|
House of Representatives Standing Committee on Regional Australia
Navigation: Previous Page | Contents
Minority report – The Hon Sharman Stone MP and
Mr Michael McCormack MP
On the 29th of June 2012 the Murray Darling Basin
Ministerial Council asked the MD Basin Authority to respond to the calls by
South Australian Premier Jay Weatherill to “complete a relaxed –constraints
model scenario with a Basin-wide reduction in diversions of 3200GL/y. The
purpose of this scenario (was) to explore the flow regime changes and
potential in environmental benefits that would result if some major existing
river operating constraints in the southern connected system were relaxed” (MDBA
Hydrologic modelling of the relaxation of operational constraints in the
southern connected system, Methods and Results, October 2012. P.1.)
This Bill, the consequence of this modelling as requested by
the South Australian Premier, provides the funding of some $1.7bill for the
acquiring of an additional 450GL of water to add to the 2750 GLs of
environmental water identified as still needed in the Murray Darling Basin Plan.
This Bill has been so poorly drafted that the Federal
Department was required to give the committee an interpretation of the intended
meaning of some key sections. For example, while the Explanatory Memorandum
implies that water should only be found from on farm water use efficiency
savings, this is not made clear. Our concern extends, however, well beyond the
proposed sources of the additional 450GLs of water to be pushed down the
southern connected system.
We are deeply concerned about the flooding impacts on the
environment the regional economies and the communities if the natural barriers
and constraints in the system are removed. For example, from the data
available, it would seem that widespread flooding of the Lower Goulburn Flood
Plain, and the Murray below Yarrawonga, would occur on a regular basis (ie
every 2.5years). On the Goulburn floodplain this would be a 40,000ML/D flood
for a median duration of four days between June and November for 40% of the
years, i.e every two and a half years. This would, quite simply, devastate a
highly productive region and inundate infrastructure, including the flooding of
some 100 houses in Shepparton. The flatness of the topography would see water
accessing aquifers, retriggering salinization problems.
The Bill claims that pushing this extra volume of water down
the systems will improve the condition, in particular of assets at the mouth of
the Murray and the Lower Lakes in South Australia. In fact, due to the barrages
and other engineering works in place for over 70 years in these parts, it was
observed that despite some of the biggest volumes of water on record recently
surging past Lake Albert and the southern Coorong, neither of these assets
benefited from the record flood flow due to these barrages. Unfortunately this
Bill does not address these engineered impediments to achieving a natural
flushing of the mouth of the Murray or the salinity levels of the lower lakes.
As the October 2012 MDBA report entitled: The
Hydrological Modelling of the Relaxation of operational constraints in the
southern connected system states:
“the removal of some of these constraints may lead to
increased flow peaks further downstream, which may create nuisance flooding on
privately held land. If this were to be pursued in reality (rather than in
modelled scenarios), it is likely that governments would approach this by
negotiation of easements. Assessing the downstream implications of managing
higher flow rates from a flooding perspective will require detailed
hydrological modelling of the river system and was not within the scope of this
work. P8.”
Despite this absence of “detailed hydrological modelling”,
Basin communities are expected to accept the assurances that the additional
450GLs of environmental flow can be achieved without social or economic
detriment although again this pre-condition is not clearly stated in the Bill.
It is quite unrealistic to expect the appropriation of the
extra funds identified in the Bill would be sufficient to cover the “range of
projects” which we are told would be required to remove “constraints” to enable
the extra 450GLs to be pushed out to sea. These “projects” we are told could
include the acquisition of flood easements, provision of access works (for
example bridges and culverts) changed watering regimes and increased outlet
capacity on major dams and storages.
Unfortunately, the Murray Darling Basin Plan does not
include environmental watering plans. This Bill is to fund the acquiring of
huge additional volumes of water, equal to nearly half of the remaining
irrigator entitlement in the Goulburn Murray Irrigation System, without these
watering plans, without any reasonable expectation of additional environmental
benefit, but potentially additional environmental degradation in the areas to be
artificially flooded, without detailed hydrological modelling, or delivery risk
assessments.
We believe it is disingenuous of the Government to change
the order of speaking business in Parliament on 27 November such that the Water
Amendment (Water for the Environment Special Account) Bill 2012 was debated.
This ensured Members who spoke on this important piece of
legislation did not have the benefit of the final recommendations of the House
of Representatives Standing Committee on Regional Australia or this minority
report.
We cannot support this Bill.
The Hon Dr Sharman
Stone MP
Member for Murray
Mr Michael
McCormack MP
Member for Riverina
Navigation: Previous Page | Contents
Back to top