Chapter 3 Issues and Conclusions
Site Selection
3.1
The ACS explained that the proposed site at The Circuit, Brisbane Airport was selected after an exhaustive process that involved an intensive assessment
of a number of other accommodation solutions. According to the ACS the
proposed site represented best value for money on the basis that it best
reflected the long-term needs of the agency including security requirements,
design, accessibility for clients, and other issues.[1]
3.2
The ACS informed the Committee that the building would be purpose built,
constructed by the BAC, and be of approximately 9,000 square metres spread over
four floors. The proposed area has been designed to include the relocation of
staff from the current premises located in the Brisbane CBD, as well as
providing the opportunity to accommodate further staff increases.[2]
3.3
Construction of the building is due to commence in October 2007 and be
completed by 2008. This time-frame coincides with ACS planning for the
commencement of the building fit-out, and the completion of leases on existing
office accommodation.[3]
Tenancy
3.4
In its opening statement to the hearing, the Committee was informed by the
ACS that it will be the sole tenant of the building. This is in contrast to
the present arrangements whereby the ACS shares office accommodation with a
number of other federal government departments, including the Australian
Taxation Office and the Australian Quarantine and Inspection Service (AQIS),
and some state government agencies. A sole tenancy agreement will provide the
opportunity for the ACS to install features that will be unique to its
requirements, including; measures to allow for the discreet transfer of
detained goods and operational fire arms into and out of the building; investigations
areas and an armoury.[4]
3.5
Under the terms of the leasing arrangements with the BAC, the ACS
informed the Committee that it had negotiated a 15-year lease, with two further
options of 5 years each, commencing in July 2009.[5]
3.6
As the intention of the current project is the collocation of a number
of work groups into a single building, it will provide the opportunity for
operational efficiencies by removing duplicate facilities including the closure
of the shop-front at the current premises in the Brisbane CBD, and reduce costs
and time in the transport of detained goods and weapons seized at the Brisbane
Airport that are currently transported to the city. The new accommodation will
also serve as hub for staff deployed to other ACS business units located in the
airport precincts.[6]
3.7
The Committee inquired as to the effect the closure of the shop-front at
the current Brisbane office would have on the agency’s clients including the
public.
3.8
The ACS explained that the numbers of people accessing the shop-front
was small, and that in the main these were people seeking to collect firearms,
or businesses depositing papers for the clearance of customs goods. The
majority were in the category of the former, which were already located at the
airport, and were inconvenienced by having to process documentation at the city
shop-front.[7]
Current Leasing Arrangements
3.9
In its opening statement to the inquiry, the ACS informed the Committee
that:
Given that the leases in the CBD and air cargo premises are
due to expire in 2009, it was viewed as opportune to identify an appropriate
accommodation solution that met our needs and represented a value for money
option.[8]
3.10
The Committee sought clarification as to the timing of the move from the
existing accommodation to the new premises, with reference to the avoidance of ‘dead’
rent on the present office space.
3.11
The ACS informed the Committee that it will implement a transitionary
arrangement for moving staff from existing accommodation to the new building
over the six months beginning from January 2009. The agency has informed the
current lessor that it will not forgo the options on the existing lease until
all approvals for the fit-out have been received. According to the ACS this
approach offers some protection over existing accommodation in the event of
building delays or some other unforseen event.[9]
Consultations
3.12
In its submission the ACS stated that the principal stakeholders, namely
the BAC and AirServices Australia have been consulted and discussions are
continuing, and will be continued up until final design and prior to the
commencement of the construction works.[10]
3.13
ACS further stated that preliminary briefings of the proposed new
arrangements had also taken place with industry clients on the proposed
relocation, and that this would be continued as the project develops.[11]
Staff Consultations
3.14
In its main submission, the ACS states at paragraphs 2.19.1 to 2.19.6
that it has engaged in a range of consultations with staff that are ongoing.
The agency proposes to develop:
A comprehensive Communication Strategy for internal and
external consultation with clients following the execution of the Agreement to
Lease.[12]
3.15
In response to questions from the Committee relating specifically to the
extent of staff consultation, the ACS informed the Committee that staff had
been kept informed of the progress of the project.[13]
In evidence, the agency described the mood of the staff toward the proposed
office relocation as positive, although some concerns have been expressed
relating to transport for which the ACS are exploring possible solutions.[14]
3.16
Although decisions relating to transport are continuing, the ACS has
formed a Transport Working Group to discuss with transport operators what
options might be available for staff arising from additional travel to the new
offices. The Group has been in contact with the BAC that is in negotiation
with the operators of the ‘airtrain’ with the intention of securing a
commitment for a third station that coincidentally is within walking distance
of the proposed new office.[15]
3.17
On the matter of staff consultation more generally, the ACS informed the
Committee that as it indicated in its main submission, it would be providing an
‘intranet site’ on its internal computer network that would allow wider
opportunities for staff feedback. Access to the mailbox will enable staff to
e-mail the project management team with suggestions and comments.[16]
3.18
In addition to opportunities provided to staff to directly comment on
the proposed building, and to provide feedback to the various forums established
by the agency for this purpose, the Community and Public Sector Union (CPSU)
have also been engaged in the consultative process through newsletters and
other information exchanges.[17]
Re-use of Furniture, Fittings and Equipment.
3.19
During the in-camera hearing the Committee, acknowledging the
possibility that some new items of furniture, fittings and equipment (FFE) may
need to be purchased, inquired as to what scope existed for the reuse of
furniture and equipment from the current premises at the new office site.
3.20
The ACS responded that provision had been made for the relocation of
secure storage facilities – safes and server room storage units – but indicated
that items such as filing cabinets would be replaced with a more efficient file
storage system. According to the Project Director for the project:
Much of the furniture we have inspected as part of our
process, particularly… chairs and meeting room furniture, is starting to become
tired and non-functional. We are looking down the track, and we will get
another two years out of that furniture. We have looked at the budget from the
point of view that, in two years time, much of that furniture will be beyond
its useable, functional life span.
3.21
By way of further explanation, the Project Director informed the
Committee that a significant part of the costs for FFE was directed towards the
provision of shelving for the detained goods store.
3.22
Subsequently the Committee was informed by the ACS that the estimate for
FFE is directed to the replacement of items that will be ten years old at the
time of occupancy of the new building. The agency identified a number of items
it proposes to reuse, including boardroom tables, electronic whiteboards, audio
visual equipment, all computer terminals, fume cabinets, and lounge style
furniture, from which it expects savings to be derived.[18]
Staff Amenities
Child Care
3.23
In its opening statement to the Committee, the ACS made note of the rapidly
expanding services and amenities facilities within the airport precinct.
According to the ACS, BAC planning is underway for the development of a
shopping centre, a medical centre and child care facility all of which are
scheduled for completion by 2009.[19]
3.24
The Committee sought comments from the agency regarding the child care
facility and whether children of staff would be given preferential access to
the facility, and whether the centre would be operated by a private provider.
3.25
The ACS informed the Committee that it had recently received a letter from
the BAC in response to one sent by the agency indicating that the proposed
child care centre would be privately operated, and that the ACS would need to
contact the operator to reserve spaces for the children of staff.[20]
Other Staff Amenities
3.26
In its submission the ACS stated that the base building design included
provision for a gymnasium, showers and change room facilities, kitchens and
lunch room facilities, and tea points on each floor.[21]
In evidence to the Committee the agency further elaborated that it would also
include provision for bicycle parking as well as lockers.[22]
3.27
In addition, car parking would be provided for 60 official car parks
under the building. This would be supplemented by the provision for up to 210
private vehicles on pay-and-display car park facility to be provided within 150
metres of the new building.[23] However according to
the ACS the matter of whether these 210 car parking spaces will be reserved for
the agency is still under discussion with the BAC.[24]
3.28
For staff travelling on public transport, the ACS was considering the option
of a shuttle bus from the nearest train station to the new office, until the
issue of a third Airtrain station in closer proximity to the new building had
been resolved.[25]
3.29
ACS further informed the Committee that:
The design planning to date…has allowed a flexible and
efficient fit-out design that provides a workplace that is open and dynamic and
places an emphasis on team culture and interaction. We have dedicated meeting
rooms that blend work and non-work activities, including break-out areas on each
floor.[26]
Project Cost
3.30
The estimated cost of this proposal is $15.84 million based on a fit out
and provision of services of approximately 8,100 square metres. This estimate
also includes:
n An amount of $1.4
million for the fit-out of a future expansion area of 855 square metres;
n an escalation of 9 per
cent;
n an allowance for
consultancy costs;
n authority fees and
charges;
n base building
modifications;
n fit-out building
works;
n furniture, fittings
and equipment;
n contingency
allowances; and
n relocation costs.[27]
Recommendation 1 |
|
The Committee recommends that the proposed fit-out of new
leased premises for the Australian Customs Service at the Circuit, Brisbane Airport, Queensland proceed at an estimated cost of $15.84 million (including GST).
|
Hon Judi Moylan MP
Chair
16 August 2007