Budget Review Article, 2024-25

Defence changes course to implement national defence strategy

Author

David Watt, Nic Brangwin, Karen Elphick

Go to section

Introduction

After the 2024 National Defence Strategy (NDS) and revised Integrated Investment Program (IIP) the Defence budget was predictable, but not business-as-usual.

The 2023 Defence strategic review (DSR) recommended far-reaching changes to the Australian Defence Force’s (ADF) strategic posture and capability in response to what it termed ‘radically different’ strategic circumstances (pp. 17 and 23). The DSR explained that intense China-US competition is the defining feature of our region and our time, and Australia now faces the prospect of major conflict directly threatening its national interest.

The 2024 NDS described further strategic deterioration and the IIP identified necessary force structure changes (see below); parts of the budget papers read quite differently as a result.

Large increases in defence funding, but not yet

In 2024–25 Defence (including the Australian Signals Directorate and the Australian Submarine Agency) will get $55.7 billion, which the Minister for Defence’s Budget media release states should rise to approximately $100 billion by 2033–34. The resourcing section of the NDS stated that this funding line involved an additional $5.7 billion across the forward estimates and $50.3 billion over the decade to 2033–34. As Table 1 shows, despite a worsening strategic outlook, budget planning has not changed much between the 2020 Defence strategic update and the 2024 NDS.

Table 1 Defence funding

$b

2024–25

2025–26

2026–27

2027–28

Defence strategic update

55.5

58.1

61.2

64.6

NDS

55.5

58.4

61.2

67.9

Defence budget 2024–25

55.6

58.4

61.0

67.46

Sources: Australian Government, Portfolio Budget Statements 2024–25: Budget Related Paper No. 1.3A: Defence Portfolio, 2024, Table 4a, 16; Australian Government, National Defence Strategy, Department of Defence, 2024, 67; Australian Government, 2020 Defence Strategic Update, Department of Defence, 2020, 54.

It is apparent from the table that the largest portion of the $5.7 billion increase comes in the final year of the forward estimates. This has troubled some commentators because Defence’s buying power does not increase much until 2027–28 and it has to some extent been undermined by the inflation spikes of the past few years (for which the Defence Budget has not been adjusted). As Strategic Analysis Australia’s Marcus Hellyer has written:

It’s an increase of $2,356 million (4.4%) in nominal terms over the 2023-24 budget, but only $889 million (1.6%) in real terms. That means this year Defence is only just keeping its nose ahead of inflation.

Hellyer goes on to say:

Many commentators have noted the vast bulk of this funding sat outside the forward estimates in the last six years of the decade. From the PBS we can see that it’s even worse than that: $3.8 billion of the $5.7 billion sits in 2027-28, the final year of the forward estimates – at least one and maybe two elections away. That means there’s only $1.9 billion of new money in the next three years. It’s one of the glaring discrepancies between the Government’s stated assessment of the need for urgency in light of our rapidly declining strategic environment and its funding model—it’s only increasing the funding line it inherited from the previous government by around 1% over the next three years.

Are the submarines distorting the defence budget?

Another issue attracting comment has been the dominance of the AUKUS nuclear-powered submarines and the general-purpose frigate program in the $50 billion of increased funding across the decade. Marcus Hellyer breaks down the $50 billion as follows:

  • $38.2 billion of the released contingency reserve (the initial $30.5 billion plus the first year of the on-going $7.7 billion—this covers the SSN funding gap
  • $11.1 billion previously announced by the Government to cover the general purpose frigates
  • the $1 billion listed above to accelerate delivery.

The question will be whether the $1 billion noted above plus the as-yet-unknown funding being found as a result of the reprioritised IIP will be sufficient to meet the ADF’s other needs.

Where are the savings?

Substantial new spending in some acquisition projects is revealed in the 2024–25 portfolio budget statement (PBS), including $2,591 million for the nuclear submarine project (DEF 1). However, the overall expenditure for approved military equipment acquisition projects has increased by only $679 million for 2024–25, and overall new spending for Defence is just $400 million. There must, therefore, be nearly $2 billion in reductions, but they are hard to find.

Much of the spending in this Budget appears to have been achieved by ‘reprioritisation’. That is, the government has juggled project schedules, bringing some capability acquisition forward while slowing or reducing spending on other projects. The Defence Minister previously identified ‘an initial $7.8 billion reprioritisation’; however, the government has not provided a list of the affected projects.

Future defence annual spending is planned over a 10 to 20-year timeframe. Money is notionally allocated to various projects and schedules adjusted to smooth Defence spending. Adding a large project, like the nuclear submarines or the general-purpose frigates, means other planned, but not yet funded, projects must be cancelled or delayed to avoid a big jump in annual spending. Several acquisition programs which appeared in the 2020 Force Structure Plan or had been announced, are now absent from the IIP. Chief among those is the cancelled Attack class submarine program. Other reductions include:

  • the delay or cancellation of programs to acquire:
    • a fourth squadron of F-35 JSF combat aircraft
    • a second regiment of AS9 Huntsmen self-propelled howitzers (LAND 8116)
    • medium-range missile defence systems (AIR 6502)
    • 2 sea lift and replenishment ships.
  • reducing the planned 450 Redback infantry fighting vehicles to 129 (LAND 400 Phase 3)
  • early retirement of 2 Anzac class frigates, which reduces planned sustainment and upgrade costs
  • a more limited Anzac class frigate upgrade.

Strategy of denial – prioritising long-range strike and ADF resilience

The NDS states that a strategy of denial will become the ‘cornerstone’ of defence planning (p. 7). To counter emerging threats, the ADF must be able to deny an adversary freedom of action by demonstrating the capability and resolve to respond to attacks on Australian territory and further offshore along critical sea lines of communication (NDS, pp. 21–25). Necessary changes identified by the IIP include:

  • increasing long-range strike capability and littoral manoeuvrability
  • improving ADF operating resilience through increased interoperability with allies, deepening munitions stockpiles and hardening northern bases to survive attack
  • accelerating local production of munitions, guided weapons and other systems to reduce vulnerability in long supply chains for Australia and allies.

The key long-range strike capability, and the one that dominates the Defence budget, is the nuclear-powered submarine program.

Nuclear-powered submarine program

Australia’s acquisition of nuclear-powered, conventionally armed submarines is a key part of the AUKUS Partnership announced on 16 September 2021. On 14 March 2023 the pathway for this acquisition was revealed. The main elements involve:

  • developing Australia’s industrial capacity to support nuclear-powered submarines (NPS) through increased UK and US submarine visits to HMAS Stirling, WA. This will evolve into the Submarine Rotational Force – West from 2027
  • acquiring at least 3 (potentially 5) Virginia class submarines from the US in the early 2030s
  • constructing a new class of submarine, SSN-AUKUS, with the UK constructing the first of class in the late 2030s and Australia building its first, in Australia, in the early 2040s.

The Defence Minister stated that the cost of the NPS program would roughly amount to 0.15% of GDP for the life of the program, which Prime Minister Albanese estimated could be ‘between $268 billion and $368 billion’. Last year, the Parliamentary Budget Office estimated the amount to be $367.6 billion in out-turned dollars, which included a $122.9 billion contingency.

The 2024 IIP provided $53 to $63 billion of planned investment from 2024–25 to 2033–34, of which $13 billion was approved and $40 to $50 billion unapproved (IIP, pp. 15, 24 and 29).

Given this undertaking, it is unsurprising the NPS program is the most prominent feature of the 2024–25 Defence budget and will be for decades to come.

The newly established Australian Submarine Agency (ASA) is a new line item in the ‘Funding from Government’ table in the 2024–25 PBS (Table 4a, p. 16) and a new section is dedicated to the ASA near the end of the PBS (pp. 183–202). ASA’s actual estimated funding for the current financial year is $243.4 million, with regular annual increases peaking at $527.4 million in 2026–27, then reducing to $378.1 million in 2027–28. Funding over the forward estimates totals $1,719 million (p. 16).

The NPS program is funded in the 2024–25 Defence Budget under the IIP, with its budget and expenditure shown in Defence Program 2.16 (2024–25 PBS, p. 184). This is separate from ASA funding, although ASA is responsible for the expenditure of Program 2.16. The 2024–25 Defence Budget allocates more than $11.8 billion over the forward estimates to Program 2.16 (this figure excludes the estimated actual figure of $475.2 million for 2023–24) (2024–25 PBS, p. 92).

Figure 1 below illustrates the long-term funding statements in line with current budget allocations. The 2024–25 Defence Budget figure is a consolidated ASA and Program 2.16 figure.

Figure 1        NPS program expenditure over the life of the program

Source: Richard Marles (Deputy Prime Minister and Minister for Defence), ‘AUKUS’, transcript, 14 March 2023; Anthony Albanese, Questions Without Notice: AUKUS, House of Representatives, Debates, 27 March 2023; Australian Government, Portfolio Budget Statements 2024–25: Budget Related Paper No. 1.4A: Defence Portfolio, 16; 92.

For the first time, the NPS program is listed in the Top 30 military equipment acquisition program table and identified as DEF 1 (PBS, Table 54, p. 127). It shows an approved total project expenditure of $13.6 billion over the forward estimates (this figure includes acquisition costs totalling $11.8 billion and other project inputs totalling $1.8 billion), which shows around $2.6 billion is to be expended in 2024–25.

Where these funds are being directed is not clear. The project description notes the ‘project includes a fair and proportionate contribution to our AUKUS partners’ submarine industrial bases …’ (p. 127). ASA’s February 2024 Additional Estimates briefing notes state the proportion of investment towards the US submarine industrial base is estimated at US$3 billion. The 22 March 2024 announcement on the Australia-UK Submarine Strategic Partnership stated Australia would contribute £2.4 billion over 10 years to ‘expand the Rolls-Royce facility in Derby in the UK’. While media reports converted these amounts to Australian dollars (an estimated A$4.7 billion for the US and A$4.6 billion for the UK), the actual costs at the time of transfer will be subject to currency fluctuations.

Additionally, there are 2 major infrastructure projects related to DEF 1:

The 2024–25 Defence budget also includes NPS sustainment costs (p. 17). While the figures are relatively low, totalling $322.8 million from 2023–24 to 2027–28, this product (along with Guided Weapons and Explosive Ordinance sustainment) has been reclassified from Other Minor Sustainment to separate line items in the PBS.

Reprioritisation – notable funding changes in military equipment acquisition and sustainment

Library analysis suggests that many of the Top 30 acquisition and sustainment projects underspent in 2023–24 have also had spending reduced for 2024–25. However, any changes among the hundreds of projects that do not appear in the Top 30 tables are not visible in the Budget.

The tables below show notable increases and reductions in Top 30 programs. Where an increase appears due to a program underspend being carried forward, no change to spending is noted. If the full underspend is not brought forward, it is treated as a reduction.

It is important to be aware that variations in annual spending are normal; expenditure is not even across each year of a big acquisition project. Annual spending is typically low during the design phase, rises to a peak through acquisition (which is longer for long-term build projects) and slowly declines through the sustainment phase. It is only possible to know with certainty that a particular project has been decelerated or accelerated by comparing tables of planned annual spending – which are not visible in the Budget.

Air domain

Table 2 identifies air domain spending that has increased and Table 3 outlines reductions in spending. The IIP requires that the Royal Australian Air Force deepen stocks of air-launched missiles. While AIR 6004, the project to acquire the JASSM ER missile, appears to have been substantially boosted, the increase is largely due to its merging with AIR 3023, the project to acquire Long-Range Anti-Ship Missiles. While there is still a significant boost in overall approved expenditure, annual spending for the 2 projects combined has slowed.

Spending for the EA-18G Growler (AIR 5349) at first glance also seems to have jumped, but again it appears that the previously separately funded Phase 3 (airborne electronic attack capability upgrade) and Phase 6 (next generation of major EA-18G upgrades) have been integrated and annual spending has slowed. By contrast, both the P-8A Poseidon maritime surveillance aircraft acquisition and capability upgrade and sustainment programs have been given increased funding. Hardening of northern bases is an area prioritised by the IIP, however, airfield capital works for Curtin, Tindal and Townsville had a significant underspend last year and reduced funding this year.

Table 2         Air domain new and increased spending ($m)
Project Approved expenditure at 2023–24 PAES Approved expenditure 2024–25 Revised budget estimate at 2023–24 PAES Estimated expenditure 2023–24 (a) Budget estimate 2024–25
Air-launched multi domain strike
(AIR 6004)
now includes AIR 3023
576 2,508 180 486 412
P-8A Poseidon
(AIR 7000)
6,624 8,448 145 352 274
P-8A Poseidon sustainment (CAF35) - - 187 - 247
MC-55A Long-Range ISREW Aircraft sustainment (CAF40) - - 88 - 130

(a) Calculated by subtracting Cumulative Expenditure to 30 June 2023 in Table 64 of 2023–24 portfolio additional estimates statements (PAES) from Estimated Cumulative Expenditure to 30 June 2024 in Table 54 of the 2024–25 PBS.

Source: Parliamentary Library calculations

Table 3         Air domain spending reduced ($m)
Project Approved expenditure at 2023–24 PAES Approved expenditure 2024–25 Revised budget estimate at 2023–24 PAES Estimated expenditure 2023–24 (a) Budget estimate 2024–25
MQ-28A Ghost Bat (AIR 6014)
previously DEF 6014 Phase 1
858.0 858.0 364.0 283.0 212.0
EA-18G – Growler
(AIR 5349)
AIR 5349 Phase 6 and Phase 3 integrated
7,564.0 7,563.0 378.0 402.0 302.0
Airfield capital works P0006 (Curtin, Tindal and Townsville) 95.3 95.3 12.4 2.0 9.4
Short-Range Ground Based Air Defence (LAND 19) 1,529.0 1,527.0 311.0 312.0 201.0

(a) See note at Table 1.

Source: Parliamentary Library calculations

Land domain

Army is required to restructure 3 combat brigades to emphasise amphibious capability, with a new dedicated fires brigade and littoral manoeuvre group. If required, these brigades can deploy forward to positions along Australia’s sea lanes and provide long-range strike against adversary ships and aircraft. Spending increases listed in Table 4 show the beginning of prioritisation of new littoral manoeuvre capabilities. Accelerated projects include the acquisition of HIMARS long-range rocket artillery and the Redback infantry fighting vehicle. Delivery of Army’s planned 18 landing craft medium and 8 landing craft heavy (LAND 8710 Phases 1-2) has also been brought forward 7 years, but the planned cost of
$7–10 billion over the decade does not yet appear in the Budget. Table 5 demonstrates some of the reductions in other land domain projects.

Table 4         Land domain new and increased spending ($m)
Project Approved expenditure at 2023–24 PAES Approved expenditure 2024–25 Revised budget estimate at 2023–24 PAES Estimated expenditure 2023–24 (a) Budget estimate 2024–25
UH-60M Black Hawk Utility Helicopter (LAND 4507) 3,872 3,871 396 365 645
Redback Infantry Fighting Vehicle
(LAND 400 Phase 3)
- 7,246 - 318 (b) 626
Explosive Ordnance – Army Munitions Branch sustainment (CA59) - - 242 - 395
AH-64E Apache Attack Helicopter
(LAND 4503)
5,146 5,144 126 170 284
First Long-Range Fires Regiment
(LAND 8113 Phase 1)
- 2,337 - 104 (b) 199
Individual Combat Equipment
(LAND 300)
includes LAND 159
538 1412 154 876 145

(a) See note at Table 1.
(b) New project in 2023–24 so there was no cumulative spending to 30 June 2023.

Source: Parliamentary Library calculations

Table 5         Land domain spending reduced ($m)

Project

Approved expenditure at 2023–24 PAES

Approved expenditure 2024–25

Revised budget estimate at 2023–24 PAES

Estimated expenditure 2023–24 (a)

Budget estimate 2024–25

Boxer Combat Reconnaissance Vehicles
(LAND 400 Phase 2)

5,918

5,903

625

504

656

Armoured Combat
(LAND 907)

2,395

2,428

634

591

624

AS9 Huntsmen Self-Propelled Howitzers (LAND 8116)

1376

1371

262

253

246

(a) See note at Table 1.

Source: Parliamentary Library calculations

Maritime domain

Table 6 shows the scale of new and accelerated spending in the maritime domain. The most important of the Collins class life of type extension programs (SEA 1450) appears to have accelerated, and initial annual funding of $2,591 million for the future nuclear-powered submarine program is now visible. Naval long-range strike weapons are another priority area and Hobart class destroyers will be upgraded to an Aegis baseline 9 combat system to allow better targeting and the addition of longer range strike missiles. Additional Seahawk helicopters, which have a role in submarine detection, are also being acquired. Projects to acquire new capabilities in maritime mining and maritime electromagnetic manoeuvre warfare (electronic warfare) appear in the Top 30 for the first time. The IIP planned spend of
$7–10 billion over the decade for the first batch of general purpose frigates also does not yet appear in the Top 30 table.

Table 7 shows some reduced spending. Despite the need for deeper stocks of strike weapons, the SEA 1300 guided weapons budget has reduced by 7.2% this year. The medium-term reduction in the number of surface combatants (including early retirement of 2 Anzac class frigates) will likely move demand for additional missiles towards the end of the 10-year plan.

The Hunter class frigate also appears to have a reduced spend this year. However, only spending for the Phase 1 design and construction budget appears in the Budget. The main construction phase is planned to begin early in 2024–25. That is likely to result in an increase of approved expenditure of around $20 billion for construction of the first 3 ships. The annual increase in spending will depend on the build schedule.

Table 6         Maritime domain new and increased spending ($m)
Project Approved expenditure at 2023–24 PAES Approved expenditure 2024–25 Revised budget estimate at 2023–24 PAES Estimated expenditure 2023–24 (a) Budget estimate 2024–25
Nuclear-powered submarines
(DEF 1)
- 13,588 - 456 (b) 2,591
Collins Life of Type Extension
(SEA 1450) previously sustainment CN62
- 1045 160 318 240
Aegis Baseline
(SEA 4000 Phase 6)
2,360 2,477 506   582
MH-60R Seahawk Helicopter
(SEA 9100)
- 5,149 - - 523
Maritime Electromagnetic Manoeuvre Warfare
(SEA 5011)
- 726 - - 141
Maritime Mining
(SEA 2000)
- 932 - - 136

(a) See note at Table 1.
(b) New project in 2023–24 so there was no cumulative spending to 30 June 2023.

Source: Parliamentary Library calculations

Table 7         Maritime domain underspending and reduced spending ($m)
Project Approved expenditure at 2023–24 PAES Approved expenditure 2024–25 Revised budget estimate at 2023–24 PAES Estimated expenditure 2023–24 (a) Budget estimate 2024–25
Maritime Guided Weapons and Munitions
(SEA 1300)
8,953 8,937 763 733 708
Hunter Class Frigate
(SEA 5000)
7,263 7,254 1,250 1,203 813

(a) See note at Table 1.

Source: Parliamentary Library calculations

Space and cyber domain and joint capability

Table 8 shows spending has increases on some priority logistic and enabling projects. Command, control, communication and targeting will be hardened against disruption and sped up by improving interoperability between the 3 services and Australia’s allies. There is also a new project to improve fuel security.

Local explosive ordnance manufacturing capacity will be increased. Spending to support that expanded capacity has been increased by 45% since the 2023–24 Budget when it was $100 million.

Table 9 shows that a program which would be expected to be a priority after the IIP – to increase and harden guided weapons and explosive ordnance (GWEO) storage – commenced after the last Budget and was first captured in the 2023–24 PAES, but there was, a large underspend in 2023–24 and a significantly reduced estimate for 2024–25.

Table 8         Joint capability new and increased spending ($m)
Project Approved expenditure at 2023–24 PAES Approved expenditure 2024–25 Revised budget estimate at 2023–24 PAES Estimated expenditure 2023–24 (a) Budget estimate 2024–25
Integrated Air and Missile Defence Command and Control
(AIR 6500)
- 1,209.0 - 389.0 238.0
Explosive Ordnance Manufacturing Facilities (CJC01) - - 134.0 - 145.0
Defence Fuel Transformation Program – Tranche 2 Facilities Project - 286.9 - 9.7 82.0
Facilities to Support JP 8190 Phase 1 Deployable Bulk Fuel Distribution 15.0 15.0 2.6 0.1 10.6

(a) See note at Table 1.

Source: Parliamentary Library calculations

Table 9         Joint capability reduced spending ($m)
Project Approved expenditure at 2023–24 PAES Approved expenditure 2024–25 Revised budget estimate at 2023–24 PAES Estimated expenditure 2023–24 (a) Budget estimate 2024–25
GWEO storage (c) 161.9 161.9 72.4 43.1 45.6

(a) See note at Table 1.
(c) Cumulative figures from 3 projects in Table 66 in the 2023–24 PAES and Table 56 in the PBS.

Source: Parliamentary Library calculations

 

All online articles accessed May 2024