm or undue
risk
[43]
3.54 In the sections that follow, the Committee examines the evidence
relating to the possible impact of HIFAR and a new reactor on community
health and the environment. The Committee also addresses the potential
accidents and risks that HIFAR and a new reactor pose and the measures
in place to address these issues.
Possible health impacts
3.55 The Committee heard widely conflicting evidence concerning the possible
health impacts of radiation doses to the public arising from HIFAR's routine
liquid and airborne discharges. The health implications of HIFAR and the
proposed new reactor represent a major concern for many Sutherland Shire
residents. This concern has been exacerbated by the uncertainty surrounding
the actual magnitude of reactor emissions and nature of health risks they
pose. As a local resident, Ms Maria Psaltis noted:
How do the emissions affect our air, plant and animal life, waterways,
our backyard vegetables and humankind in general? [44]
3.56 In an effort to allay such concerns, reactor proponents pointed
to the extent of radioactivity occurring naturally in our food and environment.
As well, a number of inquiry participants cited studies that have that
found reactor operations do not pose a health risk to Sutherland Shire
residents.
3.57 The National Health and Medical Research Council (NH&MRC) recommends
a general radiation dose limit for the public of one millisievert [45]
annually. According to the Nuclear Safety Bureau (NSB), this represents
approximately half the average background radiation received by Australians.
In respect of HIFAR emissions, ANSTO advised that the maximum possible
annual dose of radiation is less than 0.01 millisieverts, which is equivalent
to the dose received by an airline passenger on a return flight from Sydney
to Melbourne. [46]
3.58 The NSB endorsed the safety of emission levels from HIFAR, confirming
that dose limits are well below the recommended level of the NH&MRC.
Together with the Australian Radiation Laboratory, the NSB is responsible
for independent monitoring of both airborne and liquid radioactive discharges
from the Lucas Heights Science and Technology Centre. The NSB advised
that, in respect of HIFAR, the most significant radioactive airborne discharge
is argon-41, a short-lived radioactive gas produced by the neutron activation
of air inside the reactor irradiation facilities. [47]These
emissions still fall within recommended levels, as observed by the NSB:
Although the assessed maximum doses to the most highly exposed member
of the public approach ANSTO's ALARA [48] objective of 20 Sv per year, below which
it is not necessary to demonstrate that the doses are as low as reasonably
achievable, work is continuing at HIFAR to identify the sources of and
to reduce the amount of airborne discharges from the reactor. [49]
3.59 Furthermore, the NSB argued that the likely radiation doses arising
from the new reactor would be even smaller than is currently the case.
Different processes employed by the new reactor would minimise discharges,
specifically of argon-41 and liquid discharges of tritium.
As the replacement reactor would not incorporate air-cooled irradiation
facilities, and will use light water cooling, very little, if any, of
these discharges would be released. The major discharges from a pool
reactor would be very short-lived nitrogen-16 gas, and trace amounts
of solid contamination in the pool water. It is expected that the radiation
impact of these discharges would be less than the current discharges
from HIFAR. [50]
3.60 Despite the assurances of ANSTO and the NSB, key inquiry witnesses
indicated dissatisfaction with discharge levels from the ANSTO site. The
Sutherland Shire Council submitted that the United States Environmental
Protection Agency currently sets an effective dose limit for public exposure
to radioactivity three times more stringent than ANSTO. [51]The
Council also cited recent research indicating that the health impacts
of airborne and other radioactivity may be worse than previously estimated
by the international nuclear fraternity. [52]
3.61 Echoing such concerns, paediatrician Dr Helen Caldicott gave a graphic
account of the possible impact of ionising radiation on living tissue.
Describing in turn the destructive effects of strontium on bones, plutonium
on testes, and iodine on children's thyroids, Dr Caldicott warned of the
longer term consequences of radioactive emissions:
... as we accumulate nuclear waste into the environment, so the incidence
of these diseases will increase over time, but we will not live to see
it. It takes 20 generations for recessive genes to express themselves
.So
what we are doing is playing around with evolution. By producing radioactive
waste we are producing random, compulsory genetic engineering for the
rest of time. [53]
3.62 ANSTO and DISR claimed that Dr Caldicott provided a misleading account
of radiation biology, omitting information essential for an understanding
of the comparative risk arising from reactor emissions. In particular,
they claimed that Dr Caldicott failed to acknowledge the background radiation
to which we are all exposed, and the fact that this far exceeds even the
worst hypothetical levels of exposure arising from HIFAR emissions. ANSTO
and DISR representatives argued:
A given dose of radiation from a naturally occurring source has the
same biological effect as the same dose from a man-made source. The
risk from ionising radiation depends on both the intensity of the source
and the length and nature of exposure. It should be noted that international
and Australian standards have been developed as providing acceptable
limits on the risk arising from exposure to ionising radiation. Provided
these standards are adhered to, the risks associated with the use of
radioactive materials are very low. [54]
3.63 Furthermore, ANSTO and DISR claimed that no detrimental health effect
arising from background radiation has been demonstrated. This is the case
even when the natural radiation reaches levels of 5-10 millisieverts annually,
as occurs in parts of Europe such as Sweden, Switzerland, Austria, Spain
and Finland. [55]
3.64 The Committee also notes the findings of both the 1993 RRR and PPK
environmental impact statement regarding the new reactor proposal. These
findings corroborate ANSTO and DISR's position on the safety of HIFAR
emissions. After consideration of various internationally respected consultants'
reports, the RRR concluded that the health of residents in the Sutherland
Shire is not affected by HIFAR emissions; indeed, it is normal when compared
with another equivalent shire and New South Wales overall. [56]
Possible impact on the natural environment
Geology, soils and water
3.65 Although geology, soils and water within the Lucas Heights Science
and Technology Centre will be disturbed during the construction phase
of the project, specific management measures proposed by the draft EIS
appear adequate to mitigate any longer term environmental damage. The
draft EIS noted that an erosion and sedimentation control plan would be
prepared prior to commencement of the reactor's construction. [57]
Thereafter, once the reactor had commenced operation, key environmental
management strategies would encompass close monitoring of stormwater flows,
including construction of barriers for any emergency containment of contaminated
liquids. The draft EIS summarised the major potential water-related impacts
of the new reactor as encompassing:
- short term impacts on local drainage lines arising from potential
sediment release during construction, particularly for Melinga Molong
Gully on the southern side of the proposed new reactor site;
- potential short term reductions in water quality in local streams
following rain from increased stormwater discharge;
- long-term minor impact of increased hard surface area, which may increase
runoff velocities and consequently erosion and sedimentation of local
streams; and
- minor impacts on groundwater flow and groundwater quality. [58]
Air quality
3.66 With the major exception of atmospheric release of radionuclides
which is discussed in chapter 4, the draft EIS indicated that the likely
impact of the new reactor on air quality is minimal. Air pollution generated
during the construction phase of the new reactor was predicted to be on
a par with that of any similar sized building project, and unlikely to
contribute to a sustained or significant deterioration in local air quality.
As a possible management strategy, however, the draft EIS noted that air
quality safeguards could include controlling the amount and effect of
dust generated from earthworks and emissions from construction plant and
equipment. [59]
3.67 In respect of greenhouse gases, the draft EIS found that although
heat is a by-product of the fission process and is discharged to the atmosphere
via a series of heat exchangers, the impact on air humidity would be localised
and have a negligible greenhouse effect. No greenhouse gases such as carbon
dioxide would be released through the operation of the new reactor. [60]
Flora and fauna
3.68 After a detailed study of the flora and fauna present within the
Lucas Heights Science and Technology Centre, the EIS judged the likely
impact of the new reactor on flora and fauna to be minimal.:
Taking into consideration the low conservation significance of the
site of the proposed replacement reactor, the low scale of impacts likely
to result from construction activities and the abundance of bushland
adjoining the site, the overall impact of the proposal on flora and
fauna is considered to be low. [61]
3.69 The most significant impacts will be the loss of approximately 1.5
hectares of Red Bloodwood/Scribbly Gum Woodland vegetation and approximately
one hectare of open heath vegetation, triggering an associated loss of
habitat for native fauna. As with other areas of environmental impact,
however, a range of environmental management measures can be used to mitigate
the impact on local flora and fauna, both within the construction phase
and operation of the new reactor. The draft EIS claimed that with careful
management of the buffer zone for the protection and long-term maintenance
of biodiversity and natural ecosystem processes, the research reactor's
presence would assist long-term conservation of the flora and fauna within
the buffer zone. [62]
Accident potential and risk management
Safety regulation and management
3.70 Various safety aspects of ANSTO's operations have been overseen
by three bodies:
- the Nuclear Safety Bureau (NSB);
- the Safety Review Committee; and
- the Australian Radiation Laboratory (ARL).
3.71 Both the NSB and the Safety Review Committee were established by
the Australian Nuclear Science and Technology Organisation Act 1987.
The NSB was until recently responsible for monitoring and reviewing the
safety of ANSTO's nuclear plant, and for setting limits on radioactive
materials discharged from HIFAR. Radioactive discharges measured by ANSTO
were independently verified by the ARL. The Safety Review Committee had
a more general, overarching charter to review and assess the effectiveness
of standards and procedures adopted by ANSTO, to ensure the safety of
its operations.
3.72 Despite the existence of these three regulatory bodies, the 1996
Senate Select Committee on the Dangers of Radioactive Waste identified
a gap in the regulation of Commonwealth radiation sources and practices
outside of HIFAR and associated plant. The Australian Radiation Protection
and Nuclear Safety Act 1998 [63] addresses
this problem through the creation of a new regulatory body, the Australian
Radiation Protection and Nuclear Safety Agency (ARPANSA). Under the Act,
which came into effect on 5 February 1999, ARPANSA combines the resources
of the ARL and the NSB. The Act also introduces regulatory controls in
respect of all Commonwealth radiation and nuclear activities by prohibiting
Commonwealth agencies from dealing with radioactive materials or apparatus,
or any aspect of a nuclear facility, unless licensed to do so by the Chief
Executive Officer of ARPANSA. [64]
3.73 ARPANSA has taken over from the NSB as ANSTO's key safety regulator
overseeing all aspects of nuclear activity, including the design, construction,
commissioning, operation and decommissioning of nuclear facilities. The
NSB (now ARPANSA) conducted its safety compliance monitoring through a
variety of channels ranging from formal submissions provided by ANSTO,
to safety assessments, audits and inspections conducted by NSB experts.
NSB advised that, on average, it conducted some form of inspection at
ANSTO each week, and that its procedures complied with recommendations
of the International Atomic Energy Agency for independent regulation and
are comparable to regulatory processes in other OECD countries. [65]
Furthermore, to ensure the transparency of NSB processes, its findings
were reported to the Minister for Family and Community Services [66] on a quarterly and annual basis; all such reports
were tabled in both houses of the Federal Parliament. [67]
3.74 The NSB required that radiation doses arising from reactor operations
wereless than the limits set by the Australian National Health and Medical
Research Council and conformed to the principle of As Low As Reasonably
Achievable. However, both the accuracy of radioactivity monitoring
and extent of information disclosed for public scrutiny were questioned
by opponents of the new reactor.
3.75 In the view of a number of opponents of the new reactor proposal,
public information concerning ANSTO operations is seriously deficient.
For example, Mrs Suzanne Ireland, a long term resident of the Sutherland
Shire, recounted for the Committee her difficulties in obtaining information
about operational incidents:
I have lived at Engadine, Heathcote and Woronora Heights in the surrounding
areas over the last 20 years. Perhaps all of us out there are naive.
We did not realise that anything got past the site. We never knew that
in 1992 the EPA made a raid on ANSTO and found leaking waste. We never
knew that two kilograms of hexafluorene went up the stack accidentally
in 1984 and there was an internal inquiry which decided that there was
insignificant damage done to the population. [68]
3.76 Dr Helen Caldicott made comments in a similar vein about the availability
of public information concerning ANSTO operations:
The deficit of data is quite amazing about the releases in terms of
the number of curies released by the reactor, and of radioactive iodine,
noble gases, caesium 137, frontium 90, alphamitters and tritium. For
someone to assess what is going on at this reactor, one needs the data,
and it is surprisingly deficient. [69]
3.77 ANSTO vigorously disputed this claim, pointing to a range of public
documents produced regularly by ANSTO and independent assessors such as
the NSB and Safety Review Committee. ANSTO noted that it had always published
the full results of extensive environmental monitoring in an annual Environmental
Survey Report. As well, its submission to the 1993 RRR was a public
document that contained an extensive account of the historical waste produced
at Lucas Heights, including all the emissions and environmental monitoring
data for much of the history of the site's operations. [70]
Emergency Planning Procedures
3.78 In addition to the monitoring of radioactive emissions, a vital
element of safety management at the Lucas Heights Science and Technology
Centre is the emergency planning procedure. The NSB has been the independent
assessor of ANSTO's emergency planning arrangements. Together with other
Commonwealth and State agencies, the NSB periodically observed practice
exercises to assess the viability of these arrangements. Over the past
three years, the findings from these exercises have been incorporated
in a complete redraft and updating of ANSTO's emergency arrangements for
the Centre. [71] Standing Operating Procedures
detailing the response of each of ANSTO's operational units also have
been developed. The NSB indicated that ANSTO's emergency arrangements
are `suitable and resources are in a satisfactory state of preparedness'.
[72]
3.79 A different conclusion was reached by some local residents and other
critics, however, who warned of inadequacies in ANSTO's emergency planning
arrangements. Ms Maria Psaltis, a long-term resident of Barden Ridge (formerly
known as Lucas Heights) which neighbours the Lucas Heights Science and
Technology Centre argued that ANSTO has never properly prepared the community
for an incident. [73] Furthermore, Dr Helen Caldicott claimed that,
in the event of major catastrophe, HIFAR could meltdown in eight minutes,
leaving little time for proper evacuation and emergency strategies to
be implemented. In discussing ANSTO's official Emergency Planning Arrangements
document , Dr Caldicott argued:
All (the document) contained was who was responsible: this one, this
one, and that one. But there was nothing in it about what people should
do with their children, how they get out their potassium iodine tablets,
or how Sydney would evacuate and where to. [74]
3.80 ANSTO, with the support of independent analysis, disputed the possibility
of a meltdown at the Lucas Heights Science and Technology Centre, let
alone one that could occur within eight minutes. ANSTO's position was
supported by representatives of the Australian Manufacturing Workers Union
employed at the Lucas Heights Science and Technology Centre. Mr John Edwards
observed:
.in general terms, the training of staff and the expectation
of what to do if such an emergency should arise is, I believe, perfectly
adequate. Where exercises have been carried out and in many cases,
these have been combined exercises involving the Sutherland Shire and
the local emergency services they have been done in the form
of tabletop exercises, with independent review and auditors and referees.
There have also been more realistic exercises carried out. While it
is not my area of work, it is my understanding that and it is
not as though they have been without problems; no exercise ever would
be no significant problem has been identified. [75]
3.81 The Committee does not consider that Dr Caldicott's doomsday scenarios
are realistic. However, the Committee believes that ANSTO should do more
to advise and educate the community about its emergency management procedures.
Accident and emergency risks
3.82 The risk of a nuclear related accident occurring at the Lucas Heights
Science and Technology Centre is of great concern to many local residents.
Together with the issue of pollution, it represents one of the major reasons
for opposition to the proposed new reactor. However, evidence to the Committee
indicated that both the risk and potential impact of accidents or other
emergencies occurring at the site are significantly less than generally
feared. Indeed, in keeping with the assessment of the NSB, the PPK environmental
impact assessment of the new reactor proposal found that:
... the hazards and risks of the proposed replacement reactor are within
nationally and internationally accepted standards and criteria and are
As Low As Reasonably Achievable. [76]
3.83 Although the proposed new reactor will have a higher neutron flux
than HIFAR, and will be submerged in a deep pool of water rather than
a closed tank, PPK claimed that this will not have a detrimental effect
on safety. The NSB endorsed the PPK view that use of a pool will in fact
enhance safety by providing a shield around the reactor and spent fuel,
acting as a cooling agent and offering the potential to retain the majority
of any fission products released in the event of an accident. [77]
3.84 PPK's conclusion regarding the safety of the proposed new reactor
reinforced the findings of the 1993 RRR. Despite the natural concerns
surrounding nuclear activity, the RRR found that the weight of evidence
to its inquiry supported the view that HIFAR operates safely by an adequate
margin and well within international safety standards. The RRR went so
far as to claim:
The risks to people living in the Sutherland Shire are very much less
than the risks of traffic accidents, lightning strikes, bushfires, and
several other forms of natural hazards. [78]
3.85 Nonetheless, many local residents and nuclear opponents remained
unconvinced. The Sutherland Shire Council cited expert evidence disputing
the safety standards of ANSTO operations. In 1995 the Council commissioned
an independent study by MHB Technical Associates, California, to analyse
the possible impact upon the district of a severe research reactor accident.
An alarming finding of the study was that accident likelihood and source
team studies prepared for HIFAR were:
... technically inadequate and/or badly dated and no longer in keeping
with the state of art in risk assessment. [79]
3.86 In response, ANSTO argued that the MHB report was confused about
nuclear operations at Lucas Heights. According to ANSTO, the MHB report
not only misunderstood the Australian standard and system for radiation
protection of the public but also applied the wrong US standard in assessing
the operation of HIFAR. ANSTO stated that the radioactive emissions from
HIFAR satisfy the standards of the US Environment Protection Authority.
[80]
3.87 ANSTO also provided evidence to the Committee indicating that scenarios
based on a reactor `meltdown' such as Dr Caldicott's assertion
of an `eight minute meltdown' are unrealistic. A meltdown refers
to major damage to the fuel elements in the reactor core that would release
a significant quantity of radioactive fission. [81] ANSTO disputed that such a catastrophe could
occur at the Lucas Height Science and Technology Centre given the design
and proven safety record of both HIFAR and similar reactors operating
overseas. According to ANSTO, internationally there is a more than 50
year history of operation of several hundred research reactors without
any core meltdown accidents affecting the public. [82]
International Atomic Energy Agency reports indicate that between 1945
and 1961 there were four research reactor accidents leading to six worker
fatalities. Since that time, however, no lives have been lost as a result
of reactor accidents. The IAEA also reported that no members of the general
public have been affected by reactor accidents. [83]
3.88 The `eight minute meltdown' claim appears to be based on a scenario
fabricated as part of a 1986 hypothetical accident. Conducted by a HIFAR
Safety Analysis Working Party, the study postulated that a core meltdown
might occur in eight minutes following the simultaneous occurrence of
multiple random and severe events, including the total failure of the
HIFAR Emergency Core Cooling System. If such a crisis were to occur, ANSTO
argued that the radiological consequences at the edge of the buffer zone
would be below the NH&MRC's lower intervention levels for any emergency
countermeasures. [84] Professor Garnett, Executive
Director of ANSTO stated:
The NSB has also, along with international authorities and using international
assessments, identified that there is no accident that could occur at
Lucas Heights that would even require any evacuation of anybody in the
community. The worst possible hypothetical case and I stress
that is where there may need to be some sheltering for a very
brief period of time. The maximum distance that would occur from ANSTO
is up to 2.5 kilometres. [85]
3.89 Aside from accidents or emergencies occurring as a result of technical
malfunction, natural disasters, specifically bushfires, pose a realistic
threat to the Lucas Heights Science and Technology site. A detailed bushfire
strategy is included in ANSTO emergency guidelines. It was called upon
in December 1997 when major fires ravaged the area. According to the Sutherland
Shire Environment Centre, these fires proved Lucas Heights to be a potential
`disaster area', as evidenced by the forced evacuation of Barden Ridge,
the suburb closest to the Science and Technology centre, and the destruction
of eleven houses in the next suburb of Menai. [86]
However, both ANSTO and the NSB appear satisfied that the necessary precautions
are in place to protect HIFAR from serious threat.
3.90 At the height of the December 1997 fires, ANSTO took the precaution
of ceasing reactor operations for a 24 hour period. HIFAR itself was not
evacuated with reactor operators maintaining their posts throughout the
emergency. [87] In ANSTO's view, a shutdown of HIFAR is the worst
possible impact bushfires might have on nuclear operations at the site.
Given the extent of firebreaks, warning systems and non-combustible building
materials surrounding HIFAR, ANSTO was confident that there is no credible
way in which a bushfire could lead to a reactor accident. This conclusion
was endorsed by the Acting Director of the NSB, who informed the Committee
that:
We are satisfied with the ability of HIFAR to withstand bushfires.
Indeed I think that the bushfire that occurred sort of vindicated that
conclusion. [88]
3.91 Nonetheless, the Committee notes that access to the reactor site
is limited to one road and that during the bushfires this road was closed
at times. The Committee considers that it is unsatisfactory to have a
situation where access to the reactor site cannot be guaranteed at all
times.
3.92 Regardless of reassurances regarding accident and emergency risks,
the Sutherland Shire Council believes that, in the worst case scenario
that an incident does affect local residents or their property, current
public liability arrangements are inadequate. Legal advice commissioned
by the Council indicates that, by relying on the common law, nuclear liability
in Australia is primitive by international standards. [89]
Although Australia has signed the 1997 Convention on Supplementary
Compensation for Nuclear Damage, [90] ratification
of the convention is a long way off. Therefore, in the meantime compensation
for any damage would have to be claimed under common law. Whether the
Commonwealth or ANSTO would be liable for any losses or damage would depend
on the details of the particular case. The Commonwealth has indicated
that it would ensure ANSTO has the capacity to meet any damage claims
which might conceivably be awarded. [91] It is noted in the Supplement to the Draft EIS
that a deed of indemnity was signed between the Commonwealth and ANSTO
on 27 August 1998. [92]
Transportation risks
3.93 Transportation of nuclear waste and radioisotopes from the Lucas
Heights Science and Technology Centre is a further area of significant
accident potential. It is of particular concern to local residents and
neighbouring councils in areas through which radioactive materials are
moved. Both the NSB and the ARL have been responsible for monitoring all
transportation arrangements for radioactive materials.
3.94 Stringent regulations adopted by the International Atomic Energy
Agency underpin the NSB and ARL's monitoring of radioactive materials'
transportation. These regulations demand safety assessments at a number
of levels. In respect of each type of radioactive material, the regulations
specify design criteria for the transportation container and recommend
appropriate handling and stowage procedures. A key aspect of the NSB's
work, therefore, has been to:
assess the (radioactive waste) transport casks and packages
against those regulations. We witness the tests of those packages and
we are completely satisfied as to the fitness for purpose of the transport
packages. Additionally we have reviewed the transport plan for the movement
of those wastes outside of the site. [93]
3.95 The NSB concluded that there is no undue risk to the health and
safety of the public arising from the transportation of nuclear waste.
[94] This was also confirmed in evidence from
the Commonwealth Department of Transport to the 1996 Senate Select Committee
on the Dangers of Radioactive Waste, which indicated that there have been
no significant incidents in the transportation of radioactive materials
in Australia during the last 30 years. [95]
Conclusions of the Draft EIS
3.96 Based on its broad analysis of the likely environmental impact of
a new reactor located at Lucas Heights, PPK Environment & Infrastructure
reached the following general conclusion:
The cumulative impacts arising from the construction and subsequent
operation of the proposed replacement reactor for a period of not less
than 40 years are expected to be small, particularly if the management
measures outlined in the Draft EIS are implemented.
The site for the proposed replacement reactor has been well characterised
and the impacts of HIFAR monitored over the past 40 years. Provided
the mitigating measures are taken, and given the commitment that radioactive
waste would be removed from Lucas Heights, the analyses in the draft
EIS have indicated that there are no significant issues raised under
the principles of ecologically sustainable development. [96]
3.97 The principles of ecologically sustainable development as defined
in the New South Wales Environmental Planning and Assessment Regulation
1994 underpinned PPK's analysis. Intergenerational equity is one of
the four key principles of ecologically sustainable development. It concerns
the legacy passed from one generation to the next in respect of health,
diversity and productivity of the environment. According to the draft
EIS, some of the benefits of the proposed new reactor in relation to the
principle of intergenerational equity would be:
- economic benefits to the local, regional and national communities
of interest through generated employment, income and economic input;
- increases in the standard of health care through the availability
of a reliable supply of radiopharmaceuticals and access to increased
numbers of radiopharmaceuticals;
- enhanced opportunities for neutron beam research to Australia's scientists
and engineers;
- better analytical services to improve Australian industry competitiveness;
and
- maintenance of technical expertise to provide sound advice to Government
in international affairs. [97]
3.98 In ANSTO's view, further studies relating to issues raised in the
public submission process, confirm `the findings of the Draft EIS and
hence the findings of the Final EIS are unchanged from the Draft EIS'.
[98]
Key findings of independent peer reviews of the new reactor EIS
3.99 Three independent reviews of some of the key nuclear issues considered
in the EIS were commissioned by Environment Australia. The reviews were
conducted by the International Atomic Energy Agency, Parkman Safety Management,
and Ch1M HILL respectively. All three reviews had the goals of:
- ensuring rigorous independent expert scrutiny of the draft EIS;
- assisting stakeholders in understanding the EIS technical issues,
and in preparing their submissions on the draft EIS; and
- assisting Environment Australia in its assessment of the proposal.
The International Atomic Energy Agency Review
3.100 The International Atomic Energy Agency (IAEA) review was largely
concerned with the radiological risks associated with both normal operations
of the proposed new reactor and possible accidents. In particular, the
review was requested to evaluate the EIS in terms of the appropriateness
and adequacy of data and methodologies used; the appropriateness of any
standards used and basis for their use; and the correctness or reasonableness
of any assumptions, comparisons or conclusions made, particularly in relation
to siting. [99]
3.101 Based on an assessment of available information, discussions with
key parties and a site visit, the IAEA concluded that Lucas Heights would
be an acceptable location for the proposed new reactor. In the opinion
of the IAEA, the proposed site:
has no negative characteristics which would make it unacceptable
from a nuclear or radiological safety point of view. Any deficiencies
of the site can be compensated by engineering design. [100]
3.102 This finding by the IAEA is not surprising given that Lucas Heights
has been the site of the HIFAR reactor for forty years.
3.103 However, in reaching its conclusion, the IAEA noted shortcomings
in the so-called `Reference Accident' [101] evaluated in the EIS. The IAEA judged the Reference
Accident to lack detail and noted that a full justification for the choice
of accident was not included in the EIS. Accordingly, the IAEA recommended
that the Final EIS include substantiation for the Reference Accident,
citing all other accident scenarios considered (including those with external
initiators) and a justification for why they were screened out. [102]
The Parkman Safety Management Review
3.104 The second EIS peer review was conducted by the UK based Parkman
Safety Management (PSM), and focused on the preliminary hazard and risk
assessment contained within the new reactor EIS. As with the IAEA review,
PSM identified scope for improvement in the analysis of the EIS's Reference
Accident. In particular, PSM noted that the same Reference Accident was
evaluated by ANSTO in its Siting Safety Assessment submitted to the NSB
in April 1998. However, ANSTO used different modelling assumptions concerning
dispersion parameters and receptor behaviours in its assessment. Consequently,
PSM recommended that these differences be explained in terms of their
sensitivity to key aspects of the hypothetical accident including:
- the height of fission product release;
- weather conditions;
- lifestyle assumed for the most exposed person; and
- collective dose cut-offs.
3.105 This recommendation was addressed by ANSTO and PPK in the Final
EIS. The differences in the modelling assumptions used by ANSTO and PPK
were stated in the report. [103] The Final EIS claimed that the effect of these
differences did not alter the conclusions in the draft EIS regarding the
Reference Accident. According to ANSTO and PPK:
It should be recognised that the Siting Safety Assessment is part of
a regulatory submission intended to obtain Site Authorisation for the
replacement nuclear research reactor
and hence serves a different,
yet complementary, purpose to the EIS.
The differences in modelling assumptions result from the independence
of the NNC calculations from those of ANSTO and also provide an indication
of the effect of a range of realistic assumptions on the results of
the Reference Accident assessment. It should be noted that the assumptions
made in the Draft EIS and the Siting Safety Assessment Reference Accident
are pessimistically bounding in that it is not credible to make more
conservative assumptions. For example, the timing of the release from
the reactor building is assumed to coincide with F/D cycling of weather
which provides the maximum credible dose. Both the Siting Safety Assessment
and Draft EIS results for the doses from the reference Accident are
within the relevant criteria put forward by the Nuclear Safety Bureau.
[104]
3.106 Aside from this one area of weakness, PSM judged the Reference
Accident to be appropriate for bounding any fault that could occur on
a well designed reactor system. In addition, PSM commented that the risks
and hazards assessment of the EIS had been undertaken in accordance with
currently accepted methodologies and internationally verified computer
codes. Although some shortfalls in information requirements were identified,
PSM generally supported the conclusion that the effects of up-rating can
be accommodated without increased off-site doses. [105]
The Ch1M Hill Review
3.107 Ch1M HILL was the third group to conduct a peer review of aspects
of the new reactor EIS. Specifically, Ch1M HILL considered the nuclear-related
aspects of the EIS, focussing on the:
- appropriateness and adequacy of information presented;
- appropriateness of any standards used and the basis for their use;
- correctness and reasonableness of any assumptions, comparisons or
conclusions made;
- overall adequacy of materials presented in the EIS in addressing relevant
nuclear matters;
- comments on any commitments by ANSTO for future studies; and
- recommendations or suggestions for additional work. [106]
3.108 Ch1M HILL concluded that the draft EIS had adequately identified
the risks associated with the new reactor proposal, and that the possible
related impacts were appropriately described as minimal. Ch1M HILL noted
a need for further detail within the EIS, particularly with respect to
the shipment of spent nuclear fuel and wastes; disposal of radioactive
wastes; and regulations and operational criteria.despite these minor shortcomings,
the company was unable to identify any conditions precluding the construction
and operation of the new reactor. [107]
Committee's conclusions regarding siting
3.109 The Committee concludes that adequate public consultation within
the limits of the EPIP Act took place over the new reactor proposal but
that the process could have been significantly improved. Conducting public
meetings, similar to those relating to the Holsworthy Airport proposal,
would have allowed for more open channels of communication between both
sides of the new reactor debate and may have helped allay some of the
concerns of local parties.
3.110 In the Committee's view, the process surrounding the environmental
impact study (EIS) was independent. But it too could have been enhanced
by appointing an independent environmental auditor in an oversight role
similar to the approach taken with the Holsworthy and Badgery Creek airport
proposals. This would have improved the transparency and accountability
of the EIS process.
3.111 While the EIS process was independent, it was incomplete and inadequate
insofar as it did not consider alternative sites to Lucas Heights for
the new reactor. The 1993 RRR stated explicitly that an `exhaustive search'
for alternative sites was essential before a decision could be made on
a new reactor. Neither the internal departmental study on alternative
sites, nor the methodology and criteria informing that study, has been
released by the Government to the Committee. The Committee has been kept
in the dark on a fundamental stage in the decision making process for
the new reactor.
3.112 The Committee concludes that the decision to build a new reactor
was made without proper consideration of the recommendations of the RRR
in regard to exhaustive analysis of alternative sites. The Committee
recommends that alternative sites be properly and fully investigated by
an independent public inquiry.
Footnotes
[1] Submission No.29, p. 3.
[2] Formerly the Department of Industry, Science
and Tourism, until 22 October 1998; Commonwealth of Australia Gazette
Special; Administrative Arrangements Order, 22 October
1998.
[3] Submission No.29, p.11.
[4] K R McKinnon, Future Reaction, Report
of the Research Reactor Review, Commonwealth of Australia, August
1993, p.162.
[5] K R McKinnon, Future Reaction, Report
of the Research Reactor Review, Commonwealth of Australia, August
1993, p.164.
[6] Submission No.33, p.1.
[7] K R McKinnon, Future Reaction, Report
of the Research Reactor Review, Commonwealth of Australia, August
1993, p.164.
[8] K R McKinnon, Future Reaction, Report
of the Research Reactor Review, Commonwealth of Australia, August
1993, Recommendation 20.1, p. xxiv.
[9] Submission No.7, p. 4.
[10] Evidence, p. 380.
[11] Submission No.29, p.3.
[12] Evidence, p. E14.
[13] Evidence, pp.E102-103.
[14] Submission No.25, p.18.
[15] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.3.33.
[16] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.6.29.
[17] Submission No.20, p.2.
[18] Submission No.20, p.1.
[19] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, pp.2-42-5.
[20] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.2-5.
[21] Submission No.33, p.1.
[22] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
, Volume 2/Appendices, p.C-4.
[23] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
, Volume 2/Appendices, p.C-8.
[24] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.7-17.
[25] Twyford Consulting, Evaluation of an
EIS Community Consultation Process for ANSTO and Sutherland Shire
Council. August 1998, p.8.
[26] Twyford Consulting, Evaluation of an
EIS Community Consultation Process for ANSTO and Sutherland Shire
Council. August 1998, p.11.
[27] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 3/Supplement, p.2-14.
[28] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 3/Supplement, p.2-11.
[29] Evidence, p.E302.
[30] Evidence, p.E306.
[31] Evidence, p.E294.
[32] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 3/Supplement, p.2-14.
[33] Evidence, p.E295.
[34] Submission No.25, p.10.
[35] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.2-7.
[36] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.20-6.
[37] Submission No.7, p.1.
[38] Submission No.7, p.1.
[39] Evidence, p.E295.
[40] Evidence, p.E298.
[41] Evidence, p.E273.
[42] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 3/Supplement, pp.5-75-8.
[43] Submission No.22, p.2-3.
[44] Submission No.19, p.2.
[45] The sievert is the unit measure of the
effects of ionising radiation on living cells, and one thousandth of a
sievert is known as a millisievert (1000 Sv). PPK Environment & Infrastructure,
Draft EIS, Glossary, p.G-17.
[46] Submission No.29B, p.1.
[47] Submission No.28, p.7.
[48] The ALARA objective refers to doses being
`as low as reasonably achievable'.
[49] Submission No.28, p.7.
[50] Submission No.28, p.12.
[51] Submission No.25, p.15.
[52] Santa Susana Field Laboratory Epidemiological
Study: Report of the Oversight Panel, September 1997, referred
to in Submission No.25, p.15.
[53] Evidence, p.E169.
[54] Submission 29B, p.2.
[55] Submission 29B, p.2.
[56] K R McKinnon, Future Reaction, Report
of the Research Reactor Review, Commonwealth of Australia, August
1993, p.205.
[57] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p. 8-14
[58] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.8-16.
[59] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p. 9-8.
[60] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.9-7.
[61] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.12-17.
[62] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.12-17.
[63] Assented to 24 December 1998, commenced
5 February 1999.
[64] Evidence, p E 410.
[65] Submission No.28, p.3.
[66] Formerly the Minister for Health and Family
Services until 22 October 1998.
[67] Evidence, p.E78.
[68] Evidence, p. 308.
[69] Evidence, p.E164.
[70] Submission No.29B, p.5.
[71] Copies of the Lucas Heights Site Emergency
Plan and the ANSTO Emergency Plan (DISPLAN) are available for inspection
at the reception centre at ANSTO, at Sutherland Shire Council libraries
and at the Sutherland Shire Environment Centre. The Sutherland Shire Local
Disaster Plan (DISPLAN) and the Georges River District Disaster Plan (DISPLAN)
are also available at libraries.
[72] Submission No.28, p.11.
[73] Submission No.19, p.2.
[74] Evidence, p.E181.
[75] Evidence, p.E68.
[76] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.20-11.
[77] Submission No.28, p.12 and PPK Environment
& Infrastructure, Replacement Nuclear Research Reactor, Draft Environmental
Impact Statement, Volume 1/Main Report, p.11-22.
[78] K R McKinnon, Future Reaction, Report
of the Research Reactor Review, Commonwealth of Australia, August
1993, p.166.
[79] Submission No.25, p.16.
[80] Submission No.29B, Attachment - Comments
on MHB Report etc., p.2.
[81] Submission No.29B, Attachment - Research
Reactors and Meltdowns, p.1.
[82] Submission No.29B, Attachment - Research
Reactors and Meltdowns, p.1.
[83] Submission No.21, p.8.
[84] Submission No.29B, Attachment - Research
Reactors and Meltdowns, p.2.
[85] Evidence, p.E240.
[86] Submission No.7, p.7.
[87] ANSTO Safety Division, Report on Bushfires
of December 1997, February 1998, p.12.
[88] Evidence, p.E92.
[89] Submission No.25, p.17.
[90] The Convention on Supplementary Compensation
for Nuclear Damage requires ratification by one third of the world's
nuclear power generating countries before it comes into force. Thereafter,
Australian legislation will need to be established to meet the obligations
of the Convention. PPK Draft EIS, Main Report, p.11-48.
[91] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.11-48.
[92] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Supplement to Draft Environmental
Impact Statement, Volume 3/Supplement, p ES-19.
[93] Evidence, p.E83.
[94] Evidence, p.E83.
[95] Senate Select Committee on the Dangers
of Radioactive Waste, No Time to Waste, April 1996, p.84.
[96] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.xxvii
[97] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Draft Environmental Impact Statement,
Volume 1/Main Report, p.20-12.
[98] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Supplement to Draft Environmental
Impact Statement, Volume 3/Supplement, p. ES-20.
[99] International Atomic Energy Agency, Review
of the Draft Environmental Impact Statement for the Replacement Nuclear
Research Reactor, September 1998, p.1.
[100] International Atomic Energy Agency,
Review of the Draft Environmental Impact Statement for the Replacement
Nuclear Research Reactor, September 1998, p.17.
[101] A hypothetical accident scenario used
to assess nuclear facility siting, accident management and emergency planning.
See PPK Environment & Infrastructure, Replacement Nuclear Research
Reactor, Draft Environmental Impact Statement, Volume 1/Main Report,
p.G-16.
[102] International Atomic Energy Agency,
Review of the Draft Environmental Impact Statement for the Replacement
Nuclear Research Reactor, September 1998, p.17.
[103] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Supplement to Draft Environmental
Impact Statement, Volume 3/Supplement,Table 11.5, page 11.38.
[104] PPK Environment & Infrastructure,
Replacement Nuclear Research Reactor, Supplement to Draft Environmental
Impact Statement, Volume 3/Supplement, p.11-37.
[105] Parkman Safety Management, ANSTO
Replacement Nuclear Research Reactor EIS: Peer Review of Hazards and Risks
Analysis, September 1998, p.1.
[106] Ch1M HILL, Report to Environment
Australia: Replacement Reactor Draft EIS Technical Review, September
1998, p.2.
[107] Ch1M HILL, Report to Environment
Australia: Replacement Reactor Draft EIS Technical Review, September
1998, p.1.