Chapter 3
Infrastructure and Transport portfolio
Department of Infrastructure and Transport
3.1
This chapter contains the key issues discussed during the 2011-2012
budget estimates hearings for the Infrastructure and Transport portfolio. A
complete list of all the topics discussed, and relevant page numbers, can be
found at appendix 4.
3.2
The committee heard evidence from the department on Wednesday 25 May and
Thursday 26 May 2011. The hearing was conducted in the following order:
-
Corporate Services
-
Infrastructure Australia
-
Nation Building—Infrastructure Investment
-
Surface Transport Policy
-
Australian Maritime Safety Authority
-
Policy and Research (incorporating the Bureau of Infrastructure,
Transport and Regional Economics)
-
Major Cities Unit
-
Australian Rail Track Corporation
-
Inspector of Transport Security
-
Office of Transport Security
-
Aviation and Airports
-
Airservices Australia
-
Civil Aviation Safety Authority
-
Australian Transport Safety Bureau
Corporate Services
3.3
The committee began by discussing key initiatives of the department set
out in the budget. The Secretary, Mr Mike Mrdak, outlined initiatives in two
main areas, planning and infrastructure investment.
3.4
In planning, the government released its national urban policy, which
sets out objectives and priorities for improved planning and investment in 18
major cities. There are two key projects within the Sustainable Australia
initiative: A $20 million initiative to help improve the capacity of regional
cities to undertake strategic planning for urban renewal, and a $61.4 million
program, which will fund small infrastructure technology to reduce traffic
congestion and improve demand management on major motorways.[1]
3.5
In infrastructure investment, an additional $1 billion has been
allocated to the continuing work of duplicating the Pacific Highway, taking the
total Commonwealth funding to over $4 billion. The Moreton Bay rail link has
had $133 million brought forward and savings within the Nation Building
Program to fund natural disaster recovery efforts have also been brought into
account for the 2011-12 budget. Furthermore, the five Bruce Highway projects
that had been deferred have now been reinstated.[2]
3.6
The committee asked the department to explain the process behind the
reinstatement of the five Bruce Highway projects in Queensland. The Secretary
informed the committee that the projects were deferred because they were still
in the early stages and the deferral aimed to meet the costs of the
disaster-recovery requirements in Queensland at the time. It also reflected
advice from the Queensland Government that, due to the requirements of the
restoration effort, it may not be in a capacity to proceed with the projects.
The decision to reinstate the projects came after the Queensland Government
advised that it had identified savings elsewhere in the Nation Building Program
for these projects.[3]
3.7
The committee heard that the Council of Australian Governments has
agreed that Australia will have fully-operational, single national regulators
for heavy vehicles, rail and maritime safety by 2013.[4]
3.8
The committee asked the department how it planned to meet its efficiency
dividend. The Secretary informed the committee that the overall impact of the
efficiency dividend is $2.7 million for the department, which will be allocated
across the portfolio divisions pro rata, and the department will then seek to
gain the efficiencies through systems and non-fixed costs. The non-fixed costs,
such as travel, stationery supplies and consulting support may have more
discretion in relation to future decisions.[5]
3.9
The committee sought further information on the staffing levels for the
department. Officers told the committee that 186 staff transferred to the
Department of Regional Australia, Regional Development and Local Government,
and that despite a small increase in staff, the figure is still below the
projected staffing level for 2011. The small increase in staff has been
predominantly in the Office of Transport Security, where positions have been
refilled due to staff turnover.[6]
3.10
The committee discussed the Perth Airport Gateway Roads project and
noted it is being funded through the Regional Infrastructure Fund. The
committee asked the department to clarify how it defines 'regional'. The
Secretary explained that generally within the portfolio, 'regional' is taken to
mean regional areas outside capital cities, however, 'in relation to the Regional
Infrastructure Fund, the government has made it clear that these are projects
which are linked to the resource sector'.[7]
Infrastructure Australia (IA)
3.11
The committee discussed Infrastructure Australia's additional $9 million
of funding each year for the next four years and what impact that will have on
resources. IA informed the committee of the steps involved to make IA more
independent and transparent, such as publishing its cost-benefit analysis of
projects. IA told the committee that its June report is under consideration as
to what cost-benefit figures can be released, however, consultation with some
proponents will need to occur prior to publication due to commercial
in-confidence issues.[8]
3.12
IA informed the committee of the statement of expectations from the
Minister for Infrastructure and Transport to the chair of the Infrastructure
Australia Council. As part of these expectations, IA will continue its work on
remote infrastructure issues for Indigenous communities, with a stronger focus
on opportunities for private sector financing.[9]
3.13
In relation to staffing, IA informed the committee that despite the
increase in funding, it is not looking to expand its staff level significantly.
However, this will ultimately be a decision for the Infrastructure Australia
Council.[10]
3.14
The committee discussed capacity issues at ports and asked IA how it
planned to deal with these concerns. IA told the committee that the National
Port Strategy will focus on these issues, with a long-term approach. This
strategic approach will aim to address capacity issues before it becomes critical,
rather than attempting to fix them afterwards. The prioritising of these issues
will take into account immediacy, different interest groups, the capacity to
link to Sydney and Melbourne, and congestion issues around road and rail.[11]
Nation Building—Infrastructure Investment
3.15
The committee requested an update on Black Spot, rail and road projects
announced under the economic stimulus plan. Officers informed the committee
that of the 605 Black Spot projects announced, 604 have been completed, with
the final project due to be completed within the month.[12]
3.16
The committee heard that of the 17 rail projects announced, 11 have been
completed and five are underway, with completion dates ranging from December
2011 to March 2013. The final project, the Hunter Valley Liverpool Range new
rail alignment, is in planning with a scheduled completion date of mid-2014.[13]
3.17
Of the 14 road projects announced, 12 are still under construction. The
department informed the committee of the specific details for the two completed
projects, noting that the remaining 12 all have completion dates ranging
between 2012 and 2014.[14]
3.18
The committee sought an update on truck stop projects and asked the
department if the new stops and restorations to existing stops would meet the
National Transport Commission's guidelines. The department informed the
committee that it could not confirm the final result as the project is still
rolling out, however, the Secretary stated:
There is no doubt it is one of the key priorities for the
heavy vehicle industry, and we share their concern that we need to invest more
into these facilities. This is a matter which I am sure the government will
look at in forthcoming consideration of the Nation Building Program 2.[15]
3.19
The committee sought to confirm the funding for the Mid-North Coast
Aviation Plan, in relation to upgrades to infrastructure and facilities as part
of the regional aviation plan. The Secretary informed the committee that
responsibility for this plan moved to the Department of Regional Australia,
Regional Development and Local Government in October 2010 in accordance with
the administrative arrangement orders. The Secretary clarified:
Until the formation of the department of regional Australia,
my department had a number of discussions with the Port Macquarie council in
relation to the aviation projects. From recollection, Mr Wilson and I and my
officers met at least three times with the chief executive of the council and
certainly at officer level, quite extensively. They provided a number of
business plans and business cases to the department in the lead-up to that
period. I cannot comment on what discussions have taken place since October
when this matter has been taken over by Regional Australia.[16]
3.20
The committee requested an update on the North Sydney rail freight
corridor study, which was due to be completed in early 2011. The department
informed the committee that the report is still underway, with its completion
expected in 2011. When questioned on the delay, the department told the
committee that it can be attributed partly to New South Wales RailCorp seeking
to find a preferred investment program that maximises the freight paths, but also
partly to a memorandum of understanding between the Commonwealth and the New
South Wales Government which is yet to be signed.[17]
3.21
The committee asked officers to detail the progress of a number of road,
rail and port projects, their likely completion dates and whether the funding
allocated is ongoing or additional.[18]
Surface Transport Policy
3.22
The committee requested an update on the progress of the national heavy
vehicle reform. The department told the committee that the heavy vehicle
national draft law has been going through a period of consultation, calling for
submissions and feedback. All states and territories have agreed to the draft
proposals.[19]
Significant progress has been made, as the Australian Transport Council
ministers met and agreed to forward the intergovernmental agreement to the
Council of Australian Governments (COAG). The agreement will detail how the
jurisdictions agree on the operational aspects of the national legislation.[20]
3.23
The committee heard that once the consultation on the draft laws is
complete, providing COAG approves the intergovernmental agreement, the final
legislation will be brought to the Queensland parliament. It can then be 'adopted
by each of the other jurisdictions as a single piece of national law'.[21]
The department told the committee that while differences have been settled,
there is room for jurisdictions to retain some local variations within the
proposed legislation.[22]
3.24
The department informed the committee that the expert panel, established
to resolve all of the various differences between the jurisdictions on heavy
vehicle law, identified approximately 340 differences between the jurisdictions
which apply to heavy vehicles. The Australian Transport Council has agreed to
the recommendations of the expert panel which has enabled the items to move
forward as a single piece of legislation.[23]
3.25
The department informed the committee that it is trying to ensure that
there is one piece of legislation that applies across all jurisdictions.[24]
The national heavy vehicle regulator is expected to be appointed in the second
half of 2012, and the department estimates it will be fully operational by
January 2013.[25]
Australian Maritime Safety Authority (AMSA)
3.26
The committee requested an update on AMSA's progress to becoming the
national regulator for all commercial vessels in Australia. AMSA told the
committee that there is funding within the budget to establish its systems to
become the national regulator, which is on track to take place in January 2013.[26]
The committee heard that the ministerial council has met, and that the next
step will be for COAG to agree to the draft intergovernmental agreement.[27]
3.27
The committee sought further information on AMSA's role in the rewrite
of the Navigation Act 1912. AMSA informed the committee that it is
working closely with the department to provide technical advice, on issues such
as the Safety of Life at Sea Convention, to make sure that the new legislation
will provide for these necessary conventions.[28]
3.28
AMSA told the committee that there will be two aspects to the new legislation:
the legislation enacted in the Commonwealth Parliament, and the laws that
states and territories will apply to cover what AMSA cannot, under its limited
constitutional powers. The committee heard that:
[t]here will be two parts to this, but effectively the text
remains the same. It will be amended through the Commonwealth parliament.[29]
3.29
The committee discussed examples of cases and AMSA explained whether it would
come under national law or the particular jurisdiction.[30]
AMSA informed the committee that the implementation of the law will be
nation-wide, however, AMSA will engage with the state jurisdictions to handle
the enforcement.[31]
Policy and Research (incorporating the Bureau of Infrastructure, Transport
and Regional Economics)
3.30
The committee discussed heavy vehicle statistics in relation to
accidents and fatalities. The department provided its quarterly statistics on
heavy vehicles, however, undertook to provide a breakdown of the cause of
accidents over the last 10 years on notice.[32]
3.31
The committee heard that the number of fatalities involving articulated
vehicles has decreased by 3.4 per cent over the last three years. The
department indicated that it keeps a database with information on the causes of
those accidents to get an indication of what issues to focus on.[33]
Major Cities Unit
3.32
The committee sought further information on the direction of the Major
Cities Unit following the release of the National Urban Policy, Our Cities,
Our Future. The Executive Director informed the committee that the next
step will be to develop the implementation plan of the action plan, which will
include a broad range of initiatives covering the Commonwealth's commitments,
but will also include work with state jurisdictions.[34]
3.33
The committee asked the Major Cities Unit to provide its definition of
'major cities'. Officers informed the committee that the Major Cities Unit
works from the Australian Bureau of Statistic's definition of 'major cities',
which is all cities with populations of 100,000 and above. This includes the
eight capital cities, plus 10 regional cities with that population level.[35]
3.34
The committee discussed the proposed Managed Motorways program, which will
involve spending $61.4 million on four motorways, to implement ramp metering
and information technology systems to improve the flow of traffic. These
motorways were identified by Infrastructure Australia as motorways that would receive
optimal benefit from the improvements.[36]
The performance indicators for this program will include improved performance
of the motorway in terms of flow, reduced congestion and reduced travel time.[37]
Australian Rail Track Corporation (ARTC)
3.35
The committee raised concerns about issues presented in the 7:30
Report regarding track maintenance on the Sydney to Melbourne line, as well
as the main east-west track in Perth. The Chief Executive Officer informed the
committee that the ARTC is familiar with the issues raised in the program and
that it has been subject to an internal review to produce a rectification
program to deal with the issues in the coming months.[38]
3.36
The committee heard that the Sydney to Melbourne line had been
particularly vulnerable to heavy rainfall that created mud holes, which
resulted in rail track issues. However, the ARTC informed the committee that
it did not believe that the east-west rail line was similarly affected.[39]
The ARTC told the committee that it has budgeted $40 million for maintenance
work this year, which is consistent with the budgets in place for the next five
years.[40]
3.37
The committee discussed the side insertion method in relation to the
replacement of timber with concrete sleepers on the rail track. The ARTC told
the committee that in 2007 it looked at a range of insertion methods and it was
decided that the side insertion method was the most efficient, as it allowed
better access to the track and higher productivity.[41]
3.38
The committee considered the practicality of using the side insertion
method in places that have a similar rainfall to the Sydney to Melbourne line,
where mud holes are known to be a problem. The ARTC informed the committee
that side insertion has been used in other areas of Victoria, with conditions
not dissimilar to the Sydney to Melbourne line, and the same problems have not risen
in those areas.[42]
The committee also heard that regular maintenance for most tracks can occur
because of mud holes, as their appearance is not rare across a range of tracks.[43]
3.39
The committee was interested in other insertion methods, including those
used in other countries. The ARTC told the committee that there are other
methods of insertion, which the ARTC has also employed, and advised that all
are acceptable methods of installing concrete sleepers.[44]
Office of the Inspector of Transport Security
3.40
The committee asked the Inspector to provide a brief description of the
Office's work since its creation in 2004. The Inspector informed the committee
that the purpose of its creation was to allow a no-blame style assessment of
transport and offshore security in a proactive, rather than reactive, manner.
The Inspector stated that as a result of that brief, the Office has conducted
inquiries into:
- surface transport following the London bombings;
- an airport security breach at Sydney Airport;
- large passenger ferries focused on the Great Barrier Reef; and
- maritime piracy.[45]
3.41
The committee requested further information on the inquiry into maritime
piracy. The Inspector told the committee that the report was released in April
2011, and the findings were as a result of consultation with the United
Nations, the Office of Drugs and Crime in Kenya, the United Nations Office on
Drugs and Crime, the International Maritime Organisation and the International
Maritime Bureau. The Office has since checked all the draft findings and
recommendations will those international bodies. The committee heard that
while Australia does not have many commercial vessels that travel in that area,
it does have a high number of important cargo, particularly livestock and cargo
from the mining industry, travel through those waters.[46]
Office of Transport Security
3.42
The committee discussed the visitor identification card (VIC) scheme at
length, specifically, the process of obtaining a card and the requirements for
the card holder once they have obtained it. The committee heard that a visitor
must provide photographic identification to obtain the card, even though the
VIC does not have a photo on it. The visitor must also be signed in by an Aviation
Security Identification card holder who has confirmed their identity. The card
only entitles the holder access to specific areas, with supervision, and must
be returned when they exit. The department informed the committee of further
specific information regarding the VIC scheme.[47]
3.43
The committee heard that there is a rigorous regime of compliance
checking of airport management systems in relation to VICs. There are
on-the-spot compliance checks and the small number of incidents involving non-compliance
has resulted in enforcement action.[48]
3.44
However, the department told the committee that the Commonwealth has acknowledged
that there is a need for continuous improvement and that an enhanced set of
regulations has been developed following extensive consultation with industry, and
will be in place by late November 2011.[49]
Aviation and Airports
3.45
The committee sought further information on the planning coordination
forums that were created as a result of the Aviation White Paper. The
department informed the committee that the purpose of the forums is to bring
together senior state officials, airport executives and representatives from
local councils and the Commonwealth to discuss broader planning directions and
the interaction between airports and surrounding areas when planning discussions
take place.[50]
3.46
The committee heard that all airports required have established a forum
and held initial meetings. The department told the committee that in these
forums, the residential areas affected have raised traffic and noise impacts as
concerns, and the airports have raised concerns regarding residential infill
and increased residential areas in zones affected by aircraft noise.[51]
3.47
The committee asked the department if it had conducted any work looking
at the possible impact on the Australian aviation industry of an emissions
trading scheme in the European Union (EU). The department informed the
committee that it has not conducted a cost analysis of the impact because
elements of the scheme that will apply to Australian carriers are still being
resolved.[52]
However, the department confirmed that the EU scheme would not apply to
domestic flights in Australia, or the first leg of flights between Australia
and the EU and that Australia does not currently have any direct flights to the
EU.[53]
3.48
The Minister informed the committee that the Commonwealth has stated its
opposition to the unilateral application of the emissions trading scheme in the
EU, and that it has taken the approach that an agreed, multilateral framework,
working within the International Civil Aviation Authority, is the most
effective way to address emissions from international aviation. The Minister
continued:
The United States air transport association and three US
airlines are challenging the aviation inclusion in the European Union's ETS
through the European Court of Justice. Media reports indicate that the China
Air Transport Association and three major Chinese airlines also plan to mount a
similar legal challenge. The Australian government has no current intention to
take action and we are not aware that any Australian airline is planning to
join the actions by either the United States airlines or the Chinese airlines.
As I am advised, the department will continue to monitor these actions and work
with the Department of Climate Change and Energy Efficiency in providing advice
and updates to the government.[54]
3.49
The committee discussed the enroute subsidy and its decrease of funding
in the budget. The Secretary confirmed with the committee that the decision to
terminate the program took place in 2008, however, aeromedical services will
continue.[55]
The Secretary clarified:
The subsidy will remain available to aeromedical operators.
The subsidy is paid to the operator of the airline or flight service. The
subsidy is by way of a recompense for the payment of their en route charges to
Air Services Australia. It is not a matter that involves the airport operator.[56]
3.50
The committee sought further information on the proposed plan to target
the enroute subsidy for routes that are less profitable. The department
informed the committee that while these specific changes have not occurred,
there are two measures in the place of those changes. First, an extension to
the operators that are entering routes where previously it was not available
and second, a continuation of the subsidy on all routes that were previously eligible.[57]
Airservices Australia
3.51
The committee requested an update on the Aircraft Noise Ombudsman (ANO).
The Chief Executive Officer informed the committee that the position was filled
in September 2010 and is funded entirely by Airservices Australia. The position
was allocated $500,000 for the first year of operation, to cover salary, travel,
staffing and the establishment of a separate office.[58]
3.52
The committee heard that the ANO released its first report in February
2011, which reviewed the complaint handling system of Airservices Australia.
The report produced 18 recommendations, which Airservices Australia has
accepted.[59]
3.53
The committee sought further information about the pricing of
firefighting services. Airservices Australia told the committee that it is working
with the ACCC to review the pricing proposal for the next five years. This
timeframe is seen as an advantage by both Airservices Australia and the
airlines as it provides certainty for a definite period of time.[60]
3.54
The committee asked officers what bullying and discrimination policies
are in place at Airservices Australia. The Chief Executive Officer informed
the committee that a number of processes have been put in place. For example,
the fair treatment process has been revised, staff have been appointed as
contact officers for workplace harassment, an internal campaign was conducted to
ensure understanding of acceptable behaviour, and management level staff
received training to deal with situations appropriately.[61]
Civil Aviation Safety Authority (CASA)
3.55
The committee discussed declarable interests in relation to CASA
employees belonging to the Chairman's Lounge. The Chief Executive Officer
informed the committee that officers are required to declare any pecuniary
interests each month, which is recorded on an internal document. CASA is
receiving legal advice as to whether or not membership of the Lounge should be
a declarable interest.[62]
3.56
The committee raised concerns about possible conflicts of interest in
relation to staff coming to CASA immediately after working for an airline.
CASA informed the committee that for airworthiness or flying operations
inspectors, there is a 12 to 18 month period before that employee can conduct
those investigations. However, officers told the committee that there are
variations depending on the organisation the employee has come from and what
position they hold at CASA and offered to take the specifics of the question on
notice.[63]
3.57
The committee sought further information on the fees CASA charges in
relation to air operator certificates, noting concern over the price for
particular services. CASA informed the committee of the specific prices, explaining
that the hourly rates are based on the skill set of the relevant officer. CASA
also informed the committee that every five years it conducts a cost recovery
impact statement, which reviews all charges within CASA, and then seeks
feedback from industry. Once the feedback is received CASA sends its cost
recovery statement to the Minister for approval. If there are any changes,
they would go through the normal legislative process.[64]
3.58
The committee requested clarification on CASA's management of foreign
operators in relation to staff training for emergencies. The committee heard
that CASA issues foreign air operator certificates to overseas airlines that
operate in Australia, and that these are only issued if the cabin and technical
crew have the appropriate training systems.[65]
Australian Transport Safety Bureau (ATSB)
3.59
The committee discussed the proposed expansion of the ATSB and asked
officers to provide further information. The ATSB informed the committee that
$3 million of funding has been allocated in 2012-13 to prepare the ATSB
for an expansion into the role of rail and possibly maritime investigations. The
proposal is being developed in parallel with the establishment of the single
national rail safety regulation and the ATSB would have the jurisdiction to
investigate all rail safety occurrences in Australia.[66]
3.60
The committee sought further information on the ATSB's ability to
investigate Royal Australian Airforce (RAAF) incidents. The ATSB told the
committee that, unlike CASA's regulatory limitations for RAAF, there are no
constraints on its capacity to investigate, providing the incident involves a
civil registered aircraft. The ATSB also informed the committee that Defence
and Airservices Australia are both required to notify it of any occurrences.[67]
3.61
The committee discussed the nature of airlines reporting to the ATSB in
relation to different reporting between airlines. The ATSB told the committee that
it has observed variations in the nature of reporting within individual operations,
and less so between the air operators themselves. The committee heard that the
adequacy of the reporting system has been raised with the ATSB, but that after
investigations, the only issue the ATSB found was that operators were uncertain
about what was reportable. The ATSB recognises this and informed the committee that
it is being addressed by tightening and clarifying the regulations.[68]
Senator Glenn
Sterle
Chair
Navigation: Previous Page | Contents | Next Page