Chapter 9 Audit Report No. 31 2009-10 Management of the AusLink Roads to
Recovery Program
Introduction[1]
9.1
Of the nation’s 810,000 kilometres of public roads, more than 650,000
kilometres (80 per cent) are local roads within the responsibility of local
government.[2] Approximately one-third
of these roads are sealed, with the remainder being unsealed (unformed, formed
or gravel roads).[3]
9.2
The AusLink Roads to Recovery Program is an administered program within
Outcome 1 (‘Assisting the Government to provide, evaluate, plan and invest in
infrastructure’) of the Department of Infrastructure, Transport, Regional
Development and Local Government (DITRDLG). Roads to Recovery is the largest
investment in local roads ever undertaken. In total, over 13 years, $4.18
billion[4] is to be paid by the
Australian Government to local government for expenditure on the construction
and maintenance of roads.
9.3
There have been four Roads to Recovery (R2R) Programs. The initial
Program was established by the Roads to Recovery Act 2000 (R2R Act) and
provided $1.2 billion over four years. It commenced in early 2001 as a single
intervention to address the concern that local government road infrastructure
was near the end of its economic life and its replacement was beyond the
capacity of local government. The initial program was the subject of an
Australian National Audit Office (ANAO) performance audit tabled in March 2006.[5]
9.4
A second four-year program commenced in July 2005, as part of the
AusLink Land Transport Initiative. The AusLink R2R Standard program was
established under the AusLink (National Land Transport) Act 2005 (AusLink
Act or the Act)[6] and provided $1.23
billion. There was also a separate, but related, AusLink R2R Supplementary
Program concurrently in operation from June 2006 to June 2009 that provided
$307.5 million (the third program).
9.5
A fourth program commenced under the Nation Building banner[7]
on 1 July 2009 and will continue through to 30 June 2014. The Nation Building
R2R Program will provide $1.75 billion.
9.6
It is the second and third R2R Programs (the AusLink R2R Programs) that
are the subject of this performance audit.
AusLink R2R Programs
9.7
Under the AusLink R2R programs, a total of $1.537 billion was paid to more
than 720 Local Government Authorities (LGAs) between July 2005 and June 2009.
The distribution of R2R funds between the States and Territories was determined
at the Ministerial level. In arriving at the actual distribution, consideration
was given to the historical results from using the Financial Assistance Grants
(FAGs) identified for local roads; and population and length of road under the
control of the local government, with each of these two statistics weighted
equally.[8] In turn, the allocation
of funds within each State was determined using the formula applied by State
Grants Commissions for FAGs identified for local roads.
9.8
Under the Standard Program, each Local Government Authority (LGA) was
guaranteed its full life of program allocation by 30 June 2009, subject to the
submission of satisfactory documentation such as work schedules and Quarterly
and Annual Reports. Almost all LGAs received their full R2R allocation. Larger
LGAs generally received an annual allocation capped at one quarter of their life
of program allocation. However, subject to meeting certain conditions, smaller
LGAs could access their full allocation at the start of the program. LGAs were
required to spend all of their Standard Program funds by 31 December 2009.
9.9
The May 2006 Budget announced that a further $307.5 million would be
provided in 2005-06 as a supplement to the AusLink R2R Standard Program. Under
the Supplementary Program, each funding recipient received a grant equal to one
quarter of its life of program allocation under the Standard Program. The funds
were distributed and administered under similar funding conditions to those of
the Standard Program, with funding recipients being required to acquit their
project expenditures by submitting Quarterly and Annual Reports. However,
unlike the Standard Program, funding recipients received their Supplementary
Program allocations as a one off payment in June 2006, and were required to
expend these funds by 30 June 2009.
9.10
The focus of the R2R Program is the renewal of local roads to meet social
and economic needs. Most of the funds are provided in the form of grants direct
to LGAs. These grants, together with other aspects of the program, are
administered by a manager and up to three staff in the South East Roads Branch
within the Canberra offices of DITRDLG. The small number of staff reflects the
following program delivery decisions made at the time the program was first
introduced:
- funds were to be paid
directly to LGAs;
- project priorities
were the choice of LGAs; and
- the process by which
grants were paid to the LGAs was to be simple, with appropriate audit and
accountability systems and arrangements put in place to ensure that there is
due recognition by LGAs of the Commonwealth’s contribution to local road
projects.
The Audit
Audit scope and objectives[9]
9.11
The audit scope covered the management of the AusLink R2R Standard
Program and the AusLink R2R Supplementary Program. The scope did not include
management of the Nation Building Roads to Recovery Program, which has only
recently commenced. The audit objectives were to:
- assess the
effectiveness of the management of the AusLink Roads to Recovery program;
- assess the delivery
of the program and management of the funding, including the extent to which the
program has provided additional (rather than substitute) funding for land
transport infrastructure; and
- identify
opportunities for improvements to the management of the program.
9.12
A key part of the audit involved examination of the use of, and
accountability for, R2R funds by a representative sample of 41 LGAs from four
States/Territories (representing almost six per cent of all funding recipients
and eleven per cent of total funding provided under the program). This work
included site inspections of more than 560 R2R funded projects, analysis of
financial and other reports provided by the 41 LGAs to DITRDLG, and
substantiation of the amounts charged to the program for selected projects. To
supplement the audit sample, ANAO analysed data in the Department’s
Infrastructure Management System (IMS).
Overall audit conclusions[10]
9.13
The ANAO made the following overall audit conclusions:
The R2R Program encompasses the largest investment in local
roads undertaken by the Australian Government. By the time the Nation Building
R2R Program concludes in June 2014, some $4.18 billion will have been paid over
13 years to local government for expenditure on the construction and
maintenance of roads.
As part of the AusLink R2R Standard and Supplementary
Programs audited by ANAO, more than $1.5 billion was paid to local government
for expenditure on the construction and maintenance of roads in respect of more
than sixteen and a half thousand projects. Almost all LGAs received their full
R2R allocation under the Standard Program and all LGAs received their Supplementary
Program allocations as an up front, once only payment. Accordingly, the key
aspect of the programs relating to distribution of funds to local government
and LGAs using these funds for road works have been effectively administered.
In terms of the benefits from the R2R Program, a fundamental
principle underpinning the program is that the funding provided to LGAs was to
be additional to existing road funding. Accordingly, LGAs are required to
maintain their own spending on local roads and report their performance in this
regard to the department. Over time, the expenditure maintenance obligation
placed on LGAs has been made less demanding but still, there have been
significant numbers of LGAs that have not maintained their own expenditure in
one or more years (and some LGAs have not maintained their own expenditure in
any year). In these circumstances, the administrative practice adopted has been
to waive the requirement where a satisfactory explanation has been provided and
ask that the shortfall be made up in later years; but this often does not
occur.
Another key aspect of program design was to pay LGAs
quarterly in advance based on LGAs reporting the expenditure to date and
forecast expenditure for the next three months in respect to each project they
were undertaking under the program. Paying up to three months in advance was
seen as necessary so that LGAs did not have to transfer funds from roadworks
funded from their own resources.[11] However:
- there have been many
instances of LGAs being paid more than three months in advance due to factors
such as accelerated funding during the last quarter of each financial year (so
as to fully spend the annual program allocation) notwithstanding that these
payments did not reflect LGA cash flow needs, and LGAs overstating their actual
expenditure and/or submitting unreliable expenditure forecasts;
- experience with the
program has shown that many LGAs do not require payments to be made in advance,
such that 54 per cent of all payments made under the Standard Program have been
made in arrears (and 90 per cent of LGAs were paid in arrears in one or more
quarters); and
- the cost to the
Commonwealth of advance payments remains considerable (up to $16.3 million over
the life of the AusLink R2R Standard Program).[12]
Reflecting the
judgement that LGAs were best placed to make decisions on road investment at
the local level, the grant payment and acquittal processes were designed to be
simple. However, there have been a range of important funding conditions where
LGA compliance has been less than satisfactory. In this respect, and without
detracting from the responsibility of individual LGAs to adhere to the
prescribed funding conditions, there would be benefit in the department
adopting a range of cost-effective strategies aimed at improving understanding
of, and adherence to, program funding conditions and administrative
arrangements by LGAs and their auditors. ANAO has made one recommendation to
this end.
In addition, in
light of experience as to how the program has operated over its first ten
years, there would be benefit in the department reviewing key elements of the
program design so as to confirm their continuing appropriateness, or otherwise
proposing variations (recognising that decisions on program design are a matter
for Government). In particular, there is value in consideration being given to:
- the formula that has
been used to allocate R2R funding to individual LGAs in light of evidence of
capacity constraints that affect the ability of some LGAs to both spend their
R2R funds as well as maintain their own source expenditure on roads; and
- paying LGAs in
advance rather than in arrears given that many LGAs have not sought payments to
be made in advance and a significant proportion of advance payments that have
been made have remained unspent by the respective LGAs for considerable periods
of time.
DITRDLG has
substantially implemented all recommendations made during the previous audit
aimed at improving the administration of the program. In light of further
experience with the program, ANAO has made a further two recommendations
directed towards enhancing the administration of program accountability
arrangements and strengthening the program governance framework.
ANAO recommendations
Table 9.1 ANAO recommendations, Audit Report No. 31
2009-10
1.
|
ANAO recommends that the Department of
Infrastructure, Transport, Regional Development and Local Government
strengthen the governance framework for the Roads to Recovery program,
including by:
a) better
resourcing the existing program of contracted financial audits of Local
Government Authorities so that the program of audits is able to be fully
delivered; and
b) giving greater
emphasis to structured risk management and program evaluation.
DITRDLG Response: Agree.
|
2.
|
ANAO recommends that, in light of the experience to
date with the program, the Department of Infrastructure, Transport, Regional
Development and Local Government review and advise Ministers on program
design arrangements that will promote timely local government expenditure of
Roads to Recovery funding on road work that is additional to that which would
have otherwise occurred.
DITRDLG Response: Agree.
|
3.
|
ANAO recommends that the Department of
Infrastructure, Transport, Regional Development and Local Government improve
accountability to the Parliament for the Roads to Recovery Program by setting
and reporting in its departmental Annual Report against an effectiveness
target for the program.
DITRDLG Response: Agree.
|
4.
|
ANAO recommends that, given the importance to both
the Roads to Recovery and Strategic Regional Programs of Local Government
Authorities maintaining their own level of expenditure on roads, the
Department of Infrastructure, Transport, Regional Development and Local Government:
a) obtain
greater assurance over the accuracy of own source roads expenditure reported
to it by Local Government Authorities by requiring these figures to be
included in the scope of the Audit Certificate included with each Authorities’
Annual Report on the use of program funds; and
b) develop a more
effective range of sanctions to apply in circumstances where own source
expenditure has not been maintained, with a particular focus on those Local
Government Authorities that frequently fail to maintain their annual
expenditure and/or that do not make up shortfalls in later years.
DITRDLG Response: Agree.
|
The Committee’s review
9.14
The Committee held a public hearing on Monday 21 June 2010, with the
following witnesses:
- Australian National
Audit Office (ANAO); and
- Department of
Infrastructure, Transport, Regional Development and Local Government (DITRDLG).
9.15
The Committee took evidence on the following issues:
- expenditure
maintenance requirements;
- data quality;
- reporting;
- strategic planning;
and
- specificity of recommendations.
Expenditure maintenance requirements
9.16
The ANAO noted that, to deter cost shifting from Local Government Authorities
(LGAs) to the Commonwealth under the R2R program, LGAs were expected to
maintain the level of their own source expenditure on maintenance and
construction of local roads.[13] However, the ANAO noted
that DITRDLG has adopted an administrative practice of waiving this expenditure
requirement ‘where a satisfactory explanation has been provided and [asking]
that the shortfall be made up in later years.’[14]
9.17
The Committee noted that DITRDLG has never refused such a request from a
LGA and asked DITRDLG to provide reasons for these decisions. The Department
explained that the decision is determined on the information supplied by the
LGA for the request and admitted that the process could be tightened:
... if the work has not proceeded for a particular reason and
it is reasonable or if the council has not expended its money in the six months
after receiving it and there is a good enough reason, then the department will
be inclined to provide a waiver. It is true that no waiver was refused during
the life of the programs that this audit was looking at, but ... we are
seriously looking at how those sanctions might be better applied to deal with expenditure
maintenance.[15]
9.18
The Committee observed that there had been a distinct improvement in
some of the breaches and waivers of expenditure maintenance requirements from
2005-06 to 2008-09. The Committee noted the halving of the total deficiency and
asked DITRDLG how the improvements had been achieved. The Department told the
Committee that implementation of the recommendations from a previous ANAO
report had contributed to the improvement.[16] DITRDLG also cited
improved communications between the Department’s team and LGAs and indicated
that LGAs have gained familiarity with the processes and requirements of the
program.[17]
Data quality
9.19
The ANAO found that the reporting of own source expenditure by LGAs has
been prone to error for a number of reasons, calling into question the accuracy
of DITRDLG figures regarding compliance with expenditure maintenance
requirements.[18] The Committee asked the
ANAO and the Department to clarify its concerns regarding the accuracy of the
figures.
9.20
The ANAO identified the self-reporting nature of the process as a major
concern:
... to date those figures only report those councils which
are actually acknowledging to the department that they have not met their
obligations. ... In general people do not say they have not met something when
they have; the error goes the other way.[19]
9.21
DITRDLG identified another concern as the reference amount used by LGAs
to determine their own source expenditure requirement.[20]
The reference amount is a ‘moving average’ and changes over time as the LGAs’
road expenditure changes.[21] The Department explained
that the changes in the reference amount of individual councils distorts the
aggregated data:
So in some councils they can be considered to be meeting
their expenditure maintenance obligation today by spending much less than they
were spending in the first year of the program. What we are saying is that just
the percentage of councils that meet the requirement does not tell the full
story because the requirement has got easier over time, but also the way that
councils can report against that has got easier as well, so that does not give
you the full picture.[22]
9.22
The Committee asked what DITRDLG has done to improve the accuracy of the
data collected on own source expenditure. The Department told the Committee
that it has taken steps to more precisely define the reporting requirements for
the current R2R program.[23] DITRDLG has also
adjusted the formula used to calculate its own source revenue figure. The
figure was previously calculated by averaging the previous four years own
source expenditure or taking the highest and lowest figure.[24]
The Department now provides LGAs with a third option which includes an
escalation factor to accommodate those councils experiencing a loss of revenue:
If a council’s own source revenue declines, the ready
reference amount can be adjusted downwards accordingly. The Department’s view
is that it would be unfair to require a council to maintain its own source
expenditure on roads at a fixed level if its own source revenue is declining.[25]
9.23
The Committee expressed some concern that allowing LGAs to choose the
method of calculating the reference amount could open the system to abuse.
DITRDGL reminded the Committee that the aim of the program was to facilitate
road works in regional areas by providing funding to LGAs through a simple
process that was not onerous for councils to administer.[26]
The Department assured the Committee that appropriate checks are in place:
It does provide flexibility, and the department does actually
check off on the choice made by a council. It is not arbitrary. We agree that
that is the approach that a council will take.[27]
Reporting
9.24
The ANAO noted that in 2008-09 the Portfolio Budget Statement (PBS)
required DITRDLG to report against the key performance indicator of ‘efficient
and effective management’ of the R2R Program.[28] The target was that the
program be ‘administered in accordance with relevant legislation, published
guidelines and ANAO guidance’.[29] The ANAO found that
DITRDLG’s 2008-09 Annual Report did not mention this indicator.[30]
9.25
The Committee asked DITRDLG why this information had not been included
in the 2008-09 Annual Report and whether or not it would be included in the
2009-10 Annual Report. The Department was unsure why it had not been included
in the 2008-09 Report and assured the Committee the information will be
included in the 2009-10 Report.[31]
9.26
The Committee notes with some concern that the indicator is included in
the 2009-10 Report but that there is no clear indication of how the indicator
was measured. The Committee also notes that although it has been reconfigured, the
information included in the 2009-10 Report is similar to the information
included in previous reports and does not address the concerns raised by the
ANAO.
9.27
Overall, the ANAO found that the Annual Program Reports to Parliament
were neither timely nor effective and recommended that the Department improve
accountability to the Parliament by ‘setting and reporting in its departmental
Annual Report against an effectiveness target for the program.’[32]
The Committee asked DITRDLG what steps have been taken to implement this
recommendation and improve the standard of reports to Parliament.
9.28
DITRDLG advised the Committee that it is undertaking a review of the
administrative arrangements and, in the course of that review, will develop an
effectiveness target for the program. The Department added that the review will
be completed by April 2011 and the results will be included in the Annual
Report for 2010-11.[33]
Strategic planning
9.29
Committee Members cited anecdotal evidence indicating that there is a
flurry of road maintenance work in communities just before the end of the
financial year suggesting that LGAs are not taking a strategic approach to the
delivery of road works. The Committee asked DITRDLG if there was evidence of a
planned approach by LGAs. The Department pointed out that local roads are of
immediate concern to LGA constituents and that the evidence indicates that LGAs
are concerned to use their funding effectively:
The councils have a very strong vested interest in the
quality of the road network in their council area. I would say that they have a
very strong interest in spending the money wisely.[34]
Specificity of recommendations
9.30
The Committee raised a general concern with the ANAO regarding the
specificity of its recommendations. Members of the Committee voiced the opinion
that more detailed recommendations would provide better guidance for
departments.
9.31
The Auditor General replied that the ANAO has found it more effective to
deliberately focus on a number of key issues arising from each audit.[35]
The Auditor General told the Committee that the ANAO has also become ‘outcomes
orientated in our recommendations rather than articulating a particular
process’.[36] Using the example of the
R2R Program, he demonstrated to the Committee that the development and
implementation of new policy and procedures requires lengthy consultation with
all stakeholders to ensure an effective result.[37]
This needs to be undertaken by the department concerned if workable solutions
to the issues identified by an audit are to be put in place.[38]
Conclusion
9.32
The Committee acknowledges that there has been a distinct improvement in
the noncompliance figures with regard to expenditure maintenance requirements
for the R2R Program. However the inconsistencies identified by the audit in the
quality of data used to measure the efficiency and effectiveness of the program
are of concern to the Committee.
9.33
The Committee notes that DITRDLG has agreed to implement all of the ANAO
recommendations and notes the Department’s assurance that future Annual Reports
will provide the Parliament with a more accurate assessment of the Program. The
Committee will keep this matter under review.