Chapter 2 Issues
Christmas Island Housing Program
2.1
On 20 December 2010, DRARDLG notified the Committee that it would
proceed with Project One (Drumsite Village) of the Christmas Island New Housing
Program (the Program).
2.2
Projects Two and Three will be referred to the Committee for inquiry.
The Committee views the three projects as stages of one greater project.
2.3
The Committee received a detailed briefing from DRARDLG and inspected
the housing program sites on the Island.
2.4
The key project objective is the provision of approximately 40 dwellings
to accommodate additional essential staff on Christmas Island, enabling housing
currently leased on the private rental market to be released for use by the
Christmas Island community.
2.5
The nominated site for Project One of the Program is located within an
existing area of residential development at Drumsite, known as ‘Drumsite
Village’, an area zoned for medium density residential use with existing
service connections.
2.6
Sixteen dwellings will be delivered in Project One by early 2012.
Another 16 dwellings will be built as Project Two, to minimise the use of the
private housing market. In Project Three, the public housing stock will be
extended by approximately ten dwellings, to make additional affordable housing
available to the community.
2.7
The Committee is pleased with the progress of this project and
appreciates the efforts of officials from DRARDLG in keeping the Committee
informed and updated.
2.8
The Committee looks forward to receiving the referral for Projects Two
and Three.
Wastewater and water supply
2.9
The Committee received a detailed briefing from DRARDLG and officials
from Water Corporation, and inspected the Island’s wastewater treatment plant
(WTP). The WTP is currently being upgraded so that it has the capacity to meet
current and future demands.
2.10
The regular Island population of approximately 1,500 produces 400
kilolitres of wastewater per day (kL/d). The rapid increase of the Island’s
population, primarily through the detention centre at North-west Point, resulted
in a peak flow of 1,900 kL/d.
2.11
The WTP was originally designed to handle 920 kL/d, however was only
capable of adequately treating 650 kL/d.
2.12
The plant’s inability to adequately process high inflows resulted in
final effluent quality being below that required under licence conditions.
2.13
The upgraded WTP is being converted from an ‘intermittent decant’ system
to ‘continuous flow’, and will be capable of treating 1,750 kL/d.
2.14
The Committee was satisfied that the WTP upgrade is necessary to meet
the Island’s needs.
2.15
However, there were two key aspects of the WTP that concerned the
Committee, namely the discharge of treated water and the disposal of sludge.
Both relate to the security of the Island’s fresh water supply and are
discussed below.
Discharge of treated water
2.16
The Committee was informed during a briefing that treated wastewater was
released to the ocean. At the site inspection, the Committee learned that
treated wastewater is actually released down into a fissure in the limestone
bedrock at the edge of the plant area, with that fissure leading directly to
the ocean.
2.17
It is understood that the fissure also leads back and up into the area
behind the WTP. The Committee is concerned that there is the possibility of
contamination of the Island’s water supply, particularly given that freshwater
is drawn from close to sea level at some places on the Island.
2.18
The Committee seeks reassurance from all relevant authorities, including
DRARDLG, Water Corporation and the Christmas Island Shire, that treated
wastewater is not entering the freshwater supply on the Island.
Recommendation 1 |
|
The Committee recommends that the Australian Government
undertake an assessment of water flows to determine what happens to treated
wastewater that leaves the Christmas Island Wastewater Treatment Plant, and
the potential risks to the freshwater supply. |
Sludge disposal
2.19
A by-product of the wastewater treatment process is the remaining solid
material, commonly known as sludge. The upgraded WTP has a new sludge
processing system in the form of a large dryer. The WTP produces approximately
one tonne of dry sludge per day.
2.20
Currently, the only way of disposing of sludge on the Island is to
deposit it at the Island’s landfill site, which is located at a high point on
the Island.
2.21
The Committee is concerned that there is currently no certainty about
the risk that the sludge might impact on the Island’s water supply, which is
drawn from ground water.
2.22
Additionally, it is the view of the Christmas Island Shire that the
aquifer supplying fresh water to the Island’s inhabitants is not fully
understood.
2.23
The Committee seeks reassurance from all relevant authorities, including
DRARDLG, Water Corporation and the Christmas Island Shire, that adequate
measures are taken to ensure that contaminants from sludge are not entering the
freshwater supply on the Island.
Recommendation 2 |
|
The Committee recommends that the Australian Government
undertake an assessment of the Christmas Island water supply to determine
whether any water supply areas are affected by contaminants from the Island’s
landfill site. |
Recommendation 3 |
|
The Committee recommends that the Australian Government
examine alternatives for disposal of solid waste from the Christmas Island
Wastewater Treatment Plant. |
General waste disposal and recycling
2.24
During the Committee’s inspections, particularly at the Island’s
landfill site, it was evident that general waste disposal and recycling are
issues that need to be dealt with by the Christmas Island Shire and the Island
community in general.
2.25
Currently, the Christmas Island Shire does not operate any waste
minimisation or recycling strategies or programs. The Shire’s website states
further:
The development of effective strategies will require
community participation and cooperation and island residents are encouraged to
start considering how they may individually contribute towards waste reduction
within their own households.[1]
2.26
With no waste minimisation strategies or recycling programs, and limited
options for disposal of waste, it is necessary for the Christmas Island Shire
to develop and implement innovative strategies to deal with waste on the
Island.
2.27
DRARDLG informed the Committee that a Waste Management Strategy has been
developed by Murdoch University. DRARDLG explained that a funding agreement to
implement the recommendations in the strategy has been agreed with the Shire of
Christmas Island. However, the allocated funding will not cover the cost of all
the recommendations in the strategy and the Shire has informally requested an
additional $2.1 million to complete the waste management project.
2.28
The Committee notes that the Christmas Island Shire may learn from some
examples of strategies for dealing with waste on islands with small populations
in other parts of the world. For example, the community on New Zealand’s
Stewart Island (population of approximately 400 people) established a resource
recovery centre to process and recycle up to 40 per cent of material that would
otherwise need to be shipped, at significant cost, to landfill at Invercargill
on the South Island.[2] The Rakiura Resource
Recovery Centre on Stewart Island was built by Southland District Council and
provides facilities for recycling, composting, hazardous waste storage, a
‘Second Chance’ shed, and a baler for pressing cardboard and paper. Innovative
recycling uses at the Centre include turning glass bottles into base course for
tracks and drainage around the island (there is no gravel available on the
island). Waste wood is used for firewood, and a tonne of kitchen scraps goes to
a worm farm each week.[3] An estimated 1,200 tonnes
of waste have been diverted from landfill over a seven year period.[4]
2.29
The Committee trusts that the Shire of Christmas Island adheres to the
Australian Government’s National Strategy for Ecologically Sustainable
Development[5] and the National Waste
Policy[6] as it begins the process
of waste minimisation policy development and implementation.
2.30
The Committee looks forward to receiving feedback from DRARDLG and the
Shire of Christmas Island on the development and implementation of waste
management strategies for the Island.
Power generation
2.31
The Committee received a detailed briefing from DRARDLG and inspected
the Christmas Island Power Station. This project will increase the output of
the Christmas Island Power Station through the replacement of three ageing,
diesel driven, electricity generators.
2.32
The replacement generators will be sited adjacent to existing power
generators and will have secure housing, ventilation, fire suppression, cooling
water and fuel intake facilities.
2.33
Prior to the commencement of the project, there were six diesel driven
generator sets installed at the Christmas Island Power Station:
n generator sets Nos 1,
2 and 3 are 40 years old;
n generator set No 4 is
37 years old, and expected to provide a further five years’ service; and
n generator sets Nos 5
and 6 are 14 years old and are expected to provide a further 20 to 25 years of
service.
2.34
Diesel generator sets Nos 1, 2 and 3 have reached the end of acceptable
life, largely due to poor design for their current application, poor
environmental performance and lack of manufacturer’s support.
2.35
In addition, there is a need to increase overall capacity at the station
to cater for an increase in population on the Island, which has largely been
driven by an increase in the number of detainees at the immigration detention
centres, and the associated increase in Commonwealth agency staff and
contractors.
2.36
DRARDLG informed the Committee of the progress of the works, indicating
that:
n mechanical,
electrical and civil design has been completed and off-site construction is
well advanced;
n the four new
generator sets have been constructed, and acceptance testing has been
completed; the sets were shipped from Finland in April 2011 and were scheduled
to arrive on the Island at the end of May 2011;
n construction of civil
works started in April, as soon as practicable after the end of the monsoon
season; construction of the concrete foundations was scheduled for mid June
2011; and
n a new building to
house the generators was prefabricated in Perth; concrete wall panels have
arrived on the Island.
2.37
DRARDLG stated that the project is on track for completion by
25 November 2011.
2.38
The Committee is aware that the largest user of power on Christmas
Island is the immigration detention centre at North-west Point (prior to the
centre opening, the phosphate mine on the Island was the largest user of power).
The Committee noted that, during its inspection at the detention centre at
North-west Point, there appeared to be minimal effort at conserving power;
almost all external lights were on during daylight hours.
2.39
The Committee was satisfied that the power station upgrade is necessary
to meet the Island’s needs.
Approval of projects
2.40
The wastewater treatment plant upgrade and the power supply upgrade
projects were notified to the Committee on 15 December 2009. The cost of the
works was estimated to be $44 million. The Australian Government considered
these projects to be urgent works, with a letter from the Attorney-General’s
Department[7] stating that ‘these works
need to commence before February 2010’, that is, before Parliament resumed. The
projects were not referred to the Committee, nor were expediency motions on the
grounds of urgency moved in the House of Representatives.
2.41
The Committee acknowledges the circumstances but is uncomfortable with
the decision made by the department that the works proceed without referral or
expediency motion.
2.42
The Committee received a public briefing on the two projects from
Attorney-General’s Department officials on 11 March 2010.[8]
During that briefing, the Committee was informed that design parameters for the
project were to consider a total Island population projected to increase to
about 4,000 by March 2010.[9]
2.43
With regard to these projects being considered urgent, the Committee
notes that the Attorney-General’s Department, after being informed of the
projected Island population increase in October 2010, did not act until 15
December 2010, less than two weeks into a two month parliamentary recess.
2.44
The Committee notes that House sat until 2 December 2010, essentially
allowing considerable time for the Department to refer the projects or indeed
to seek an expediency motion on the grounds of urgency.
2.45
The Committee also notes that the Governor-General may refer a public
work to the Committee at any time when the Parliament is not in session or the
House is adjourned for a period exceeding one month. A referral to the
Committee could have seen the inquiry process completed by mid February.
2.46
The Committee noted during its inspections in June 2011that both
projects were still not complete.
Detention centre medical facilities
2.47
The Committee inspected the three immigration detention facilities on
Christmas Island, namely:
n Christmas Island
Immigration Detention Centre (North-west Point);
n Construction Camp Alternative
Place of Detention (Construction Camp); and
n Phosphate Hill Alternative
Place of Detention (Phosphate Hill).
Access to health care
2.48
The Committee is aware of media reports from June 2011, suggesting that
detainees have been denied medical care.[10] The Committee
understands that provision of health care services may be difficult given
logistical boundaries and the particular circumstance on Christmas Island. However,
the Committee expects detainees to have the access to medical treatment that
every member of society expects.
North-west Point
2.49
The Committee met with contracted medical staff working at North-west
Point. The staff members indicated that the medical facilities area is too
small given the number of clients at the detention centre.
2.50
Despite being a purpose-built medical facility, staff stated that there
are not enough consultation rooms for the number of patients. Some offices had
been converted to examination and consultation rooms as a way of addressing the
shortfall.
2.51
The Committee observed that the waiting area for clients is too small,
with many having to wait outside. It also appeared that clients accessing
mental health and counselling services received little privacy, having to share
waiting areas with clients accessing general medical services. Maintaining
confidentiality and privacy is essentially impossible.
Recommendation 4 |
|
The Committee recommends that the Australian Government
Department of Immigration and Citizenship review existing medical facilities
and services at the Christmas Island Immigration Detention Centre (North-west
Point), with a view to ensuring that all detainees have full access to all medical
services in an appropriate and suitable medical centre environment. |
Construction Camp
2.52
The Committee also met with contracted staff from the medical centre at
the Construction Camp detention centre. It was immediately obvious to the
Committee that the medical facility is far too small and not fit for purpose.
2.53
The medical facility is highly unlikely to be able to cater for a full
client load at the detention centre, nor would it be able to cope with any
client surge capacity.
2.54
The Committee observed that:
n the examination
spaces are small, side by side and have no privacy whatsoever;
n there are no discrete
waiting areas for medical centre clients;
n the office, kitchen
and ablutions facilities for staff are poor;
n the drugs store and
supply facility is removed from the medical facility itself, in a quite
separate location;
n interpreters use the
facility as a waiting area; and
n the medical facility
is wholly within the detention centre, requiring staff to move through the
compound to get to and from their workplace; this may prevent egress for staff
during times of unrest in the compound.
2.55
The Committee understands that Construction Camp is an Alternative Place
of Detention, meaning that it is designed to take overflow clients once the
immigration detention centre at North-west Point is near or at capacity.
2.56
The Committee was informed that, as at 25 September 2011, the Christmas
Island detention centres housed the following numbers of clients:
n North-west Point –
663
n Construction Camp – 252
n Phosphate Hill – 0
2.57
The Committee was informed that North-west Point has an operational
capacity of 400, with a contingency capacity of 850. Construction Camp’s
operational capacity is 200, with a contingency capacity of 310.
2.58
The Committee is of the opinion that the building and operation standards
of a detention facility that is intended to be used irregularly, such as
Construction Camp, should not be lower than that of any other centre.
2.59
Regardless of Construction Camp’s status, or how often or how long the
centre is used, the medical facilities there should be of the same standard as
those found at a regularly used, continuous-operation immigration detention
centre. The medical facility should be fit for purpose, if and when it is used.
2.60
The Committee recommends that a fit-for-purpose medical centre be
designed and constructed for the Construction Camp detention centre. Design
must be completed in consultation with detention centre management, medical
staff and the Department of Immigration and Citizenship’s Health Advisory Group.
Recommendation 5 |
|
The Committee recommends that the Australian Government
design and construct a fit-for-purpose medical centre for the Construction
Camp Alternative Place of Detention on Christmas Island, which will include
(but not be limited to):
n a
sufficient number of discrete and appropriately sized consultation and
examination rooms or suites;
n appropriate
client waiting areas;
n a
secure drug store and dispensary;
n separate
waiting and consultation areas for mental health care and counselling
services;
n adequate
storage for all medical supplies; and
n suitable
kitchen and ablution facilities for staff.
The medical facility should be attached to existing
administrative areas and/or compound entrance or exit to facilitate access
and egress for staff, while still allowing access for detention centre
clients. Detention centre management, medical staff and the Department of
Immigration and Citizenship’s Detention Health Advisory Group must be consulted
regarding the design of any proposed medical facility. |
Phosphate Hill
2.61
The Committee inspected the medical facility at the Phosphate Hill
detention centre, and observed that it functions largely as an extension of the
main medical facility across the road at Construction Camp.
2.62
The Committee noted that the Phosphate Hill medical facility seems
sufficient for consultation services at this point in time.
Australian Federal Police headquarters
2.63
The Committee appreciated the opportunity to inspect existing Australian
federal Police (AFP) facilities on Christmas Island, and briefly inspected a
potential site for a proposed new AFP headquarters.
2.64
Information concerning the proposed AFP headquarters discussed below was
largely drawn from meetings and discussions with representatives of the AFP,
representatives of DRARDLG, and from a strategic business case[11]
prepared for DRARDLG by consultants GHD Pty Ltd.
2.65
On inspection, the Committee found the existing facilities at the AFP
headquarters to be inadequate, sub-standard and not fit for purpose.
2.66
In particular, the Committee made the following observations regarding
the facilities:
n there is no separate
and secure space for incident control;
n there is little or no
dedicated space for processing persons in custody;
n there are only very
small and inadequate spaces for storage of policing equipment;
n office space for AFP
staff is small and cramped;
n the weapon unloading
facility is currently in a disused cell and is grossly inadequate;
n a cell unfit for
occupation is used as a storage area;
n the remand area,
including cells and yard, is inadequate, with officers unable to observe
persons in cells, and is unsafe for both officers and persons on remand; the
yard is also subject to significant seawater inundation during storm surges;
n kitchen facilities
are small and immediately adjacent to a toilet; and
n there has been
significant structural damage to the building, due to a recent earthquake, to
the point where the building may be unsafe for occupation;
n poor structural integrity
has led to fixtures such as window pelmets becoming unsafe, and paint peeling constantly;
n toilets facilities
are inadequate, with no separate facilities for men and women.
2.67
The Committee also noted that there are no facilities for periodic
substantial increases in the number of AFP officers who travel to Christmas
Island for several weeks at a time to provide support to security operations at
the immigration detention centres.
2.68
The Committee was disappointed to discover AFP officers operating in
such appalling conditions. These officers are already operating in a highly
stressed environment and deserve better accommodation.
New headquarters
2.69
The Committee understands that DRARDLG recognised that a new AFP
headquarters as a priority need. DRARDLG engaged GHD Pty Ltd in November 2010
to develop a strategic business case for a new Christmas Island Australian
Federal Police Headquarters.
2.70
One of the recommendations from the GHD report is for a detailed business
case to be prepared as soon as possible to confirm the suitability of the
recommended scope and site for a new facility for the AFP.
2.71
DRARDLG anticipates that a detailed business case will be completed by
March 2012. DRARDLG expects to seek funding for a new AFP headquarters in the
2012-13 Budget process.
2.72
The Committee is deeply concerned by the sub-standard condition of the
existing AFP headquarters on Christmas Island. The Committee recognises that
AFP officers are currently asked to work in inadequate and potentially unsafe facilities,
and often in very trying circumstances.
2.73
The Committee considers the establishment of a new AFP headquarters an urgency
priority.
2.74
The Committee therefore recommends that the Australian Government move
to construct new headquarters for the AFP on Christmas Island as a most urgent priority.
Recommendation 6 |
|
The Committee recommends that the Australian Government, as
an urgent priority and outside of the normal Budget process, construct new
headquarters for the Australian Federal Police on Christmas Island. |
Accommodation for other agencies
2.75
The Committee understands that DRARDLG is currently reviewing the accommodation
of Commonwealth agencies on Christmas Island, with a view to consolidating some
accommodation and moving agencies to the most appropriate location.
2.76
Further, the Committee was advised that there is the possibility of
establishing a consolidated government agency facility which would accommodate
the AFP headquarters, DRARDLG staff and the Christmas Island Administrator.
2.77
The Committee looks forward to the outcomes of the accommodation review.
Ms Janelle Saffin MP
Chair
13 October 2011