Chapter 2
Strategic Review of the NBN
Background
Purpose of the Strategic Review
2.1
While in opposition, Mr Turnbull made frequent claims that the Coalition
broadband policy could be implemented for a third to a quarter the cost of the
NBN. For example:
FTTN in Europe and North America has been described to me by
those actually building new generation networks as costing between one third
and one quarter of FTTP. Given our relatively high labour costs and the fact
that FTTN’s main virtue is that it reduces the civil works which is mostly
labour, the difference in Australia is likely to be even higher.[1]
2.2
And:
Why can we do it cheaper? Fibre to the node, around the
world, costs between 1/4 and 1/3 of fibre to the premises. That is the
experience in North America and Europe. And in Australia with very high labour
costs the differential would likely be even more.[2]
2.3
Minister Turnbull also repeatedly asserted that the “real” cost of the
NBN would be different to the figures in NBN Co’s Corporate Plan. For example,
he told Tony Jones on Lateline in February 2013:[3]
We're going to do a couple of things. We will do a rigorous
cost/benefit and have a rigorous cost/benefit analysis done, but very quickly
we will ensure that we get a fully transparent and accurate assessment of what
it is really going to cost both in terms of dollars and time to complete the
project on the basis of the Government's strategy and then what it will cost in
terms of dollars and time to complete it on a variation along the lines we've
been proposing and we'll get that up very quickly.
2.4
Launching the Coalition policy on 9 April 2013, Mr Turnbull quantified
the expected saving, saying:[4]
We wouldn’t have gone about this this way and there will be
billions of dollars that Labor has wasted that we cannot recover but we will
save many billions of dollars, at least $60 billion, by taking the approach we
have described in this policy.
2.5
The Coalition’s Broadband Policy included a table labelled “The Choice
at a Glance”:[5]
2.6
The table asserted the likely required funding for the existing NBN was
$94 billion, while estimating required funding for the Coalition plan as $29.5
billion. This inflated estimate for the NBN was achieved by making four
assumptions: that real Average Revenue Per User (ARPU) would not grow as
forecast; that the number of “mobile only” households would be higher than
forecast; that costs would be higher than forecast; and that construction would
take longer than forecast.[6]
2.7
At a hearing of the Joint Committee on the National Broadband Network on
19 April 2013, executives from NBN Co demonstrated that the assumptions
underpinning the Coalition’s $94 billion claim were false.[7]
In particular, they demonstrated that actual costs for the fibre build were
falling and that all other costs were within budget. They also demonstrated
that the calculation of ARPU increase used by the Coalition was wrong. Finally
they noted that the effect of a delay in the rollout would result in a decrease
in peak funding, not an increase.
2.8
However, notwithstanding the falsehoods in the Coalition policy, the
Committee notes that the peak funding amount of the proposed Coalition
plan—$29.5 billion—is approximately “a third” of the inflated $94 billion cost
of the NBN, in accordance with previous statements made by Minister Turnbull.
This would not have been the case, of course, had the proposed Coalition peak
funding amount of $29.5 billion been compared to the $44 billion peak funding
figure in NBN Co’s 2012-15 Corporate Plan, which—as outlined below—was signed
off by the NBN Co Board and independently reviewed by KPMG.
2.9
As mentioned in Chapter 1, the Strategic Review was one of the
commitments made in the Coalition’s Broadband Policy taken to the 2013
election. In announcing the terms of reference of the review the Minister said:
Labor's made shocking mistakes. There are billions of dollars
that Labor has wasted that we will never be able to recover. This has been a
shockingly misconceived exercise...wasteful exercise in public policy. We are
endeavouring to recover value for it and get the job completed as quickly and
cost-effectively as we can. So we need to know, what is the state of the
project right now, accurately...[8]
2.10
A draft of the Strategic Review was provided to Government on 2 December
2013.[9]
Following board approval, a final report was provided to the Minister for
Communications and the Minister for Finance on 12 December 2013. This final
report was released in a heavily redacted form when it was tabled by the
Minister for Communications on the same day.[10]
2.11
Prior to its publication, two comments about the potential conclusions
of the Strategic Review were made publicly: the first by former NBN Co board
member Brad Orgill, and the second by former NBN Co CEO and Executive Director
Mike Quigley.
2.12
In a column in the Australian Financial Review on 4 October 2013, Mr
Orgill said:
Selective data, conservative assumptions and extrapolations
out to 2021 could be formulated to argue why the NBN might have comprehensively
blown out its costs and not achieved its objective. It would be a continuation
of the Coalition's attacks from opposition on NBN management and the board
including threatening a Royal Commission of Inquiry.
2.13
On 2 December 2013, in an address to TelSoc, Mr. Quigley said:
Rates to build the fibre network based on the existing design
and architecture were rising. But those rate increases would not have produced
a cost increase because we had identified and validated, network and design
changes that would have offset those increases. Which is why I find it
incomprehensible to hear the suggestion that the increases in LN/DN rates
should be built into the forward projections and cost reductions that have
already been identified, should not be. Unless, of course, your objective is to
try to confirm a pre-conceived position.
Key findings of the Strategic
Review – Revised Outlook
2.14
The Strategic Review provided a detailed review of the costs and
deployment timing of the existing deployment model for the NBN (called the
Revised Outlook). The Revised Outlook asserted that:
-
The fibre rollout project will take three years longer to
complete than indicated in the Corporate Plan, with a revised end date of June
2024;
-
The Revised Outlook for brownfields Premises Passed at June 2014
is 357,000 compared to 1,129,000 in the Corporate Plan;
-
Delays in deployment and take-up, lower ARPU and higher levels of
non-subscription result in ~$13-14 billion less Revenue to FY21;
-
The Capital Expenditure required will increase from $37.4 billion
to $55.9 billion;
-
The peak funding requirement will be $72.6 billion peaking in
FY24 which is $28.5 billion higher than the Corporate Plan ($44.1 billion); and
-
The Independent Assessment concluded that it is highly unlikely,
in the absence of a government guarantee, that debt funding will be available
from a third party financier in the near to mid-term.
2.15
As will be demonstrated below, these assertions were arrived at by the
use of variants of the same assumptions used by the Coalition in its April 2013
$94 billion claim: higher unit costs, rollout delays, lower growth in ARPU and
fewer premises connected.
2.16
The Strategic Review makes five key findings in relation to the
performance to date of NBN Co. These are:[11]
-
From a forensic perspective, the Independent Assessment found
that no material issues exist within the accounts of NBN Co;
-
The Independent Assessment concluded that, although the Corporate
Plan is based on detailed and quantitative analysis, it is “extremely
optimistic” and very unlikely to be achieved;
-
At 30 September 2013, the rollout of the brownfields FTTP network
was 48 percent behind the planned Premises Passed in the Corporate Plan, with
only 227,483 Premises Passed at that date. Of these premises only 153,977 are
serviceable by NBN Co. The greenfields and Fixed Wireless rollouts are also
behind Corporate Plan;
-
Total Expenditure to 30 June 2013 was 26 percent under the
Corporate Plan at that date. Whilst this is an under-spend relative to the
Corporate Plan, it is significantly ahead of the expenditure which would have
been required in the Corporate Plan to reach the levels of actual rollout
achieved; and
-
The Independent Assessment found that NBN Co has attracted a
committed, motivated, and generally capable group of people who want to do
important, meaningful work. It concluded that the culture and leadership of the
organisation are widely seen to be a major problem, and that the organisation
is currently carrying a level of overhead and headcount predicated on the
achievement of the Corporate Plan, which is in excess of current requirements.
2.17
As noted above, the Strategic Review found the Corporate Plan 2012-15
was based on detailed and quantitative analysis. At the hearing of 17 December,
Mr Korda provided an explanation for the difference between the Corporate Plan
2012-15 and the Revised Outlook:[12]
CHAIR: Can I confirm that the independent assessment
found that the revised outlook analysis is based on a revised and more
realistic review. Could you explain to me what that means.
Mr Korda: What we found in the corporate plan—I will
tie this together—was that, as BCG said, the revenue forecasts were optimistic.
I think deployment was optimistic. I think the level of overheads was
optimistic. The capex was optimistic. So what you get—I think we said—is a very
extremely optimistic corporate plan. We have reviewed each of those line items
based on the facts and have taken a realistic and more prudent view of where we
are at.
2.18
The Strategic Review also considered five alternative scenarios. These
are:
-
Scenario 2 – Radically Redesigned FTTP
-
Scenario 3 – FTTN short loop, FTTB large MDUs
-
Scenario 4 – HFC in HFC footprint
-
Scenario 5 – FTTN & HFC
-
Scenario 6 – Optimised Multi-Technology Mix
2.19
The Section 2.3 assesses the recommended option, the “Optimised Multi
Technology Mix.” However, as will be detailed below, scenarios utilising FTTN
and HFC depend on assumptions about possible outcomes of negotiations for
access to infrastructure and the state of that infrastructure. The assumptions
underpinning these scenarios are not as robust as the data available for the
all-FTTP scenarios (Scenarios 1 and 2).
Conduct and methodology
2.20
The terms of reference of the Strategic Review required NBN Co to report
on:
-
The progress and cost of the rollout and NBN Co’s financial and
operational status;
-
The estimated time and cost to complete the NBN under a
fibre-to-the-premises (FTTP) model (i.e. Government policy prior to 7 September
2013);
-
The estimated cost and time to complete the NBN if variations
were made to the current plan such as increased use of fibre-to-the-node (FTTN)
in established (brownfield) areas;
-
The economic viability of NBN Co under alternative strategies;
-
The implications of capital costs and principles of cost recovery
on wholesale and consumer prices under existing and alternative strategies;
-
Recommendations for organisation restructuring, any amendments to
the construction model and a revised NBN Co strategy to achieve Government
policy objectives; and
-
Any other matters the Chair deems relevant to the strategic
consideration of NBN Co’s present situation and future prospects.[13]
2.21
NBN Co tendered for advisory firms to contribute to the Strategic
Review. Three firms were appointed on 25 October: Deloitte, KordaMentha and the
Boston Consulting Group (BCG). Each performed a different function as part of
the review process.[14]
KordaMentha contributed to the analysis of the NBN operational and financial
performance; BCG reviewed the timing, financials and product offers under
alternative models; and Deloitte provided governance and program management
office services to ensure the Strategic Review met the parameters and deadline
for submission set by the Government.
2.22
At the committee's public hearing in Sydney on 17 December 2013, it was
revealed that the total cost of preparing the strategic review was in the order
of $8 million. This included the cost of the consultancies and NBN Co's
internal resources.[15]
It was also explained that BCG rather than KordaMentha was used for the revenue
estimates “given their international experience.” NBN Co could not provide any
specific expertise BCG had in relation to Australian revenue modelling.
2.23
The strategic review process was led by NBN Co's Head of Strategy and
Transformation, Mr JB Rousselot, and a 'cross-divisional team of internal
employees' working closely with the external consultants on the review.[16]
NBN Co executives told the committee that approximately 25 people were involved
in the review on a dedicated basis, led by Mr Tim Ebbeck, chief commercial
officer at NBN Co. During the course of the review, 280 workshops were held
involving different groups from within NBN Co.[17]
2.24
During the Supplementary Estimates hearing in November 2013, Dr
Switkowski summarised the approach to be used by the strategic review:
The way this review is structured is that there are two substantial
parts, one headed by KordaMentha, which is a forensic analysis of the costs of
NBN Co. to date and expectations of a business-as-usual scenario and associated
costs; then there is another analysis, which will be informed by BCG, as to the
costs and execution issues of an alternative technology path. BCG is
commissioned to do a complete analysis of the technical challenges of rollouts
around Australia, identifying options that extend from fibre to the premises,
fibre to the node, fixed wireless satellite, HFC and 4G wireless. That will all
come together and be integrated by the third of the advisory firms, Deloitte,
and will then constitute the report that the board will present to the
minister.[18]
2.25
For the Revised Outlook, KordaMentha undertook the review of costs and
rollout timeframes, while BCG undertook the review of revenue. At the Committee
hearing on 17 December, NBN Co explained that this decision was made because
the revenue assumptions would be common across all scenarios:
CHAIR: For the independent assessment, why was
KordaMentha used for the costs, but BCG for the revenue? There seems to be a
split in the way it was designed and I am interested in the thinking behind it.
Mr Rousselot: The revenue forecast we had to do was
going to be applied to all scenarios going forward—so, not only the revised
forecasts but also all the other scenarios we are going to have. That is why we
had to have one of the two companies produce the revenue forecast. We selected
BCG to do so, given their international experience. The costs of the revised
outlook were only relevant to the revised outlook, and that is why those were
done by KordaMentha.[19]
2.26
At a doorstop on the day the Strategic Review was announced, the
Minister made it very clear the review was to be “owned” by the board and
management:[20]
That is the most urgent priority, and the reason that we've
asked the board to do it, or the company to do it, and of course it will be
substantially a new board, and there will be a lot of new management there as
well no doubt, is that we want the company to own it. You see, in the past,
this project has been riddled with politics, and the company has been under
pressure to deliver numbers and answers and documents that met the political
priority of the previous government.
What I have said to the company is I just want the plain
unvarnished facts. We do not want spin. We do not want the company to tell us
what they think we might want to hear. We want to know what the real facts are.
And then armed with those facts, then we can make decisions about the future of
the project and Australians will see the actual factual context in which we're
making them. That is terrifically important.
And the reason the company should undertake this is because
we want them to own it. See, you can - there's any number of consulting firms
you can hire, and the NBN Co's hired most of them over the last four years, but
you can hire a consulting firm, they'll come in and write a report. But the
directors, the executives may have no sense of ownership of it. They may - it's
just something that descended from outside.
It's really important that the directors and the management
own this.
Committee analysis – Revised Outlook and Radical Redesign
Preliminary Observations
2.27
The committee notes the heavily redacted nature of the public version of
the Strategic Review. In-depth scrutiny of the Strategic Review's findings with
regards to delays in FTTP deployment (including construction delays), Fixed
Wireless deployment, and financial performance (particularly Direct Operating
Expenditure) is compromised by these redactions.[21]
Of particular concern to the committee is the redacted information on cost per
premises. Cost per premises is used in the Strategic Review as the key
benchmark for the comparative analysis of alternative scenarios.
2.28
The Minister for Communications has refused to release to the committee
(in camera) an unredacted copy of the Strategic Review, on the grounds
of public interest immunity. This was set out in a letter of 17 December 2013.[22]
However, the committee considers that the Strategic Review underpins a
potential Commonwealth investment of more than $40 billion—not including
flagged technology upgrades—and should be made available to the Parliament, in
accordance with the Minister’s many undertakings on transparency and
accountability. This will be discussed further in Chapter 4.
2.29
The Committee notes that the Strategic Review states in its Legal
Notice:
Given the required time frame for the Report’s completion,
NBN Co has relied on the Experts for the matters within their scope of work and
has not independently verified or audited the information presented in the
Report through the work of the Experts.
2.30
The committee asked NBN Co whether the Strategic Review had been subject
to the same independent scrutiny that had been applied to NBN Co’s Corporate
Plans:
CHAIR: Thanks for that, but what I was asking you was
to confirm what was in the legal notice stated in the strategic review—that it
has not been independently verified or audited. I am just asking you to confirm
that is what the strategic review says.
Dr Switkowski: You are asking about our review?
CHAIR: Yes, the legal notice.
Dr Switkowski: It has not had any further
verification.[23]
2.31
At the public hearing on 17 December 2013, the committee put to Dr
Switkowski that without the unredacted information, the committee and the
public will have to take NBN Co's word that the cost assumptions in the
Strategic Review are correct:
Senator LUDLAM: Apart from that, I have never seen so
many blacked-out rectangles on an NBN committee. It is almost as though the
whole operational security mantra has been imported into telecommunications
policy. I know I am being a bit tongue in cheek here, but it is a linchpin of
your entire project, those numbers: the remediation costs and any operational
expenses for keeping it maintained while it falls apart around you.
Dr Switkowski: I agree that those numbers matter. I
can only give you an assurance that they have been determined to the best of
our ability with considerable debate as to what the range of numbers should be
to characterise those costs. They have been incorporated in our models.
Senator LUDLAM: So you cannot tell us what they are,
but can you tell us how you arrived at them? We can ask this of Telstra in 20
minutes and they will tell us that those numbers are commercially sensitive as
well, but you must have landed on a particular number or a range of numbers.
How have you done that? Have you concluded negotiations with the companies
concerned?
Dr Switkowski: Clearly we have not. We have barely
started discussions.[24]
2.32
Despite the difficulties presented by the redactions, the committee
notes that a number of assumptions in the Strategic Review are transparent, or
can be derived from a close reading of the report. The committee has also
collected substantial evidence from committee hearings and relevant secondary
sources.
2.33
Section 2.2 reviews the Revised Outlook (“Scenario 1”) and the Radical
Redesign (“Scenario 2”). This is because these two scenarios are both based on
an FTTP rollout to the full fixed line footprint. It is also because cost
savings identified in Version 13 of the Corporate Plan 2013-16 were included in
the Radical Redesign scenario, and had that plan been used as the base case for
the Revised Outlook a different conclusion would have been reached. This will
be demonstrated below.
Base case used for the Strategic
Review
2.34
The Strategic Review notes that:[25]
For purposes of performance comparison, the Independent
Assessment used the August 2012 NBN Co Corporate Plan (referred to as the
Corporate Plan), which is the most recent Shareholder approved plan.
2.35
NBN Co released its Corporate Plan 2012-15 on 8 August 2012. This plan
noted:
-
Wholesale broadband prices are projected to fall over time in
both real and nominal terms;
-
The Internal Rate of Return (IRR) remains above 7% per annum;
-
Total forecast Capital Expenditure to end of the Fibre
Construction period increased by 3.9%;
-
Construction Commenced or Completed for approximately 758,000
Fibre premises by December 2012; and
-
Fibre Construction period extended by 6 months despite 9 month
delay in Commencement Date.
2.36
The 2012-15 Corporate Plan also noted that there had been changes to the
scope of work since the first Corporate Plan. This included changes to the
design reflecting the Telstra definitive agreements and the Optus HFC
Agreement, and decreases in construction and equipment costs referred to as
“Type 2 Architecture”. These efficiencies are the principal reason capital
expenditure only changed by 3.9 per cent between the 2012-15 Corporate Plan and
NBN Co’s 2011-13 Corporate Plan released in December 2010.
2.37
This issue was discussed during the 11 December hearing:
CHAIR: In developing the 2012-15 corporate plan, NBN
Co. moved to type 2 architecture. Would you explain the changes from type 1
architecture. I suspect Mr McLaren is the lucky respondent.
Mr McLaren: Yes, absolutely. The type 1 architecture
was an initial architecture for the fibre network—this is the passive network,
which we commonly also call the local and distribution network. It was an
architecture we developed for our initial trials that NBN ran in five cities
and commenced in 2011. It used an architecture that essentially relied on what
we call stranded fibre—strands of individual fibres that are deployed and
individually spliced, so quite a lot of fibre splicing has to go on. It is
essentially what the Australian market had been deploying for many years and
was an evolution through that. It also used quite a lot of the technology in some
of our initial learnings that we had seen overseas. So it was very much an
initial deployment, particularly informed by what Verizon were doing in the
United States, which was very much an aerial build. We took a lot of the
learnings from that company and applied it for those trials.
During that period, we had been looking at other options. We
were particularly concerned by the amount of fibre splicing that would be
involved with that architecture. As I said, each individual fibre had to be
sliced, which was not only time consuming; it was very much a cost and resource
issue in terms of getting the number of splices to be able to do it. So we were
looking for ways to reduce that burden in the build. The main change with the
type 2 architecture was to bring in what we call ribbon fibre. That is where we
have 12 fibres in a ribbon and they are all spliced, basically simultaneously,
with some new fibre-splicing machines.
CHAIR: There was a significant cost saving for you in
that process. You said one of the reasons you looked at this was cost savings.
Mr McLaren: Yes cost savings, as I just mentioned,
with the actual splicing itself. We have also been going—
CHAIR: Have you found a way to reduce the cost of the
build?
Mr McLaren: Obviously, we were looking at all options
to reduce the cost of the build through this time. The cost also came down to
how we went through our procurement process at the time. Type 1 was initial
work with our suppliers. We went through a more extensive procurement process
for type 2 and worked with the whole market, and were able to use the savings
that came to that procurement process as well.
2.38
NBN Co submitted its 2013-16 Corporate Plan to shareholder Ministers on
3 July 2013. This plan, known as “version 12,” confirmed the headline figures
for the NBN as set out below, compared to the previous Corporate Plan.[26]
Version 12 of the 2013-16 Corporate Plan was subsequently leaked to the
Australian Financial Review and is available on its website.[27]
Major Operational & Financial Metrics
2.39
Prior to its submission to the previous government, the Corporate Plan
2012-15 was independently reviewed by KPMG. The 2013-16 Corporate Plan was also
independently reviewed by KPMG. This was confirmed during a November hearing of
the Senate Environment and Communications estimates committee. The Secretary of
the Department of Communications, Mr Clarke, noted that:
The department as a matter of course commissioned analysis on
corporate plans on an annual basis.[28]
2.40
Mr Robinson, Deputy Secretary for the Department of Communications,
added that:
I think it is a matter of record that, at least for the last
couple of years, we commissioned KPMG to provide advice.[29]
2.41
The NBN Co board also commissioned Ernst & Young to review the
2013-16 Corporate Plan. This was confirmed during the same estimates hearing:[30]
Senator LUNDY: Did you engage any advisers for the
2012 to 2016 plan?
Mr Payne: For the June draft of the 2013 to 2016
corporate plan the board engaged Ernst & Young to review some of the key
assumptions...
Senator LUNDY: Did that review provide any advice that
the data did not appear to be aligned with the corporate plan assumptions?
Mr Payne: I think, overall, it said that the
experience to date supported the broad assumptions made in the corporate plan.
Senator LUNDY: So the Ernst & Young adviser
reviewing the corporate plan for the 2013 to 2016 plan found that all the
assumptions were correct.
Mr Payne: That was so for the key assumptions that
they looked at. They did not look at everything.
Senator LUNDY: What did they look at? Did they look at
the capital expenditure parameters?
Mr Payne: I do not have the report with me. They
certainly looked at some of the key capital expenditure areas, some of the
revenue assumptions and so on.
Senator LUNDY: Did that review provide any advice that
the actual data did not appear to tally with the corporate plan assumptions on
revenue or capital?
Mr Payne: No. As I said, overall it supported the
assumptions. There were a couple of areas that the report called out that it
was very early days and hard to draw too many conclusions from the data to
date, but overall—
Senator LUNDY: You had an external adviser—and
independent adviser—advise that the 2013 to 2016 corporate plan was consistent
with the performance of the company.
Mr Payne: Certainly on the assumptions, yes.
Senator LUNDY: That was before the report was
submitted to the government.
Mr Payne: Correct.
2.42
Version 12 of the 2013-16 Corporate Plan was received by Government
while Telstra remediation was suspended due to asbestos concerns. Subsequently,
NBN Co sent shareholder Ministers a letter noting that the duration of the
stoppage in remediation work was more prolonged than expected and had put at
risk the deployment targets in the 2013-16 Corporate Plan. Shareholder Ministers
asked NBN Co to resubmit the plan to take these developments into account. NBN
Co prepared a revised Corporate Plan—called ‘version 13’—which was submitted to
the NBN Co Board in September 2013, after Telstra pit work had recommenced in
mid-August 2013. As Mr Payne noted during the 19 November estimates hearing:
I think the board approved [version 12] for lodgement in
June, so it would have gone in at the end of June to the shareholder ministers.
At around that time, you may recall, there were some issues particularly around
remediation ceasing, and so, I think, the company wrote to the shareholder
ministers to say that the short-term targets may need to be revised because
there was expected to be a prolonged cessation in remediation. So the shareholder
ministers asked us to resubmit the plan with that taken into account; hence the
second version in September.[31]
2.43
The “second version” referred to by Mr. Payne—known as ‘Version 13’—is
the most recent version of the NBN Co Corporate Plan, incorporating the effects
of the Telstra stop-work on remediation. NBN Co was asked about this Corporate
Plan at the 11 December 2013 hearing:
CHAIR: Mr Brown, Mr McLaren, Mr Cooney or even Mr
Adcock, was a draft version 13 of NBN Co.'s 2013-16 corporate plan provided to
the board for its meeting on 19 and/or 20 September?
Mr Brown: Each year, as required under the GBE
guidelines, we submit a corporate plan.
CHAIR: Thanks. Now could you answer the question I
asked? Was a draft version 13—1 and 3, comes after 12 and before 14—of NBN
Co.'s 2013-16 corporate plan provided to the board for its meeting on 19 and/or
20 September 2013? Yes or no?
Mr Brown: Yes, there was a copy submitted.
CHAIR: Version 13?
Mr Brown: Can I take that on notice? I am not aware of
exactly what version it was.
2.44
To date, NBN Co has not answered this question on notice. However, the
committee notes that a Corporate Plan was scheduled for board consideration on
19 or 20 September 2013.
2.45
NBN Co and the Departments of Communications and Finance were asked
whether a copy of this plan was submitted to shareholder departments. NBN Co
gave the following evidence:[32]
CHAIR: What is the normal practice for NBN Co.
communications to shareholder departments when it comes to documents that must
be considered by the government?
Mr Brown: The normal practice is NBN would put
together whatever that document is. I assume in this case we are talking about
the corporate plan....normally it would go to the board and, with their
agreement, it would be submitted as a draft to our shareholder ministers,
consistent with the GBE guidelines.
CHAIR: Can you confirm that version 13 of the corporate
plan was submitted to the shareholder departments via the portal prior to the
considerations. That would tend to suggest that perhaps it was not, but if you
could take on notice whether or not version 13 was supplied to the departments
before that board meeting. Was this version of the corporate plan approved by
the board on 19 or 20 September?
Mr Brown: I would need to take that on notice to
review the minutes of that board meeting.
2.46
The committee has not received an answer to this question on notice.
2.47
The Department of Communications gave the following evidence:[33]
CHAIR: What is the normal practice for NBN Co.
communications to shareholder departments? You may have heard that we had a
discussion earlier today about this. When it comes to documents that have to be
considered by government, do these documents appear on a portal?
Mr Clarke: Yes. There is a secure portal arrangement
to facilitate the transfer of confidential documents.
CHAIR: Is it the case that drafts of these documents
are often provided to shareholder departments prior to board consideration to
enable shareholder departments to prepare timely advice for government?
Mr Clarke: I can—
CHAIR: We both know the answer, but you need to say it
on the record.
Mr Clarke: For board documents it is less common, but
for documents that are conveyed between the parties, yes, that is a common
practice.
CHAIR: So was the draft of version 13 of NBN Co.'s
2013-16 corporate plan submitted to shareholder departments via the portal
prior to its consideration by the NBN Co. board on 19 September? It is a
simple, factual question. You know it has already been asked. It should be very
easy to ascertain.
Mr Clarke: I am not going to answer it.... I am choosing
to uphold the principle that the communications that are intended between the
agency through the department to the government—the nature of them; what was on
the table when, which is implicit in your questioning—are a confidential
matter.
2.48
The committee notes that NBN Co has yet to answer questions on notice
about the status of version 13 of the Corporate Plan, and the Department of
Communications has flatly refused to answer questions on whether a copy was
provided to Government. The committee further notes that the Minister made
reference to the content of version 13 of the Corporate Plan during the NBN
Rebooted conference in November 2013:[34]
Shortly before the election, the NBN Co revised its June 30
2014 premises passed target down to 600,000 brownfield premises.
2.49
In his speech to TelSoc on 2 December 2013, Mr Quigley also made some
observations about the content of Version 13 of the Corporate Plan:[35]
We did have to advise the Government in September that, the
issues with the LN/DN construction combined with the remediation stoppage moved
the construction end date from June 2021 to December 2021. The effect on the
financials of that six month shift in the construction end date was that
revenue returned to $23Bn since there was 6 months more revenue, but Opex
increased by about half a billion dollars due to the extra six months of
operating costs. The Capex spend is spread across a 6 month greater period
which leaves the total funding and the IRR unchanged. The contingency was also
unchanged.
Just to re-emphasise a previous point – our December of 2010
Corporate Plan contained a capex contingency of 10% or about $3.6Bn, the last
plan which was submitted in September retained the same level of contingency.
If the Management team had any doubt about offsetting the increased LN/DN rates
by the cost reductions we had planned, we would have made use of some of that
contingency. We had no such doubts.
What is remarkable is how little the financials changed over
the 3 years.
2.50
The most recent version of the NBN Co Corporate Plan—the most accurate
“base case”—was the 2013-16 Corporate Plan (Version 13) referred to by Mr Payne
in his testimony, prepared by NBN Co management and submitted to the board on
20 September 2013. Dr Switkowski was asked why version 13 was not used as the
base case during the 17 December 2013 hearing:
CHAIR: He [Mr Robin Payne] said in evidence at
estimates that the government asked that the company further review the June
draft to incorporate the consequences of the delay due to remediation. Given
that version 13 of the corporate plan 2013-16 was the NBN Co.'s response, why
wasn't that used as the baseline?
Dr Switkowski: We certainly are of the view that the
baseline that had to be referred to was the one that was formally in the system
and approved, and that any update of the performance of NBN Co. was within the
mandate of the current review, and that is what we presented in the [Strategic
Review] last week.[36]
2.51
Subsequent to this exchange, Mr Rousselot confirmed for the committee
that Versions 12 and 13 of the Corporate Plan 2013-16, as well as other documents,
were made available to the Strategic Review team.[37]
Summary of findings—Base Case used
for the Strategic Review
-
In July 2013, the NBN Co board submitted to shareholder
Ministers the NBN Co Corporate Plan 2013-16 (“version 12”). Former shareholder
Ministers requested that “Version 12” be amended to incorporate the effects of
Telstra’s stop work on remediation. NBN Co prepared a revised Corporate
Plan—called ‘version 13’—which was submitted to the NBN Co Board on 19 or 20
September 2013.
-
It is normal practice for NBN Co to provide shareholder
departments with the Corporate Plan prior to Board consideration so that timely
advice for government may be prepared.
-
“Version 13” of NBN Co’s Corporate Plan 2013-16 represents the
most recent and accurate “base case” for the NBN. Despite this, the Strategic
Review used the fifteen-month old NBN Co Corporate Plan 2012-15 as the “base
case.” The reason for this will be examined in the following section.
Treatment of architecture changes
2.52
In his speech to TelSoc on 2 December 2013, Mr Quigley said:
With our LN/DN rate increases, we had exactly the same
situation. Increases in the LN/DN rates would be offset by other cost
reductions. And I am not talking about speculative cost reductions, where you
say to yourself: “oh, we need to find $2Bn in savings, somehow”. I am talking
about things that had already been identified, like smaller diameter cables
that had already been designed by cable companies, reduced and more efficient
testing, smaller footprint multi-ports that had already been designed,
reductions in fibre counts and corrections in planning tools that allowed
smaller mandrels and greater fill ratios for ducts. We called these changes our
2.x architecture. At the end of September, NBN Co was on track to implement
these cost reductions, as any sensible company would.
So, let me be clear. Rates to build the fibre network based
on the existing design and architecture were rising. But those rate increases
would not have produced a cost increase because we had identified and
validated, network and design changes that would have offset those increases.
Which is why I find it incomprehensible to hear the suggestion that the
increases in LN/DN rates should be built into the forward projections and cost
reductions that have already been identified, should not be.
Unless, of course, your objective is to try to confirm a
pre-conceived position.
2.53
On 11 December 2013, an article in the Australian Financial Review
by Philip Coorey & James Hutchison cited an NBN Co Board paper dated 20
September 2013.[38]
The NBN Co Board paper states:
The COO and CTO teams have undertaken a review of the current
network architecture for the access fibre network with the aim of identifying
and implementing a set of cost saving design and construction initiatives. Cost
savings from these initiatives, together with other productivity initiatives
underpin the assumed reduction in the CPP to FY18. This review incorporates a
number of in-flight Project Fox initiatives and pragmatic cost saving solutions
into a combined revised architecture which will be incorporated into future
FSAM designs. The planned changes are as follows:
-
Reduced fibre allocation per premise
-
Mandrel sizing and FOND cable diameter correction
-
Introduction of small diameter fibre cables
-
Removal of PON protection in certain circumstances
-
Fibre testing optimisation
-
Introduction of the small footprint multiport for underground
build.
2.54
Further:
The proposed architecture savings and cost reduction
initiatives represent a combined value of greater than $4.5 billion, which
support the assumptions in the Corporate Plan of a reduction in CPP to
construct the access fibre network from $1500 in FY14 to $1054 by FY18. The
initiatives will continue to be progressed through the COO and CTO teams with a
target to finalise an implementation plan for both new and current in-flight
designs by the end of September.
2.55
The cost savings identified in Mr Quigley’s speech and the 20 September
NBN Co board paper—“smaller diameter cables that had already been designed by
cable companies, reduced and more efficient testing, smaller footprint
multi-ports that had already been designed, reductions in fibre counts and
corrections in planning tools that allowed smaller mandrels and greater fill
ratios for ducts”—were discussed at length during the 11 December public
hearing.[39]
2.56
In relation to the smaller diameter cables:
CHAIR: Has the NBN Co. looked at introducing smaller
diameter fibre cables?
Mr McLaren: Yes. We are working with our vendors in
the fibre supply to obviously look to see improvements with smaller fibre
cables.
2.57
In relation to reduced and more efficient testing:
CHAIR: Has NBN Co. ever looked at optimising its fibre
testing?
Mr McLaren: Yes. As with many of these items, we are
always looking to optimise our testing for anything that has a cost in the
build.
2.58
In relation to smaller footprint multiports, Mr McLaren noted:
We have been working with our suppliers to introduce a
smaller form. It is not so much that it is smaller, but it is more flexible and
able to fit into Telstra's pits more easily. It will allow the work to proceed
quickly and there will be not be so much work in remediating those pits. We
have introduced that and it is already rolling out, as I understand it, in our
fieldwork now, a smaller footprint multiport.
2.59
In relation to corrections in planning tools that allowed smaller
mandrels and greater fill ratios for ducts:
CHAIR: Has a mandrel size change been implemented?
Mr McLaren: Yes.
2.60
In relation to the reduced fibre counts in the second leg:
CHAIR: Has NBN Co. ever looked at reducing the fibre
counts in distribution cable from 576 fibres to 433 fibres?
Mr McLaren: Yes, we have been investigating that
opportunity. Again, it is an opportunity to have smaller diameter cables, as we
talked about.
2.61
In relation to removing the second leg of a distribution loop:
CHAIR: Has NBN Co. ever looked at removing the second
leg of a distribution loop in certain FSAMs where the effect can be managed
within the terms of the WBA?
Mr McLaren: Yes. In some instances in the current
build of our network where that second leg is very difficult and costly, we
have made the decision not to build it.
2.62
In relation to the implementation of “Architecture 2.X” more generally,
Mr McLaren observed:
Mr McLaren: 2.x is not a big bundle of change. There
are incremental changes in many different parts of the network. We mentioned
the small footprint multiport. We mentioned techniques, and I think you
mentioned the now more efficient [mandrel]. There is testing which we use in
our rodding and roping, giving us a more accurate gauge on the available duct
space, and we have introduced those changes. So a number of changes are
incrementally being introduced into the design process over time.
2.63
The committee notes that by end September 2013, NBN Co was in the
process of implementing, or had already implemented, network changes to reflect
the move to Architecture 2.x. This is confirmed by Mr McLaren’s testimony, the
20 September Board paper and Mr Quigley’s speech. These architecture changes
resulted in greater than $4.5 billion in capital expenditure savings.
2.64
However, the Strategic Review only identifies $1 billion in cost
savings, and reduces these savings by a further 50 per cent:[40]
The Independent Assessment notes that there are opportunities
for cost reductions in the future. Some potential savings have been identified
in network design and architecture, primarily in reduced equipment costs,
however a business case needs to be prepared. Business cases for ~$1 billion of
potential savings have been completed and implementation of some of these
improvements is underway. These could be achieved over time, but allowing for
the time to introduce these concepts and other risks, it is prudent to adjust
the amount by 50 percent.
2.65
This issue was raised in the 17 December 2013 public hearing:
CHAIR: So to reiterate again, the strategic review
ignored over $4 billion worth of savings because there was no business case
presented notwithstanding the board previously had actually had a submission
put up by the company to them and an assumption has been made—which you are not
able to assist us with other than saying, 'I agree with it,'—that $500 million
of the savings should be dumped—just dumped—because it is prudent.
Mr Rousselot: As I said, the analysis that we did of
the potential savings was one that looked at it, and talked with people within
the company, either in operations or in design, to understand the status of the
savings that had been identified.
CHAIR: But as for the billion dollars, business cases
had been provided for the billion dollars.
Mr Rousselot: I do acknowledge that that is the case,
yes.
CHAIR: And you just halved it?
Mr Rousselot: We took a consideration of risk that was
still attached to implementing those savings.
CHAIR: Mr Quigley, in his speech, seemed to predict
this would happen. He said he found it incomprehensible to hear the suggestion
that the increases in LNDN rates should be built into the forward projections and
that cost reductions that have been already identified should not be 'unless,
of course, your objective is to try and confirm a preconceived position'. It is
getting pretty hard to disagree with Mr Quigley, Mr Rousselot, if you are
ignoring savings deliberately and you are not applying any productivity
learnings and savings across the entire project except for two years in four
years time. It is getting pretty hard to disagree with Mr Quigley.
Mr Rousselot: The level of prudence that we have
applied to this particular scenario we have applied to the other scenarios.
2.66
A number of the cost savings identified above appear in the Strategic
Review in Scenario 2 (‘Radically Redesigned FTTP’). For example, the Strategic
Review provides that scenario 2 includes:[41]
Cost-efficient architecture and materials (a saving of
[redacted] per premises passed) including reducing from 3 to 1.2 fibres per
premises, increased use of aerial deployment, removal of PON protection, using
smaller diameter fibre cables, use of gel-free cables and eliminating the
battery back-up for the NTD.
2.67
The committee has put several questions in writing to NBN Co requesting
information about why these $4.5 billion in cost savings were excluded from the
Revised Outlook, and instead included in the ‘Radical Redesign’. In response to
a question in writing asking about the $4.5 billion in cost savings identified
in the 20 September NBN Co board paper, NBN Co replied:
As stated at the Senate Committee hearing on 17 December
2013, many working documents including these Board papers were made available
to the expert advisers. The advisers have formed the view that some elements of
the savings proposed may be realised in a scenario where current FTTP practices
are reviewed and optimised significantly – e.g. a “radically redesigned FTTP
rollout”.[42]
2.68
Similarly, the Strategic Review characterises the “radically redesigned”
scenario as follows:[43]
Based on overseas experience, it is possible to radically
redesign the NBN Co FTTP deployment to reduce the Cost Per Premises. The
changes to deployment include changes in the delivery model, which in turn
result in labour productivity improvements, different and more cost-efficient
architecture and materials, and cost-efficient construction techniques. This
radically redesigned FTTP deployment is estimated to cost [redacted] build
Capital Expenditure per brownfield premises passed, representing savings of
[redacted] per premises passed versus the Revised Outlook.
2.69
In an answer to another question on notice, NBN Co stated that:[44]
The Revised Outlook considered the operational and financial
position of the company based on the continuation of current rollout plans. As
highlighted in paragraph 3.2.8, these potential efficiencies may be realisable
through a step-change and transformation of the organisation.
2.70
And:
Scenario 2, Radically Redesigned FTTP contemplates NBN Co
making significant changes to its FTTP deployment approach to improve NBN Co’s
productivity and construction techniques. Within this scenario, it is expected
that these “radical” changes will increase rollout speed and decrease costs.[45]
2.71
The committee notes that the architecture changes (2.X) resulting in
these cost savings were characterised by NBN Co’s Chief Technology Officer, Mr
McLaren, as ‘incremental’ improvements that did not represent ‘a big bundle of
change.’ Mr Quigley similarly characterised these improvements as business as
usual: “at the end of September, NBN Co was on track to implement these cost
reductions, as any sensible company would.”
2.72
However, when asked about why these savings were not incorporated into
the Revised Outlook, NBN Co characterises them as ‘radical’ and ‘significant’
and requiring a ‘step-change and transformation of the organisation.’
2.73
The Committee considers that the Revised Outlook and the Radical
Redesign scenarios make different assumptions about the future trends for cost
per premise passed for FTTP. In fact, the so-called “radically redesigned” FTTP
scenario represents a better estimate of the costs that would be incurred by an
active and interested management than the Revised Outlook. This is supported by
the fact that many of the savings based on Architecture 2.x had already been
incorporated by previous NBN Co management into the September 2013 Corporate
Plan (Version 13).
2.74
The committee considers that the implementation of these architecture
changes was business as usual for NBN Co, and the exclusion of the associated
savings from capital expenditure assumptions distorts the outcome of the
Revised Outlook. The committee also notes that had the Strategic Review used
Version 13 of the NBN Co Corporate Plan as the ‘base case’ for the Revised
Outlook, the Revised Outlook would have arrived at a different outcome.
Summary—Treatment of architecture
changes
-
By end-September 2013, NBN Co had implemented, or was in the
process of implementing, a number of incremental changes to the fibre rollout
known as Architecture 2.x. Combined, these changes represented $4.5 billion in
capital expenditure savings.
-
Version 13 of NBN Co’s Corporate Plan 2013-16, prepared for
Board consideration on 20 September 2013, incorporated these architecture
changes and the associated savings to capital expenditure. It also incorporated
changes to the deployment schedule from Telstra’s stop-work on remediation.
Version 13 is the most recent and accurate NBN Co Corporate Plan.
-
Despite this, the Strategic Review used NBN Co’s fifteen-month
old 2012-15 Corporate Plan as the ‘base case’ for the Strategic Review. Only
$500 million of the architecture savings were included in the Revised
Outlook—the bulk of these savings were incorporated into Scenario 2 rather than
the Revised Outlook. This was justified by characterising the changes as
‘radical’ rather than incremental.
-
The committee considers that the implementation of these
architecture changes was business as usual for NBN Co, and the exclusion of the
associated savings from capital expenditure assumptions distorts the outcome of
the Revised Outlook by bolstering costs.
Assumption of brownfield delays
2.75
The Revised Outlook has factored in a delayed roll out schedule compared
to the 2012-15 Corporate Plan. This is set out in Exhibits 2-10 and 2-11:
Deployment Schedule—Corporate Plan
Deployment Schedule—Revised Outlook
2.76
Some general observations justifying this assumption are set out in the
Strategic Review, although many of these are redacted.[46]
These include: “[redacted]; the complexity of the interfaces between NBN Co and
the Delivery Partners, the uniqueness of an infrastructure build of this scale
and nature in Australia, and the lack of deep project management resources,
particularly as the volumes have increased; delays in dealing with Telstra
[redacted]; ineffective collaboration between NBN Co and its Delivery Partners
in resolving contract, design and construction issues; and disproportionate
focus on workforce size and Premises Passed as key drivers of behaviour rather
than Premises Activated driven by more effective design and collaboration.”
2.77
Version 12 of the 2013-16 Corporate Plan targeted 850,000 brownfields
premises passed by 30 June 2014.[47]
As set out above, this deployment profile was questioned by previous
shareholder Ministers, and the company was asked to develop a new Corporate
Plan taking into account the Telstra stop work on pit remediation. NBN Co did
so, but the September plan (“version 13”) has not been made public. However, as
noted above, the Minister made reference to the 30 June 2014 brownfields target
in version 13 of the Corporate Plan during the NBN Rebooted conference in
November 2013:
Shortly before the election, the NBN Co revised its June 30
2014 premises passed target down to 600,000 brownfield premises.
2.78
In his speech of 2 December 2013, Mr Quigley noted that the effect of
the revised 30 June 2014 target was to shift the construction end date by six
months:
We did have to advise the Government in September that, the
issues with the LN/DN construction combined with the remediation stoppage moved
the construction end date from June 2021 to December 2021.
2.79
As of 24 August 2013, build contract instructions had been issued for
512,818 brownfields premises.[48]
The issue of build contract instructions for the fibre network commences what
is referred to in the Strategic Review as the “construction phase.”[49]
The Strategic Review found that:
The construction phase is being completed in an average of
approximately 216 days (7.1. months), which is in line with the Corporate Plan.[50]
2.80
On this basis, by mid-March 2014 (216 days after 24 August 2013), NBN Co
was on track to pass approximately 512,000 premises. This is consistent with a
30 June 2014 target of 600,000 premises passed.
2.81
The interim Statement of Expectations was issued by shareholder
Ministers to NBN Co on 24 September 2013.[51]
Among other things, it states that:
In regard to rollout in brownfield areas, NBN Co should
continue existing construction where build instructions have been issued to
delivery partners. Any further build or remediation instructions should not
ordinarily be issued pending further analysis and discussion. Management of
existing design work should occur so as to optimise value in the context of the
Government’s policy for a flexible architecture.
2.82
In other words, permission must be sought from the Minister before build
contract instructions can be issued to delivery partners. The practical reality
of this constraint was illustrated by Dr Switkowski at the 17 December
committee hearing:
In fact, we have spent time in recent weeks petitioning the
government, as we must, to continue to authorise us to go as fast as we
possibly can and not be required to keep checking in with the department or
whatever with numbers.[52]
2.83
The Strategic Review began its work in October/November 2013. In
November 2013, when visiting Blacktown with Dr Switkowski, the Minister said:
[NBN Co has] issued design instructions for more premises,
twice as many premises to be passed by June 30 next year, as the NBN Co has
passed to date.[53]
2.84
This statement was later clarified by Josh Taylor of ZDNet:
Turnbull's office clarified that the NBN will have passed
450,000 brownfields premise[s] by the end of June. The NBN has currently passed
237,324 brownfields premises, with 164,501 able to order a service.[54]
2.85
The Strategic Review assumes that only 357,000 premises will be passed
by June 2014. This delay, in tandem with workfront assumptions, is then
extrapolated across the entire build, pushing the rollout completion date to
2024. According to the Strategic Review, this reduces revenues by approximately
$11.6 billion, increases operating expenditure by $5.4 billion, increases
interest payments by $7.5 billion and, ultimately, increases the assumed peak
funding amount for the fibre rollout by approximately $13 billion. This issue
was discussed during the 17 December hearing:
Mr Rousselot: The slower rollout is indeed driving the
bulk of the reduction in revenue for the period FY 2011 to FY 2021, which is
the number you are referring to. The slower rollout, however, is not based on
my assumptions; it is based on the actual track record that we have and the
review that has been done since then by KordaMentha, supported by the newly
appointed operations team of NBN Co...
CHAIR: ...But this is an assessment that has been done,
based on assumptions about a whole range of things—and we are going to get to them.
I just want to make it so we are all going to be talking about the same thing.
You say 'the vast bulk', I say that it is more than $11.6 billion, but $11.6
billion is the figure characterised by you, or by the strategic review, as the
hit on the revenue base of NBN Co. by the decision—the assumption, the
forecast—that you will extend by three years. That is just a fact.
Mr Rousselot: If I may, because we look back to FY
2012 plan, there are in fact actuals that cover the period between FY 2012 and
now. So this is not an assumption; it is a fact. Yes, there are assumptions
being made in terms of from now onwards. So it is a mix of the fact and the
track record that we have achieved between when the plan was published and
today, and then a forecast made for the period going forward.
CHAIR: I note that the strategic review assumes that
government equity does not change in the revised outlook. Is that correct?
Mr Rousselot: Yes, that is the assumption we have
worked under.
CHAIR: So, under your decision to incorporate all of
these in the review, this decision to delay the completion date by three years
halves the revenues to 2021, and what that means is that NBN Co. has to get
more money from private debt markets. Is that right?
Mr Rousselot: Again, you have mentioned 'my
decisions'. It is not my decision. It is a forecast that we have made based on
the actuals and assumptions that have been made going forward. And, yes, you
are correct; this is the impact on the revenue.
CHAIR: Thank you. And more money is needed from the
private debt markets because of this assumption that you have made. I am not
trying to split hairs. You keep changing between 'decisions', 'assumptions',
'forecasts', 'advice'; I do not mind which of them you pick. This is your
document, Mr Rousselot—that has been extensively explained to us by Dr
Switkowski—so you cannot keep trying to blame other people. Your name is on it.
Mr Rousselot: I am not blaming other people. I am just
stating the fact that, to build the numbers that you are looking at, we have
actuals to date and we have forecasts going forward; and your point on the debt
is we have assumed, when we look at the revised outlook, that the
current funding arrangement with the government would apply, which is a maximum
equity contribution of $30.1 billion, $30.5 billion, and any fund that is
required in addition, given the re-forecast that is made based on actuals and a
revised forecast, we have assumed to be funded through debt.
CHAIR: Okay. So the extra interest that NBN Co. has to
pay up until 2024, from 2021 to 2024, in this situation is $7.5 billion,
according to your chart on page 38?
Mr Rousselot: I think that is correct.
CHAIR: So your costs are up by $7.5 billion because of
the decision. Your revenue is down by $11.5 billion because of your assumption,
decision, interpretation, whatever. So what happens to opex if the rollout is
slowed by three years?
Mr Rousselot: I believe that the opex vary little
during the period. I think the biggest changes—
CHAIR: On page 38 it suggests that it increases by
$5.4 billion—that is a lot by my standards; it might be a little by yours.
Mr Rousselot: I understand why you have that. Certain
payments that are made that are in fact more representative of the rollout are
treated as opex, and I think that is why you have a difference in that number.
I will have to check...
CHAIR: ...So where we are is that by slowing the rollout
by three years you have added a lazy $13 billion to peak funding—it is just
mathematics; it is just that that is what happens?
Mr Rousselot: That is the result of the forecast that
we have made, yes.
2.86
The 357,000 target was discussed at both the 17 December 2013 hearing of
the committee, and the 25 February hearing of the Senate Estimates committee.[55]
During the 17 December hearing, graphs were presented which demonstrated the
various rollout trajectories of NBN Co (see Appendix 4).[56]
Also during this hearing, it was demonstrated that NBN Co was tracking at
approximately 5,000 premises per week—considerably in excess of what was
required to reach the 357,000 target. In response, Dr Switkowski said:
This to me illustrates one of the big problems around the
commentary with respect to NBN. You, from the outside, have taken a bunch of
numbers and challenged our ability to make forecasts when we have all of the
data and we understand what is happening out in the field. How does that work?
For example, you cannot take 5,000 homes passed per month and not allow for the
fact that from the middle of December to the middle of January the industry
shuts down. There is 20,000 off your number to start off with. You have got to
get down to that level of analysis to form a forward view. What we will not do
is come up with numbers that are excessively optimistic, which I assert has
characterised previous forecasts. To have people from outside the organisation
attempt to reinterpret our forecasts is ludicrous.
2.87
During the 25 February hearing of the Senate Estimates committee, Dr
Switkowski confirmed that NBN Co’s weekly average was between 4,500 and 5,000
premises per week.[57]
He also confirmed Mr Adcock’s comment at NBN Co’s half yearly results briefing
that NBN Co expected this number to be 6,000 premises per week by 30 June
2014—once again, substantially in excess of what was required to reach a target
of 357,000:
Senator CONROY: Do you recall the graphs of the
various rollout trajectories for NBN Co. that I showed you at the December
hearing of the Senate select committee?
Dr Switkowski: Generally.
Senator CONROY: During that discussion I noted that
NBN Co. was passing, on average, about 5,000 premises per week. I also noted
that if NBN Co. plateaued at its current level of activity NBN Co. would easily
pass more than 400,000 premises by 30 June 2014. I do recall, Dr Switkowski,
you took a very dim view of this 5,000 average, given that it included downtime
over the Christmas break. What is NBN Co's current weekly average?
Dr Switkowski: Somewhere between 4,500 and 5,000
premises passed.
Senator CONROY: I also note that Mr Adcock said last
night that NBN Co. expects to be doing 6,000 premises by 30 June. Is that
correct?
Dr Switkowski: That was the statement that was made,
yes.
Senator CONROY: I have been doing some maths of my own. NBN
Co's weekly average for brownfield premises—and I think you are roughly
indicating this—passed over the past 17 weeks is about the 4,500. If you
exclude the two weeks Christmas shutdown where contractors appear to have
down[ed] tools, it comes to 5,078, between, as you said, 4,500 and 5,000. If
you extrapolate 5,000 premises, which is less than your own chief operating
officer is indicating, to 30 June, and there is no Christmas shut down between
now and 30 June—that is right, isn't it?
Dr Switkowski: Just Easter.
Senator CONROY: You are having an Easter shutdown as
well?
Dr Switkowski: I am just reflecting how the industry
operates.
Senator CONROY: Fantastic. NBN Co. gets to slightly
more than 400,000 premises. Even if you take the 4,500 weekly average and
assume a steady linear growth to Mr Adcock's 6,000 per week by 30 June, NBN Co.
will still pass more than 400,000 brownfield premises by 30 June. Without you
having done the maths and hoping that I am not seriously misleading you at the
desk, does that sound about right?
Dr Switkowski: Your algebra is certainly right.
2.88
The Strategic Review also makes assumptions about the daily run rate
(premises passed per day at the peak of the rollout). The medium term outlook
factored in the extension of the design to delivery schedule to 15 months.[58]
This was projected to be brought back into the original 12 month schedule in
two years.[59]
This revision includes an escalation of the daily roll out rate to a peak of
4,800 premises passed, compared to Corporate Plan peaks of more than 5,400 per day
for the brownfields deployment.[60]
The Revised Outlook’s only basis for the lower peak rate is a comment that:
Based on workforce modelling previously undertaken by NBN Co,
and the Independent Assessment, it is not anticipated that construction field
labour is a limiting factor in the FTTP deployment. The biggest constraint to
the network rollout is the availability of network designers, senior and
experienced project managers, in-field supervisors and project control staff to
provide leadership and oversee program delivery....
This constraint allows a maximum of 200-300 concurrent
workfronts (for example, an FSAM, a set of nodes or HFC in-fill areas) and
dictates the highest practical deployment speed achievable.
2.89
The Strategic Review did not address the question of what strategies
could be employed to lift this constraint (e.g. training, additional contract
resource from Telstra). Nor did the Strategic Review acknowledge that many
construction projects in other sectors are approaching completion, releasing additional
project management resources. Rather, productivity improvements were “assumed
out” of the Revised Outlook and “assumed in” to the Radically Redesigned FTTP.
As NBN Co noted in answer to a question in writing:
Scenario 2, Radically Redesigned FTTP contemplates NBN Co
making significant changes to its FTTP deployment approach to improve NBN Co’s
productivity and construction techniques. Within this scenario, it is expected
that these “radical” changes will increase rollout speed and decrease costs.[61]
2.90
The Committee also notes the testimony of NBN Co’s Chief Financial
Officer, at the JCNBN hearing on 19 April 2013. When asked the financial impact
of extending the rollout, Mr Payne replied:[62]
The biggest impact of a one- or two-year delay will not have
much impact on the internal rate of return. With a two-year delay we would
probably still expect to see an internal rate of return of around seven per
cent. Where it does have a big impact is on the peak funding requirement. Under
the existing plan, we have a peak funding requirement of just over $44 billion.
If we extended the rollout, it would reduce that peak funding requirement
because we are spending capex after a time when we have gone to cash flow
positive. That would come down by $2 billion or $3 billion.
2.91
This evidence demonstrates that, by itself, a deployment delay does not
necessarily produce an increase in peak funding. The delay must work in tandem
with an assumption that shifts the timing of when NBN Co becomes cash flow
positive. Put another way, if revenues are not assumed away (beyond 2021) from
the delayed deployment schedule, then according to Mr Payne’s testimony the
result of assumptions of delay in the brownfields deployment schedule would be
a decrease in peak funding.
2.92
NBN Co was asked in writing following the 17 December public hearing to
reconcile Mr Payne’s comment with the conclusion of the Strategic Review. At
the time of writing the question is unanswered.
2.93
The committee has serious concerns with the delayed deployment forecast
of the brownfields fibre build in the Revised Outlook. The June 2014 target of
357,000 premises passed by June 2014 is at odds with NBN Co’s weekly average,
statements made by the Minister before the Strategic Review concluded its work,
and NBN Co’s own statements at its half yearly results briefing. Furthermore,
the committee notes that NBN Co’s fibre deployment speed is conditional upon
the political control evident in the interim statement of expectations.
2.94
The revised deployment schedule—and the assumption that $11.6 billion in
revenues will be foregone as a result—has another consequence in the Strategic
Review. Revenues for the full fibre rollout are stripped out of scenario
comparisons, while the full assumed costs are included. This is visible in the
table comparing the financial outcomes of the scenarios (Exhibit 4-6,
reproduced below). This table includes revenues to FY2021 (when scenario 6 is
assumed to be complete) but capital expenditure to 2024 (when the Revised
Outlook assumes that the full fibre rollout will be complete). Incidentally,
this is true of delay assumptions for all network elements in the Revised
Outlook (more on this below). The committee also notes that the revenues
excluded from the Revised Outlook in Exhibit 4-6 are the three years when the
Revised Outlook assumes revenues will be the highest—$15 billion over FY2022,
FY2023 and FY2024.[63]
Exhibit 4-6 (Strategic Review)
2.95
The committee considers that the 30 June 2014 target—and the revised
deployment schedule—has been “lowballed” to achieve political objectives. This
includes setting a target so low that NBN Co could not fail to meet it—and in
fact would have to reduce its weekly run rate to avoid exceeding it. It also
provides support for the claimed three year rollout extension, which is assumed
to reduce revenues by approximately $11.6 billion, increase operating
expenditure by $5.4 billion, increase interest payments by $7.5 billion and,
ultimately, increase the assumed peak funding amount in the Revised Outlook by
approximately $13 billion. The committee also notes that a ‘lowball’ target
also provides a platform for NBN Co and Government to trumpet exceeding this
target in July 2014. As Dr Switkowski noted at the February estimates hearing:
I hope to be in front of the committee after June explaining
how we did better than the early forecasts.[64]
Summary—Assumption of brownfield
delays
-
The Revised Outlook assumes that NBN Co will pass 357,000
brownfields premises by 30 June 2014, compared to 600,000 in the Corporate Plan
(version 13). This assumption—in concert with conservative estimates of
premises passed at peak rollout—is reflected in the revised deployment
schedule, which assumes the fibre network will not be complete until 2024.
-
The 30 June 2014 target is at odds with NBN Co’s current run
rate, the number of build instructions issued by NBN Co by August 2013, and the
Strategic Review’s own finding that the construction phase is being completed
in line with Corporate Plan timing assumptions. The committee notes also that NBN
Co’s speed of fibre deployment has been brought under direct political control.
These factors cast doubt on the revised deployment schedule in the Revised
Outlook, and the assumed consequences of this assumption.
-
The committee considers that the 30 June 2014 target has been
“lowballed” to achieve political objectives. This includes setting a target so
low that NBN Co could not fail to meet it. It also provides support for the
claimed three year rollout extension, which delivers the following financial impacts:
- revenues are decreased by approximately $11.6 billion;
- operating expenditure is increased by $5.4 billion;
- interest payments are increased by $7.5 billion; and
- the assumed peak funding amount is increased by approximately
$13 billion.
Cost per premises assumptions –
brownfields[65]
2.96
NBN Co’s Chief Financial Officer gave the following evidence at the
November hearing of the Senate Environment and Communications Estimates
Committee in relation to the cost per premises passed of the NBN fibre build:[66]
Senator LUNDY: I understand that in April NBN Co.
advised the Joint Committee on the NBN that the current cost of building the
local network and distribution network falls between $1,100 and $1,400 per
premise. Is that correct?
Mr Payne: At the time we presented that to the joint
committee, that was our best estimate of the costs of completing the areas that
we were building in at that time. So that was our best estimate at that point
in time.
Senator LUNDY: Has it changed since that point in
time?
Mr Payne: Since that point in time we have done a
number of things. We have obviously started in more areas and have had some
contract renegotiations. Looking today at our estimate of completion on
premises we are doing now, it would be a bit higher than that.
Senator LUNDY: How much is a bit higher?
Mr Payne: I think it is between about $1,450 and
$1,500.
2.97
On 29 November 2013, the Department of Finance was asked whether they
were aware of any cost increases beyond this amount:
Senator CONROY: You said you were watching the
testimony earlier. You would have seen Dr Switkowski claim there was a material
blow-out in costs in one part of the bill. In your weekly meetings with NBN Co.
are you familiar with any information to that end? And I think the gentleman
behind you indicated you had a weekly meeting, Ms Mason. Mr Robinson indicated
he was not at the weekly meetings, so I can only ask you.
Ms Mason: I am not necessarily at the weekly meetings
either. I am not aware of any particular cost blow-outs.[67]
2.98
The 20 September NBN Co Board paper states in relation to costs per
premises passed:
The assumption of $1500 in FY14 is consistent with our July
2013 cost per premises reporting which estimates the following:
-
The Estimate at Completion (EAC) for 152 FSAMs with a Fixed Price
Lump Sum (FPLS) is currently tracking at $1335 per premises
-
The EAC for 50 FSAMs issued under “fast-track” construction
projects is tracking at $1487 per premises
-
The impact of the Syntheo and Silcar contract changes is
currently being modelled in detail, and is likely to increase costs by between
$50 and $100 per premises across the total number of premises.
2.99
However, the Revised Outlook in the Strategic Review assumes:[68]
A 78 percent increase in the average Cost Per Premises for
LNDN (including provision) from $1,123 to 1,997 per premises.
2.100
Increased costs for premises passed are set out in Exhibits 2-26 and
2-27.[69]
Although some general commentary is provided to justify these price increases
(pp. 62-65), the exact unit costs and the applicable assumptions behind these
increases are redacted.
Cost per Premises Passed (Revised Outlook)
2.101
The Strategic Review extrapolates the higher cost per premises passed
assumption of $1,997 out to the new rollout end date of 2024, without a single
efficiency saving for three years, and only 2.5 percent in two of the remaining
seven years.[70]
This was established at the 17 December hearing:
CHAIR: Does the revised outlook assume that the $1,997
figure is reflected all the way up until the end of the tanked rollout
completion date in 2024? In other words, you have extrapolated it right through
the rest of the build?
Mr Rousselot: I believe that it is an average, what
you see there, and my understanding is that the way the hypothesis is built is
that, at some point, we introduced an element of cost saving that will allow us
to save money towards the outer years of the rollout.
2.102
It is an axiom of construction projects that efficiencies are gained as
the construction ramps up and learnings are applied. The Strategic Review makes
this point on page 78:
Costs also tend to reduce over time, due both to cost erosion
and to scale and learning effects. For example, Verizon's Cost Per Premises
fell from ~US$2,600 to ~US$1,600 between 2004 and 2006
2.103
Similarly, the 20 September NBN Co Board paper noted:
The draft Corporate Plan v13.0 assumes that the cost per
premises to construct the access fibre network will reduce from $1,500 per
premises in FY14 to $1,054 from FY18 to the end of the construction period.
2.104
Remarkably, however, in the case of the Revised Outlook, the Strategic
Review states:[71]
It is considered likely that the Delivery Partners will
become more efficient as they are provided with more consistent work flow,
experience less interference in the design process, and are better managed
through clearer delegated authority within NBN Co. These efficiencies are
required to make the modules profitable for the Delivery Partners. Therefore,
it is anticipated that any efficiency gains will primarily benefit the Delivery
Partners and the revised figures have only included limited efficiency gains
for NBN Co (2.5 percent per annum for FY17 and FY18 only).
2.105
In other words, the Strategic Review cedes virtually all cost savings
from efficiency gains to NBN Co’s delivery partners. This assumption was
discussed during the 17 December 2013 hearing:[72]
CHAIR: I am just reading your figures. You keep the
average of $1,997 through almost the entire build but you give yourself an
efficiency benefit only in year 2018, in four years’ time. Okay. I think there is
a graph about to come up from the joint parliamentary committee hearing in
April which demonstrates—as you would expect and, I think, you indicate in the
report—that, with all large infrastructure projects, the costs come down over
time as you learn and become more efficient. The strategic review makes a
similar observation on page 78:
Costs also tend to reduce over time, due both to cost erosion
and to scale and learning effects. For example, Verizon's Cost Per Premises
fell from ~US$2,600 to ~US$1,600 between 2004 and 2006...
I just wanted to be clear. Verizon achieved a near 40 per
cent reduction in cost per premises over two years for its fibre build, from
learning and experience. In NBN Co's case, in your strategic review, in your
future forecast, NBN only achieves an efficiency gain in the year 2018, four
years from today. So, putting aside that you are pretending you have learnt
nothing from the last three years—and even I would agree that NBN would have
learnt plenty in the last three years—how can Verizon be so smart and you guys
be so dumb?
Mr Rousselot: Those are your words. The assumptions
that we built here were ones where we wanted to be prudent. If you look at our
estimates at completion, currently, it is still going up. So today we are not
yet capable of truly, accurately forecasting the cost that we will end up
having to pay for those types of assets.
CHAIR: But, seriously, you have actually forecast
costs still to be going up at the end of 10 years for a project that everybody
else in the world has been able to get a 40 per cent saving in two years.
Mr Rousselot: Again, the rationale for those costs
going up is not only the productivity improvements but also the effect of
inflation, cost increases and things like this.
CHAIR: Don't Verizon have the same challenges to
overcome? They didn't have inflation to overcome in the United States? I admit
it has been low, but—
Mr Rousselot: I do not know enough about Verizon's—
CHAIR: So everybody else in the world can make an
efficiency saving but, for the purpose of pumping up a re-baseline figure, you
have no productivity gains built in—other than in two years—in four years’
time.
2.106
The graph referred to in the Chair’s testimony was tabled at the April
hearing of the JCNBN.[73]
Reproduced below, it exhibits the efficiencies that NBN Co has already realised
in the past three years of the fibre build:
NBN Co Cost Per Premises Passed (April 2013)
2.107
During the April 2013 JCNBN hearing, the cost per premises connected was
also discussed. As set out below, NBN Co was already realising efficiencies in
connecting premises. Former NBN Co CEO Mike Quigley made the point that:[74]
We did a number of initial sites—several thousand—on a
different model and the cost of those was $2,400. We got some learnings from
that, we changed the model and now we are proceeding into volume. That is, once
again, several thousand. This is a blend, by the way, of SDUs and MDUs—single
dwelling units and multi-dwelling units. The volume actuals we are getting are
around $1,100, which is in fact right on our corporate plan estimate of
$1,100.
NBN Co Cost Per Premises Connected (April 2013)
2.108
However, the Revised Outlook in the Strategic Review assumes:
A 50 percent increase in the Cost Per Premises for
Connections from $1,398 to 2,100 per premises.
2.109
Once again, the Strategic Review has extrapolated the higher cost per
premises connected assumption of $2,100 right to the end of the reforecast
rollout end date in 2024, with marginal efficiencies of 2.5 per cent included
for FY17 and FY18 only.[75]
The Strategic Review states that this reflects “the intrinsic complexity of the
project.”[76]
2.110
The Strategic Review assumes that the consequence of higher unit costs
in the fibre rollout—in concert with assumptions that NBN Co will benefit from
no reasonable build efficiencies over the 10 year reforecast build period—is an
increase of $14.4 billion in capital expenditure. This is visible in Exhibit
2-25 of the Strategic Review, reproduced below.
Revised Capital Expenditure Assumptions—Brownfields
2.111
The Strategic Review makes a number of additional capital expenditure
assumptions about the brownfields fibre rollout:
-
An increase in the BSS/OSS and other IT Capital Expenditure costs
of $0.7 billion;
-
A $0.5 billion increase in other Capital Expenditure as a result
of increased capitalised labour over the revised deployment schedule; and
-
An increase of $1.4 billion required to maintain a 10 percent
contingency.
2.112
It is not possible to assess the IT and labour capital expenditure
assumptions on the information provided in the Strategic Review. However, the
committee notes that the $1.4 billion increase in contingency—to maintain the
contingency at 10 percent of the total assumed capital expenditure amount—is a
direct result of increasing other capital expenditure assumptions. The
increased capital expenditure assumed in the long term satellite program will
be examined below.
Summary—Brownfields Cost per
premises assumptions
-
On 19 November 2013, NBN Co’s Chief Financial Officer Mr Robin
Payne confirmed that the brownfields cost per premise was “between about $1,450
and $1,500.” An NBN Co Board paper dated 20 September confirmed that the
brownfields cost per premise passed of $1,500 was consistent with July 2013
Estimates at Completion. In November 2013, Department of Finance personnel
indicated that they were aware of no cost increases.
-
The Strategic Review assumes that the brownfields cost per
premise passed has increased by 78 percent to $1,997 and the brownfields cost
per premise connected has increased by 50 percent to $2,100. Unit price
increases and assumptions are redacted. The Strategic Review extrapolates these
assumptions out to the new forecast end date of 2024, without a single
efficiency saving for three years, and only 2.5 percent in two of the remaining
seven years.
-
The Strategic Review assumes that the combined result of these
assumptions is to increase capital expenditure in the Revised Outlook by $14.4
billion.
-
The $1.4 billion increase to maintain a 10 per cent
contingency is a direct result of other assumptions that increase capital
expenditure.
Capital Expenditure Assumptions –
Satellite
2.113
The Revised Outlook assumes approximately $2.4 billion additional capital
expenditure for the Fixed Wireless and Long Term Satellite components of the
network. This is visible by subtracting the unredacted figures from the total
capital expenditure in Exhibit 2-25.[77]
The Strategic Review notes that this is due to an assumed increase in the cost
per premises for fixed wireless, and an increase in the total cost of
satellite, but the amounts of these increases are redacted.[78]
2.114
The Revised Outlook also includes 100,000 additional premises passed in
the satellite footprint than in the Corporate Plan, as of June 2021:[79]
2.115
The Strategic Review includes no direct explanation as to the addition
of this satellite. The only reference is contained on page 66:
Whilst the majority of the costs of the two long term
satellites are known, there are some elements that are yet to be finalised.
There are also risks including the following:
-
There is no clear understanding of the requirement for further
capacity which may be needed if the demand for the LTSS exceeds that outlined
in the Corporate Plan; and
-
Further Satellite capacity may be the only viable solution if
fibre and Fixed Wireless coverage is less than the 97 percent included in the
Corporate Plan.
2.116
The committee does not contest that additional bandwidth will be
required in the satellite footprint. This is one assumption in the Strategic
Review that actually reflects the reality of broadband usage: when Australians
are offered access to more bandwidth, they use it. This is visible in the
experience NBN Co has had with the Interim Satellite Service, which eclipsed
its subscriber cap and capacity limits earlier than expected, just as it is
visible in the fibre network, where Australians with access to fibre are
consuming data at rates that are approximately 50% higher than the Australian
average of 31 GB/month.[80]
The committee expects a similar result once the two long term satellites are
launched in 2015 and Australians living in rural and remote parts of the
country have access to high-quality broadband for the first time.
Data Usage on NBN Co fibre Vs Australian average
2.117
The third satellite was included in the Revised Outlook without direct
explanation, and prior to the completion of the Fixed Wireless and Satellite
Review announced in the Strategic Review. This distorts comparisons with the
Corporate Plan. Once again, by assuming that the third satellite is launched
and operational by FY 2021, the Strategic Review can factor in the capital
expenditure of a third satellite into the Revised Outlook, but include in
scenario comparisons no revenues from the additional 100,000 customers.
Summary—Satellite Capital
Expenditure Assumptions
-
The Revised Outlook includes an additional satellite without
direct explanation.
-
The committee does not contest that additional bandwidth will
be required in the satellite footprint. This is one assumption in the Strategic
Review that actually reflects the reality of broadband usage: when Australians
are offered access to more bandwidth, they use it.
-
The assumed launch of the third satellite by end-FY2021
distorts scenario comparisons by including in the Revised Outlook the capital
expenditure for the satellite, but excluding revenues from additional satellite
customers.
Assumptions of greenfields delay
2.118
The number of greenfields premises to be passed in the Corporate Plan is
determined by assumptions of construction activity. As the Strategic Review
notes:
For the first five years, the Corporate Plan has assumed that
premises growth is based on the Australian Bureau of Statistics (ABS) and
industry trends; thereafter it is aligned with ABS household population growth.[81]
2.119
As set out in Exhibit 2-10, the Corporate Plan provided for 2,111,000
greenfields premises to be passed by FY2021 and 2,659,000 greenfields premises
to be passed by 2024.
Deployment Schedule—Corporate Plan
2.120
Exhibit 2-11 provides the same detail for the Revised Outlook. The
revised deployment schedule for greenfields assumes that:
-
871,000 greenfields premises will be delayed until after FY2021;
and
-
548,000 fewer greenfields premises will be passed in FY2024 under
the Revised Outlook than under the Corporate Plan.
Revised Greenfields Deployment Schedule (Strategic
Review)
2.121
This assumption of delay in the greenfields rollout produces the same
effect in Exhibit 4-6 as it does for other network elements: costs for passing
and connecting 871,000 greenfields premises are included in the Revised Outlook
for scenario comparisons, but revenues from the additional connections are not.
2.122
Mr Rousselot was asked about this issue at the hearing on 17 December
2013. He replied:
I believe that what it considers is the delay in the rollout,
which is impacting both the brownfield and the greenfield sites, and therefore
pushes out the date at which we are able to pass these greenfield sites.[82]
2.123
This answer reflects a misunderstanding of the project. The number of
greenfields premises to be passed is determined principally by construction
activity, not deployment speed.
2.124
The Strategic Review explains that the delayed greenfields rollout
schedule is due in part to the revised brownfields schedule.[83]
This is because new developments of less than 100 lots are only completed by
NBN Co if they are in-fill.[84]
An answer to a question on notice also states:[85]
A further discount to the deployment rate was applied to the
“new developments” figures to reflect that applications made to date have been
lower than forecast. It also reflects a higher than anticipated proportion of
‘new developments’ being ‘in-fill’ rather than greenfield developments with
more than 100 dwellings. A reduction was made to 2.111 million premises to
reflect a proportion of the ‘non-residential/business GNAFs’ included in the
original Corporate Plan figure of 2.659 million premises.
2.125
While the issue of in-fill could explain the difference between the
greenfields premises passed at Corporate Plan completion in FY2021 (2,111,000),
and the Revised Outlook expectation in 2021 (1,240,000), it does not explain
the difference in the number of fixed line premises in 2024 between the
Corporate Plan and the Revised Outlook.
2.126
The committee remains concerned about this issue. In an answer to
another question on notice, NBN Co noted that “the Revised Outlook forecast for
greenfields was used for all Scenarios, including the MTM.”[86]
As noted above, greenfields deployment is based on assumptions about premises growth,
assumptions which are based on ABS data. The MTM scenario assumes that by the
end of the rollout in CY2020, 1,089,000 greenfields premises will be passed in
the fixed line footprint.[87]
This is a difference of nearly one million premises compared to the Corporate
Plan. This can be seen in Exhibit 4-2, which demonstrates that by CY2020 there
are 11.18 million premises in the fixed line footprint—the corresponding number
in the 2012-15 Corporate Plan (by FY2021) is 12.2 million premises.[88]
However, NBN Co does not indicate in the Strategic Review—or in answers to
questions put in writing—that it has significantly revised its forecasts for
the number of premises that will be constructed by CY2020. The committee will
continue to seek clarification from NBN Co on this issue.
MTM rollout at assumed completion
Summary—Assumption of greenfield
delays
-
The Revised Outlook assumes that approximately 871,000
greenfields premises will be passed by NBN Co after FY2021.
-
This has the effect of including the costs for the 871,000
greenfields premises passed between FY2021 and FY2024 in scenario comparisons,
but none of the revenues.
-
The committee will seek further clarification from NBN Co on
the accuracy of the greenfields deployment schedule assumed in the Revised
Outlook and alternative scenarios.
Revenue assumptions
2.127
Section 2.5.1 of the Strategic Review outlines revised revenue
assumptions. As stated above, these revenue assumptions were prepared by BCG
for application across all scenarios. The Strategic Review notes that the
Corporate Plan forecast cumulative revenue of $23.1 billion from FY11-21. It
further notes that the two primary drivers of revenue are the number of
connected premises (pace of network deployment) and end-customer choice on
speed and data usage.
2.128
The Revised Outlook makes a number of assumptions which trim revenue
growth for FTTP. These will be analysed shortly. However, as noted above, the
key assumption made in the Strategic Review to strip out FTTP revenue prior to
FY2021 is the delayed deployment schedule. The Strategic Review states:
As outlined in the Network deployment Revised Outlook,
deployment will take approximately three years longer than indicated in the
Corporate Plan. This delay will reduce the cumulative Revenue from FY11- 21 by
~$11.6 billion (falling from ~$23.1 billion to ~$11.5 billion). Other factors
as set out below will reduce cumulative Revenue by a further ~$1.8-2.1 billion
to FY21, resulting in total cumulative Revenue for FY11-21 of ~$9.4-9.7 billion.[89]
2.129
The “other factors” noted in this passage—responsible for a reduction of
approximately $2 billion in the Revised Outlook to FY2021—include a greater
rate of decline in residential ARPU than is included in the Corporate Plan;
fewer residential premises connecting to the NBN; lower average prices for
business premises; lower revenue from the Government sector (it is argued that
these premises are included in the business segment); and reduced revenue from
lower take-up and prices for the multicast service.[90]
2.130
The Strategic Review also states:[91]
During the period to FY21, the impact of the rollout delay is
significantly greater than the impact of changes to ARPU and other factors.
However, post FY21 the revised assumptions (particularly in relation to residential
ARPU growth), will have a significant impact on Revenue because of lower ARPU
and lower long-term growth forecast.
2.131
In other words, when deployment delays are washed out of the model, the
“other factors”—which include reduced revenue assumptions for residential and
business customers than set out in the Corporate Plan—are the reason the
Revised Outlook assumes significantly reduced revenues for the FTTP build
compared to the Corporate Plan. This is visible in the ‘steady state’
comparison provided in Exhibit 4-6, which assumes that in FY2028 NBN Co
revenues are between $6.6 and $7.5 billion—up to $3.2 billion, or 32 percent,
less than assumed in the 2012-15 Corporate Plan.
2.132
The initial prices to be charged for NBN Co wholesale products were
detailed in the Corporate Plan, as was the expectation that the wholesale
prices would decline in real and nominal terms.[92]
The maximum price that can be charged by NBN Co is covered by the Special
Access Undertaking which has been accepted by the ACCC.
Exhibit 4-6 (Strategic Review)
Exhibit 8-1 (NBN Co Corporate Plan 2012-15)
2.133
The committee has already examined the basis for the assumed delay in
the deployment schedule, and the revenue consequences of that assumption. There
are three key reasons why the committee considers that the revenue assumptions
underpinning the ‘other factors’ are overly pessimistic for the full fibre
build:
-
Existing take up and usage of NBN Co fibre products compares
favourably to Corporate Plan assumptions;
-
The Strategic Review does not consider at any point the value of,
or high demand for, uploads for small business customers. Failure to consider
broadband quality beyond download speeds is a systemic fault in the Strategic
Review; and
-
A ‘steady state’ comparison of a full FTTP build exhibits a
marginal difference in revenues to the MTM, despite the vast difference in
product sets. This will be examined in section 3.3, below.
2.134
Before going to these points, the committee notes that some of the
“other factors” reflect current Government policy and have been “imported” into
the Revised Outlook. For example, one factor—which assumes a revenue reduction
of $200 to $300 million by FY2021, and presumably more after FY2021—is in part
due to an assumption of infrastructure-based competition in MDUs, which was not
countenanced in the NBN Co Corporate Plan or the policy platform of the
previous government.[93]
Another—that “more of the business market will be serviced by third-party fibre
providers than is assumed in the Corporate Plan”—was a risk identified in NBN
Co’s advice to Government during the caretaker period when discussing the lower
revenue potential of FTTN:[94]
2.135
The initial prices to be charged for NBN Co wholesale products were
detailed in the Corporate Plan, as was the expectation that the wholesale
prices would decline in real and nominal terms.[95]
The maximum price that can be charged by NBN Co is covered by the Special
Access Undertaking which has been accepted by the ACCC.[96]
2.136
The 2012-15 Corporate Plan also provides an extensive comparison of
retail pricing on the NBN and comparisons to plans already in the market. These
demonstrate the prices are broadly comparable with ADSL prices.[97]
There are a range of plans at the 12/1 mbps tier currently available on the NBN
starting from $29.95 a month with no additional line rental—Skymesh and Harbour
ISP are two examples. Prices for 100mbps products are also broadly comparable
to existing ADSL and HFC prices—for example, Exetel currently offers a
100/40mbps service, with 100GB of data, for $69.95 a month.[98]
Similarly, iinet offers a 100/40mbps service, with 200GB of data, for $79.95 a
month.[99]
2.137
Exhibit 2-23 of the Strategic Review demonstrates that the current
take-up of higher speed tiers is ahead of Corporate Plan expectations:
Exhibit 2-23
2.138
Similar evidence was presented by NBN Co during its half yearly results
briefing on 21 February 2014:[100]
AVC Profile
2.139
The committee also notes the following testimony on fibre take up rates
from the May 2013 Senate Estimates hearing:[101]
CHAIR: How does this [take up] compare
internationally?
Mr Quigley: From all the benchmark we have seen this
is really quite dramatic. Mr Steffens came across from BT, so he knows the
European scene reasonably well. How would you describe it?
Mr Steffens: We continue to benchmark financially on a
regular basis. We met with a colleague only last week from the supply side who
is talking to many operators across the world. Fifteen per cent is often seen
as a very good take-up, and we are substantially above that.
Senator Conroy: I think the NBN executives are being
far too bashful. I should add to the answer substantially. The take-up rate for
fibre connected for 12 months or more is about 35 per cent. For areas connected
for six months or more it is around 30 per cent. Compare this to, say, ADSL
when it was introduced in 2006, where the ABS found that 28 per cent of
households had broadband six years after its introduction. In other words, NBN
Co. has achieved with fibre in six months what it took six years to do with
ADSL and HFC.
2.140
The submission to the Committee by iiNet contained examples of small
businesses utilising the higher speed services.[102]
This submission emphasised the importance of uploads, one of the key advantages
of FTTP over FTTN:
The performance of data uploading features strongly in a
variety of case studies of iiNet small business customers, attached below. In
all cases, upload performance is the key to their purchasing decision. Nowhere
in the strategic review is there any consideration of upload performance to the
small business sector of the economy, or at all. Any business utilizing
broadband will confirm that upload performance is ‘mission critical’ and yet
little attention has been given to this issue, which is strategically important
to the Australian digital economy.
2.141
A number of small businesses provided similar testimony to the
committee. For example, during the 11 March hearing, Mr Edgar Adams, Editor of
the Central Coast Business Review, noted:[103]
Also, if I just may mention, we are not just talking about
downloading. It is the uploading that is the big issue in the case of a lot of
the businesses. It took an hour last week for my magazine to be uploaded, at 50
megabits, to the printer.
2.142
Similarly, Ms Michelle Allen, CEO of a small business called
Webstuff.biz, noted:[104]
As a company that is employing people under 30—we employ six
and my company is growing but the internet is holding us back. One of things we
also do with a lot of our clients is encourage our Central Coast clients to
market outside the Central Coast—that is, selling products online. These
clients are all having problems and a lot of our clients have to get us files
by post or USB. They drive their files to our office, and this happens on a
weekly basis, because we have a massive client list. It is very difficult as a
business to be innovative and we are encouraged to be—for example, last year I
came up with an innovative idea to create a software package for cafes so they
can order lunches and things online. We made this 3D model and, when we started
looking at the feasibility to roll this product out, we realised that no-one
would be able to render the 3D models of the food online because of the
internet connections.
2.143
Ms Allen continued:[105]
I have got a client who has got a rocking horse business and
he creates the most amazing world-class rocking horses that are hand carved. He
ships these things and 95 per cent are sent out of the Central Coast. It is a
small work-at-home business but he has got to send really large photos to his
potential customers. He has to bank up his emails and send them out at night
time because he is in Matcham, which is not far from Erina, and the internet
connection is slow. His productivity is slow, and this is just money that
should be in our region.
2.144
Councillor Hillary Morris of Gosford City Council noted that this
problem is not isolated to Australians running small businesses from home; it
extends to employees of larger companies who work from home:[106]
I know of a woman who works for an international company that
is based in California. There are 50 employees who all work from home; she is a
translator and works on translating brochures, information, pamphlets et cetera
for many organisations. The company has people in Europe, Thailand, the
Philippines, India and America, and she works from a home office in Tascott.
She has two wireless modems and mobile phone hotspots that she has to implement
to download and upload her work, and often, when she is having
videoconferencing or is trying to download files to be able to quote on work,
she experiences a meltdown and cannot download her information or, if she does
download it, it takes a long time.
2.145
During the 11 March committee hearing, a local year 11 student, Mr Nick
Patsianas, asked the committee if he could have the opportunity to speak about
this issue.[107]
He noted the importance of uploads to education outside the classroom:
Video is the next thing. In school we learn in a classroom,
but we also learn out of the classroom, and video is a great way of doing that.
At our school, we are looking into a video platform to directly tie video from
the internet to our learning. There is a guy on YouTube I know, he goes by the
name of Eddie Wu, and he records all his lessons—every single lesson. I am not
sure if he has access to the NBN or not, but uploading every single lesson he
records would take a very long time on an ADSL connection. But, if he is on the
NBN, he would be able to do that easily. Heaps of students watch him. I watch
him; he has helped me so much.
2.146
At the Additional Estimates Hearing on 25 February, Dr Switkowski said:[108]
Dr Switkowski: I think if you were a small business
doing software development and moving large files between locations, hundreds
of megabytes per second can be very useful. For example, if you were doing
special effects in 3D movies, which some enterprises in Australia do in support
of Hollywood studios, they would need that kind of bandwidth and usually have
options for getting it, not waiting for NBN to provide a reticulated retail
network to do it. There will be others where the information is very data rich.
Large quantities of MRI scans et cetera that move from point to point will
require lots of bandwidth. Again, those institutions, by and large, have put in
place physical infrastructure that provides it today, as do universities. I
think the difficulty is that there are applications and organisations that use
lots of bandwidth, including big businesses. They have made their own
provision, as they always do. In terms of the retail and domestic market, it
really is hard in any practical sense to describe the activities of a family,
even with hyperactive teenagers, that would get anywhere near 100 megabytes per
second any time soon.
2.147
As set out above, in the Half Yearly Results briefing NBN Co provided
data that showed over 20 percent of NBN Co’s fibre customers select a 100 Mbps
service. This trend has been visible for many years. Despite this, the CEO of
NBN Co continues to assert that Australian households—which include multiple
small businesses, people who work for large businesses but work from home, and
students who require video to continue their education outside the
classroom—have no use for this service. Moreover, the CEO of NBN Co continues
to focus only on download speeds as key measure of broadband quality. The same
narrow focus is evident in the Strategic Review.
2.148
NBN Co was asked questions in writing to justify the revenue assumptions
set out in the Strategic Review.[109]
At the time of writing answers to these questions had not been provided. The
significance of these factors to the NBN Co business model was canvassed during
the public hearing on 28 November 2013.[110]
The Committee also asked NBN Co for financial scenarios that included the
impact of the three factors—reduced unit revenue, increased costs and a longer
deployment period—if each was conducted separately. NBN Co has replied:
The information referred to above was not prepared in these
terms at the time of the Strategic Review and is not available.[111]
Summary—Revenue Assumptions
(Revised Outlook)
-
The committee considers that the revenue assumptions in the
Revised Outlook are overly pessimistic.
-
These revenue assumptions do not reflect existing take up and
usage of NBN Co fibre products. These assumptions also ignore demand for
broadband quality, and particularly uploads, in the residential and small
business market. The committee notes that failure to consider broadband quality
beyond download speeds is a systemic fault in the Strategic Review.
-
The committee considers that these assumptions remove revenue
benefits from the superior product set available on FTTP, compared to other
technologies.
Assumptions of price increases
2.149
Section 4.4.3 of the Strategic Review sets out an ‘illustrative’
analysis of retail and wholesale pricing. This section states that in order to
achieve an internal rate of return (IRR) of 7.1% for the Revised Outlook,
prices would need to increase by 50-80 percent. This is then converted to a
retail price increase of $27-$43 per month:[112]
The required minimum price increase to deliver a 7.1 percent
IRR are also illustrated with the impact on a 50/20Mbps service, assuming a
current cost to consumers of ~$75-95 per month. The prices here are used for
illustrative purposes only.
-
The Revised Outlook would requires [sic] price increases of 50-80
percent (e.g. $27-43 more per month for a 50/20 Mbps service on top of the
illustrative ~$75-95 today).
2.150
The committee notes that the price increases are hypothesised on
recovering an inflated peak funding amount (approximately $73 billion) that is
based on the assumptions detailed above—deployment delays and revenue
consequences, a third satellite, inflated capital expenditure with no build
efficiencies, et cetera. The committee also notes that these hypothetical price
increases are based in part on assumptions of ARPU declines in the Revised
Outlook.[113]
2.151
The committee also notes that the ‘illustrative’ examples provided are
based upon a 50/20Mbps service. The selection of this speed tier to illustrate
these hypothetical price increases is odd. In statements to Parliament, the
Minister has characterised this service as representative of a ‘typical
household.’ For example, on 12 December 2013, the Minister said that the
Strategic Review confirms that:
Costs are so high that they will add $43 per month to a
typical household’s broadband bill.[114]
2.152
Putting to one side the fact that the Minister has quoted the highest
end of the hypothetical range ($27-$43), as set out above, the 50/20mbps plan
is chosen by only 5 percent of retail customers. The committee is also reminded
of Mr Abbott’s statement at the launch of the Coalition broadband policy that:
We are absolutely confident that 25 megs is going to be
enough, more than enough, for the average household.[115]
Summary of findings—Revised Outlook
The Revised Outlook:
|
Effect on NBN financials
(to new forecast end date)
|
• excludes ‘business as usual’ architecture savings
signed off by previous NBN Co management, and characterises them as ‘radical’
for inclusion in Scenario 2
|
CapEx + ~$4 billion
|
• assumes a delay in the revised deployment schedule
that is at odds with NBN Co’s current run rate, reflects deliberately
conservative estimates of premises passed at peak rollout, and cannot be
disentangled from political control of the speed of network deployment
|
OpEx + ~$5.4 billion
Interest + ~$7.5 billion
Revenues – ~$11.6 billion
.................................
Peak funding + ~$13 billion
|
• includes assumptions on (redacted) higher unit costs
for the fibre build that are at odds with recent evidence from NBN Co and the
Department of Finance, and are extrapolated out to 2024 without a single
efficiency saving for three years, and only 2.5 percent in two of the
remaining seven years
|
CapEx + ~$14.4 billion
|
• includes a third satellite without direct
explanation, with launch assumed at such a time (FY2021) to include costs but
exclude revenues from scenario comparisons
|
CapEx + ~$?
|
• makes overly pessimistic revenue assumptions that do
not reflect existing strong demand for NBN services, or the high data usage
patterns of Australians using the NBN; ignore demand for important elements
of broadband quality, particularly reliability and upload speeds; and remove
revenue benefits from the superior product set available on FTTP, compared to
other technologies
|
Revenues – ~$2 billion
|
The Strategic Review also includes apples-and-oranges
scenario comparisons that include costs and revenues for the MTM build at
assumed completion, and costs for the Revised Outlook out to 2024, but exclude
revenues for the Revised Outlook beyond 2021.
Committee Analysis – Multi Technology Mix
Overview
2.153
The Strategic Review was required to consider alternatives to the
current FTTP model to fulfil the requirements of three parts of the terms of
reference, being:
-
The estimated cost and time to complete the NBN if variations
were made to the current plan such as increased use of fibre-to-the-node (FTTN)
in established (brownfield) areas
-
The economic viability of NBN Co under alternative strategies
-
The implications of capital costs and principles of cost recovery
on wholesale and consumer prices under existing and alternative strategies[116]
2.154
In examining alternative strategies for the NBN, the review undertook a
comparative evaluation of a number of scenarios. Four scenarios were considered
as alternatives to a full FTTP roll out in the fixed line footprint. These are:
-
Scenario 3: FTTN short loop/FTTB large MDUs;
-
Scenario 4: HFC in HFC footprint;
-
Scenario 5: FTTN and HFC (no demobilisation); and
-
Scenario 6: Optimised Multi-Technology Mix.[117]
2.155
The Strategic Review provided a summary of Scenario 6, the Optimised
Multi-Technology Mix (MTM) approach:
There are many ways for NBN Co to deliver a multi-technology
approach. In this scenario, NBN Co selects which technologies will be rolled
out on an area-by-area basis, in a way that minimises peak funding and
maximises long term economics, while delivering 50Mbps to a significant
proportion (~90 percent) of the fixed line footprint by end of CY19 (covering
all areas, both broadband-served and –underserved). The technology selection by
area takes into account:
-
The earliest available technology that provides a certain speed
for that area;
-
The relative cost position (build Capital Expenditure, ongoing
Capital Expenditure and
-
Operating Expenditure) of the various technologies;
-
The constructability in relation to neighbouring areas;
-
The implications on future revenue realisation; and
-
The potential future upgrade path.[118]
2.156
The Strategic Review recommended scenario six as the preferred scenario,
explaining:
NBN Co recommends that it develops an optimised
multi-technology approach to rolling out the NBN that balances fast deployment
of 50Mbps broadband with better economics, to the highest number of
Australians.[119]
A further argument the review advanced in favour of the optimised
multi-technology mix approach is that it would provide NBN with:
...the flexibility to adapt over time. It allows NBN Co to
adjust its technology mix dynamically to leverage future technological
improvements across all types of networks (copper, fibre and HFC) and to
reflect changes in customer demands.[120]
2.157
The committee reiterates its concerns about the heavily redacted nature
of the public version of the Strategic Review. As noted, the Strategic Review
underpins a potential Commonwealth investment of more than $40 billion—not
including flagged technology upgrades—and should be made available to the
Parliament, in accordance with the Minister’s many undertakings on transparency
and accountability. During the public hearing on 17 December 2013, the committee
put to Dr Switkowski the stark difference between the Strategic Review and
committee experience in previous Parliaments:
Senator LUDLAM: But we are being asked to accept the
entire basis for this project being financially and commercially viable on the
basis of a couple of blacked-out rectangles.
Dr Switkowski: Might I say that this is a step ahead
of anything else you might have been asked to comment upon.
Senator LUDLAM: No, it is not. I have been working on
these committees for five years now and we have been provided with full
financials to the company, apart from one period where the background material
for the expert panel was not provided to anybody, including the Senate, in
2009.
Dr Switkowski: I stand corrected.[121]
2.158
This section considers the detail of the MTM approach, including an
evaluation of the assumptions therein. The assertions regarding cost of
upgrades and the related methodology issues will also be examined. First,
however, the Committee notes that NBN Co provided detailed analysis of the
implementation of the Coalition broadband policy during the caretaker period.
The following section analyses the circumstances leading to the provision of
this advice.
Caretaker advice
2.159
At the public hearing on 11 December 2013, the Secretary of the
Department of Communications, Mr Drew Clarke, explained the process for the
preparation of briefing material for a returning Government or an incoming
Government:[122]
Mr Clarke: Once the official caretaker period
commences, the department starts preparing what is colloquially known as the
'red book' and the 'blue book', the two incoming government briefs for the
alternative election outcomes. Given that we had in front of us at that time an
extensive policy statement by the then opposition, we requested advice from the
company on issues that would need to be considered, should the company find
itself in a position of having to implement that policy. So we wrote, we asked
questions and we received documents, and the department incorporated the advice
that it received, looked at it, made judgements and incorporated that advice in
our preparation of the incoming government brief—the blue book in this case.
2.160
Further information about the “advice from the company on issues that
would need to be considered, should the company find itself in a position of
having to implement that policy” was outlined during the same hearing:
Senator SMITH: I want to go back the question that I
was asking before. What date did the letter come from the department to NBN Co.
requesting material to support it in its preparation of the blue book or the
red book?
Mr Cooney: I will have to take the exact date on
notice. It was shortly into the caretaker period.
2.161
The answer to this question on notice stated that:[123]
The request from the department was dated 5 August 2013.
2.162
Mr Cooney confirmed at the 11 December hearing that NBN Co did not
commence the preparation of the caretaker advice until 6 August 2013:
Senator SMITH: So despite the fact that the election
for a long time was going to be held on 14 September, NBN Co. did not do any
work or prepare any materials for a request that you knew would come from the
department to prepare material for a blue or red book?
Mr Cooney: No. We began the process that you are
talking about on the day after we received that request. Individual people were
aware of different options and were looking into those just as part of working
within the industry, true. But any preparation in response to the request from
DBCDE came after that.
2.163
An answer to a question on notice described the nature of the written
advice that NBN Co supplied to the Department of Communications during the
caretaker period.[124]
This document states:
At the commencement of the caretaker period on 5 August 2013,
DBCDE requested that NBN Co provide information on a series of topics. This
information was provided progressively to DBCDE from 14 August 2013. Following
this, the dispersed information that had already been provided progressively to
DBCDE was collated into one Board paper for presentation to the Board at its
meeting on September 20, 2013.
2.164
On 29 November 2013, a document obtained by Fairfax described as “NBN
Co’s internal analysis for the incoming Abbott government” was cited in an
article in the Sydney Morning Herald called “Confidential briefing: NBN
unlikely to meet Coalition's deadline.”[125]
The full document was later published on the Delimiter website.[126]
The document is 163 pages long, exhibits “FOUO: Board” in the footer, and
contains NBN Co’s full analysis of the issues involved with implementation of
the Coalition broadband policy. On page 56 it states:
2.165
The committee considers that this document (or collection of documents)
is NBN Co’s input into the ‘blue book’ developed by NBN Co and “provided
progressively to DBCDE from 14 August 2013.”
2.166
In an interview on Channel 9 on 29 November 2013, Minister Turnbull
stated in relation to the leaked document that:
What they’ve got is, they’ve got a document which was
prepared at the Labor Government’s request more than six months ago by the NBN
Co management....this document is A: out of date, B: it is defending a failed
project. It has no credibility, absolutely none.[127]
2.167
The Committee understands that the Delimiter website invited Turnbull to
retract his comment on national television that the document had been created
six months ago for the Labor Government. The website reports that “Turnbull’s
spokesperson has not responded to a request for the Minister to retract the
comment.”[128]
2.168
As the Department of Communications has refused access to the Incoming
Government Brief, and the Minister has not accepted invitations to provide it
himself, the Committee is unable to ascertain how much of the NBN Co advice was
included in the Incoming Government Brief.[129]
However, noting the importance of the National Broadband Network within the
communications portfolio, and the serious issues with implementing a key
Coalition policy identified in the NBN Co caretaker advice, it is the
Committee’s view that the Departments of Communications and Finance had a clear
duty to include in the Incoming Government Brief all substantial information
contained in the caretaker advice from NBN Co dealing with the implementation
of the Coalition broadband policy.
Summary of findings—Caretaker
Advice
-
On 5 August 2013, the Department of Communications wrote to
NBN Co requesting advice from the company on issues that would need to be
considered to implement the Coalition broadband policy. NBN Co commenced
developing this material on 6 August 2013, and provided its advice progressively
to the Department from 14 August 2013.
-
NBN Co’s advice to the Department was later collated into one
Board paper for consideration on 20 September 2013. The collated advice from
NBN Co to the Department was leaked in November 2013, and is available on the
Fairfax and Delimiter websites.
-
The committee considers that all substantial information from
this advice dealing with the issues/problems of implementing the Coalition
broadband policy was included in the Incoming Government Brief.
Methodology
2.169
A significant deficiency in the comparative evaluation used in the
Strategic Review is a primary focus on cost per premises. The Strategic Review
notes that:
The key measure of rollout cost is Cost Per Premises. This is
not a tightly defined measure, however, international benchmarks provide useful
comparisons for consideration by NBN Co.[130]
2.170
To the extent that service capability was considered, the Strategic
Review only focussed on download speeds. Other characteristics of broadband
quality—such as latency and jitter—were not considered. In particular, the
Strategic Review is silent on the upload speeds of alternative technologies. As
noted above, this is systemic fault in the Strategic Review. As iinet noted in
its submission:[131]
2.171
The committee also has concerns with elements of the MTM approach which
reflect incumbent rollout strategies. For example, the Strategic Review states
that FTTP should be built in brownfields areas:
where it is the most economical choice: either because of
high revenue potential (especially in business areas) or because of the high
cost associated with deploying FTTN/dp.[132]
2.172
Similarly, the Strategic Review assumes that:
FTTN is concentrated in areas with relatively short-loop
lengths and (relative to FTTP) lower revenue potential.[133]
2.173
The MTM openly advocates deploying higher quality technologies (FTTP) in
areas with high revenue potential and cheaper technologies in areas with lower
revenue potential.
2.174
The committee rejects a strategy that tailors deployment technologies on
the basis of the socioeconomic profile of a rollout area. This is appropriately
the prerogative of private enterprise, and reflects to a large extent the
existing distribution of privately-funded broadband infrastructure in
Australia. It is not an appropriate rollout strategy for a taxpayer-owned
company charged with correcting market imbalances by providing high-quality
broadband to all Australians.
2.175
A similar approach is evident in the Fibre on Demand product expected to
be offered on the MTM. The Strategic Review is mostly silent on this
product—noting only that there are policy issues to be resolved. However, the
potential pricing of this product—which uses taxpayer investment to subsidise
the fibre link from the Fibre Access Node (FAN) to the FTTN Node—was discussed
as the 12 March public hearing:[134]
Senator CONROY: Are you aware that Openreach has
recently increased the prices for fibre on demand in the UK? From 1 May this
year it will cost somewhere between A$4,100 and A$13,200 in the first year to
buy this service, not including usage. Are you aware of those—
Dr Switkowski: I had not heard the details—
Senator CONROY: Let me take you through it so that you
are fully aware. Mr Turnbull keeps telling you to look at BT. For a premise
less than 200 metres from the node it will cost 300 pounds—that is about
A$550—for the upgrade, plus 750 pounds or A$1,380 to connect, plus 1,188 pounds
or about A$2,200 for the annual rental charge. That is for 200 metres. For a
premise two kilometres from the node it is 6,000 pounds or about A$11,000 for
the upgrade, plus 750 pounds to connect, which is A$1,300, and 1,188 pounds or
A$2,200 for the annual rental charge.
2.176
Dr Switkowski noted subsequently:
I think BT Openreach is not a bad reference point for much of
what we are thinking about.
2.177
One of the contributors to the Central Coast Broadband Alliance
submission, Ms Da Costa, noted that:[135]
Large business can afford the cost of connecting from the
node, but small business - where most Australians are employed - cannot.
2.178
This issue was discussed further at the 11 March committee hearing:[136]
Senator CONROY: Gosford have got it for free but you
guys may have to pay thousands and thousands of dollars just to get it
connected. Is that fair? Can you afford that sort of impost?
Dr da Costa: I do not think businesses can. As the
executive officer of the chamber of commerce, I am chasing people who are
struggling to pay their chamber of commerce membership fees—and that is a few
hundred dollars, not thousands of dollars to connect. So I think it is an
equity issue. If some businesses get cheap infrastructure and, because of the
toss of a coin, others simply have an inequitable access and an extra business
cost, that is not a level playing field in the business world. What we are
after is a level playing field. We are after a level playing field that
increases productivity, increases employment and, with respect to Austen, as a
regional area within Australia, we want to have more capacity for people to
work here, closer to home. I have spent several years commuting four hours a
day to Sydney. If you have staff who do not have to spend four hours a day
commuting, they are happier. Happier staff are more productive staff. A
work-life balance is not just a feel good thing; it is a true business decision.
What will happen to Erina is that people will try to cram into Gosford and that
will overload the infrastructure system there. We want to spread out the
business community on the Central Coast and we need equality of access to
infrastructure.
2.179
As set out above, demand for broadband quality—and particularly upload
speed—is visible in the residential market as well as the business market. This
reflects rising average data usage trends, but also small businesses in
residential premises, Australians working for large businesses from home, and
the increasing bandwidth demands of health and education services being
delivered to—and from—the home. This demand is evident before other
factors—such as entertainment—are taken into account. The MTM, however,
reflects the views of the CEO of NBN Co that these bandwidth demands are
limited to businesses which will make ‘their own provision, as they always do.’[137]
2.180
The committee considers that access to high quality broadband—and
particularly the upload speeds made available over FTTP—will be rendered
prohibitive to many Australian households and small businesses by the user-pays
approach advocated by the current Government, and reflected in the MTM. This
will entrench widespread inequality in access to infrastructure for Australian
households and small businesses.
Summary—MTM Methodology
-
The MTM advocates deploying higher quality technologies (FTTP)
in areas with high revenue potential, and cheaper technologies in areas with
lower revenue potential. This is not an appropriate rollout strategy for a
taxpayer-owned company charged with correcting market imbalances by providing
high-quality broadband to all Australians.
-
Failure to consider broadband quality beyond download speeds
is a systemic fault in the Strategic Review. This manifests itself in the
methodology evident in the MTM.
-
The proposed Fibre on Demand product—based on BT Openreach
prices—will be too expensive for many small businesses and will entrench
widespread inequality in access to infrastructure for Australian households and
small businesses.
MTM Assumptions
2.181
The financial model for the MTM was built using primarily international
benchmarks and estimates, rather than empirical field data. Key parameters for
implementation of the MTM model include:
-
The cost, if any, to acquire Telstra’s copper from pillars to
premises;
-
The cost of building or acquiring IT systems to manage the copper
assets;
-
The cost of remediating the copper assets including removal of
bridge taps and rectification of poorly maintained joints;
-
The cost of maintaining the copper network;
-
The cost, if any, of acquiring the HFC networks;
-
The cost of integrating the HFC networks into the transit
architecture of NBN Co;
-
The cost of maintaining the HFC;
-
The cost to upgrade the HFC to increase upload speeds and reduce
contention on download speeds;
-
The cost to add an additional 700,000 premises to the HFC
networks; and
-
The cost of connecting HFC to MDUs.
The FTTN deployment recommended by NBN Co requires access to
the Telstra’s copper customer access network (CAN). The caretaker advice
developed by NBN Co on the state of the copper plant made the following points
in regard to network remediation and maintenance of the CAN:[138]
2.182
The caretaker advice further noted:[139]
2.183
The caretaker advice was corroborated by a number of witnesses who gave
testimony to the Committee, including the Communications Electrical and
Plumbing Union (CEPU), the Electrical Trades Union (ETU) and Central Coast
Telecommunications Services (CCTS). Each of these witnesses represented
workforces with direct experience of the copper plant in the field.
2.184
Mr Shane Murphy of the CEPU stated during the 28 November hearing that:[140]
Telstra fieldworkers and contractors who we represent have
been regularly reporting to the union for many years now the exact state of the
Telstra copper network right across the country. Workers' frustrations have
boiled over as Telstra has driven a culture of quantity over quality. Since the
privatisation of Telstra, maintenance budgets have been continually slashed
year in year out, thousands of skilled workers have been made redundant and the
end-result is that we are left with plastic bag joint and ring bark cable right
across the nation.
Telstra has been consistently pushing workers to simply get
the customer services up and running, bandaiding the network and moving the
employee or contractor quickly onto the next job. This has resulted in
thousands upon thousands of plastic bags and ring bark cables lying bare in the
pits and manholes across the country in every major city and regional and
remote country town. In every street or road in this country where there is a
Telstra pit or manhole, it will either have a plastic bag joint or a ring bark
cable lying bare in the pit.
I will bring you one example. Just at the weekend in Sydney I
happened to be travelling through a fairly highly-populated area in
north-western Sydney along Parsonage Road at Castle Hill past a number of
businesses and residential customers. I noticed that there was Telstra worker
from Victoria working in Sydney due to the number of customers off the air up
there and I stopped to have a quick chat. In the space of 300 metres of this
road at Castle Hill where the Victorian linesman was working, in five different
pits were three plastic bags and two ring bark cables. This was all in the
space of about 200 or 300 metres—and we did not walk the whole street. Some of
those photos are provided for the committee today.
This provides the committee with a sample of just how bad it
is out there, and Telstra relies upon statistics to continually hide the real
problem of how bad the Telstra copper network is. The union relies upon actual
evidence provided by workers such as CNI reports, photographs and videos taken
by workers at the jobsites around the country. The union currently has a
collection of thousands of photos and videos showing the true state of the
Telstra copper network. These have been collected now for some time and the
collection is still growing by the day. Today the CEPU provides this committee
with a good sample of photos recently taken on a job by Telstra fieldworkers
across various states and territories, and I will come to this slideshow
shortly.
2.185
As noted, the CEPU provided an extensive range of pictures of the copper
plant during this hearing, taken by technicians working in the field. These are
available on the committee website.[141]
A selection of these photographs is reproduced below.
2.186
The CEPU was also asked how widespread these conditions were in the
copper network:[142]
Senator LUDLAM: Would you want to hazard a guess as to
what proportion of the pits are in that kind of condition? Parts of this
network are decades old.
Mr Murphy: I would say 75 to 80 per cent of the
network is in that condition.
2.187
At the committee hearing in Perth on 29 January 2014, CEPU
representatives showed the committee similar photos demonstrating the problems
with the Telstra copper network, including some of the more innovative
solutions which had been used by technicians:
2.188
Similarly, at the committee's 4 February 2014 public hearing in Hobart,
union representatives supplied evidence demonstrating the degradation in parts
of the Telstra copper network in Tasmania:
2.189
Mr Richter, from Central Coast Telecommunications Services (CCTS),
provided the following comments at the 11 March hearing about the copper
network in general and in the Central Coast in particular:[143]
Mr Richter: As you know, the copper network is in a
fairly sad state. It obviously needs this remediation work from Telstra for it
to achieve what the fibre to the node needs to do. That is why they are going
through and remaking the joints so you have that continuity. There is a lot of
bad network out there, there is no question about that.
Senator O'NEILL: When you say 'out there' do you mean
on the Central Coast?
Mr Richter: The Central Coast is particularly bad,
probably one of the worst. It is just the nature of the beast—it is an old
area.
2.190
Telstra representatives denied claims put to the committee by the CEPU
that the network was in poor repair. Further, from the outset, the new
management of NBN Co was publicly sanguine about the state of the copper
network, despite being in negotiations with Telstra to acquire it. At the 19
November estimates hearing, Dr Switkowski stated:[144]
Dr Switkowski: ...as best as I can tell, the copper
network continues to perform robustly and, without knowing the numbers, Telstra
must have millions of broadband customers using ADSL on copper delivering
speeds of up to—I do not know—10 megabits per second. Yes, there are pair gain
systems in the network and they are an issue—a relatively small proportion of
the 10 million plus lines. So this suggests to me that the network is still robust
and the concerns that are expressed about the network maybe not being the basis
for the next generation broadband platform, I think, are misinformed.
Senator LUNDY: That is certainly what Telstra are
saying in their advocacy at the conference that has been going on for the last
couple of days. They are talking up their copper network like never
before...given that they are currently in negotiations with NBN Co. about
accessing it. I guess we would expect that from Telstra; I must say I did not
expect it from you.
2.191
Similarly, at the 29 November hearing of the committee:[145]
Senator LUDLAM: If you did not see the testimony, I
will not labour the point, but it will definitely be worth you reviewing it,
given that you are about to take over responsibility for the network. I do not
think it is at all a safe assumption that those recommendations were adhered
to. In fact, since privatisation it appears that maintenance of the copper
network is in substantial disrepair.
Dr Switkowski: Senator Ludlam, but is it not the
case—and here I ask the question without knowing what could possibly be the
answer—in the last few years there are millions of ADSL customers and services
in Australia. If I had to hazard a guess, there would be five million or six
million running over the copper network, delivering speeds in the several- to
10-megabit-per-second range, with customer satisfaction and customer problem
report levels at what would be called normal levels that have not moved around
a lot since probably the end of my tenure at Telstra. That leads me to conclude
that the network is in reasonable condition. Also I have learnt since Senate
estimates, as I have talked to people in the industry, that work continues
around trying to establish the condition of the copper network around the
country, and various RSPs have in the past worked together to determine
initially generally a heat map of the performance of the copper network and
then specifically down to individual lines what the fault rates are in order to
perhaps better guides Telstra in their remediation plans. So I am sort of
encouraged by that level of attention to the performance of the network and
presume it can be sustained at a sufficiently good quality to take us to the
next level with VDSL.
2.192
At Supplementary Estimates in November 2013, Dr Switkowski advised that
no assessment of the state of the Telstra network had been done prior to the
Strategic Review beginning work:[146]
Senator LUNDY: In that work have you ever assessed in
what percentage of cases the copper network would not be suitable for fibre to
the node?
Dr Switkowski: It is a question in front of us. We
have most recently started the process of working with Telstra on a pilot
approach that will give us more information about fibre to the node on the
copper network and how to scale it. That may well reveal whether there are
unanticipated issues with the network.
Senator LUNDY: I will come to that, but you did not
actually answer my question which was: have you done any assessment prior to
the considerations of the strategic review?
Dr Switkowski: No, not that I am aware of.
2.193
The Strategic Review provides redacted assumptions about the extent and
cost of remediation that will be required to ready the copper customer access
network (CAN) for VDSL deployment.[147]
Without these figures, it is of course not possible for the committee to
evaluate the appropriateness of these assumptions. However, the committee notes
that the figures provided are no more than estimates. This is confirmed by the
Strategic Review:[148]
The Strategic Review did not have access to detailed or
specific data on the quality of Telstra's copper network, so field tests and
detailed network inventory data will be needed to make an accurate estimate of
remediation costs as a next step beyond this Review.
2.194
The committee notes that some of the assumptions that are transparent in
the Strategic Review are problematic and, in some cases, not supported by other
evidence. For example, the Strategic Review states: [149]
Experts and experience at ‘VDSL operators’ BT and KPN
indicate that little to no remediation has been necessary in high-speed VDSL
deployments including vectoring deployments. Their experience indicates that if
analogue voice works satisfactorily, VDSL will also work satisfactorily in most
cases, as the analogue voice signal is more sensitive to noise and poor copper
quality than digitised signals such as VDSL.
2.195
The only stated evidence for this claim is unsourced, anecdotal comments
from BT and KPN. This was reinforced by an answer to a question in writing which
noted that:
Information from BT and KPN was supplied in confidence. Both
operators stated remediation was almost never required, but quantitative
evidence was not released.[150]
2.196
By contrast, the ACMA provided the following evidence on this issue in
response to a Question on Notice:[151]
Copper twisted pair cables which are intended for telephony
services operate optimally at lower frequencies and experience greater signal
loss as frequencies increase....Voice services (300Hz to 3400Hz) are low in
frequency, compared to ADSL2+ services (25kHz to 2.2MHz), and VDSL2 (138kHz to
30MHz) are higher again. For a given thickness and length of copper, services
using higher frequency signals will experience greater degradation compared to
lower frequency signals.
2.197
It also appears that NBN Co has no information on high frequency fault
rates, which explains why the Strategic Review is silent on this matter. In an
answer to a question on notice, NBN Co said: [152]
NBN Co does not have any information on the fault rates from
“high frequency interference” on Telstra’s copper network. Telstra would be
best placed to answer this question.
2.198
The caretaker advice prepared by NBN Co points to the substantial costs
associated with remediation and maintenance of the copper network, and the consequent
increases in operating expenditure. The committee has heard similar evidence
from witnesses representing the workforce in the field. The committee notes
that the FTTN footprint proposed in the MTM (approximately 41 percent) is
smaller than the footprint proposed in the Coalition policy (approximately 71
percent). This would affect the quantum of increased operating expenditure, but
not the key point of the caretaker advice: operating expenditure for the MTM
will be significantly higher than for a new fibre build.
2.199
Exhibit 4-6 sets out the difference in operating expenditure between the
Revised Outlook and the MTM (see below). The $2.4 billion operating expenditure
for the full fibre build in Exhibit 4-6 is the same amount assumed in the NBN
Co 2012-15 Corporate Plan. However, the Strategic Review assumes operating
expenditures for the MTM that are only marginally higher—$200 million more in
FY2028.
Operating Expenditure in the ‘Steady State’
Operating Expenditure in the Corporate Plan
Summary—MTM Assumptions
-
The financial model for the MTM was built using primarily
international benchmarks and estimates, rather than empirical field data.
-
The caretaker advice prepared by NBN Co points to the
substantial costs associated with remediation and maintenance of the copper
network. The committee has heard similar evidence from witnesses representing
the workforce in the field.
-
Operating expenditure is expected to be significantly higher
for the MTM than for a new fibre network. However, the Strategic Review assumes
that operating expenditure for the MTM will be similar to what is required for
a new fibre build.
Revenue Assumptions
2.200
The caretaker advice provided evidence on the sort of “field tests” that
would be required to adequately assess the quality of broadband that would be
achievable over the copper plant:
2.201
This was corroborated by Mr Adcock at the 19 November estimates hearing:[153]
Senator LUNDY: I understand from presentations by
Alcatel Lucent that deployment of VDSL requires every copper pair to be tested.
I understand that that testing has to be done at the pillar location and will
need to be done before there is a decision to use the copper. Is that your
understanding of it? I know the copper varies enormously in quality and in its
configuration, but is NBN Co. going to insist on getting a status report on
those copper pairs before it commits to a costing around a fibre-to-the-node
network?...
Mr Adcock: The current thinking is that there would be
testing done. Whether it informs the strategic review or whether the strategic
review makes some assumptions to then be tested, I think, is the way that I
would frame it at this point. It is an unknown. But your point about testing
the copper pair for VDSL is valid.
2.202
In a submission to the committee, well-known blogger and the creator of
the independent rollout tracker myNBN.info site, jxeeno, expressed his concern
with the MTM approach, arguing that it will limit network capability based on
locality.[154]
He explained that the FTTN/dp/B and the HFC networks have problems which mean
that network speeds cannot be guaranteed. For example, the FTTN/dp/B network,
relying as it does on the existing Telstra copper network, is highly
susceptible to environmental factors such as water ingress and signal
interference.[155]
2.203
Similar evidence was given by Shane Murphy of the CEPU at the 28
November hearing:[156]
It does not matter what state—whether it is Perth, Sydney,
Adelaide or Melbourne. Look at the spike immediately after a drop of rain comes
along or there has been a bit of rain and then there is a bit of humid weather,
because we are at that time of year now. If you check the ACMA report, you will
see the spike automatically go bang. For example, Sydney alone had two or three
days of rain. Yes, it was heavy at times. It was not consistently heavy all
day, but there were some heavy showers. There were definitely some storms.
Normally Sydney runs at 2,000 or 2,500 [services down]. It was actually at
14,000 last week. It is now at 10,000, and climbing again by the day. That
gives you an example of just how bad it is. It is okay for Mr Switkowski to
say, yes, they see a spike in calls when there is a bit of rain around. The
proof is in the pudding of why exactly that is occurring. It is because the
copper can no longer withstand the water.
2.204
As noted above, the ‘steady state’ comparison of a full FTTP build with
the MTM contained in Exhibit 4-6 exhibits a marginal difference in revenues to
the MTM. Although the Strategic Review discusses ‘illustrative’ upgrade paths
and ‘hypothetical’ upgrade timing, no upgrade costs for the MTM are included in
the financial metrics set out in Exhibit 4-6.[157]
Exhibit 4-6 (Strategic Review)
2.205
In the caretaker advice, NBN Co assessed the impact on product offerings
that would result from a move to an alternative FTTN architecture.[158]
The advice states:
2.206
NBN Co assessed that these impacts could reduce NBN Co revenue by as
much as 30 percent:[159]
2.207
The caretaker advice based its financial analysis on the broadband
policy the Coalition took to the election. The committee notes that this policy
assumed a much larger FTTN footprint than assumed in the Strategic Review
(approximately 71 percent of premises in the policy compared to approximately
41 percent in the Strategic Review). This would affect the quantum of the
revenue declines, but not the key point made in the caretaker advice: that the
‘limited speeds and product capabilities’ available on FTTN would result in
reduced revenues compared to a full fibre rollout in the fixed line footprint.
2.208
In this context, the committee notes statements made by the CEO of NBN
Co in regard to 'guaranteed' access speeds for end-users. Media reports have
noted that the Minister for Communications promised prior to the federal
election minimum download speeds of 25 Mbps by 2016.[160]
The Department of Communications states the Government's aim in relation to the
NBN is:
...that all households and businesses should have access to
broadband with download data rates of between 25 and 100 megabits per second
(Mbps). At the completion of the rollout, the Government expects download data
rates between 50 and 100 Mbps to be available to at least ninety per cent of
Australians in the fixed line footprint.[161]
2.209
However, in evidence to the committee at the public hearing on 17
December 2013, Dr Switkowski refused to make any guarantee about minimum
download speeds delivered by the MTM approach:[162]
CHAIR: I understand the limitations of the technology
you have chosen and you would be foolhardy to try and promise you can deliver
on those speeds. I think you accept that.
Dr Switkowski: I think you are adding a colour that is
not intended. The conclusions of this review are summarised in this document
and they use words like 'in a certain year a certain percentage of our
customers will have access to, for example, 25 megabits per second'. That is a
perfectly accurate conclusion supported by very full analyses. I stand by it.
2.210
As set out in the caretaker advice and testimony from Mr Adcock, NBN Co
will need to conduct extensive—line by line—field tests before the speeds and
broadband quality that can be obtained in the fixed line footprint under an MTM
scenario will be known. The speeds and quality that may be offered—particularly
over the copper CAN—are too variable for this to be known at this point in
time. Nor will the CEO of NBN Co provide any guarantees. This issue was flagged
in NBN Co’s caretaker advice to the Department in August 2013:[163]
2.211
The committee notes that the Strategic Review—in the absence of
concrete performance data—assumes revenues for the MTM that are only marginally
less than the revenues for a full fibre rollout—$6.3 to $7.2 billion versus
$6.6 to $7.5 billion in FY2028.[164]
Summary—Revenue Assumptions (MTM)
-
The caretaker advice from NBN Co to Government notes that
‘limited speeds and product capabilities’ available on FTTN would result in
reduced revenues compared to a full fibre rollout in the fixed line footprint.
-
NBN Co will need to conduct extensive—line by line—field tests
before the speeds and broadband quality that can be obtained in the (non-FTTP)
MTM fixed line footprint will be known empirically. Even then, quality is
likely to be variable, particularly in the FTTN footprint.
-
The Strategic Review assumes revenues for the MTM that are
similar to those for a full fibre rollout, despite the vast difference in
broadband quality and product sets.
Complexity Creates Cost
2.212
In its submission, iiNet provided a view of the MTM approach from its
perspective as an RSP. iiNet noted that:
The NBN was initially designed to provide a national,
standardised, uniform interface to a single provider. More than 90% of all
services were planned to be delivered over FTTH technology. This simplified
design promised a beneficial reduction in the complexity and cost of operating
on-line services over the NBN.[165]
2.213
In relation to the MTM, iinet observed:
2.214
NBN Co’s caretaker advice notes that increased complexity from operating
multiple fixed line networks will not be limited to RSPs. It will drive
increased costs for NBN Co in:
-
operating small pockets of FTTP within FTTN footprints:[167]
-
business processes, people and IT system capabilities:[168]
2.215
Further, the MTM introduces significant complexities in the provision of
voice services over VDSL and HFC. The caretaker advice was clear in this
regard.[169]
These complexities extend to copper cutover and migration, which is made
considerably more complex over FTTN than is the case with the existing
migration to FTTP. The caretaker advice notes:[170]
2.216
NBN Co concludes that additional complexity will result in “material”
additions to capital and operating expenditure for NBN Co:[171]
2.217
The committee notes that NBN Co’s caretaker advice was developed under
the Coalition’s pre-election policy (which did not include the addition of HFC
to NBN Co’s operations environment). The committee considers that the addition
of HFC networks will drive even greater complexity costs than flagged in NBN
Co’s caretaker advice. Indeed, the Strategic Review indicates that it is the
intention to pursue copper disconnection in the areas covered by HFC as well:
As discussed in section 3.2.4, the scenario analysis for the
Strategic Review has assumed voice will be provided via CPE that uses VoIP. It
assumes that, as for FTTP areas, Telstra will continue to maintain and operate
the existing copper plant only insofar as required to maintain special services
(discussed in section 3.2.5), and that a similar disconnection and migration
framework applies to Telstra and Optus as exists today in relation to
disconnection and migration to FTTP.[172]
2.218
The Strategic Review factors in no additional operating expenditure to
accommodate a more complex operations and technology environment, despite Mr
Korda’s observation—noted above—that “the level of overheads [in the Corporate
Plan] was optimistic.”[173]
Rather:[174]
Operating costs in network operations are usually expected to
increase in order to support a more complex technology environment. However NBN
Co’s level of Operating Expenditure in the Corporate Plan is significant.
Benchmarks with comparable multi-network wholesale telecommunications companies
suggest there is substantial cost reduction potential in both ongoing operating
and overhead costs for NBN Co. The Strategic Review therefore assesses that cost
increases due to increased complexity can be more than offset by potential cost
reductions.
Summary—Complexity Creates Cost
-
The caretaker advice from NBN Co flags “material” capital and
operating expenditure increases from a more complex technology environment.
Increased complexity is likely to increase costs for RSPs as well.
-
The caretaker advice did not consider the addition of HFC
networks to NBN Co’s operations environment. The committee expects this will
further increase complexity costs under the MTM.
-
The Strategic Review has assumed no additional operating
expenditure to accommodate a more complex technology environment, arguing that
these costs will be offset by “potential cost reductions.”
Upgrade Costs
2.219 The Strategic
Review asserts that under the MTM model at least 65 percent of premises in the
fixed line footprint will have access to download speeds of 100mbps by CY20.[175]
The Strategic Review also provides an estimate of Net Present Value (NPV)
savings of an upgrade approach versus building FTTP today. Once again,
consideration of upload speeds or other elements of broadband quality is
completely absent from the analysis.
2.220
Section 4.3.2 of the Strategic Review analyses the upgrade paths of the
technologies employed in the MTM scenario. The Strategic Review states that all
scenarios ‘provide clear upgrade paths to higher speeds and better quality of
service for all premises served.’[176]
Upgrade paths are provided in Exhibit 4-4. These are described as
‘illustrative.’ ‘Hypothetical upgrade timing’ is also provided.
2.221
The Strategic Review acknowledges that the MTM will need to be upgraded,
although not ‘before CY2023’:[177]
2.222
No explicit costs for these upgrades are provided for the MTM model in
the Strategic Review.
2.223
The Gigabit-Capable Passive Optical Network (GPON) architecture employed
by NBN Co in the current FTTP rollout is already capable of delivering high
quality, reliable broadband including symmetrical gigabit speeds and dedicated
information rates.[178]
Further, NBN Co Corporate Plans present a 30 year business case (to 2040). NBN
Co explains:[179]
Retaining the same end point for the long range explicit
forecasting (30 June 2040) will allow ‘like-for-like’ comparisons as subsequent
Corporate Plans are produced.
2.224
By contrast, the outlook for the MTM presented in the Strategic Review
is short to medium term. No explicit costs for necessary upgrades are provided.
The committee considers that the full cost of the MTM will only be known once
flagged upgrade costs are included in the model.
Summary—Upgrade Costs
-
The Strategic Review acknowledges that the MTM will need to be
upgraded, but provides no costs for these flagged upgrades.
-
The committee considers that the full cost of the MTM will
only be known once these upgrade costs are included in the model.
Concluding Remarks and Recommendations—Strategic Review
2.225
The committee considers that the assumptions and conclusions set out in
the Strategic Review are unreliable in the case of all examined scenarios.
2.226
The Revised Outlook provides a different perspective to NBN Co’s
Corporate Plan on the costs, revenues and timeframe of a full FTTP build in the
fixed line footprint. The Committee’s concerns with the Revised Outlook
include:
-
the exclusion from the Revised Outlook of ‘business as usual’
architecture savings signed off by previous NBN Co management, and their
characterisation as ‘radical’ for inclusion in Scenario 2;
-
an assumption of a delay in the revised deployment schedule that
is at odds with NBN Co’s current run rate, reflects deliberately conservative estimates
of premises passed at peak rollout, cannot be disentangled from political
control of the speed of network deployment, and has the assumed effect of
stripping out $11.6 billion in revenues;
-
assumptions on (redacted) higher unit costs for the fibre build
that are at odds with recent evidence from NBN Co and the Department of
Finance;
-
higher unit costs that are extrapolated out to 2024 without
normal and reasonable allowances for build efficiencies;
-
the addition of a third satellite in the Revised Outlook, without
direct explanation, with launch assumed at such a time (FY2021) to include
costs but exclude revenues from scenario comparisons;
-
overly pessimistic revenue assumptions that:
-
do not reflect existing strong demand for NBN services, or the
high data usage patterns of Australians using the NBN;
-
ignore demand for important elements of broadband quality,
particularly reliability and upload speeds;
-
have the effect of removing the revenue benefits that would
result from the superior product set available on FTTP, compared to other
technologies; and
-
apples-and-oranges scenario comparisons that include costs and
revenues for the Multi-Technology Mix (MTM) build at assumed completion, and
costs for the Revised Outlook out to 2024, but exclude revenues for the Revised
Outlook beyond 2021.
2.227
The Committee has equally strong concerns about the reliability of
assumptions underpinning the MTM, the recommended option. These include:
-
the financial model for the MTM was built using mostly
international benchmarks and estimates, rather than field data;
-
operating expenditure for the MTM is expected to be significantly
higher than for a fibre network. The caretaker advice prepared by NBN Co points
to the substantial costs associated with remediation and maintenance of the
copper network. The committee has heard similar evidence from witnesses
representing the workforce in the field. Material operational costs are also
expected from a more complex technology environment. Despite this, the
Strategic Review assumes that operating expenditure for the MTM will be similar
to what is required for a new fibre build;
-
the ‘limited speeds and product capabilities’ available on FTTN
are expected to result in reduced revenues compared to a full fibre rollout in
the fixed line footprint. Further, NBN Co will need to conduct extensive field
tests before the speeds and broadband quality in the (non-FTTP) MTM fixed line
footprint will be known empirically. Despite this, the Strategic Review assumes
revenues for the MTM that are similar to those for a full fibre rollout,
despite the vast difference in broadband quality and product sets;
-
the Strategic Review acknowledges that the MTM will need to be
upgraded, but provides no costs for these flagged upgrades. The full cost of
the MTM will only be known once these upgrade costs are included in the model.
2.228
NBN Co’s previous Corporate Plans have been developed over a period of
many months, in some cases longer, and have been subject to independent
oversight and verification. For example, the 2013-16 Corporate Plan—finalised
in late June 2013—was independently reviewed by both Ernst and Young and KPMG
before it was signed off by the NBN Co Board and submitted to Shareholder
Ministers for approval. By contrast, the Strategic Review—which presents a
different view of the information set out in the NBN Co Corporate Plan—was the
result of “five weeks of intensive work on the part of lots and lots of
people” and was subject to no independent external oversight.
2.229
The committee rejects the rollout strategy advocated by the current
Government and reflected in the MTM. In particular:
-
the deployment of higher-quality broadband (FTTP) to high value
suburbs, and the deployment of inferior broadband (FTTN) to low value suburbs
is an inappropriate use of taxpayers’ money. As a Government Business
Enterprise, NBN Co should not have a rollout strategy that favours one suburb
over another;
-
the proposed Fibre on Demand product is expected to be too
expensive for many residences and small businesses. This will create
competitive disadvantages for individuals and small businesses outside the
fibre footprint, and will entrench broadband inequality in Australia.
2.230
The Committee considers these rollout strategies reflect a fundamental
misunderstanding of broadband quality—particularly uploads—and demand for this
quality and reliability in the residential and small business market. Failure
to consider that broadband quality and capability goes beyond download speeds
is systemic in the Strategic Review. The Strategic Review also fails to
consider the value of widespread access to this infrastructure to the digital
economy.
2.231
The Committee concludes that the Strategic Review does not comprise a
sufficient information base for the NBN Co Board or the Minister to adopt an
alternative deployment path for the NBN.
2.232
The Committee is aware of management concerns with building stability
with its supply partners. As a consequence, NBN Co should be directed to
continue the FTTP roll out at the maximum rate possible while the further
analysis is undertaken by NBN Co, the Departments and the Minister. NBN Co
should be allowed to proceed without political interference in the roll out.
Recommendation 1
NBN Co should submit a revised Strategic Review that
provides transparent assumptions and corrects deficiencies and distortions. The
revised Strategic Review should provide details of only two scenarios:
-
An optimised FTTP rollout that adopts the technology changes
and other management initiatives outlined in Scenario 2, together with a plan
to address identified industry capacity constraints; and
-
A revised Multi-Technology Mix that is based on actual costs
for FTTN and HFC derived from discussions with Telstra, Optus and vendors. This
scenario should also include all costs to undertake the flagged upgrades to 100
Mbps by 2023, 250 Mbps by 2028 and 1000 Mbps by 2030.
The revised scenarios should include consideration of
broadband quality beyond just download speeds, and the demand for attributes
like upload speeds and reliability in the residential and small business
market.
Prior to submission, the Strategic Review should be
scrutinised and verified by an independent advisor engaged by the Department of
Communications and the Department of Finance.
Recommendation 2
NBN Co should continue to accelerate the roll-out of the
FTTP network while further analysis is undertaken.
NBN Co should be allowed to proceed free from political
interference.
Navigation: Previous Page | Contents | Next Page