Chapter 2 Major projects
2.1
During the 2008-09 financial year the Defence Materiel Organisation
(DMO) expended $4.8 billion ‘on major and minor capital acquisition projects.’[1]
2.2
According to the Australian National Audit Office (ANAO), keeping major
projects on schedule remains a major challenge for the DMO. In its 2008-09
Major Projects Report, the ANAO examined the history of the 15 major
projects[2] noting that:
- eight project schedules
slipped by a total of 378 months against original dates for achieving final operational
capability (FOC); and
- seven projects have
experienced in year schedule slippage totalling 119 months or an average seven
per cent increase in the FOC schedule.[3]
2.3
This chapter examines a number of joint major acquisitions as well as
major acquisitions for the Navy, Army and Air Force focussing on the current
status and challenges of each project.
Tri-Service
High Frequency Modernisation Project
Background
2.4
The High Frequency (HF) Modernisation Project, JP 2043 Phase 3, provides:
…for the procurement of a Modernised High Frequency
Communications System for Defence long–range communications. The Fixed Network
component comprises four High Frequency stations, one station in each of the
Riverina (New South Wales), Townsville (Queensland), Darwin (Northern
Territory) and North West Cape (Western Australia) areas together with primary
and backup Network Management Facilities in Canberra. The project will also
provide upgrades to selected Australian Defence Force [ADF] sea, land and air
mobile platforms to make them compatible with the top–level capabilities of the
modernised network.[4]
2.5
The first stage of Phase 3, completed in 2004, ‘replaced the existing
Navy and Air Force High Frequency networks and is now supporting Australian
Defence Force operations.’[5]
2.6
The second stage of Phase 3 ‘will provide increased levels of
automation, improved capability, enhanced security and survivability, reduced
reliance on staff and will incorporate the new equipment into selected mobile
platforms.’[6]
2.7
The project has been subject to significant delays. In its Defence
Annual Report 2008-09, Defence noted the difficulties experienced by the
prime contractor with ‘certain complex elements of design, integration and
testing’ and pointed out that a revised schedule had been agreed with the prime
contractor.[7]
2.8
In its 2008-09 Major Projects Report, the ANAO noted the schedule
slippage and was of the view that these ‘delays, together with platform
availability problems, mean that the Mobiles program[8]
may extend to 2016.’[9] Of particular risk to the
mobiles program is:
The tasks of integrating the HF upgrade equipment with
existing communications systems of varying levels of maturity and
sophistication, and accommodating the new equipment within the spaces
available…[10]
2.9
The ANAO did note that, despite the delays, the ‘Core System is
currently providing a highly reliable service in support of operational ADF
platforms, meeting or exceeding the specified availability.’[11]
Current Status
2.10
At the public hearing, Defence highlighted that the delivery schedule had
been delayed and as a result the Commonwealth had sought compensation stating:
We completed the negotiations on 25 April last year and that
adjusted the schedule in return for a net amount of compensation, both monetary
and in kind, to the Commonwealth valued at $13 million. The new schedule, as a
result of that, is that final system acceptance is due to occur in July 2010.
At the moment Boeing is ahead of that schedule, with the contract completion
due on 20 August.[12]
2.11
Defence also noted that extensive delays in the project’s schedule have
required Defence to undertake a review of which platforms require upgrades to
HF. Defence stated:
The platforms that are currently on the list are based on
what was originally approved in the mid to late 90s. Now that we have
demonstrated the system and we know what it is capable of, it provides us the
opportunity to look at those platforms that can truly benefit from the additional
level of functionality provided by the network versus those that just would
benefit from straight HF communications. That review is currently underway by
CDG [Capability Development Group].[13]
2.12
The Committee asked for Defence’s views on whether recent acquisitions,
such as the Armed Reconnaissance Helicopter (ARH) and the Multi Role Helicopter
(MRH), have an equal or better communications capability than platforms
retrofitted with HF communications.
2.13
Defence were of the view that the communication suites in the new ARH
and MRH were both comparable and compatible with the upgraded HF communication
suites in the Black Hawk and Chinook helicopters, stating:
The ARH Tiger and MRH90 helicopter fleets have an improved
suite of communications over current helicopters. The High Frequency (HF)
communications capability of these two aircraft fleets is as capable as the HF
upgrade to Black Hawk and Chinook, and is compatible with the modernised high frequency
communication system. The ARH and MRH also have integrated satellite
communication systems to assist with non line of sight communications (this is
required, for example, for long range flying and in mountainous terrain). ARH
and MRH also have data link systems which can operate via HF and satellite.[14]
2.14
Defence added that the contractor, Boeing Australia Limited, will
deliver most of the requirements to the technical specifications of the system.[15]
2.15
On 12 May the Government announced that the ‘final Fixed Network system
has recently been formally accepted from the prime contractor, Boeing Defence
Australia.’[16]
Multi Role Helicopter
Background
2.16
The Air 9000 MRH Program will provide forty-six MRH-90 helicopters and
support systems for the Army and Navy to replace the existing Black Hawk and
Sea King fleets.[17]
2.17
In the Defence Annual Report 2008-09, Defence stated that:
Six MRH-90 helicopters have been accepted and are in service
with the Army 5th Aviation Regiment in Townsville. A further nine MRH-90
helicopters are expected to be delivered during 2009-10.[18]
2.18
Defence added that training of Army and Navy Aircrew and maintenance and
support personnel is being conducted in training facilities but that a less
than planned MRH-90 flying rate has resulted in some training delays.[19]
In particular, Defence highlighted that the ‘Army Initial Operational
Capability (IOC) of a troop of four aircraft is now expected to be achieved in
late 2011, six months later than originally scheduled.’[20]
2.19
The ANAO, in its 2008-09 Major Projects Report, also observed the
need to increase the rate of flying in order to train sufficient crews and
complete aircraft role validation.[21] The ANAO did note that
despite the ‘six month slip in achieving IOC for Army, although at risk, the
schedule forecast for achieving the IOC for Navy and FOC remains as per the
original plan.’[22]
Current Status
2.20
Defence advised, at the public hearing, that the MRH Program was about
20 per cent complete and that 11 aircraft had been accepted, of which six were
accepted in the current financial year (July 2009 – June 2010).[23]
Defence elaborated on the status of the aircraft stating:
Five of those are in the intermediate level, with a next
level of software load in particular that addressed some concerns we have had
with it. It is true that we have not achieved the flying rate with this
aircraft that we would have liked. The aircraft is still developmental, and
some of the systems are portraying that developmental status.[24]
2.21
The committee sought Defence’s view on news reports quoting an internal
German Army report that there were serious deficiencies in the MRH-90
helicopter.[25]
2.22
Defence stated that it shared the German Army’s concerns and that it is
‘taking action with the contractor and the multiple organisations that make up
NATO helicopter industries to get these addressed.’[26]
Defence noted that it had been in communication with Germany who provides a
base level of certification of the helicopter.
2.23
Defence advised the committee that it had concerns about the MRH’s floor
being too thin for Australian requirements and the physical location of the
door gun mounts.[27] Defence indicated that a
newly redesigned floor for the MRH that was trialled recently did not meet
Defence’s requirements and that more work was to be done. Defence added that
the floor may need to be retrofitted.[28]
2.24
Defence was of the view, however, that the MRH engine was ‘performing
exceptionally well in the UK Apaches at the higher level compared to some
different engine performance in some other craft’;[29]
and that its weather radar and forward-looking infrared were particularly
strong compared to other aircraft.[30]
MRH’s role in counterterrorism
2.25
The committee questioned the MRH’s role in counterterrorism (CT), and in
particular when the Black Hawk helicopters would be phased out for the MRH.
2.26
Defence advised that the Black Hawk will continue to be used until the
MRH has been assessed as suitable for the task. Defence added that the MRH
would first be introduced into standard unit operations and forecast that the MRH
will replace the Black Hawk in the CT role by about 2015.[31]
2.27
The committee also sought Defence’s advice on the current differences
between the MRH and Black Hawk in the CT role.
2.28
Defence stated that fast-roping devices had yet to be developed for the
MRH and that the entry and exit ramps still required certification. Defence
noted that the Black Hawk and MRH were comparable in speed but that the MRH had
additional internal endurance.[32]
2.29
While Defence was of the view that both the Black Hawk and MRH were very
capable and could undertake a CT role, it acknowledged that Defence had ‘not
yet tested whether they can actually get to the same task, at the same time.’[33]
2.30
The committee raised the question on whether the air and ground crew
have any concerns about the transition from the Black Hawk to the MRH.
2.31
Defence advised that:
The onus is on us to get the reliability right on the MRH90
before we ask our users to operate the aircraft, and particularly CT, where
everything has to work exceptionally precisely and right. We have seen the demands
and we have lost people over time when it has not worked correctly. The work we
need to do is to still not mature enough for them. I have asked the project
team to mature our relationship with the end users and take the aircraft in and
demonstrate to them. I have asked them to find the time, though, to make sure
that we show how capable the aircraft is and work through the issues so that,
collectively, we can develop a full CT capability using the MRH90.[34]
Air Force
Joint Strike Fighter
Background
2.32
In 2002 the then government became a partner of the Joint Strike Fighter
(JSF) project, at a cost of $US150 million. In 2006, the then government gave
first pass approval to join the JSF project’s next phase.[35]
2.33
In the 2009 Defence White Paper, the government announced its
intention to acquire around 100 F-35 JSF aircraft, along with supporting
systems and weapons.[36] In the White Paper,
Defence also announced that the first stage of the acquisition would acquire:
…three operational squadrons comprising not fewer than 72
aircraft. The acquisition of the remaining aircraft will be acquired in
conjunction with the withdrawal of the F/A-18F Super Hornet fleet, and will be
timed to ensure that no gap in our overall air combat capability occurs.[37]
2.34
The first decision to acquire the first 14 JSF aircraft occurred in
November 2009.[38]
2.35
As stated in the committee’s previous report on the Review of the
Defence Annual Report 2007-2008, the JSF acquisition will be the most
expensive single acquisition in Defence’s history. As our sole or principal air
fighting platform, it is also arguably our most important defence acquisition.[39]
2.36
In its Defence Annual Report 2008-09, Defence was of the view
that the JSF program made good technical progress but identified key risks for
the project such as ‘cost immaturity and the prospect of technical issues and
delays arising in the final development phase and the extensive ground and air
test program.’[40]
2.37
Defence was also of the view that the project’s risks were mitigated
stating:
These risks are mitigated by NACC [New Air Combat Capability]
project provision allowing for cost growth in excess of 2008-09 US [United
States] Government estimates and aiming to achieve IOC [Initial Operational
Capability] a number of years after the USAF [United States Air Force].
Additional schedule buffer is provided by the acquisition of 24 Super Hornet
aircraft.[41]
2.38
Defence also noted, in its Defence Annual Report 2008-09, that it
is working on ‘shaping the future JSF workforce (aircrew, ground crew and project
staff) and has commenced detailed facilities design for RAAF Williamtown,
Tindal and forward operating bases.’[42]
Current Status
2.39
The committee noted testimony that Dr Ashton Carter, US Under Secretary
of Defense (Acquisition, Technology and Logistics), made before the US House
Committee on Armed Services that the average price of the JSF would be more
than 50 per cent higher than it was projected to be when the program began in
2001.[43] The committee sought
Defence’s views on what it means for the costs that Australia is likely to
incur.
2.40
Defence acknowledged that the total cost of the program had gone up by
50 per cent since the program started but stated that, as Australia does not
pay a proportionate share of the aircrafts development, the average cost per
aircraft is lower than the US average cost.[44] Defence added that as
Australia is buying only the conventional take-off and landing (CTOL) version
of the JSF, the cheapest of the three JSF variants, the average price is a
little less.[45]
2.41
The committee sought information on how Defence formulated its initial
cost projections. Defence advised that:
We look at the annual reports that the US program office
delivers to congress, called selected acquisition reports, and they started as
early as 2001. Every year we look at those reports as the basis for our
estimates. We have looked at the trend in those prices year by year. We have
also done our own analysis on the history of aircraft projects and how price
has tracked over time. We did some sensitivity analysis on the key drivers for
the cost of that. We put all those things together and we always had quite a
higher estimate than the US estimate for our own provisions for a project. Then
we explicitly carry contingency on top of that for unknown risks as well.[46]
2.42
Defence also noted that, up till 2009, the US and Australia costed major
programs differently:
The Americans tend not to use contingency in their project
costs. We have always traditionally used contingency in our project estimates.
So, because major projects do increase in cost, what we do at the beginning of
a project, like we have in the NACC project, is estimate a contingency, and it
gets burnt down bit by bit as things happen to projects. The Americans tend to
report their project increases year by year.[47]
2.43
Defence advised that the expected recurring fly-away price for 100 JSF CTOL
aircraft,[48] without including any
broader project or development costs, ‘was A$75 million in 2008 dollars at a
0.92 exchange rate.’[49]
2.44
The committee questioned whether Australia would incur any additional
upfront costs for the research and development or engineering aspects of the
program.
2.45
Defence pointed out that the US ‘were going to put an additional US$2.8
billion into the project to essentially build an additional test aircraft and
an additional software test line and to cover the extra time involved in the 13‑month
extension to the test program’ and that the US had not asked Australia to
contribute any funds.[50] Defence added that the
US were withholding US$614 million of potential award fee from Lockheed Martin
but that Lockheed Martin would have the opportunity to win some of it back providing
that the project is on cost and schedule.[51]
2.46
The committee also sought Defence’s views on a current assessment of the
JSF’s capability.
2.47
Defence stated that:
We continue to review the capability of the JSF, as it is
contracted to be delivered against likely threats, and our assessment of that
has not changed. We believe it can do the job for a considerable time into the
future, but we note that we will have to continue the upgrade program, which is
built into the program, and continue to deliver new weapons as they come into
service, and the DCP [Defence Capability Plan] has provision for those.[52]
2.48
When commenting on the current anticipated delivery date for the first
JSF to Australia, Defence advised the committee that:
…at second pass approval for the first 14 aircraft, the plan
is to achieve initial operational capability, with the first squadron ready for
deployed operations, towards the end of 2018. To achieve that, we are looking
at acquiring our first two aircraft for training in 2014. The initial aircraft
will stay in the US for training and then the last four of those 14 will come
out to Australia in 2017 to do our Australia specific operational tests.[53]
2.49
Defence also advised the committee that there are many factors that
influence when the JSF will become available stating:
So the question of availability of aircraft (1) goes to
cost—the earlier you buy, the more it costs you—and (2) goes to slots, or which
ones on the production line a particular customer can buy. All the countries
are looking at the age of their current fleets. All of the partner countries
have combat aircraft at the moment, and they are ageing, so we have got an
optimisation question to look at between the cost of keeping the classic
Hornets going and the cost of buying Joint Strike Fighters either ahead or
behind particular dates. Those business cases are being worked on during 2010
so that we will have a much better piece of advice to offer government early
next year.[54]
2.50
The committee questioned whether Defence will be able to retrofit the
JSF aircraft back through block 1[55] to ensure that each
aircraft has a common capability and common line of parts.
2.51
Defence advised that there were three blocks of capability in the JSF
development program and stated that:
The hardware basically freezes at block 1, so block 2 and
block 3 are purely software upgrades. The plan beyond that is another block
every two years. The vast majority of that is in software. But about every four
years you might do some minor hardware change, which would flow back through
the fleet. But the plan is to keep all aircraft throughout the fleet at the
same block standard, primarily through software but also through some hardware upgrades
throughout their life. … One of the benefits we get is that we pay three per
cent of the cost of those development upgrades as a partner in the program but
get 100 per cent of the benefits.[56]
2.52
The committee asked Defence for an indication of how much extra noise impact
there will be from the JSF compared to the current generation aircraft of F-111s
or F/A-18s.
2.53
Defence advised that it had undertaken extensive testing in the US which
showed that the JSF is noisier on takeoff using the afterburner but that it was
less noisy in the circuit and approach than the current generation aircraft.
2.54
Defence added that it released a draft Public Environment Report (PER),
incorporated community feedback and would release the final PER, with community
comments, shortly.[57]
2.55
Defence advised that it had also released the Australian Noise Exposure
Forecast (ANEF) which contained the best estimate of likely usage of the JSF,
stating:
We have put that out based on the best estimate of likely
usage of the aircraft with some noise mitigation procedures put in place. Now
we have got the feedback, the report will go out and again we will engage with
the community and the Air Force to see what other mitigation actions might be
able to be put in place for those affected by the noise. We are engaging with
the community and the councils to work through that.[58]
2.56
Defence added that it was considering a number of options to mitigate
the noise impact, including runway extensions, flight paths and conducting
exercises away from the Williamtown base, and would conduct a full
environmental impact study in the future with the Department of Environment, Water,
Heritage and the Arts.[59]
2.57
In responding to the question of whether Defence would acquire farmland in
the vicinity of the Williamtown base to protect its approach and departure
points, Defence highlighted that it ‘generally does not acquire noise affected
properties unless there are exceptional circumstances’.[60]
More specifically, Defence stated:
For properties in the vicinity of RAAF Base Williamtown and
Salt Ash Air Weapons Range, these exceptions exist to support operational or
training requirements, to expand the boundaries of the base, and to acquire
properties in very close proximity to the runway and effectively within the
boundaries of the base.[61]
2.58
Defence noted that a decision about extending the runway would not be
made until 2012, ‘when the majority of funding comes for the facility.’[62]
2.59
The committee noted that there are noise monitoring devices at the
Williamtown base and asked when Defence would have an assessment of the actual
noise impact on the area.
2.60
Defence pointed out that ‘actual noise levels are currently being
measured for existing aircraft and will continue to be measured when new
aircraft are introduced.’[63] Defence added:
Actual noise levels for all aircraft currently operating at
RAAF Base Williamtown were included in the draft Public Environment Report for
the proposed introduction of the Joint Strike Fighter to the base.[64]
Airborne Early Warning and Control Aircraft
Background
2.61
Project Wedgetail, AIR 5077, will provide Australia with an Airborne Early
Warning and Control (AEW&C) capability. Wedgetail is an AEW&C facility
based on the Boeing 737-700 which carries a phased–array radar that can scan
through 360 degrees.[65]
2.62
In December 2000 a contract was signed with the Boeing Company to supply
four aircraft, associated supplies and support. In 2004 the contract was
amended to include an additional two aircraft.[66]
2.63
In February 2007, Boeing announced that there was a two year slip in the
program’s schedule. In May 2008, Boeing made a further announcement that there
would be an additional 10 month schedule delay due to ongoing problems with the
radar, electronic support measures development and system integration.[67]
The project is over 48 months behind schedule.[68]
2.64
In December 2008 the Commonwealth entered into a standstill deed of
agreement with Boeing:
…to enable the company to undertake a modified program of
test and evaluation to determine the extent to which the aircraft system meets
the specification and how well it will perform operationally.[69]
2.65
Under the deed, the Massachusetts Institute of Technology’s Lincoln
Laboratories conducted an independent assessment of radar performance which was
completed in April 2009. An operational utility demonstration was also conducted
in April and May 2009 during Exercise Arnhem Thunder.[70]
2.66
In the Defence Annual Report 2008-09, Defence stated that ‘IOC is
currently planned to be achieved by end 2011 and FOC by end 2012.’[71]
2.67
In its 2008-09 Major Projects Report, the ANAO was of the view
that the ‘overall technical and schedule risk remains high to very high’,
noting in particular technical challenges such as integration of the Radar and
Identification Friend or Foe subsystem, radar, electronic support measures,
communication systems and data links.[72]
Current Status
2.68
At the public hearing, Defence advised that it had taken initial
delivery of two aircraft and that it had commenced flight crew training. Defence
added that it is expecting initial acceptance in late April or early May and
that Boeing was forecasting final acceptance in December.[73]
2.69
Defence also highlighted the findings from the independent assessment of
the radar undertaken by Lincoln Laboratories and noted that they would be
seeking compensation as the assessment indicated that the existing technology
could not deliver the intended capability at this time. Defence stated:
...we had an independent group, Lincoln Laboratory from the
US, look at that radar. They advised us two things which were very important:
one was that the radar was a sound basis for moving forward; and the second was
that existing technology could not deliver that element of capability at this
time. So our compensation is one to allow us over time to introduce that
technology and get that capability; in fact, we are hopeful it will even
improve the capability beyond the original specification.[74]
2.70
Defence advised that the Wedgetail is expected to achieve a vast
majority of its technical specifications, of which there are approximately
10,000. However, Defence indicated that the electronic support measures performance,
the electronic system, and the deficiency in pulse Doppler radar performance
remain problematic.[75]
2.71
The committee sought Defence’s view on reports that the Wedgetail’s
system was failing mid-flight.
2.72
Defence acknowledged that there were system stability issues predominantly
due to software problems and that the system had different failure modes,
stating:
It has a mode where, if there are elements not working,
elements of, say, the complete radar—would you call it gradual degradation—you
can keep operating. On other occasions you can get a hard shutdown…[for] significant
periods—I think, more than 20 minutes to restart it.[76]
2.73
Defence also indicated that there were certain hardware issues with the transmit-receive
modules.[77] Defence, however,
stressed that the Air Force considered that all the other matters were at an
acceptable standard prior to initial acceptance, with the exception of the
pulse Doppler radar performance. Defence added:
We anticipate 98 per cent compliance with spec at final
acceptance. And radar stability is now at around 10 hours. But obviously we
welcome the opportunity to brief the committee on the full aspects of the
performance.[78]
2.74
The first two Wedgetails were officially accepted by the Government on 5 May
2010.[79] However, the Electronic
Support Measures and Electronic Warfare Self Protection Subsystems have yet to
be delivered and improvements need to be made to the radar performance and
integrated system performance before the aircraft reaches its full capability.
This is likely to occur over the next 12 months.[80]
Classic Hornet upgrade
Background
2.75
The project to upgrade the F/A-18 fleet, Air 5376, is being conducted in
three phases:
…the first enabling the aircraft to more effectively perform its
air defence role; the second enhancing pilot situational awareness; and the final
stage providing additional aircraft self protection. Each stage also includes an
upgrade to the aircraft software for ground support and training systems.[81]
2.76
Phase 1 (modification of the air defence role) and Phase 2 (enhancing pilot
situational awareness systems) were ‘completed in August 2003 and December
2008, respectively.’[82]
2.77
In addition to upgrading the Hornet’s performance, Defence is starting
to encounter some fatigue management issues due to the age of the Hornet fleet.
As a result, Defence has taken steps to replace the centre barrels[83]
of selected aircraft and undertake other structural refurbishment work to
extend the fatigue life of the Hornet.[84]
2.78
In its 2008-09 Major Projects Report, the ANAO noted:
In May 2008 an engineering study showed that the fatigue life
of Hornet Centre Barrels could be extended beyond the current limits. As a result
only 10 aircraft will require Centre Barrel Replacement. Additional discrete structural
modifications are being undertaken on 42 aircraft to address fatigue damage,
corrosion and other emergent ageing aircraft issues; 19 of these aircraft have been
completed as at 30 June 2009.[85]
2.79
More specifically, the ANAO report noted that:
As at 30 Jun 09, the first two prototype and one production centre
barrel replacement aircraft have been returned to the fleet. The 4th - 6th
aircraft have had the centre barrels replaced and are undergoing final rebuild at
RAAF Base Williamtown. The 7th ‑ 10th aircraft have had the centre
barrel replaced and are undergoing initial rebuild in Canada, before being transported
back to Williamtown for final rebuild and delivery[86]
2.80
The ANAO was also of the view that the project to replace the centre
barrels remained within budget and on schedule to be completed by December
2012.[87]
2.81
However, the ANAO noted that both projects contained the following
challenges:
- The key risks relate
to the development and integration of aircraft and system software, as the
systems have not previously been integrated and installed in other F/A-18
Hornet fleets;[88]
- The nature of
structural refurbishment of an ageing aircraft is such that unknown conditions
may be revealed in the process of disassembly. This may result in more
extensive refurbishment work becoming necessary and its unpredictable nature
poses a challenge to the production schedule;[89] and
- …additional parts may
be required to replace those that are found to be unserviceable. Obtaining
these parts in time to maintain the production schedule is a major risk
confronting the project.[90]
Current Status
2.82
At the public hearing, the committee focused on the project to replace
the Hornet’s centre barrel and questioned the projects status, its cost, and
the expected operational life of the Hornet.
2.83
Defence noted that the project was largely complete, having replaced
seven out of ten Hornets[91] at a total cost (for 10
centre barrel replacements) of $292 million.[92]
2.84
Defence was quite confident that the Hornet’s would have an extended
life up to 2020, with an official withdrawal date of 2018, and that no further
centre barrel work would need to be undertaken for fatigue reasons. Defence did
note that the aircraft still required some additional corrosion work to get to
2020.[93]
2.85
The committee also queried whether any additional centre barrel testing
work would be undertaken in Australia if it were required and whether L‑3
Communications MAS Inc in Canada[94] (L-3) would have the
capability for an international requirement of keeping centre barrels
operational.
2.86
Defence advised that L-3 would most likely undertake any additional
testing if it were required, stating:
In all likelihood we would probably do those in Canada. As
you can imagine, it is a very complex modification. It involves breaking the
aircraft apart and taking the wings off. It involves very complicated jigs and
fixtures, for which L-3 have that expertise. So I would imagine that would be
the case. Of course, if we were doing a very large number—indeed, when we were
looking at that in the first instance with 49 we were looking at the business
case for doing that in Australia, possibly using overseas expertise to augment
our local capability.[95]
2.87
However, Defence pointed out that while L-3 still had the capability, it
had closed the centre barrel replacement (CBR) production line and that the
Canadian Forces were ‘retaining one CBR jig until 2017.’[96]
Defence added:
Re-establishment of the capability would be possible; but would
be costly due to re-installation of the jig, engagement of trained technicians
and engineers, and the associated logistics and support infrastructure for this
large and complex modification. It would also take at least several months to
restart the CBR production line, but as L-3 MAS is the CF deeper maintenance
contractor and will be until its planned withdrawal date, the capability to do
so should still exist.[97]
2.88
Defence were of the view that any additional CBR could be carried out by
the United States Navy (USN) if required, stating:
CBR production lines at Fleet Readiness Centre South West
(North Island) and Fleet Readiness Centre South East (Jacksonville) will
continue for several years, with the Jacksonville line planning to be open
until 2017. Due to the existing continuity this may be the best option if CBR
is required for additional RAAF aircraft; although the modifications carried
out by the USN differ slightly to those that L-3 incorporated on RAAF aircraft.[98]
Super Hornet
Background
2.89
In May 2007, the Australian Government announced its intention to acquire
twenty-four F/A-18F Block II Super Hornet multi-role aircraft, Project Air 5349.[99]
2.90
The acquisition is intended to give the ADF a bridging air combat
capability during the transition from Australia’s current air combat capability
(the F/A-18 Hornet and F-111) to the acquisition of Australia’s new air combat
capability (the Joint Strike Fighter).
2.91
In the Defence Annual Report 2008-09, Defence stated that:
The program remains on schedule with the first four aircraft
to arrive in Australia in the second quarter of 2010. IOC will be achieved in
December 2010 and FOC will be achieved in December 2012.[100]
2.92
On 26 March 2010, Australia received the first five Super Hornet’s which
will be based at the Royal Australian Air Force (RAAF) Base Amberley in
Queensland.[101]
Current Status
2.93
Defence highlighted that it had recently signed a Super Hornet training
schedule with Raytheon Australia Pty Ltd and that training had commenced.
Defence was of the opinion that it was a fairly low risk exercise adding that:
Raytheon Australia, who took on that contract, also do the
training for the classic Hornets under contract. They have an experienced
subcontractor, Milskil, who also do training for Super Hornets. They have a lot
of experienced former Australian and former US instructors in that program, and
we believe it is a fairly low risk enterprise.[102]
2.94
The committee sought Defence’s view on whether the Super Hornet was less
susceptible to corrosion than its predecessor.
2.95
Defence noted that there were structural differences between the two
aircraft, with the centre barrel being the most significant, but that all
aircraft are susceptible to corrosion stating:
…the centre barrel on a Super is titanium, not aluminium, so
it has a fundamentally stronger core. It has more composite in it, but it still
comes down to aluminium. Yes, you can coat it, bond it and do those sorts of
things, but fundamentally, in the normal wear and tear of operations, it will
corrode.[103]
2.96
The committee also asked Defence to provide a status report on the
current scheduled delivery dates for the remaining aircraft.
2.97
Defence advised that the current production rate was one aircraft a
month which were being batched and tested in the US. Defence added that the
aircraft would be delivered in six waves, comprising of four Super Hornets at a
time, with waves two and three arriving towards the middle of 2010, wave four
in early 2011, wave five in mid 2011 and wave six in late 2011.[104]
2.98
Defence was of the opinion that it did not think there was a need to
acquire any more Super Hornets[105] but noted that it would
cost ‘at least $1.5 billion to $2 billion or more to acquire an additional
squadron of Super Hornets.’[106]
Navy
Guided missile frigate upgrade
Background
2.99
The project to upgrade four Adelaide Class Guided Missile Frigates
(FFGs), SEA 1390, involves both upgrading and integrating the:
…combat systems, sensors, missile launchers and associated platforms
systems, an onboard training system to the ships’ combat system, and improvements
to the reliability of the ships’ platform systems.[107]
2.100
The project, which commenced in 2009, has undergone significant delays
and is now over four years behind schedule.[108]
2.101
In its 2008-09 Major Projects Report, the ANAO provided an
indication of when each FFG was upgraded, stating:
- Provisional
Acceptance of HMA (Her Majesty's Australian) Ships Sydney, Melbourne and the
Team Trainer were achieved in December 2006, October 2007 and November 2007
respectively;
- HMAS Darwin achieved
Provisional Acceptance in August 2008; and
- HMAS Newcastle achieved
Provisional Acceptance in May 2009. [109]
2.102
In the Defence Annual Report 2008-09, Defence stated that HMA
Ships Sydney, Darwin, Melbourne conducted trials, evaluation, and training
activities and that there continue to be high risks associated with the
project:
The high risk to achieving contemporary capability
effectiveness of the electronic support and torpedo defence systems is being
mitigated by a remedial action program that will continue on through 2009-10.[110]
Current Status
2.103
Defence informed the committee, at the public hearing, that it had
accepted all four FFGs from the contractor, Thales Australia, and that:
The Chief of Navy has provided initial operational release
for the vessels and I think that project, which you know was troubled for many
years, has been removed from the projects of concern list, as announced by
Minister Combet. They are now in the hands of the Chief of Navy and are being
used as operational units.[111]
2.104
The committee noted the comments Defence made at the 16 April 2009
public hearing into the Defence Annual Report 2007-08 that the
electronic support measures system was a major area of concern[112]
and questioned whether the issue was resolved.
2.105
Defence acknowledged that there were problems with the electronic support
measures system and in particular that there were problems with the antennae
and reliability and software problems,[113] but that the problems
had been corrected, stating:
It also required a lot of testing and trialling to understand
the issues, which is a thing we often find. We went through that structured
campaign, found the problems and corrected those problems.[114]
Air Warfare Destroyer
Background
2.106
In the 2000 Defence White Paper the ADF announced that it would
replace the Navy’s FFGs with a class of at least three air defence capable
ships.[115]
2.107
On 11 August 2004 the Federal Government announced that it had ‘selected
the Aegis air warfare system as the core of the combat system for Australia’s
new air warfare destroyers’ (AWD).[116] The Aegis system is
comprised of the radar, the central command and control and the missile control
system.[117]
2.108
On 21 April 2005 the Federal Government announced that Raytheon
Australia Pty Ltd had been selected as the ‘preferred bidder for a major
electronic engineering contract in support of the combat system design and
maintenance for the Air Warfare Destroyer.’[118]
2.109
A month later, on 31 May 2005, the Federal Government announced that ASC
Shipbuilder Pty Ltd would be the preferred shipbuilder for Navy’s Air Warfare
Destroyers.[119]
2.110
The AWD Program is being delivered under an Alliance based contracting
arrangement between ASC AWD Shipbuilder Pty Ltd, Raytheon Australia Pty Ltd and
the Commonwealth of Australia.[120]
2.111
Defence stated, in the Defence Annual Report 2008-09, that the
preliminary design review was achieved in December 2008 and the critical design
review was on schedule for December 2009.[121]
2.112
In the Annual Report, Defence also stated that:
- the majority of
combat and platform systems equipment selections were complete;
- infrastructure work
was ahead of schedule at South Australia’s Common User Facility (Techport) and
the ASC Shipyard; and
- steel fabrication for
the hull blocks was scheduled to commence in late 2009.[122]
2.113
On 21 January 2010 the ASC shipyard was officially opened.[123]
Current Status
2.114
In responding to a question on the status of the AWD project, Defence
noted that despite the initial difficulties, overall progress was still good,
stating:
There [were]…difficulties encountered with the letting of the
block subcontract, in particular with NQEA. That process was terminated for a
number of reasons and, subsequently, that part of the block contract was let to
BAE Systems operating out of Williamstown in Melbourne. I am able to report
that blocks are under construction now at BAE Williamstown, Forgacs in
Newcastle and fabrication work has started at ASC in Adelaide.[124]
2.115
Defence added that it had completed the critical design review in
December 2009 and opened the ASC shipyard and common user facility in Adelaide.[125]
2.116
The committee questioned whether Defence had taken all steps to exercise
due diligence when analysing the financial status of NQEA.
2.117
Defence advised that ASC, not DMO, conducted due diligence of NQEA prior
to acceptance which was confirmed by the AWD alliance board. NQEA subsequently
amended its financial structure after the offer was accepted.[126]
2.118
The committee asked Defence to provide an update on the project’s next
phase to integrate the communications systems and sensors onboard the AWDs and
identify any risks or challenges.
2.119
Defence advised that the first system completed trials in November 2009
and is ready to be shipped to Australia, adding:
We called it the Australianised combat system so that we
could add some features that were particular needs for Australia. The first
element selected with the sonar. That work is progressing satisfactorily. We
are just about to complete the EW, electronic warfare, system down select and
should be in the process in the next week or two of informing the minister of
the alliance’s decision process. So I would say at this stage of the program we
are obviously working very closely with the US on that integration. Kongsberg
is doing what we call the Australian tactical interface, the interface into the
Aegis system.[127]
2.120
Defence was of the opinion that the technical performance measures and
financial progress of the project was satisfactory and that the project was on
schedule to deliver the first AWD in December 2014, despite the loss of some
scheduled progress.[128]
2.121
The committee sought Defence’s view on acquiring a fourth AWD and
whether the additional acquisition would become more or less financially viable
overtime.
2.122
Defence advised that they had not undertaken any assessment of how much
a fourth AWD would cost but noted that the cost of acquiring a fourth Aegis
system for one more AWD would be particularly expensive. Defence added:
America has just announced it is going to restart its DDG 51 [US Arleigh
Burke class guided missile destroyer] construction, and that would lead to them
buying more Aegis combat systems. As our fourth one at that time would have
been the very last Aegis after a break, it would have been potentially quite
expensive. But it is possible now that the Americans will restart the Aegis
production line the costs of that will come down. On the other side, you start
to introduce inefficiency on the ship construction side of it. We have not done
any detailed costing work on that for some time.[129]
2.123
Defence acknowledged that there will still be an opportunity to acquire a
fourth AWD within the next two years as the AWDs should be delivered up until
2018.[130]
Amphibious ships
Background
2.124
Under the Amphibious Deployment and Sustainment Project, JP 2048, Australia
will acquire two amphibious ships, two landing helicopter decks (LHDs) and
associated supplies and support.[131]
2.125
The contract between the Commonwealth and BAE Systems Australia Defence for
the acquisition of the two Spanish designed Canberra Class LHD ships and
support systems came into effect in November 2007.[132]
2.126
The ships hulls will be built and fitted out in Spain prior to being
transported to Australia where they will be integrated with the superstructures
in Melbourne. L3 Communications is subcontracted to provide the communications
system and Saab Systems Australia will provide the combat system and integrate
the combat management system.[133]
2.127
In the Defence Annual Report 2008-09, Defence stated that:
The hulls will arrive in Australia in July 2012 and February
2014 respectively. Delivery and acceptance of the ships is to occur in December
2013-January 2014 and July-August 2015. An in-service support strategy is
currently being developed. The initial support contract is to be in place 12
months before first ship delivery.[134]
Current Status
2.128
Defence advised the committee that 30 per cent of the modules of the
first ship are now on the slipway in Navantia, Spain, and that it expects the
ship to launch in the first half of 2010.[135]
2.129
When asked about the integration of the combat system on the ship,
Defence advised that the core combat system is a derivative of the ANZAC class frigates
combat system and that the challenge would be to integrate the system.[136]
2.130
Defence was of the view that the project had no significant delays or
cost overruns at this stage but that they were closely monitoring the design
process.[137]
Armidale Class patrol boats
Background
2.131
In December 2003 the Government announced that Defence Maritime Services
Pty Ltd had won the contract to provide 12 Armidale class patrol boats.[138]
In May 2005 additional funding was provided for an additional two patrol boats.[139]
2.132
The ANAO, in its 2008-09 Major Projects Report, stated that ‘all
14 vessels have been delivered, achieved IOC and commissioned into the Navy,
with the 14th vessel achieving Initial Operational Release in November 2007 and
commissioned in February 2008.’[140]
Current Status
2.133
At the public hearing the committee highlighted recent reports alleging
that the Armidale class patrol boats were commissioned with design defects.[141]
2.134
Defence advised that the patrol boats had two issues, water in the fuel
and toxic gas in the accommodation compartment, which delayed their formal
operational release but that the issues had been resolved.[142]
Defence added:
Both issues have now been resolved through implementation of
a number of design changes. They have been proven in [HMAS] Glenelg and will be
fitted to all of the ships in the fleet with a view to them being able to meet
Navy’s full operational release requirements by the end of 2011.[143]
Collins-class submarines
Background
2.135
In 1985 a contract was signed with the Australian Submarine Corporation,
now ASC Pty Ltd, to supply six Collins-class diesel-electric submarines.[144]
2.136
Construction on Australia’s first Collins-class submarine, HMAS Collins,
began in 1990 and construction on Australia’s sixth and final Collins-class
submarine, HMAS Rankin, began in 1995. HMAS Rankin was launched in 2001 and
commissioned in 2003.[145]
Current Status
2.137
The committee examined the progress of replacing the generator in the Collins-class
submarines and asked Defence to provide an update.
2.138
Defence informed the committee that the windings on the generators had
failed and was of the opinion that the vacuum impregnation was ‘not done properly
when they were originally manufactured.’[146]
2.139
Defence advised that it had initially estimated that repairing the
generators would take around 23 weeks and noted the size of the task:
Just due to the physical dimensions, the requirement to get
them in and out was a very big task. The Submarine Program Office—a combination
of ASC, the Navy and the DMO—have worked collaboratively to produce a much
better system of getting them in and out.[147]
2.140
Defence added that it is working with Hofmann Engineering, a confined-space
engineering company, who are repairing the generators, stating:
Hofmann undertook the challenge to have them removed,
repaired and put back in a period of approximately 57 days. They are currently
on track. The first of the generators will actually go back into Farncomb today
and will then go through a process. We are very pleased with the work that has
been undertaken to date. It has been an excellent example of the cooperation
between the whole team, as well as of getting the best of breed within
Australian engineering to help us get these Collins-class submarines back into
operations.[148]
2.141
The committee asked whether Defence had any indications that generators
on other submarines were likely to fail.
2.142
Defence noted that the original generators that were manufactured in
France are very solid but that the ‘generators manufactured in Australia are
susceptible to this particular failure.’[149]
2.143
Defence pointed out that it was monitoring the generators and examining
ways to reduce the failure rate, stating:
We are looking at the way in which we can ensure that we do
not get the same sort of failure. We do have three generators on each
submarine. The normal requirement is to only operate two. So what you can do
is: by operating them at about 80 per cent of their normal operating profile,
you restrict the likelihood of a failure. We have now also been able to prove a
world’s best practice way of doing this work.[150]
2.144
Defence also advised that it would be changing out the complete set of
generators in its Collins-class submarines.[151]
2.145
The committee also sought Defence’s views on whether the original
supplier of the faulty generators would be liable.
2.146
Defence commented that the original warranty period had lapsed and that
it would not have a case to seek recompense from the original manufacturers.
Replacement of the Navy’s combat helicopter capability
Background
2.147
The project to replace the Navy’s tactical helicopter fleet comprised of
Seahawks and Super Seasprite helicopters, AIR 9000 Phase 8, is in the early
stage of development.[152]
2.148
On 25 February 2010 the Government announced that the project had been
given first pass approval, and that ‘the new helicopter will be either the
Sikorsky-Lockheed Martin built MH-60R [Romeo] sourced through the United States
Navy, or the NATO Helicopter Industries NH90 NFH [Nato Frigate Helicopter]
sourced through Australian Aerospace.’[153]
2.149
On 28 April the Government announced that the DMO released the tender
for the supply of a new naval combat helicopter, stating that:
Under this project, the Government will acquire sufficient
helicopters to provide at least eight helicopters concurrently embarked on
ships at sea, which under the White Paper requires a fleet of 24 helicopters.[154]
2.150
A decision about which naval helicopter will be acquired is expected to
be made in 2011.[155]
Current Status
2.151
At the public hearing, the committee briefly examined Defence’s
intention to replace the Navy’s combat helicopter capability. In particular, when
comparing the two aircraft the committee put forward the view that:
- the advantages of the
Romeo are cost and risk - the risk is lower because it is a fully developed and
proven aircraft; and
- while the NH90 NFH
was more expensive, the aircraft was constructed from composite materials and
offered greater capability because it can also operate as a ship-to-shore
aircraft.
2.152
Defence acknowledged that it was ‘a fair summation of what has been
publicly described’[156] and that:
The task for us in Defence is to develop and gain the
information for a full and accurate picture of both types.[157]
2.153
The committee also questioned the cost differential between the two
aircraft.
2.154
Defence acknowledged that there was a cost difference as they are very
different aircraft, stating:
One has different maintenance requirements to the other—that
is, time taken to conduct that maintenance.[158]
2.155
On the differences in the ongoing maintenance costs between the two
aircraft, Defence added:
We are measuring this across the 30-year, whole-of-life cost.
It is the acquisition and the through-life costs, particularly where you can
move them between one or the other to a degree. From a Defence position, our
recommendations will be on the information gained for the total, whole-of-life
costs for the aircraft.[159]
2.156
Defence also advised that purchasing the aircraft ‘off the shelf’ would
keep costs down and noted that:
- …for the Romeo it is to
take the benefits of the US Navy; and
- …for the European
benefits it is to keep it as close as we can to the most common one, which is
the French Navy variant in this case, and they are in the process of accepting
their first aircraft,…which is only fitted for search and rescue. It does not
have the weapons systems or a lot of the mission systems in it at this stage.
That is not due to be delivered until sometime late in 2011.[160]
2.157
Defence advised that it had engaged a contractor to examine the cost
differences between the two aircraft and ‘to look at alternative, innovative
ways of approaching it.’[161]
Army
Light Protected Vehicle
Background
2.158
On 29 October 2008, the Government announced that it had given first
pass approval to replace the ADF’s Land Rovers with a fleet of Light Protected
Mobility Vehicles (PMV-L), project LAND 121 Phase 4.[162]
2.159
At that time, the Government also announced its intention to
‘participate in the technology demonstration phase of the US Joint Light
Tactical Vehicle (JLTV) Program, which is expected to replace over 60,000
vehicles in the US Army and Marine Corps from 2012 onwards.[163]
2.160
On 12 June 2009 the Government released a request for proposal seeking
Australian manufactured and supported PMV-L. The Government also announced that
the request for proposal would run concurrently with Australia’s participation
in the US JLTV Program.[164]
2.161
While no decision has been made, the Government is considering three
different options to acquire a PMV-L:
- simply purchase a
Military Off The Shelf vehicle;
- develop and
manufacture a vehicle in Australia; or
- continue in the
developmental US Joint Light Tactical Vehicle program.[165]
2.162
The project is currently at the pre-first pass approval stage.
Current Status
2.163
The committee examined Australia’s involvement in the US JLTV Program
and enquired about the cost of participating in the program, the estimated cost
of the vehicles, and whether Australian industry was consulted prior to
deciding to participate in the program.
2.164
Defence advised that Australia spent US$30.6 million to participate in
the current phase of the program and that while Australia is not committed to
continue in the program, it could cost an additional US$100 million to be
involved in the next phase. Defence stated:
In the middle of next year, the Americans will be thinking
about the next phase. If they were to proceed and if we were to become
involved, it could be up to $100 million. But it really does depend—and this is
the subject of ongoing negotiations between Australia and the US—on what we
will know at the end of the phase that we are in now, on what the objectives
are in their phase and on what information we get from it for what levels of
investment.[166]
2.165
Defence also noted that, to date, it had not expended any money in
Australia on developing an Australian JLTV but that it would be making
suggestions how it could be manufactured and supported:
In the advice that we will be presenting to government, the
results of the RFP, we will be making suggestions such as: what could be done
if it were manufactured and supported in Australia—what you would call the
Australian JLTV; and what options could we explore in Australia so that
decisions concerning the JLTV program are made with appropriate information
about what is possible in Australia? There are basically two streams of
development.[167]
2.166
Defence was also of the opinion that there was a potential for the
engineering, manufacturing and development (EMD) phase of the US JLTV program
to align more closely with the Australian phase noting that:
I think that might also give you a level of assurance,
perhaps, or comfort that, if we just follow the JLTV program, around the middle
of the year [the US] will make a decision about progressing to the EMD phase
and…they will re-tender. A whole bunch of new companies may come in to pick up
the requirements that we get from this test development phase and build brand
new prototypes that might look nothing like the ones that we did the original
work on. And around middle to late 2013-ish is when they expect to get to the
end of the EMD phase to make a choice on the vehicle to buy. So if you take
that as one stream, quite different but parallel, if the government proceeds
with the MSA [manufactured and supported in Australia] version, there is a peg
in the sand down here around 2013-14 where America will have got to the end of
its development and will go: ‘This is our vehicle.’ So, if you like, that is a
choice down here and that is a time line for the manufacture and support in
Australia to also achieve some level of development so that the government of
the day could make a comparison between what Australia is able to produce and
what the American line produces. In around 2013-14 they will have a very good
idea alternative to look at, provided the MSA can develop a vehicle that meets
the requirements clearly.[168]
2.167
When commenting on the unit cost for a JLTV, Defence indicated that it
was unable to provide any costings given the project was in the technical
development phase, and that:
It is a long time before we know the precise requirements and
we know who is going to build it, what it will be built of, the level of
integration and the sorts of things that will be on the vehicle.[169]
2.168
Defence advised that the total cost of the program, as stated in the
Defence Capability Plan, would be greater than $1.5 billion.[170]
2.169
On the question of whether Defence had consulted with Australian
industry prior to agreeing to participate in the JLTV program, Defence advised
that industry was consulted ‘through the Land Environment Working Group and
direct approaches before first pass on the JLTV program to see if anyone had
any plans.’[171]
2.170
The committee asked how Defence initially undertook an assessment of the
PMV-L, and in particular asked why the Thales Australia vehicle, the Copperhead
Bushmaster, was not shortlisted.
2.171
Defence advised that the project had gone to tender twice and noted that
the Thales Australia vehicle was not ready prior to completion of the first
tender process. Defence stated:
We selected a preferred tenderer for that project, from
memory back towards the end of 2007. That vehicle, which is an American
vehicle, did not pass all its tests on the proving range, so we went out to
re-tender. The first time round the Bushmaster Copperhead, or that variant
produced, the Thales, was not ready. By the time we had gone through the
re-tender, Thales had done a lot more development work and it was ready and it
was included.[172]
2.172
The committee noted reports that the US JLTV program was experiencing
difficulties and asked Defence for an update.
2.173
Defence advised that the JLTV program is currently in the technical
development phase and that Australia should receive its test vehicles by
August-September 2010 with testing to complete around May 2011. Defence added
that ‘there was no indication that that program was going to be delayed or is
in trouble.’[173]
2.174
When questioned whether there would be an Australian variant of the JLTV
that meet Australia’s requirements, Defence advised that it was still making an
assessment of its requirements as part of the technical development phase,
stating:
We are participating in the technical development phase to
test what is physically achievable balanced between protection, cost, the laws
of physics and transportability and then we will have a set of requirements
that we will know, with the Americans, is achievable.[174]
2.175
Defence noted that the request for proposal process would be completed within
a couple of months after which it would be ‘providing government with advice on
the outcomes of those assessments and recommending a way forward.’[175]
Defence added that advice would be given to the Minister and subsequently
referred to the National Security Committee of Cabinet which would lead to a
request for tender process.[176]
Armed Reconnaissance Helicopter
Background
2.176
In August 2001 the Government announced that it would acquire 22 ‘Tiger’
ARH under Project AIR 87.[177]
2.177
The first four ARH were manufactured and assembled in France by the European
Aeronautic Defence and Space (EADS) Company and the remaining ARH were
manufactured in France and assembled in Brisbane by a subsidiary of EADS,
Australian Aerospace.[178]
2.178
In July 2007 Defence stopped payment to Australian Aerospace under the
ARH acquisition contract due to extended delays in ‘achieving the IOC[179]
critical contractual milestone.’[180]
2.179
In its 2008-09 Major Projects Report, the ANAO stated that
several factors contributed to the delay ‘which in turn resulted in
insufficient numbers of aircraft, training devices and logistics support in
service to enable the required training outcomes.’[181]
2.180
In April 2008, Defence and Australian Aerospace agreed to:
…a revised Acquisition Contract Price and Delivery Schedule, a
revised Through Life Support Contract pricing structure that transitioned it to
a Performance Based Contract, and established networks for work done by
third-party support subcontractors.[182]
2.181
On 6 August 2008 Defence received the first three ARH[183]
and on 1 October 2009 the ARH reached the initial operational test and
evaluation readiness milestone which ‘marks the point where the project
transitions focus from individual flying, maintenance and support
qualifications to collective training and development of Army Aviation war
fighting skills.’[184]
2.182
At 9 July 2009 Defence had received 16 ARH. All 22 aircraft are to be
delivered by 30 September 2010 ‘with final supplies acceptance due 30 June
2011.’[185]
Current Status
2.183
Defence advised that the ARH project was about 80 per cent complete
having accepted 17 aircraft which have achieved weapons certification, noting:
The plan is to have all aircraft accepted either at the end
of this year or early next year. Some will undergo a retrofit program, but,
importantly, we achieved the end of September milestone…where they were ready
for operational test and evaluation, which means the aircraft were then
migrated into the operational unit to allow them to conduct the collective
training—the multiple aircraft type training—and develop their war fighting
skills.[186]
2.184
The committee asked when the ARH would have full operational capability.
2.185
Defence responded that the DMO is recommending that the ARH have a
‘deployable troop capability for a benign environment’ and once the Chief of
Army has made a decision the ‘objective is to then build up the operational
capability, the war fighting status, gradually as we continue to develop
aircraft and these systems.'[187]
2.186
Defence also advised that before the ARH can be deployed in higher
threat environments some additional work needs to be completed, which includes
work on the helmet-mounted sight and display, training for the trainers and
crews, and improved logistics support for the aircraft.[188]
2.187
Defence noted that it was working closely with the French who have
deployed three aircraft in Afghanistan since August 2009. Defence added that the
weapons system and reconnaissance sensors on the French aircraft were reported
to be performing well noting that:
…the reliability of some elements of it has been much better
than were forecast. Some others elements still need some work. It is still a
new aircraft, relatively, in testing but the French are exceptionally pleased
and I think, overall, we are all pleased with the performance of Tiger on
operations in Afghanistan.[189]
2.188
Defence indicated that Australia is about 18 months behind the French in
operational capability.[190]
Self-propelled guns
2.189
The Artillery Replacement program, LAND 17, will provide the Army with
new protected self-propelled guns,[191] new lightweight towed
guns, and a digitised, networked Battle Management System.[192]
2.190
On 26 September 2007 the Government released a ‘Request for Tender for
the acquisition and support of protected self-propelled howitzers.’[193]
2.191
At the public hearing, the committee explored the acquisition of self‑propelled
guns and asked Defence to provide an update.
2.192
Defence advised that it was currently examining two tender responses and
that it would be in a position to advise ‘Government about which self‑propelled
gun might be the recommended gun.’[194]
2.193
Defence noted that the project had been deferred for around 15 months until
the offer-definition period is completed, stating:
At the moment, the self-propelled howitzers are planned for
consideration for source selection by government in late 2010. It was going to
be considered for second-pass approval back in July 2009, so it is probably
about 15 months.[195]
2.194
Defence added:
The original tender process
did not result in a conclusive assessment of either of the offers, so we went
into this offer definition period before going to government to make a
recommendation for the preferred tenderer. That has involved a number of tests
and trials.[196]
2.195
The committee is mindful of the dramatic improvement in capability
self propelled artillery provides over traditional towed weapons. Whilst this
new platform includes some sophisticated systems, it is far from a complex
acquisition in the context of many other ADF acquisitions. The 15 month
delay is therefore of concern.
2.196
The committee also notes that not all potential suppliers engaged in the
tender process.
Committee conclusions
2.197
The committee is aware of the significant challenges in managing very
complex, sensitive and technical projects. However, the committee agrees with the
ANAO’s assessment that keeping major projects on schedule remains a major
challenge for the DMO.[197]
2.198
Two projects in particular have experienced extensive schedule
slippages: the High Frequency Modernisation Project and Project Wedgetail.
2.199
While the committee is encouraged to hear the ANAO’s assessment that
the core system of the HF Modernisation Project is reliable and meeting
Defence’s requirements, it notes that this project is over 6 years behind
schedule[198] and will not
meet all of the projects technical specifications. The schedule slippage is so
extensive that Defence has needed to reassess which platforms currently require
upgrades to HF.
2.200
Project Wedgetail is at least four years behind schedule, with FOC currently
planned to be achieved by December 2012,[199] and it will not deliver
the intended capability at this time.[200]
2.201
A 2009 review by The Helmsman Institute, commissioned by the DMO,
comparing project complexity between Defence and other sectors, found that the
more complex the project, the greater the risk in delivering within budget, on schedule
and to the required capability.[201]
2.202
In its 2008-09 Major Projects Report, the ANAO was also of the
view that ‘the more developmental in nature a project, the more susceptible a project
is to schedule delays compared to MOTS solutions.’[202]
2.203
The extensive delays experienced in both the above projects has been a
concern to the committee and supports the views previously expressed by the
ANAO and The Helmsman Institute.
2.204
The Joint Strike Fighter, another major developmental project, is
currently experiencing delays due to a number of complex developmental issues.
2.205
In the previous report on the Defence Annual Report 2007‑08,
the committee noted the following about the JSF project:
This is a highly complex acquisition with inherent risks that
have been highlighted by the GAO [US Government Accounting Office]. When such
issues are raised within the United States Government there are concurrent
reassurances from the manufacturer and those involved in the project. From an
Australian perspective, such inconsistencies are, at times, difficult to
reconcile.[203]
2.206
The committee’s initial concerns with scheduling have proven to be
valid in light of the recent reports that the JSF program is now facing some
significant issues. It is hoped that other concerns raised by the committee and
others in recent years about cost and performance prove to be less accurate.
2.207
The committee is aware that Australia has cost and schedule buffers
built into the project but is all too aware that such buffers on large and
complex acquisitions, such as the JSF, can slip considerably.
2.208
Defence’s current aircraft fleet is ageing rapidly making it all the
more critical that Defence manages the inherent risks of this project to ensure
that Australia is not left without a vital capability.
2.209
It is important that Defence acquire the needed capability in the
shortest time practicable and at an appropriate cost.
2.210
The unique nature of Australia’s security environment sometimes requires
tailored or special design assets and solutions. That said, many Australian
defence needs can be properly met with appropriate Military-Off-The-Shelf (MOT)
acquisitions. The adoption of high-risk first-of-type acquisitions should only
be entered into where it is clear that such an outlay, in terms of time and
money, can be clearly justified by Australia’s defence requirements. In the
absence of a clear strategic case for such purchases, MOTS should be the
default option.
2.211
The committee will pay close attention to Defence’s ability to
complete these projects and ensure that they all meet final operational
capability.
2.212
More generally, the committee will still require Defence to
demonstrate that the post-Kinnaird reforms (Defence Procurement Review 2003) are
sufficient, have been well-implemented, deliver projects on time and on budget,
and with required levels of capability.