CHAPTER 2
Employment portfolio
2.1
This chapter summarises certain key areas of interest raised during the
committee's consideration of the budget estimates for the 2015–16 financial
year for the Employment portfolio. It follows the order of proceedings and is
an indicative, not exhaustive, account of issues examined.
2.2
On 1 and 2 June 2015, the committee heard evidence from
Senator the Honourable Marise Payne, Minister for Human Services,
representing the Minister for Employment, along with officers from the Department of Employment
(the Department) and the following agencies responsible for administering Employment
policy:
-
Fair Work Commission;
-
Office of the Fair Work Ombudsman;
-
Safe Work Australia;
-
Asbestos Safety and Eradication Agency;
-
Workplace Gender Equality Agency; and
-
Fair Work Building and Construction.
2.3
Officers from Comcare attended the hearing on 2 June 2015 but were not
called to give evidence before the hearing adjourned.
Cross-portfolio matters
2.4
The committee heard evidence for approximately two hours and 45 minutes.
Enterprise bargaining agreement (EBA)
2.5
The Secretary of the Department, Ms Renée Leon, advised the committee that
negotiation continued following the unsuccessful EBA ballot in December 2014, but
another formal offer had not yet been put to staff. [1]
2.6
The committee heard evidence in relation to the Australian Government
Public Sector Workplace Bargaining Policy and the requirement to offset
remuneration increases with genuine productivity gains.[2]
The committee discussed examples of the ways in which these gains might be
achieved, such as requiring employees to work an additional six minutes per
day.
Shared Services centre
2.7
Ms Leon provided an update on the performance and staffing of the shared
services centre, which has expanded its provision of services to other
departments and agencies including the Australian Electoral Commission, the
Australian Taxation Office and the Department of the Prime Minister and
Cabinet.[3]
Outcome 1
2.8
The committee heard evidence for approximately five hours and 27
minutes.
jobactive
2.9
The committee examined the transition from Job Services Australia to
jobactive, which will operate under a revised fee structure with greater
emphasis on employment outcomes rather than job seeker activities and
administrative payments.[4]
The committee also discussed the tender process for individual employment
service providers.
National Work Experience Programme
2.10
The Group Manager, Labour Market Strategy Group, Ms Margaret Kidd, told
the committee that the National Work Experience Program 'provides an
opportunity for job seekers to volunteer to do four weeks work experience for
up to 25 hours per week in businesses'.[5]
Job seekers receive $20.80 per fortnight to cover their expenses. There is no
cost to the employer, and wage subsidies may be available if the placement
leads to ongoing work.[6]
Outcome 2
2.11
The committee heard evidence for approximately two hours and 53 minutes.
Wage growth
2.12
The committee heard that wage growth is at its slowest point since the
wage price index began in 1997, having risen 2.3 per cent in the year ending
March 2015, 3.1 per cent per annum over the past five years and 3.5 per cent
per annum over the past 10 years.[7]
Wages are expected to increase at approximately the same rate as inflation over
the next three financial years.[8]
Commonwealth cleaning guidelines
2.13
The committee sought information about effect of the abolition of the
Commonwealth cleaning guidelines. Ms Leon told the committee that 'the pay that
is being offered to the cleaners is a result of the contracts that are being
entered in to'.[9]
Ms Leon advised that departments entering into new cleaning contracts would
abide by the Commonwealth procurement guidelines, including the principle of
value for money.
Office of the Fair Work Ombudsman
2.14
The committee heard evidence for approximately four hours and 11
minutes.
EBA
2.15
The Fair Work Ombudsman (FWO), Ms Natalie James, advised the committee
that while no formal EBA offer had been made to employees, negotiations continued
and a draft offer was being revised in response to feedback from bargaining
representatives. The feedback was in relation to a range of issues including
grandfathering of the remote localities allowance and the level of wage rises.[10]
Apprentice workers
2.16
The committee heard that the Office of the FWO is in the process of
auditing 700 businesses that employ apprentices. A campaign focusing on the automotive,
electrical services, manufacturing, meat, retail trade and personal services
industries seeks to address problems such as apprentices being underpaid, not
receiving overtime and not being given payslips.[11]
The Executive Director, Proactive Compliance and Education, Ms Lynda
McAlary-Smith, told the committee:
One of the things we are doing as part of the apprenticeship
campaign is focusing specifically on the businesses who have apprentices in
their first year of apprenticeship, so that we can get in with an early start
and make sure they get off on the right foot.[12]
2.17
There is a separate national campaign targeting construction industry
workers, including apprentices.[13]
Chia Tung Development
2.18
The committee discussed Chia Tung Development, which was found to have
underpaid 43 foreign workers. Asked why the FWO did not prosecute the company,
Ms James explained:
This was a case where the employer engaged immediately with
us, was prepared to make admissions and paid back the money reasonably
promptly. So we agreed with them to enter into an enforceable undertaking in
order to put that $873,000 back into the hands of the workers reasonably
quickly, within two months. A litigation would have taken much longer, maybe 12
months. So in this case, we decided that it was not one that we would put
through the litigation route.[14]
Temporary work visas
2.19
Asked about monitoring of 457 visas, Ms James advised the committee that
between 1 July 2014 and 31 March 2015, the Office of the FWO had investigated a
total of 1 496 visa holders employed by 636 entities. Preliminary
investigations suggested that in 302 cases, or 20 per cent, either the
nominated position or the nominated salary was not in accordance with the visa.[15]
These cases are referred to the Department of Immigration and Border Protection
(DIBP) for investigation.
Fair Work Building and Construction
2.20
The committee heard evidence for approximately four hours and 50
minutes.
Proceedings and compulsory powers
2.21
The Director of Fair Work Building and Construction (FWBC), Mr Nigel
Hadgkiss, advised the committee that as of 30 April 2015, FWBC had 48
proceedings before the courts: 19 in relation to right of entry permits, 17 in
relation to coercion, 8 in relation to unlawful industrial action and 2 in
relation to wages and entitlements.[16]
Mr Hadgkiss also outlined the procedure for utilising his compulsory powers and
advised that he had exercised these powers, which he described as a 'last
resort', on 14 occasions since 1 July 2014.[17]
Chia Tung Development
2.22
The committee sought information about FWBC's investigation of a breach
of right of entry at the Chia Tung Development site in New South Wales. The
investigation was discontinued following referrals by FWBC to the FWO and the DIBP.
Mr Hadgkiss explained: 'when I became aware of the seriousness of the situation
at that location, I deemed it was in the public interest that we should cease
the investigation'.[18]
Activity based costing
2.23
Asked about the cost of investigations and court cases, Mr Hadgkiss
responded that he would only be able to provide external legal costs. He
advised the committee that he was endeavouring to introduce an 'activity based'
costing methodology taking into account the work of FWBC inspectors and
lawyers.[19]
Intimidation of FWBC staff
2.24
The committee also heard evidence in relation to alleged intimidation
and harassment of FWBC staff. Specifically, Mr Hadgkiss provided evidence that
a female investigator was subjected to numerous harassing and sexually
derogatory telephone calls by two male CFMEU officials, and that on one
occasion, the same individuals attempted to stop her car by striking her car
with a tree branch.[20]
Safe Work Australia
2.25
The committee heard evidence for approximately 16 minutes.
Chemical labelling
2.26
The committee discussed labelling requirements for hazardous chemicals
such as agricultural and veterinary medicine. The Branch Manager, Work Health
and Safety Network, Ms Julia Collins, explained that there is a five year
transition period from Australian Pesticides and Veterinary Medicines Authority
(APVMA) labelling to the Globally Harmonised System (GHS) of classification. Ms
Collins acknowledged objections to this change, but stated that it was Safe
Work Australia's view that the APVMA labels were 'inadequate for workplace
health and safety risk assessment'.[21]
From 1 January 2017 all Australian labels must meet GHS requirements and
penalties will be imposed for noncompliance.[22]
Workplace Gender Equality Agency
2.27
The committee heard evidence for approximately 20 minutes.
Methodology review
2.28
Ms Jo Wood, Group Manager, Economic Strategy Group, advised the
committee that the Department had engaged a consultant to assist the working
group reviewing the Workplace Gender Equality Agency's (WGEA) collection,
classification and analysis of data. The consultant's report will be completed
by July 2015, with the working group expected to make recommendations to
government in the second half of 2015. [23]
Equilibrium man challenge
2.29
The Acting Director, Ms Louise McSorley, described the WGEA's latest
campaign, designed to increase flexible work practices for men:
We have got a series of microdocumentaries following five men
as they negotiate flexible work. There are a whole lot of tools for employers
and employees that came off that platform, and they are to assist them
implement and manage flexible work.[24]
2.30
The program will last for six to eight months and is formally supported
by 28 organisations including Telstra, Mirvac, Corrs Chambers Westgarth and
Cisco.[25]
Asbestos Safety and Eradication Agency
2.31
The committee heard evidence for approximately 18 minutes.
National strategic plan for
asbestos awareness and management
2.32
The Chief Executive Officer, Mr Peter Tighe, confirmed that the national
strategic plan for asbestos awareness and management had been signed off by all
Australian states and territories.[26]
Mr Tighe explained that the Agency would now concentrate on implementing the
plan:
Now that it has been signed off, it is our job to reach those
outcomes and continue to report those to the minister. A lot of those outcomes
are about lifting the levels of awareness, best practice, looking at illegal
dumping, looking at the number of disposal sites around—basically gathering all
the information to assist in addressing the problem with asbestos and asbestos
related diseases.[27]
Fair Work Commission
2.33
The committee heard evidence for approximately 33 minutes.
Right of entry permits
2.34
The committee heard evidence in relation to the granting, suspension and
revocation of right of entry permits. The Director of Regulatory Compliance, Mr
Chris Enright, outlined the matters that the Fair Work Commission (FWC) takes
into account when considering an application for a permit, including whether a
person has a criminal history of violent offences.[28]
Navigation: Previous Page | Contents | Next Page