If you don't think about this upfront you're dead in the
water at the back end of this.
Lt. Gen. Christopher Bogdan, United States Air Force
1.1
I commend my colleague, Senator Peter Wish-Wilson, for instigating this
inquiry that I co-sponsored—a review into the F-35 Lightning II (Joint Strike
Fighter) was essential—given the incredible importance of this project to
national security and to the Treasury.
1.2
Whilst I broadly support the recommendations of the Committee, those
recommendations do not go far enough, noting the acquisition's importance to
Australia.
No Competition
1.3
In March 2002 Defence made a number of recommendations to the Defence
Capability Investment Committee (DCIC) which was considering Australia's New
Combat Air Capability. That advice recommended, amongst other things, the DCIC:
-
agree that sole sourcing to JSF for AIR 6000 now is not
appropriate because of concerns about capability, cost and schedule issues with
the JSF project; and
-
agree that participation in the System Development and
Demonstration (SDD) Phase of the Joint Strike Fighter project is not
recommended at this time.
1.4
Unfortunately, 7 months later, in October 2002, the then Government
approved Australia becoming a partner in the SDD phase of the JSF Program at a
cost of US$150 million. At this point in time the competition for the AIR 6000
aircraft was terminated.
1.5
Responses provided to the Committee on what happened between March 2002
and October 2006 were shallow (and will be subject of further inquiry).
1.6
The March 2002 analysis output by Defence was of the highest quality and
the most prescient. The project has gone on to have significant capability,
cost and schedule problems.
1.7
Australia has entered into one of its most expensive capital procurement
projects in a manner that lacks both competition and explanation.
Capability
1.8
The committee received submissions and heard from a number of entities
and individuals as to the performance of the F-35.
1.9
The opinions expressed to the committee varied.
1.10
Some entities and individuals, albeit with considerable experience, but
without access to classified information, suggested that the aircraft could not
and would not compete with aircraft that it might go up against in future
conflict.
1.11
Others, albeit with access to classified information but with pecuniary
interest or encumbered by considerable long term 'buy in' to the decision to
procure the aircraft, suggested the aircraft would meet its expectation and
provide the Royal Australian Air Force with a regionally superior fighter
aircraft.
1.12
The Australian Strategic Policy Institute was confident that aircraft
would meet Australia's needs, but expressed doubt in the ability for the JSF
project team to achieve full performance in an acceptable time frame.
1.13
These differing opinions, dependant on perspective, leave little choice
but to rely heavily on the analysis of the US Director of Operational Test and
Evaluation (DOTE), Dr J. Michael Gilmore. Dr Gilmore is a Presidential
appointee confirmed by the United States Senate who serves as the senior
advisor to the Secretary of Defense on operational and live fire test and
evaluation of Department of Defense weapon systems. Dr Gilmore has access to
full information and an obligation to present impartial analysis of the
program. He has on a number of occasions expressed considerable concerns about
the program. As recently as 9 August 2016 he stated:
Achieving full Combat Capability with the Joint Strike
Fighter is at substantial risk.[1]
1.14
Regard must be had to this statement. He went on further to elaborate:
While the Air Force recently declared Initial Operational
Capability (IOC) with 'basic' Block 3i capabilities, most of the limitations
and deficiencies for the F-35A with Block 3i discussed in my FY15 Annual Report
and Congressional testimonies remain and will adversely affect mission
effectiveness and suitability. In fact, the program is actually not on a path
toward success, but instead on a path toward failing to deliver the full Block
3F capabilities for which the Department is paying almost $400 billion by the
scheduled end of System Development and Demonstration (SDD) in 2018. If Initial
Operational Test and Evaluation (IOT&E) were conducted today on the
aircraft in the Block 3i configuration - with which the Air Force recently
declared IOC -the system would likely be evaluated as not effective and not
suitable across the required mission areas and against currently fielded
threats. If used in combat, the F-35 in the Block 3i configuration, which is
equivalent in capabilities to Block 2B, will need support to locate and avoid
modem threats, acquire targets, and engage formations of enemy fighter aircraft
due to outstanding performance deficiencies and limited weapons carriage
available (i.e., two bombs and two air-to-air missiles). Unresolved Block 3i
deficiencies in fusion, electronic warfare, and weapons employment continue to
result in ambiguous threat displays, limited ability to effectively respond to
threats, and, in some cases, a requirement for off-board sources to provide
accurate coordinates for precision attack. Although the program recently
addressed some of the Block 3i deficiencies, many significant deficiencies
remain and more are being identified by operational test and fielded units,
many of which must be corrected if the program is going to provide the expected
'full warfighting capability' described in the Operational Requirements
Document (ORD).[2]
1.15
This summary must be of considerable concern.
Cost
1.16
Acquisition costs in this program have been, and still are, of concern.
The
F-35 program is the US Defense Department's most expensive. The total program
costs to the US have gone from US$233 billion in 2002 to circa US$400 billion
today.
1.17
The program was subject to a Technical baseline review in 2010. Since
its conclusion cost overruns have been limited, but the August 2016 comments by
Dr Gilmore raised new concerns. He stated:
Despite needing to continue developmental testing at full
capacity for at least another year to complete the planned testing of the new
capabilities and attempted fixes for the hundreds of remaining deficiencies,
the program is already beginning to reduce the number of test personnel and
defer required fixes to beyond SDD due to funding constraints.[3]
1.18
He went on further to state:
It appears as though the program is running out of time and
out of money to deliver the required full F-35 combat capability in Block 3F
before the completion of SDD ... How the program will be able to accomplish the
balance of required test points remaining in the time and budget allotted,
given historic rates and ongoing personnel reductions, is unclear.[4]
1.19
As a result, the total cost of the program will have to rise again.
1.20
Air Vice-Marshal Deeble indicated at the public hearing that the cost to
Australia for the acquisition of 72 aircraft is likely to be $17.1 billion and
the cost of through life sustainment will be a further $43 billion. Even a
small percentage rise in either of these numbers will be costly.
1.21
With respect to acquisition, whilst Australia is immune from many of the
cost overruns in the development phase the final price it will pay for each
aircraft is subject to change. If Canada were to pull out of the program, or if
the US were to reduce the number of aircraft it ultimately procures, the cost
to Australia will rise – with no means at present to mitigate this cost
increase.
1.22
With respect to sustainment, Australia will in effect be a 'captured
market' when it comes to sustainment. US Air Force Lt. Gen. Christopher Bogdan,
the man who has run the F-35 project for the past 4 years, has indicated in the
media that, fifteen years after project initiation, the lack of clear
contractual language about ownership of technical data and software code has
put the Pentagon in a bind and has limited the government's options on how to
maintain, upgrade and manage the Pentagon's largest weapons acquisition:
I am playing catch-up now every which way I turn when it
comes to intellectual property rights in the F-35 program.[5]
1.23
Because contractors and subcontractors have tight control of the
intellectual property—from the software to major components and spare parts—the
Defense Department has limited authority, for instance, to integrate new
systems into the aircraft or do routine maintenance work in government depots.
Lt. Gen. Bogdan said further:
What I'm experiencing is the classic example that if you don't
think about this upfront you're dead in the water at the back end of this. We
didn't think much about this upfront in the F-35. We didn't write anything into
the contract very well.[6]
1.24
The US Air Force C-17 cargo aircraft program offers a cautionary tale.
Initially when the program started in the 1990s, the plan was that it would be
maintained by the contractor for life, so there was no need to ask for OMIT
data:
Years into the program, the Air Force decided that
contractor-provided maintenance was unaffordable, Bogdan said. The service
sought to move the work into its own depots, and 'when they started doing that,
there was no foundation on IP and data rights. There were mighty struggles. I'm
experiencing some of that in the F-35 today.'[7]
Schedule
1.25
I share the concerns of the committee with respect to the F-35's
schedule, particularly in light of the recent comments by Dr Gilmore. I agree
that Australia must accept that a capability gap is looming.
Recommendations
1.26
Australia has entered into a program without due process and finds
itself in a position where, it has suffered from the materialisation of
capability, cost and schedule risks that it has identified back in March 2002.
1.27
Australia should follow the Canadian lead with respect to this program.
Whilst remaining in the program, Australia should run a competition (including
a fly off) to sanity check its decision making. Although the Committee found
that none of the alternate aircraft would exactly meet Australia's
requirements, neither will an F-35 that will not achieve full combat
capability.
Recommendation 1
1.28
Whilst remaining in the F-35 program, Australia should (in cooperation
with the Canadians, who are running a competition) re-open and compete for the
New Combat Air Capability.
Recommendation 2
1.29
In the event that the F-35 wins the competition:
-
A hedging strategy to mitigate the capability gap that could
result from further schedule slippage, as recommended by the Committee, should
be sought.
-
A fixed price contract for the aircraft should be negotiated with
liquidated damages to be passed through the US Government to Lockheed Martin in
the event that the company does not deliver in accordance with contracted
performance or schedule.
-
The Department of Defence develop a sovereign industrial
capability strategy for the F-35 to ensure that Australian Aircraft can be
maintained and supported without undue reliance on other nations. This strategy
should include the negotiation of intellectual property rights (in similar
scope and terms to that which we have for Collins Class submarine sustainment
purposes) with Lockheed Martin, prior to any further purchases, which would
facilitate such a sovereign capability.
-
The government endeavour to establish Australia as the
Asia-Pacific maintenance and sustainment hub for the F-35.
Senator Nick Xenophon
Navigation: Previous Page | Contents | Next Page