Chapter 3
Infrastructure and Transport portfolio
3.1
This chapter contains the key issues discussed during the 2013-14 Budget
Estimates hearings for the Infrastructure and Transport portfolio. A complete
list of all the topics discussed, and relevant Hansard page numbers, can be
found at appendix 4.
Department of Infrastructure and Transport
3.2
The committee heard evidence from the Infrastructure and Transport
Department (the department) on Wednesday, 29 May 2013. The hearing
was conducted in the following order:
- Corporate Services;
-
Infrastructure Australia; and Nation Building—Infrastructure
Investment;
-
Australian Rail Track Corporation
-
Office of the Inspector of Transport Security;
-
Office of Transport Security;
-
Aviation and Airports;
-
Airservices Australia;
-
Civil Aviation Safety Authority;
-
Australian Transport Safety Bureau;
-
Australian Maritime Safety Authority;
-
Surface Transport Policy; and
-
Policy and Research.
Corporate Services
3.3
The committee asked the department to provide an indication of when the
government's response to the Senate Rural and Regional Affairs and Transport
Reference Committee's Aviation Accident Investigations report, which was
tabled in the Senate on 23 May 2013, will be provided. The committee is mindful
that the three month time period for government responses, as outlined in Senate
Resolution 42(1)[1],
will fall during the upcoming caretaker period.[2]
3.4
The Secretary, Mr Mike Mrdak told the committee:
...I am not in a position here today to give you an exact time
frame as to when the minister and government will formally respond to the
report... we are all very conscious of the fact that with the date of the federal
election being proposed for 14 September and caretaker mode notionally starting
on around 12 August that would fall within the normal three-month period. I can
only say to you that the government is giving this serious and urgent
consideration and looking to expedite its response as best it can.[3]
3.5
The committee sought an explanation from the department as to why
answers to questions on notice from Additional Estimates were provided seven
weeks late. Mr Mrdak advised the committee that the department did not
meet its timeframes to provide draft responses to the minister's office.[4]
3.6
The committee discussed the rate of unscheduled absences amongst staff.
Officers advised that the average rate of unscheduled absences to 30 June 2012
was 14 days per full-time equivalent employee. Mr Mrdak also explained
that the rate of unscheduled absences is not uniform throughout the department,
as 'there are certain areas of the department, which have higher rates of
unscheduled absences than others'.[5]
3.7
The committee asked for an update on the appointments that have been
made to the Moorebank Intermodal Board. Mr Wood, General Manager Rail and
Roads, explained that the appointments have been made in two tranches. Firstly,
five appointments were made in December 2012 and included Dr Kerry Schott,
Chair; Ms Claire Filson, Director; Mr Ray Wilson, Director; Mr Stephen
Williams, Director; and the Hon Andrew Fraser, Director. The committee were
told the remaining four appointments will be announced in due course by the
Minister for Infrastructure and Transport and the Minister for Finance and
Deregulation.[6]
Nation Building—Infrastructure Investment and Infrastructure Australia
3.8
The committee sought an update on the Northern Territory Regional Roads
Productivity Package, which was announced on 3 August 2012. Officers explained
that they are awaiting detailed project proposals reports and cost estimates from
the Northern Territory Government. Mr Jaggers, Executive Director, explained
that the Northern Territory government will need to undertake significant
planning 'between now and when those projects can start construction... [The]
planning process we would expect for all projects would take at least a year or
two'.[7]
3.9
In continuing interest from previous estimates hearings, the committee
sought an update on the following infrastructure projects:
-
Bruce Highway;
-
Roper Highway;
-
Pacific Highway;
-
upgrade of the Yeppen South floodplain;
-
Mackay ring road;
-
Haughton River Bridge upgrade;
-
Hume Highway pricing trial;
-
Bolivia Hill, New England Highway;
-
Cross River Rail Project;
-
Northbridge project;
-
Swan Valley bypass;
-
East-West road project;
-
Townsville Port;
-
West Connex project;
-
Parramatta Epping rail link;
-
Huon Highway;
-
Summerleas Road;
-
South Road upgrade;
-
Midlands Highway;
-
Brooker Highway;
-
Brisbane Cross River Rail; and
-
the Warrigal Road to Clyde upgrade.[8]
3.10
The committee asked Infrastructure Australia to explain its budgetary
allocation and staffing arrangements arising from the infrastructure finance
reform measure contained in the Tax Laws Amendment (2013 Measures No.2) Bill
2013. Mr Deegan, Infrastructure Coordinator, told the committee that a
resourcing plan is being developed to identify what staffing arrangements will
be required once the legislation has been passed by Parliament.[9]
3.11
Officers told the committee that the Australian Government has
contributed $4 million to the Western Australian government's light rail
planning study which is currently underway. Ms O'Connell, Deputy Secretary,
advised the committee that there is a provision for the Federal government to
allocate further funding for public transport projects in Perth.[10]
3.12
The committee discussed the National Urban Policy Conference held in
Sydney on 16 and 17 May 2013, which was convened by the Australian Housing and
Urban Research Institute in partnership with the Australian Government. Of
particular interest was a presentation by Mr Lewis Atter, Global Head,
Transport Economics and Policy, KPMG, who argued that individual infrastructure
projects should be considered and evaluated within a broader context rather
than as a single project.[11]
In response, Mr Deegan stated:
...without necessarily blowing the trumpet of my council, what
we have sought to do is to take a broad approach to where we are going, so a
national port strategy has been endorsed by the Council of Australian Governments,
a national land freight strategy, which is working its way through, and a
public transport or city transit national strategy that we are well advanced
in... we think these individual projects should be considered as part of a
broader network, and so these broader issues are considered at the same time
rather than just project by project. Indeed, we think it is one of the flaws of
the system to date.[12]
3.13
The committee discussed the funding commitments contained in the Nation
Building 1 and 2 programs for 2012-13 and 2013-14, which included the following
projects:
- Program Investment;
-
Black Spot;
-
Heavy Vehicle Safety and Productivity;
-
Roads to Recovery;
-
Improving Local Roads; and
-
Improving the National Network.[13]
3.14
The committee sought an overview of the feasibility planning for the PortLink
project in Kalgoorlie, Western Australia. Mr Wood explained that the funding of
the project is split between the Australian Government, which has provided of
$2 million, and the Western Australian government, which has provided $5 million.
The expected aims of the project are to:
-
investigate the feasibility and viability of an intermodal
terminal at Kalgoorlie;
-
develop a plan to realign the freight rail system from the centre
of Kalgoorlie to the outskirts;
-
plan to upgrade the Goldfields Highway between Wiluna and
Meekatharra;
-
develop a cost-benefit analysis regarding a bypass of Kalgoorlie;
and
-
develop long-term plans for the road and rail corridors linking
Kalgoorlie and the goldfields to the Mid-West and to the Pilbara region.[14]
3.15
The committee also discussed the following topics:
-
the Western Australian Government freight strategy;
-
the national port strategy;
-
tolls on motorways;
-
the Regional Infrastructure Fund;
-
the funding and viability of the Abt Railway in Tasmania; and
-
the electrification of the Gawler rail line.[15]
Australian Rail Track Corporation
3.16
The committee discussed the Yarraman Creek railway crossing. Mr
Fullerton, Chief Executive Officer, told the committee that a preliminary
review has found that the culvert at Yarraman Creek needs to be replaced. The
Australian Rail Track Corporation (ARTC) has a budget of $1 million in 2013-14 to
engage engineers to design and construct a new culvert which addresses the
current problem of flooding from debris blocking the culvert during times of
heavy rainfall.[16]
3.17
The committee asked officers to explain the ARTC's advanced train
management system. Mr Fullerton explained that the ARTC has been working in
association with Lockheed Martin to develop the technology to be placed
on-board trains, which can intervene and force locomotives to reduce its speed
or stop completely. The system is being trialled on the South Australian rail
network, with the aim to develop the technology's level of reliability before it
is rolled out on every rail network in Australia.[17]
3.18
The committee also discussed the following topics:
-
the Southern Sydney freight line;
-
the duplication of freight lines; and
- the Hunter Valley Rail Corridor Air Quality Report.[18]
Inspector of Transport Security and the Office of Transport Security
3.19
The committee sought an update on whether any assessments of offshore facilities
had been conducted. Mr Dreezer, General Manager, told the committee that no assessments
of offshore facilities have been made since 2007. Instead the department has
been working with the industry to develop alternative audit and inspection regimes,
which they envisage being completed by the end of the year. Mr Mrdak added
that the challenge the department faces has been 'to find a workable solution
that ensures compliance... recognises our limited resources and the difficulty of
accessing a number of these facilities'.[19]
3.20
Officers told the committee that the department has established a
government industry group through the oil and gas security forum to review the
following issues:
- the size of offshore zones;
- communication with maritime users;
- the mutually agreed approach to safety and security;
- developing a pathway to prosecute should an incursion of a zone
occur; and
- the enforcement and compliance options.[20]
3.21
Officers went on to explain that an agreement has been made between
industry, the Office of Transport Security and relevant government agencies to
run a series of exercises to test whether a one-stop shop approach would work
in the event of an incident, which includes using the Australian Government
Crisis Coordination Centre and an 1800 number. Mr Retter, Executive Director,
told the committee that:
...we are confident it [the one-stop shop] will work, but also
to give us some efficacy in terms of the numbers and types of incidents that
might require the Commonwealth to respond with the appropriate agency.[21]
3.22
The committee asked officers to provide an update on the arrangements
being made in relation to the establishment of Australia's first fully private
airport near Toowoomba. Mr Wilson, Deputy Secretary, explained that the airport
'will be required to meet the same level of standards, subject to what aviation
services it provides, as any other regulated airport in Australia.[22]
Aviation and Airports
3.23
The committee discussed the management of federal airport leases
specifically in relation to Brisbane Airport and the perceived lack of action
regarding the development of a parallel runway. Mr Mrdak, explained that:
Over the last few years, the major development plan for the
project has been lodged and approved, the various environmental assessment
processes completed and works are underway on the development.[23]
3.24
The committee sought an update on Avalon Airport in relation to the
construction of an international terminal. Mr Borthwick, Acting Executive
Director, told the committee that the department and the Department of Defence
are currently negotiating with Avalon Airport to amend the lease, which governs
the airport's site. Once the lease has been amended the development process for
the international terminal will commence.[24]
3.25
Officers also told the committee that Avalon Airport has initiated
discussions with the department and Custom, Immigration and Quarantine (CIQ)
agencies regarding the possible level of service that will be required. Mr
Borthwick, explained that until the airport reaches an agreement with an
airline to provide international services, it is difficult to determine what
level of CIQ resources are required, as it will depend on the nature and type
of services that need to be accommodated.[25]
3.26
The committee asked officers to explain why under the Adelaide Noise
Amelioration Program the Saint Nicholas Greek Orthodox Church in Adelaide was
allocated $5 million funding in the 2013-14 Budget. Mr Mrdak told the
committee that an Australian Noise Exposure Index (ANEI) is produced annually
at Adelaide Airport, which models noise exposure over a period of time. He went
on to explain that a review of the 2011 ANEI identified the Saint Nicholas
Greek Orthodox Church as being eligible for the Adelaide Noise Amelioration
Program due to the growth of air traffic and the expansion of the noise contour.[26]
3.27
Mr Wilson provided the following clarification in relation to the
funding allocated under the Adelaide Noise Amelioration Program for the Saint
Nicholas Greek Orthodox Church:
...the church will not be receiving the funding. The department
is receiving the funding and will contract the work on behalf of the church...it
is not the case that we are granting the church $5 million. The works will be
undertaken under contract to the department.[27]
3.28
In continuing its interest from previous estimates hearings, the
National Airports Safeguarding framework was discussed. The committee were
interested in the extent of support within the Standing Council on Transport
and Infrastructure regarding the National Airport Safeguarding Framework
Guideline A proposed alternate noise metrics. Mr Mrdak explained that Western
Australia and New South Wales have indicated their opposition for Guideline A
to be used for strategic planning purposes.[28]
Airservices Australia
3.29
The committee heard that Airservices Australia in conjunction with the
Department of Defence will procure and implement a new integrated air traffic
management platform. Ms Staib, Chief Executive Officer, told the committee that
a memorandum of cooperation has been signed with the Department of Defence, as
they work together to finalise the request for tender, which will be released
to industry by the end of the current financial year.[29]
3.30
Officers told the committee that Airservices Australia was recently
ranked second by the Civil Air Navigation Service Organisation (CANSO), which
undertakes an international benchmarking study of air navigation service providers'
safety management systems.[30]
Annually CANSO compares 28 countries against the following metrics:
- loss of separation rates;
- runway incursion statistics; and
- the maturity of the Safety Management System.[31]
3.31
The committee asked officers to outline the findings of the independent
review of air traffic controller numbers carried out by Nav Canada.[32]
Ms Staib told the committee the report found that Airservices Australia had the
appropriate number of air traffic controllers but it could work more flexibly
and smarter in its future workforce planning.[33]
3.32
In continuing its interest from previous estimates hearings, the
committee sought an update on the progress of the Perth Airport strategic plan
and roadmap. The standard terminal arrival speeds initiative was implemented in
March 2013. Mr Hartfield explained how the standard terminal arrival
speeds works:
...all the aircraft flying in are actually flying at
standardised speeds if they are the same type of aircraft, which gives a
certain level of predictability and consistency for the controllers...aimed at
minimising the time aircraft either spend on the runway or closing the gap
between aircraft so that we can fit more on.[34]
3.33
The committee also discussed the following topics:
- opening new services at Broome and Port Headland;
-
fatigue management of air traffic controllers;
- reoccurring training requirements;
-
information sharing with other air traffic control agencies; and
- the process of handling noise complaints.[35]
Civil Aviation Safety Authority
3.34
The committee sought an explanation regarding the apparent increase in
the number of senior management positions since 2006. Mr McCormick, Director of
Aviation Safety, explained 'we are shifting the focus to the front end of the organisation
as best we can'.[36]
3.35
The committee raised the perceived fear within the aviation industry of
retribution for speaking out against the Civil Aviation Safety Authority (CASA).
Mr McCormick, told the committee that he was:
...at a lost to understand this... no one has brought anything to
me or to my industry complaints commissioner to complain about bullying or
harassment.[37]
3.36
He also gave the following guarantee that 'if anybody threatens
retribution from within CASA or carries out retribution we will take action'.[38]
3.37
The committee also discussed the following topics:
- Robinson 44 helicopters;
- the development of CASA's aviation safety surveillance tool Sky
Sentinel;
- incidents of electronic devices being used on aircraft;
-
regulation of unmanned aerial vehicles;
-
fatigue management regulations; and
- CASA's taxi expenditure.[39]
Australian Transport Safety Bureau
3.38
The committee sought an explanation from officers in relation to the Australian
Transport Safety Bureau's (ATSB) budget position and the reduction in funding for
2013-14 and the forward estimates. Mr Dolan, Chief Commissioner, told the
committee that:
...the only response given in the construct of the budget of
our organisation to those sorts of financial pressures is to reduce our staffing
over time. That means that we have to be very focused on what matters we choose
to investigate in the future, conscious of the risk of missing something
important to safety, and in some cases we may need to constrain an
investigation because of the call on our resources.[40]
3.39
Officers told the committee that due to the recent rail reforms, the ATSB
has acquired overall national responsibility for rail investigations. Mr Dolan
expects that the increase in responsibility will also increase the ATSB's revenue
source for this year, as the costs of investigations will be recovered directly
from states.[41]
3.40
Officers were asked to comment on the findings from the committee's Aviation
Accident Investigations report, specifically, if they had decided to reopen
the investigation into the ditching of Pel-Air and if they will retrieve the
cockpit voice recorder. Mr Dolan told the committee that:
The recommendations that came out of the committee's report
as they referred to ATSB as an independent agency will be reviewed by the
commission of the ATSB...so it is not just a decision for me but for the three of
us acting collectively in accordance with our legal responsibility.[42]
Australian Maritime Safety Authority
3.41
The committee discussed Marine Orders Part 3, which outlines the
eligibility requirements for the Australian Maritime Safety Authority (AMSA)
Certificates of Competency. Officers explained that AMSA certificates are
internationally recognised under the Standards of Training, Certification and
Watchkeeping (STCW) conventions. Certificates that are issued by Australian states
are not internationally recognised unless AMSA has provided formal endorsement
that it meets the STCW conventions.[43]
3.42
Mr Kinley, Acting Chief Executive Officer, went on to explain that:
...we have not always issued those endorsements to every state
certificate because some of the certificates...issued under previous requirements
have not fully complied with STCW requirements. One of the things that we are
hoping to see...is the brining of all of the certificates issued under the new
national system to a level where we will be able to give them the equivalent
endorsements under the STCW convention.[44]
3.43
The committee sought information from officers regarding AMSA's role in
regulating vessels that transport livestock. Officers explained that AMSA must
issue, under Marine Order 43, compliance certificates for any ship carrying
livestock from Australia which is in addition to a vessel's seaworthiness. AMSA
have commenced a review of Marine Order 43 and are currently consulting with
the industry regarding any proposed amendments to the order. The review is
expected to be completed within six months.[45]
Surface Transport Policy
3.44
The committee sought an update on the new shipping reforms, which came
into effect on 1 July 2012. Ms Zielke, Executive Director, advised that:
...the licencing framework...is progressing well at this stage.
It is still early days though in relation to the reforms... we have also received
inquiries in relation to access to the tax incentives that will come into
effect at the end of the financial year... another part of the reforms was the
establishment of Maritime Workforce Development Forum. Over the last few months
the forum has produced a census in relation to the maritime skills...and an
initial workforce development strategy has also been released.[46]
3.45
The committee also discussed the following topics:
-
transitional general shipping licences;
- crew manning levels of ships; and
-
the Australian Sea Freight 2010-11.[47]
Policy and Research
3.46
The committee discussed the Keys 2 Drive Program in relation to the
funding allocated in 2013-14. Ms O'Connell explained that the program, which
commenced in 2007-08, will conclude at the end of 2013-14. The committee heard
that the program to April 2013, has had nearly 1200 driving instructors
accredited to deliver the program with almost 170 000 free lessons provided to
learner drivers.[48]
3.47
The committee asked whether the merger of the Major Cities Unit (MCU)
into the Policy and Research division would affect their mission, role,
functions or performance. Mr Collett, General Manager, explained that in the
short-term MCU did not envisage any significant changes to their role. Rather
the move provides additional Senior Executive Service officers to support MCU's
work.[49]
3.48
The committee discussed in relation to the decision by the Western
Australian government to develop a marina at Point Peron, the role of the National
Urban Policy to provide a level of protection to local communities. Mr Collett explained
that the National Urban Policy considers issues in a citywide context rather
than on a project‑by-project basis.[50]
3.49
The committee sought an update on the number of urban public transport
projects that were announced as a part of the Budget. Mr Mrdak told the
committee that the Budget provided funding for two major metropolitan rail
projects, which are the Brisbane Cross River Rail project and Perth City Link
project.[51]
3.50
The committee also discussed the following topics:
- project assessments guidelines;
-
the COAG Reform Council Capital City Strategic Planning
Systems Report;
-
the South Australian Government announcement of the structure
plan for the Playford Growth Area;
-
the Aviation White Paper; and
- the development and implementation of the NASAG reforms.[52]
Navigation: Previous Page | Contents | Next Page