Chapter 3 Issues and Conclusions
Amendment to the Statement of Evidence
Air-bridges
3.1
Attachment C (2) of Health’s statement of evidence displays two
“optional bridge links” connecting the proposed building to Scarborough House.[1]
Reference to an air-bridge is also mentioned at paragraph 1.6.7 indicating that
the air-bridges “might be incorporated in to building design to increase
departmental connectivity”.[2]
3.2
At the beginning of the public hearing, Health sought to confirm the
issue of the optional air-bridges stating that,
…there will now be no air-bridges between Scarborough House
and any proposed development.[3]
Cafeteria
3.3
Included in Attachment C (1) of Health’s main submission is space
allocated for an “optional café”.[4] As there was no further
information regarding the café included in the statement of evidence, Health
clarified that,
…there would be a café facility owned and operated by the
property owner for the benefit of staff.[5]
Project Certainty
3.4
In its main submission Health states that it has proposed an integrated
fit-out solution in an effort to deliver construction efficiencies, and reduce
cost and risk via a tender for new office accommodation with a 15 year lease
and a five year renewal option from 2009.[6]
3.5
During the public hearing Health stated in its opening statement, with
regard to the integrated fit-out with base building construction that,
The status of the tender negotiations also means that the
fit-out design is only in a very preliminary phase.[7]
3.6
The issues of project and cost certainty were also discussed during
public and in-camera proceedings, and the Committee commented that it would
require more details of project arrangements before making any recommendation
to Parliament for approval for expenditure.[8]
3.7
Subsequent to the hearing, Health wrote informing the Committee that it
was in a position to confirm that the fit-out costs as provided to the inquiry were
accurate. Furthermore, there was no material change to the design of the
proposed new building as submitted to the Committee apart from the removal of
the proposed air-bridges, and redesign of the landscaped areas to minimise
water usage.[9]
Project Delivery
Tender Process
3.8
Health stated in its main submission that fit-out construction will be integrated
with base-building construction and will be managed by the developer for a
fit-out management fee. Officials of the department will be involved in the
fit-out construction subcontractor tender process to ensure value for money is
achieved.[10] The Committee sought
further detail regarding the tender process, and whether a preferred tenderer had
been selected.
3.9
The Committee discussed in detail the tender process in the confidential
hearing. During the public hearing Health explained that the tender process
commenced with an open expression of interest (EOI) to market seeking new
accommodation in the Woden area. All submissions to the EOI were considered
and identified to go into a select tender process which was conducted as per
Commonwealth procurement guidelines. Through the evaluation process, a
preferred tenderer was selected and Health is currently in the negotiation
phase with that preferred tenderer.[11]
3.10
At the Committee’s request, subsequent to the hearing Health submitted
an update on the tender process and negotiations with the preferred tenderer.
Options Considered
3.11
The four future accommodation options considered by Health were:
n short-term leases on
the current Woden accommodation;
n long-term leases on
refurbished current Woden accommodation;
n a long-term lease on
an existing building (or buildings) elsewhere in the ACT; and
n a long-term lease on
a new building in Woden.[12]
Health’s preferred
option on a new building in the Woden precinct, in the vicinity of Scarborough
House, will meet stated accommodation objectives and provide the best value for
money, long-term accommodation solution.[13]
3.12
The Committee stated on the public record that the cost details of the
various options were discussed during in-camera proceedings and that the
differences in costs were significant. Health confirmed this evidence at the
public hearing and continued that it was assessed that the upgrade of Health’s
current accommodation to a 4.5 Australia Building Greenhouse Rating (ABGR)
incurred a level of cost and funding that was beyond that which the Department
would receive for constructing a new building.[14]
Office Configuration
3.13
In its main submission Health explained that the scope of integrated
fit-out included:
n allocated office
space for SES and EL2 officers;
n open plan office
accommodation for EL1 and APS level officers;
n modular office design
and demountable partitions;
n standard workstations
and personal storage units.[15]
The Committee requested further
detail about the specific workstation area allocation and the comparison with
current office configuration.
3.14
Health informed the Committee that the proposed office configuration is
based on the Scarborough House layout, thereby maintaining continuity between
the Health building fit-outs. Open office area workstations would be allocated
approximately 7 square metres per workstation. Senior executive officers will
be allocated office spaces.[16]
Environmental Considerations
Water Conservation
3.15
Water conservation is an issue that has repeatedly been raised in recent
Inquiries and been the source of much discussion and consideration by proponent
agencies and the Committee alike. As such, the Committee requested further
information regarding the water saving initiatives that Health have
incorporated into building and fit-out design.
3.16
Health’s consultant responded that,
The base building brief, which was tendered to the proponent,
has a requirement for 4.5 star ABGR and Green Star. However, the local
authorities have a requirement that, to successfully obtain development
approval, the developer has to build retention and detention tanks. The
detention tank will be used for flushing toilets.[17]
Health is yet to determine
whether other water conservation initiatives, such as waterless urinals and
timers on the showers, will be included into building design.
Recommendation 1 |
|
The Committee recommends that the Department of Health and
Ageing provide further details of the water conservation measures proposed as
part of the building and fit-out design.
|
Consultation
3.17
A ‘Communication Strategy’ was developed by Health for internal and
external formal and informal consultation which included:
n briefings for the
Executive and work area managers;
n work area involvement
in the development of specific requirements;
n staff consultation
and information sessions;
n staff representative
consultation and information sessions; and
n an intranet site to
provide information and for staff questions and feedback.[18]
3.18
Health’s main submission includes a list of external stakeholders and a
list of members of Federal Parliament and the ACT Legislative Assembly with
whom Health has consulted.[19]
Australian Public Trustees
3.19
Australian Public Trustees (APT) is trustee of the Government Property
Trust, which owns Penrhyn House. Penrhyn House is one of the five Woden leases currently held by Health, and is adjacent to the proposed new building.
3.20
APT made a submission to the inquiry stating that a number of factual
errors were contained in Health’s main submission.[20]
Health responded to these claims in its supplementary submission, specifically addressing
two of the seven issues raised by APT. [21] The Committee sought
further information on how Health had addressed the issues and raised by APT
and any consultative process that has been undertaken.
3.21
At the public hearing, Health explained that APT did seek to tender for
the proposed project, however submitted its tender late. Subsequent to the
hearing Health provided a copy of the list of organisations invited to tender,
and the letter inviting for tenders containing details such as project scope and
specification, and closing time and date for submission.[22]
3.22
Health continued that, at the time of the hearing, it was still in
negotiation with tenderers, and that once the preferred tenderer had been selected
Health would debrief APT, and other tenderers, on the tender process. Health
assured the Committee that any outstanding issues would be discussed during the
debrief with APT. The Committee requested that Health report back to the
Committee once the meeting with APT had taken place.[23]
3.23
Subsequent to the hearing, Health informed the Committee that it had met
with APT and that all outstanding issues had been addressed to the satisfaction
of both parties.[24]
Recommendation 2 |
|
The Committee recommends that the Department of Health and
Ageing continue close consultation with all relevant stakeholders.
|
Staff Consultation
3.24
The Committee enquired as to the level of staff consultation that Health
had undertaken to date. Health responded that,
Staff are aware of the concept of stage 2 of the central
office accommodation plan, through a number of communications both locally
within the various buildings and through a couple of messages the Secretary has
put out to staff. From a function design point of view, detailed staff
consultations regarding fit-out requirements and local business needs are due
to be undertaken in the next couple of weeks.[25]
Recommendation 3 |
|
The Committee recommends that the Department of Health and
Ageing report to it on the outcome of the detailed staff consultations
regarding the proposed fit-out.
|
Fire Authorities
3.25
Health’s main submission stated that the base building brief
incorporated a number of fire protection initiatives.[26]
The Committee sought clarification whether there had been any consultation with
the local fire authorities with regard to the proposed project.
3.26
Health responded that the local fire department had been notified of a
development approval and building application, and were provided the
opportunity to scrutinise building plans. The fire department may provide
advice as to whether the proposed building plans are in accordance with BCA and
associated fire protection requirements.
3.27
At the time of the hearing, Health understood that base building plans
were progressing through this process. Health added that,
…we [Health] have only thought of block planning and numbers,
we do not have a plan as yet how we are going to plan them. Once we get to the
provisional sketch plan stage, our consultants will have a fire consultant on
board, who will consult with the fire brigade to ensure the safety of the
staff.[27]
Staff Amenities
Childcare Facility
3.28
In its main submission Health proposed to lease space in the new
building for a childcare facility which would provide 100 places. It is
envisaged that an independent childcare service provider would sublet the space
and fund a purpose-designed fit-out. The childcare facility would be a cost
neutral arrangement, having no capital or operating expenditure implications
for the Department.[28] The Committee asked for
further information on the current and proposed childcare provisions and the
associated arrangements.
3.29
Currently each Health staff member must make individual childcare
arrangements, therefore Health views the inclusion of a childcare facility as a
benefit to some individuals and families within Health. Whilst a formal survey
has not been conducted, Health proposed that the provision of childcare would
be brought to staff members’ attention in due course.[29]
Health informed the Committee that an EOI had not yet been sought.
3.30
Health continued that the proposed arrangement for childcare would be
between the staff member and the childcare operator, without any involvement
from the Department. Health stated that whilst other federal departments in
the area have indicated interest in the childcare facility, Health personnel
would receive preference of access.[30]
Recommendation 4 |
|
The Committee recommends that the Department of Health and
Ageing inform the Committee of the final arrangements for the proposed
childcare facility.
|
Car Parking Bays
3.31
In its main submission Health states that the proposed new building will
include a minimum of 350 car-parking spaces, including four disabled
car-parking spaces, 20 motorcycle bays, and 120 bicycle parking spaces, located
on two basement levels.[31] The Committee enquired
as to how the proposed car parking arrangements differ from current
arrangements.
3.32
During the public hearing Health informed the Committee that the
proposal incorporated approximately 370 car parking spaces and 20 motorcycle
bays, which represents more than the Department requires by way of entitlements
for staff. However, at the time of the hearing, Health had not yet determined
how excess car parking bays would be allocated.[32]
Recommendation 5 |
|
The Committee recommends that the Department of Health and
Ageing inform the Committee of the car parking arrangements, once finalised,
for the proposed building.
|
Bicycle Parking
3.33
Included in the parking design of the proposed building is to
incorporate 120 bicycle parking spaces.[33] The Committee enquired
as to how Health determined the level of bicycle accommodation, and associated
facilities, to be provided.
3.34
Health responded that it considers itself a department that encourages a
healthy lifestyle, part of which may include riding a bicycle to work.
Furthermore, the base building is designed to 5-star Green Star level, in
addition to the 4.5 star ABGR. Part of achieving a 5-star Green Star rating is
the provision of an appropriate level of bicycle parking spaces. Whilst the
design in still at a schematic stage, Health’s consultant will be undertaking
staff consultation to further gauge the level of bicycle usage.[34]
Future Growth
3.35
Health indicated in its main submission that part of the reason for
adopting the proposed course of action was to meet predicted future space
requirements to enable the collocation of all central office personnel into two
leases, including Scarborough House, so as to maintain and further enhance the
operational efficiencies achieved via stage 1 (Scarborough House) of the
project.[35] The Committee sought
further information regarding current and predicted future staff numbers, and
how Health proposed to address changes in staffing levels.
3.36
Health responded that according to its 2005-06 Annual Report, the number
of staff is approximately 3,050. Due to a number of budget measures for aged
care, Health estimates that it currently has between 3,200 and 3,300 personnel.
3.37
Health has estimated that it will have about 4,000 work points which
includes those at Scarborough House, and that there will be an estimated
increase in the number of work points that will be available in the new
building.[36]
Recommendation 6 |
|
The Committee recommends that the proposed fit-out of new
leased premises for the Department of Health and Ageing in the Sirius
Building, Woden Town Centre, Australian Capital Territory, proceed at the
estimated cost of $67 million.
|
Hon Judi Moylan MP
Chair
9 August 2007