Chapter 2 Construction of Projects Two and Three of the Christmas Island
New Housing Program
2.1
The Department of Regional Australia, Local Government, Arts and Sport
(the Department) states that Christmas Island (CI) is facing a critical housing
shortage which impacts on the provision of public services.[1]
Accordingly, the Department is seeking approval from the Committee to proceed
with Projects Two and Three of the Christmas Island (CI) New Housing Program.
2.2
The CI New Housing Program consists of three separate projects. On 17 December
2010, the Department notified the Committee of a medium works project, being
Project One of the CI housing program, at an anticipated cost of approximately
$8.9 million.[2] The Committee determined
that it had no objections to Project One proceeding as a medium work. However, the
Committee took the view that the three projects were stages of one larger
housing project and advised the Department that Projects Two and Three should be
referred.[3]
2.3
Notwithstanding that Project One is not the subject of this inquiry, the
Committee has reviewed the progress of this Project as it relates to Projects
Two and Three, and the New Housing Program as a whole.
2.4
Project One commenced in September 2011 and comprises the construction
of 16 dwellings and associated infrastructure. The current contract value for
the medium work is estimated to be $11.4 million.[4]
2.5
Project Two comprises the construction of a further 14 dwellings to
accommodate the increase in personnel required for policing, health, administration
and education services. The increase in the number of dwellings corresponds
with the growth in the island’s population, due to an escalation in immigration
activity on CI.[5]
2.6
Project Three proposes the construction of a further two dwellings,
should funding allow following the finalisation of costings for Project Two.[6]
2.7
Projects Two and Three were referred to the Committee on 3 November
2011.
Conduct of the inquiry
2.8
Following this referral, the inquiry was advertised nationally and
submissions sought from those with direct interest in the proposed project.
2.9
The Committee received one submission and three supplementary confidential
submissions from the Department. A list of submissions can be found at Appendix
A.
2.10
The Committee conducted a public hearing on the project and an in-camera
hearing on the project costings on 2 March 2012 at Parliament House in
Canberra.
2.11
A transcript of the public hearing and a copy of the Department’s public
submission to the inquiry are available on the Committee’s website.[7]
2.12
The Committee visited CI between 7 and 10 June 2011, to inspect approved
public works on the island and receive briefings regarding projects which would
be referred to the Committee in the near future. During this visit, the
Committee inspected various sites for the CI New Housing Program and received a
briefing from representatives of the Department regarding the housing program.[8]
Need for the works
2.13
The Department submitted that the new housing project was needed to
reduce the number of houses leased on the private rental market to accommodate
Commonwealth employees, which would in turn reduce housing demand and rental
costs for the local community.[9]
2.14
The Department told the Committee that the main driver of the project
was to meet the need for housing on CI:
A significant driver for this project was that the sheer
demand for housing on the island could not be met and that the private sector,
for reasons best explained by the private sector, was not responding in
building additional housing to meet the demand. That was putting a lot of
pressure on rentals. By observation, it is not atypical of what happens in
smaller or remote mining towns as well where you get sudden demand and rents go
up significantly. Our expectation is that one of the outcomes of the project
will be that we will release a number of leased houses back on to the private
market which should increase supply and, in theory, should then take pressure
off prices. You certainly cannot give a guarantee that it will reduce prices,
because we do not control that, but it should increase the supply of houses in
the private market which should, in turn, take some pressure off.[10]
2.15
The Department considered purchasing existing dwellings on CI, however
determined that this option would not reduce pressure on the local housing
market.[11] The Department submitted
further that many existing dwellings were not fit for purpose:
We have bought where it is appropriate to do so. A lot of the
housing stock on the island is old and is not what meets the expectations of
modern families in terms of amenities. A lot of the houses need substantial
continuing maintenance—they are probably beyond their useful life. There is
significant asbestos in privately owned houses which, if we acquired them, we
would have to remediate, and for many of them it would be cheaper to build a
new house. There is also the important aspect of the longer term development of
the island.[12]
2.16
The dwellings would primarily house professionals who have not been able
to be recruited locally to deliver state types of services and meet the demand
driven by the increased activity on the island. The Department submitted:
Primarily the people will be either departmental staff,
through our Indian Ocean territories administered arrangement where we employ
people such as nurses and other medical professionals, or Australian Federal
Police officers or teachers employed by the WA department of education delivering
education services and the like.[13]
2.17
The base population on the island is approximately 1,300 people and
according to the Department, there is a continuing requirement for doctors,
nurses, police, teachers and other professionals to service the community’s
needs. The housing project aimed to attract the best possible personnel to the
island and entice them to live on the island for a significant period building
strong relationships within the community. This option was preferred to
employing a largely fly-in fly-out workforce:
Our experience with short-term health staff, with locums, is
that it is significantly more expensive than employing people for the long
term. You have to pay a premium to get them there; paying for accommodation in
hotels and the like is extremely expensive compared to doing it through
ownership; and, as I said, there is the harder to tangibly quantify cost of not
having the strong relationships [with the community].[14]
2.18
In addition to meeting the current need for housing on CI, the project
also factored in future economic growth on the island and a resulting increase
in population:
A lot of the work that was done recently with the major
investments the Commonwealth has made that you have been involved with,
particularly around the utilities, the waste water and power, has the long-term
benefit in that it meets the current driver, which is clearly around
immigration based activity, but it sets the island up for further growth
outside of that, well beyond its current residential population. Most of the
utilities infrastructure is designed around a population of 5,000.[15]
2.19
The New Housing Program was designed to improve the overall amenity of
the island as a whole and attract longer-term investment on the island:
We are obviously very conscious that the [phosphate] mine has
a finite life and that we need to do work now to set the environment so that
tourism and other activities can become attractive. This project is one small
part of that, in that it will provide a modern, high quality environment that
has visual amenity. Some parts of the island are, frankly, pretty tired at the
moment and need to be updated. The Commonwealth cannot do it all; the private
sector and the community have a significant role there. But this is one area
where the Commonwealth can make a long-term investment that will be paying
dividends in 15 to 20 years as well as meeting immediate needs.[16]
2.20
Six site options were considered for the construction of new housing on
CI. Drumsite Village and Guano Village were chosen as preferred sites for
Projects Two and Three, due to a number of factors, including that the sites
were immediately available, were located in well-established areas and had
access to existing residential facilities and services.[17]
2.21
The Committee is satisfied that there is a need for the works.
Scope of the works
2.22
The Department summarised the scope of the proposed CI New Housing
Program as follows:
Project 1 will deliver 16 houses on the Drumsite site.
Project 2 will deliver 14 houses, also at Drumsite, and there will be a further
two houses in Silver City that will be constructed on current vacant lots. In
addition to this we purchased two houses through the program's funds which do
not form part of the construction program. These two houses are ones that we
had on leases and were considered to be suitable for long-term acquisition, and
there is a long-term cost saving to the Commonwealth for taking ownership of
them.[18]
2.23
The Department noted that work upgrading the existing service
connections to the site and internal road works form part of the scope of
Project One. Project Three was dependent on available funds following the
completion of Projects One and Two.[19]
2.24
Feedback was obtained from stakeholders to ascertain the demand for
accommodation on CI and the mix of housing options required:
The significant demand for 2 and 3 bedroom dwellings is clear
and will be particularly met by Project 1 which will provides 10 two bedroom
units and 6 three bedroom townhouses. The provision of additional 2 or 3
bedroom units should still be considered as part of Project 2 and 3 to allow
existing tenants, who have been allocated larger houses than they require, to
be relocated to more appropriate dwellings. However, the demand for larger 4
bedroom dwellings is recognised and needs to be addressed in Projects 2 &
3.[20]
2.25
The Committee queried whether there was a demonstrated need to proceed
with Project Three, if this project would only proceed if funding allowed. The
Department responded:
They are less essential than Projects 1 and 2, but they do
fill a gap for those relatively small numbers of cases where you may have a
doctor or a nurse who has a large family, and this does occur, so we want to
have some greater flexibility in the housing stock that we have, to suit
alternative family circumstances, so that the lack of accommodation does not
mean that you have to say to someone, 'Gee, it's going to be really hard to
find a house for you.' So we want to make it as attractive as possible to get
the best possible people to go to the islands.[21]
2.26
The proposed housing designs responded to the climatic and physical
needs of the proposed sites and were designed to blend in with the local
vernacular architecture, using a limited palette of materials to enhance the
contemporary tropical aesthetic and be resilient to the harsh maritime tropical
climate.[22]
2.27
The type of construction proposed for Projects Two and Three was
summarised as follows:
The type of construction we are proposing for Projects 2 and
3 is modular and lightweight. The housing components, walls, roofs, roof
trusses and so on are manufactured in a factory in Brisbane and then assembled
on-site. This has the effect of reducing the amount of labour required on
Christmas Island.[23]
2.28
The housing proposed was intended for long term residents and was
designed to encourage a sense of place and community. A number of the homes
constructed would be ‘adaptable’ with a view to meeting future housing needs of
the Christmas Island community that may arise because of age, disability or
changing circumstances.[24]
2.29
It is anticipated that construction on Project One would be complete in
June 2012. Subject to Parliamentary approval, Projects Two and Three were
anticipated to be complete by June 2013.[25]
2.30
The Committee finds that the proposed scope of works is suitable to meet
the need.
Cost of the works
2.31
The Department noted that the total budget for the CI New Housing
Program was $26.6 million over three years.[26] Noting that Project One
was not specifically the subject of this inquiry, the Department confirmed that
the anticipated cost for Projects Two and Three of the housing program was
$11.1 million.[27]
2.32
The Department informed the Committee that the anticipated total cost of
Project One had increased since the notification of medium works in December
2010. The change in scope of Project One is discussed further below.
2.33
The Committee is satisfied that the costings of the project provided to
it have been adequately assessed by the proponent agency.
Project issues
Changes to Project One
2.34
The Department advised the Committee of the progress of Project One
during the public hearing, including changes to the scope, cost and schedule.
Initial site works were underway on the project, however the Department stated
that there were delays in the delivery of some of the prefabricated modules
resulting from the MV Tycoon incident on CI in early January 2012.[28]
2.35
Additional elements had been included into the scope for Project One
which had increased the anticipated cost of the project from approximately $8.9
million to $11.4 million. These elements included a construction camp on
Phosphate Hill to accommodate approximately 20 construction workers, the
construction of 16 instead of 15 dwellings and some infrastructure site works
for the whole of the Drumsite location.[29]
Committee comment
2.36
The Committee is satisfied from the evidence provided by the Department
that the increase in scope to Project One is necessary, fit for purpose and
value for money for the Commonwealth. The Committee notes the increase in costs
for Project One will have some consequences for the progress of Projects Two
and Three, whereby Project Three may not proceed.
Rock-fall studies
2.37
A geotechnical investigation conducted for Project One identified
evidence of a rock-fall hazard from the cliff to the south of the proposed
site, with several boulders visible at the base of the slope below the cliff indicating
potential ongoing instability of the cliff.
2.38
The Report on Geotechnical Investigation attached to the Department’s
submission noted:
It is recommended that a further assessment of the cliff is
made utilising rope access techniques to better assess the rock fall hazard.
The assessment should be designed so that the cliff will be inspected to identify
the nature of the potential hazards and that rockfall modelling be undertaken
to assess the impact on the proposed development. Recommendations can then be
made on appropriate solutions to mitigate the risk from rock falls on the
residential development.[30]
2.39
The Department undertook to conduct further detailed engineering work to
establish and manage the rock-fall risk for Project Two and would report back
to the Committee regarding the outcome of this work.[31]
Committee comment
2.40
The Committee had no objection to the further work regarding rock-fall
risk proceeding immediately, notwithstanding that Projects Two and Three had
not yet been approved to proceed. The Committee was satisfied that it was
necessary to undertake this work in order to ascertain any risks to Projects
Two and Three. The Committee looks forward to receiving a further report from
the Department regarding the outcome of this engineering work.
Zoning issues
2.41
According to the Department, the Drumsite Village site for Projects One
and Two is a vacant Commonwealth-owned site of approximately 9,200 square
metres, with flexible housing options.[32]
2.42
The Committee was interested in the planning scheme for the new housing
program and whether the land could subsequently be strata titled before being
sold.
2.43
In a supplementary submission to the inquiry, the Department advised
that strata titling was permissible pursuant to Western Australian planning
policy. The Principals Project Requirements (PPR) required the design and
construction contractor to ensure that these future planning requirements were
addressed and met in their designs for the New Housing Program. This included
undertaking works during these projects to facilitate a future change to strata
title, through appropriate road design, adequate street lighting, sewer lines
and other infrastructure works.[33]
Committee comment
2.44
On the evidence provided in the supplementary submission from the
Department, the Committee is satisfied that it would be open to the
Commonwealth to strata title the Drumsite Village site in the future, to
maximise value for money for the Commonwealth, in the event the site is no
longer required and subsequently sold.
Final Committee comment
2.45
The Committee is satisfied that Projects Two and Three of the CI New
Housing Program are necessary, fit for purpose and signify value for money for
the Commonwealth. The Committee notes the challenges the Department faces in
ensuring that all three projects fit within budget and meet the projected scope
and schedule, having regard to issues such as weather and logistics on CI.
2.46
The Committee trusts that the Department will keep the Committee
updated, should there be any further changes to scope or cost, as the projects
progress.
Recommendation 1 |
|
The Committee recommends that the House of Representatives
resolve, pursuant to Section 18(7) of the Public Works Committee Act 1969,
that it is expedient to carry out the following proposed work: Construction
of Projects Two and Three of the Christmas Island New Housing Program. |