The Christmas Island Immigration Detention Centre Project Update

Print Appendix B (PDF 40KB) < - Report Home: Appendix A

Appendix B: Table of Budget Increases

 PWC Budget (2003)

INCREASE 1:
Construction Works
Market Testing (Dec 04)

INCREASE 2:
Project Delays
(Feb 05)

Current Budget

Finance

Fees
Project management $2,800,000   $3,700,000 $6,500,000
Design $8,790,000   $6,710,000 $15,500,000
Sundry fees and costs $500,000   $4,500,000 $5,000,000

Total fees

$12,090,000

 

$14,910,000

$27,000,000

Construction
Building works (accommodation) $33,909,000      
Building works (ancillary) $39,543,000      
External works $24,024,000      
Works off site $5,944,000      
Other costs $50,213,000      

Total construction

$153,633,000

$59,300,000

$45,090,000

$258,023,000

Allowances
Contingency $7,532,000      
Escalation $4,500,000      

Total Allowances1

$12,032,000

 

 

$12,032,000

Sub-total

$177,755,000

 

 

 

Expenditure prior to 2003 hearing

$19,945,000

 

 

$19,945,000

FINANCE

 

$197,700,000

$59,300,000

$60,000,000

$317,000,000

DoTARS

 

$58,000,000

 

 

$58,000,000

DIAC

 

$20,500,000

 

 

$20,500,000

TOTAL

 

$276,200,000

 

 

$395,500,000

Notes:

1  Allowances’ can be treated as construction costs, and have been expended.

 

 


Print Appendix B (PDF 40KB) < - Report Home : Appendix A