Chapter 2 F-111 Fuel Tank Maintenance
The need for F-111 fuel tank repairs
2.1
In October 1963, the Australian Government placed an order for 24 F-111C
aircraft from the United States Air Force (USAF). While delivery was scheduled
for October 1968, technical issues and the loss of some USAF F-111 aircraft in Vietnam meant that the Australian order was not delivered until June 1973. This delay resulted
in the Australian aircraft being in storage in the US for a period of some five
years.
2.2
The F-111 possesses a number of special and even unique capabilities.
One of these is its long range capability, enabling the aircraft to operate
without refuelling over very long distances. To accomplish this, the F-111
maximises the storage of fuel in a way not adopted with any other aircraft in
the RAAF. It is in one sense a ‘flying fuel tank’ with armaments attached and a
cockpit for the pilot. Unlike many other aircraft, there is no fuel bladder in
the F-111.
2.3
The Chief of Air Force (CAF) described the structure of the aircraft’s
fuel carrying capacity:
Because of the F111’s role as a long-range strike aeroplane—
which, again, it was very good at—and the shape of the aeroplane. A classic one
is the A2—the aft tank between the two engines. In most normal aeroplanes you
would not try to fit fuel in there. To maximise the amount of fuel that it
carried, pretty much every nook and cranny in the aeroplane where fuel could be
put was looked at, and that is where they put the fuel.[1]
2.4
Approximately three months after delivery, the RAAF discovered
deteriorating sealant while investigating fuel leaks. Shortly after this, the
RAAF became aware of serious fuel leak issues being experienced by the United
States Air Force (USAF) in their F-111 aircraft. The discovery of the
deteriorating sealant, coupled with the fact that the aircraft had spent such a
long time in storage meant that the RAAF was required to rectify major fuel leak
issues on the aircraft.[2]
The Formal Deseal/Reseal Programs
2.5
Notwithstanding that ‘pick and patch’ work commenced almost immediately
that aircraft were in service, it was in October 1977, following a similar
program put in place by the USAF at the Sacramento Air Logistics Centre (SM-ALC), that the RAAF instituted a formal Deseal/Reseal (DSRS) program at No. 3 Aircraft Depot
(3AD) to ‘deseal’ and then ‘reseal’ the fuel tanks with new sealant. Some
eleven aircraft were maintained at RAAF Base Amberley while the remainder, were
sent to the USAF in Sacramento between May 1981 and December 1982. This first
Australian program ceased in February 1982. Additional DSRS programs were
conducted from 1985 – 1992, 1991 – 1993 and 1996 – 2000.
2.6
The Department of Defence provided a timeline of the various DSRS
programs:
1977-1982: The first Deseal/Reseal program ran from 1977 to
1982 and used the chemical SR51 (SR= sealant remover) and SR51A, which are now
considered to be toxic. This involved RAAF personnel from No 3 Aircraft Depot.’
1985 – 1993: The separate, but linked, ‘wings’ program ran
from 1985 to 1993. This program did not involve fuel tank entry.
1991 -1993: The second Deseal/Reseal program ran from 1991 to
1993 and used more benign chemicals, but still demanded exacting (mechanical)
cleaning standards.
1996 – 1999: The less rigorous spray seal program ran from
1996 to 1999.This process involved a basic clean and then a spray of sealant in
the tanks…While the chemicals were also relatively benign, the exposure to
airborne particles of sealant exposed maintenance staff to a hazard.[3]
2.7
It should be noted that the Board of Inquiry (BOI) report states that
the ‘wings’ program ran from, 1985 – 1992. The Committee has been advised that
the date of 1993 as stated in the above submission was in error.
2.8
Defence informed the Committee that the most accurate estimate of the
number of people involved in the formal programs is 872, based on work done for
the SHOAMP. This comprised 785 RAAF personnel, 48 civilian contractors and 39
individuals who did not identify their rank at the time of the BOI.[4]
The Committee is also aware that some school students undertaking job
experience may also have been exposed to this work, albeit for comparatively
short periods of time.
The first program
2.9
The first formal DSRS program ran from October 1977 to December 1982.
This program was modelled on a similar program being run by the USAF at the SM-ALC in Sacramento. One of the key elements of the USAF program and the first DSRS program at
Amberley, was the use of the chemical desealant, SR51, supplied by the Eldorado
Chemical Company in the USA. SR51 was not used in subsequent programs.
2.10
It was noted that the DSRS process produced highly noxious odours and
potentially flammable fumes and therefore a specific facility was established
at Amberley.[5] This facility was
building 661 at Amberley and was commonly known as the ‘rag hangar’. The
building was a canvas-covered, air-transportable hangar, situated some distance
from the other maintenance facilities at Amberley. Access to the ‘rag hangar’
was restricted due to the use of SR51. The BOI noted that warning signs
relating to hazardous chemicals were prominently placed in the hangar during
the desealing process.[6]
2.11
The recommended DSRS process itself is well documented in the BOI,
However, much evidence has been taken demonstrating that on many occasions, the
recommended safety procedures were not followed.
2.12
For example, Personal Protective Equipment (PPE) guidelines were seldom
followed due to failures in the PPE, the restrictive confines of the internal
tanks, availability of PPE and often very high temperatures in the work
environment. Evidence regarding work procedures and PPE are covered later in
this report.
The ‘wings’ program
2.13
Inspection of the wing tanks in Australia confirmed the USAF experience
that the sealant in the wing tanks had also begun to deteriorate. The RAAF
began a DSRS program on the wing tanks of the F-111 aircraft from 1985 until 1992.
The work was conducted in Hangar 277, a general purpose aircraft maintenance
hangar staffed with a combination of RAAF personnel and civilian contractors.
2.14
The ‘wings’ program differed from the first and subsequent programs in
that tank entry was not required. Work in very restricted areas common in the
other F-111 fuel tank work, was therefore not an issue with wing tank work. It
is neither reasonable nor accurate to regard the wing repair work as similar to
or as difficult as the F-111 fuselage tank repair work.
The second program
2.15
The USAF experience showed that major deterioration of the sealant could
be expected after about seven years. It had also been found that the techniques
in the first program and subsequent formal and informal ‘pick and patch’
activities did not remove all of the degrading sealant.[7]
Further fuel leaks had begun to appear and a second DSRS program was instituted
at 3AD in 1991 and continued until 1993.
2.16
The BOI points out several differences between this program and its
predecessor, most notably the decision to send the program to tender to
Australian industry due to staff shortages at Amberley. The ‘wings’ program was
not included in the tender documentation. Five aircraft were also sent to SM-ALC in the USA for DSRS.
2.17
Other notable differences could be seen in the methods and sealants
employed in comparison to the first program. The Materiels Research Laboratory
(now known as the Defence Science and Technology Organisation or DSTO)
conducted some research on the reasons behind the failures of the sealants and
discovered that the existing sealant could be peeled from the tank surface,
even when prepared under the manufacturer’s instructions.
2.18
Two options were thus put forward. The first was to remove old sealant
with the help of a chemical softening agent (such as the SR51 in the first
program) or the use of hydrolasers. The latter option was chosen due to
concerns about the health effects caused by the softening agent from the first program.
A decision was also taken that the cleaning solvents to be used would not
differ from those already in use in the ‘wings’ program.
2.19
The eventual tender was won by Hawker de Havilland, a subsidiary of
Boeing. Several changes were made as part of the contractual arrangements
between Hawker de Havilland and Defence including that warnings of the toxicity
of chemicals and the need for PPE were included with ‘DSRS Work Sheets’
(officially known as Australian Aircraft Publications and issued internally by
the RAAF).[8]
2.20
The facilities to be used were hangars 278 and 280 belonging to 3AD and
later, 501WG.[9] Contractual arrangements
also left Hawker de Havilland responsible for some physical aspects of the work
area including drainage, ventilation, power, light, water, first aid, the
provision of a fresh air supply and adherence to all Commonwealth and State
environmental laws. Importantly, as part of the contract, several training
modules were also put into place – a five-day DSRS training course run by 3AD
(which included aircraft safety, the DSRS process, OH&S and use of the
hydrolaser), a DSRS operator’s course conducted by Hawker de Havilland,
hazardous substance training (for the safe use and handling of chemicals) and
confined space entry training.
The spray seal program
2.21
The final program, the ‘spray seal’ program ran from 1996 to 1999. The
RAAF became aware of a new process developed by Lockheed which used
polythioether sealants. The process involved spraying the new sealant over the
old sealant, without the need to remove the old sealant. Trials by Lockheed on
F-117 aircraft showed minimal leaks over the course of four years.
2.22
The USAF at SM-ALC had not adopted the method developed by Lockheed due
to its prohibitive cost; however RAAF began trials with similar chemicals on
the F-111. At the same time, an industrial hygiene survey was conducted by
Armstrong Laboratory in the USA which found that this process could be safely
conducted using recommended PPE and safety procedures.
2.23
An Australian trial on an F-111 aircraft was approved in 1992 on the
proviso that the Armstrong Laboratory instructions were fully complied with.
The trial was conducted at 501WG and involved two technicians from SM-ALC providing instruction and also providing some additional PPE as used by the USAF. A report on
the trial described it as successful. The SM-ALC technicians stressed the need
for a specific minimum level of PPE due to the hazardous nature of the spray
seal process.
2.24
The spray seal process was approved in January 1997 and was to be
conducted at the 501WG Paint Shop. The BOI found that while the RAAF had
appropriate approval and documentation of the processes involved, there were no
specified time limits that personnel could be inside the fuel tanks. This was
in contrast to the USAF which specified a maximum two-hour shift, with no more
than four hours in any eight-hour shift to be performed inside the tanks. Like
the second program, training was specified and included a confined spaced entry
course, spray seal process training, hazardous substance training and a
refresher course for the confined spaces entry course for previous
participants.[10]
2.25
The Department of Defence informed the Committee:
In 2000, following growing concern from Unit management at
the number of F-111 fuel tank maintenance personnel reporting health problems,
the spray seal program was halted on 28 January and a unit investigation began.[11]
2.26
Following the suspension of the program, a BOI was commissioned to
investigate areas of concern.
Flight Line maintenance
2.27
Several types of maintenance programs existed – the longer term major
fuel leak repairs, conducted in the formal DSRS programs described above, and
operational flight-line repairs, conducted in the maintenance squadrons,
detailed below.
2.28
Within the formal DSRS programs, there was a full-scale maintenance
program to ‘deseal’ and then ‘reseal’ fuel tanks. The formal programs also
conducted a program of ad-hoc repairs which did not require a complete DSRS
overhaul. This was known as ‘fuel tank leak repair’ or colloquially as ‘pick
and patch’. Importantly, these ‘pick and patch’ repairs were also conducted as
part of the maintenance work on the F-111s within the maintenance Squadrons 1,
6 and 482 outside of the formal DSRS programs. This form of ad-hoc repair was
also conducted prior to the formal DSRS programs. ‘Pick and patch’ was also
conducted at 3AD and 501WG even when no formal DSRS activities took place. The ‘pick
and patch’ work began in 1973 and continued concurrently with all of the formal
DSRS programs.
2.29
It should be noted that the ‘pick and patch’ repair processes within the
formal DSRS programs were exactly the same as those used in the squadrons. This
ad-hoc maintenance was conducted during times when the formal DSRS programs
operated and also during periods when no formal DSRS operations were performed.
Occupations involved
2.30
Defence advised that the main occupation of those engaged
in squadron-level ‘pick and patch’ was that of Airframe Fitter (AFFITT) (later
renamed Aircraft Technician or ATECH). Some of these personnel also
participated in the formal DSRS program. The Department estimates:
…the figure of 2300 covers all AFFITT/ATECH personnel
involved in the four formal deseal/reseal programs and at F-111 Squadrons and
aircraft depots. Consequently, it is clear that a number of these personnel,
approximately 600, have already received an ex gratia lump sum payment from
their involvement in the deseal/reseal programs.[12]
2.31
The Committee has taken evidence from many of those who worked in areas
associated with DSRS and ‘pick and patch’ operations. It should be recognised
that these individuals, worked in occupations that from time to time included
work on F-111 fuel tank repair, or in related activities. Evidence to the
Committee has been taken from those who worked in other occupations such as:
n Electrical fitters
n Surface finishers
n Incinerator operators
n Equipment Officers
n Non-Destructive
Inspection Technicians
n Instrument Fitters
n Photographers
n Fire-fighters.
2.32
Of these various trades, evidence to the Committee
indicates that the occupations of electrical fitters and surface finishers in
particular were more likely than others to spend time in fuel tanks.[13] One contributor to the Inquiry notes:
As an Electrical Fitter I was responsible, among other
aircraft systems, for the Fuel Management Systems on the Fl 11 aircraft. This
included Fuel Contents, Fuel Quantity, Fuel Distribution, Fuel Transfer and
Fuel Dump Systems. As a result, I and other Aircraft Electrical Fitters worked
with and in conjunction with the Aircraft Airframe Fitters/ATECHs on many of
the fuel system problems experienced on the F111 aircraft.[14]
2.33
Other evidence has suggested that checking and
repair of electrical wiring within the airframe was not uncommon when the ‘pick
and patch’ activities were being undertaken and whilst the aircraft was
defueled. One witness notes that, while these trades were not specifically involved
in the actual ‘deseal’ and ‘reseal’ of the aircraft:
…some other trades may have entered the tanks for such things
as crack or damage recognition and/or repair, or for wiring or fuel probe
removal and/or installation or repair.[15]
2.34
There was some evidence to suggest that while individuals had specific
tasks to complete:
…quite often all aircraft maintenance workers working in the F111C
Hangar would pitch in to ensure that aircraft were available for flying duties.
This meant that all aircraft trades would be exposed to the types of chemicals
used to conduct the pick and patch fuel tank repairs… This practice was quite
widespread and, I believe, was condoned by the management.[16]
2.35
Mr Barry Gray, as a former warrant officer engineer in 482 Squadron told
the Committee:
…the reverted sealant, it was everywhere. It was all over the
aircraft, running down the sides. To get that cleaned for a flight was very
difficult. We used all sorts of chemicals to get rid of it, similar to the
tanks. The leaks were that bad we used to joke that you had a put a raincoat on
when you walked around the aircraft to do a pre-flight.…When we did the pick
and patch, we would be in that tank up to eight or nine hours a day and that
could be for a week until you found the leak. In this time, we would defuel the
aircraft, get in there and find the leak, if we could, patch it and let the
sealant go off. [17]
2.36
In reply to the Committee’s observation that it was evident that there
was ‘a wide range of people who were involved in one way or another’[18]
Mr Doug Steley, a leading aircraftman (LAC) photographer at Amberley between
1976 and 1979, said:
The reason for the photographs at that stage was that there
were 24 squadrons operating F111s [worldwide] and any defect in any aircraft
had to be shown to every other squadron so that they could check that area of
the aircraft to make sure that there were no similar problems…you would climb
up onto the aircraft and go down into the tanks with one of the workers. They
would point out the areas that were to be photographed…Everything that happened
inside that fuel tank from the time it had the fuel drained from it to the time
it was ready to fly had to be documented.[19]
2.37
While it is accepted that AFFITT and ATECH classifications spent most
time in the fuel tanks, it is apparent that there were other staff in
occupational categories who entered fuel tanks.[20]
For most, but not necessarily all in this category the time spent working in
the difficult conditions of fuel tanks was substantially less than others who
worked in either the formal DSRS programs or as Airframe Fitters in the
squadrons.
Civilian contractors
2.38
In addition to those RAAF personnel who worked in the formal DSRS
programs, contract personnel were also used to conduct repairs. These
contracted staff worked only in the four formal DSRS programs and therefore
would be entitled to the ex-gratia payment and the SHOAMP Health Care Scheme (SHCS)
where they met the criteria.
2.39
With respect to compensation, whilst RAAF- employed personnel are
covered by the Safety, Compensation and Rehabilitation Act 1988 (SRCA)
or the Veterans’ Entitlements Act 1986 (VEA) or both, civilian
contractors have recourse only to the Workers Compensation and
Rehabilitation Act 2003 (Qld).
Tasks involved
2.40
Defence outlined the differences in tasks between those involved in a
‘pick and patch’ type activity, and those involved in formal DSRS.[21]
2.41
Defence advised that the range of activities and time in fuel tank
repair work undertaken in DSRS was greater than in ‘pick and patch’;
…workers re-entered the fuel tanks to ‘hand pick’ and
physically remove any remaining sealants. This was achieved by using an
assortment of dental picks, wire brushes, scrapers and rags…. This process used
a general purpose solvent and took approximately 28 days for 24 hours per day
utilising three shifts a day to complete. Similar tasks using general purpose
solvents were undertaken during squadron pick and patch activities, but were
generally of much shorter duration than the hand pick and cleaning phase of the
Deseal/Reseal programs and significantly less intensive in terms of the amount
of sealant needing to be removed…[22]
2.42
The Committee has taken a great deal of evidence from individuals who
were not officially employed in a specified DSRS section at Amberley, but were nonetheless
exposed to the same or similar working conditions as those in the formal DSRS
programs. The SHOAMP recognised that:
Some repair work similar to DSRS was conducted on the F-111
fuel tanks prior to, during, and after the formal Deseal/Reseal programs. The
operation known as “Pick and Patch” was used to repair F-111 fuel tanks that
were leaking. As with the formal DSRS programs, the Pick and Patch process
involved entering the F-111 fuel tanks, carefully locating suspect areas of
sealant, and removing the sealant from the area of concern plus a margin around
it using solvents and tools such as dental picks. A patch of new sealant would
then be applied. The aircraft subject to this process were in operational
squadrons. As such, the Pick and Patch process involved running (ad hoc)
repairs by the best means available whenever needed – and with a sense of
urgency given the requirements for a certain number of aircraft to meet flying
commitments at any one time. [23]
2.43
In addition, some depuddling of fuel tanks was required
prior to ‘pick and patch’ work. For example, Mr Lawler noted that fuel
needed to be removed from tanks or ‘depuddled’ before technicians could get to
the sealant to be removed and the area patched:
‘The other issue is that there was fuel left in the tanks.
Those vapours continued to build up and cause us problems.’ Although those
involved in ‘pick and patch’, ‘did not pull all of the sealant out of the
tanks…Sometimes we spent weeks at the squadrons, without exaggeration, digging
up different parts trying to patch it. A lot of the time we sent the aircraft
back out, it leaked again, and we brought the same aircraft back in.[24]
2.44
Air Vice-Marshal Brown noted in evidence that the ‘pick and patch’
activities in both the formal DSRS programs and squadrons were essentially the
same:
In reality there was no real difference
between the pick and patch work done at Squadrons 1, 6 and 482 and what was
done in the reseal-deseal section.[25]
2.45
Whilst the ‘pick and patch’ work undertaken in the formal DSRS program
was virtually the same as that undertaken in the informal program, those in the
formal DSRS programs were engaged in more extensive and prolonged work inside
the F-111s. Those who undertook informal ‘pick and patch’ work had other duties
unrelated to F-111 fuel tank repair. Defence notes:
There were guys in squadrons 482, 1 and 6 who spent
considerable time in the tanks doing pick and patch work… At the squadrons
there would have been people who worked inside the tanks, but they would have
also done other work. They might have rigged flaps, done ramp servicing, and
things like that. The whole time they were in the squadron was not spent inside
the tanks. [26]
2.46
There can be no dispute that F-111 fuel tank repair work was not limited
to the formal DSRS programs run at 3AD and 501WG. While these areas were
responsible for larger and more complex maintenance on the fuel tanks, the
personnel in 1, 6 and 482 Squadron were responsible for the day to day
operational requirements to keep the fleet flying. In fact, fuel tank leak repair
(or ‘pick and patch’ as it is more commonly known) was conducted solely by 482
Squadron from 1973 until the commencement of the first DSRS program in 1977.
2.47
It is noted that the RAAF provided an allowance to some F-111 fuel tank
workers during the period 1981 – 1990.[27] In 1990, this DSRS
allowance was revoked and replaced by Arduous Conditions allowance.[28] The details are
as follows:
RAAF Deseal-Reseal Allowance
3. An allowance called “RAAF Deseal - Reseal Allowance” is
payable to a member who, during the day, performs –
(a) deseal or reseal
duties, other than supervision duties, in the fuel tanks on F111 aircraft,
under adverse working conditions; or;
(b) supervision, under
adverse working conditions, of a member refereed to in paragraph (a).
Rate of Allowance
4. Subject to clause 5, RAAF Deseal – Reseal Allowance is
payable –
(a) in respect of a member
to who paragraph 3(a) applies – at the rate of $6.00 for each day on which he
performs duties under adverse working conditions; and
(b) in respect of a member
to whom paragraph 3(b) applies – at the rate of $3.00 for each day on which he
performs supervisory duties under adverse working conditions. [29]
2.48
The Committee took evidence that the payment of this allowance was at
times haphazard and inconsistent.