Chapter 2 Major Projects Report 2011–12
Introduction
2.1
This chapter provides an overview of the 2011–12 Major Projects Report
(MPR) and a summary of the Australian National Audit Office (ANAO)’s findings
in regard to cost performance; schedule performance; capability performance;
and governance and business processes.
2.2
The objective of the MPR is to provide:
- comprehensive
information on the status of selected Major Projects, as reflected in Project
Data Summary Sheets (PDSSs) prepared by the Defence Materiel Organisation
(DMO);
- the Auditor-General’s formal
review conclusion on the ANAO’s review of the preparation of the PDSSs by the
DMO;
- ANAO analysis on the
three key elements of the PDSSs—cost, schedule and capability—and in
particular, longitudinal analysis across projects over time; and
- further insights and
context by the DMO on issues highlighted during the year (not included within
the scope of the review by the ANAO).[1]
2.3
The MPR consists of three parts:
- Part 1: ANAO
overview;
- Part 2: Commentary
and overall analysis by the DMO; and
- Part 3:
Auditor-General’s independent review report; statement by the Chief Executive
Officer DMO; and the PDSSs.
2.4
In appendices, the report also includes a copy of the endorsed guidance
for the development of PDSSs (part of the MPR Guidelines); a copy of the DMO’s
response to the Committee’s recommendations on its review of the 2010–11
report; and the ‘Lessons Learned’ for a project that was reported on for the
last time in 2010–11 MPR (AIR 5376 Phase 3.2 – F/A-18 Hornet Upgrade Structural
Refurbishment).
2.5
The PDSSs prepared by the DMO have been refined over the years since the
first MPR was developed in 2007–08. These changes have been made by the DMO and
ANAO with the support of the Joint Committee of Public Accounts and Audit (JCPAA).
2.6
The main changes to the PDSSs for the 2011–12 MPR were the addition of a
project financial assurance statement in regard to cost performance; the
removal of base date dollars from project budget and expenditure history,
consistent with the move to reporting financial information in an ‘out-turned’
format; and the addition of a graph depicting project cost and schedule status.[2]
2.7
In their current form, the PDSSs provide data in the following sections:
- Section 1 – project
summary;
- Section 2 – financial
performance;
- Section 3 – schedule
performance;
- Section 4 – project
cost and schedule status;
- Section 5 – materiel
capability performance;
- Section 6 – major
risks and issues;
- Section 7 – project
maturity;
- Section 8 – lessons
learned; and
- Section 9 – project line
management.[3]
Major Projects included in 2011–12
2.8
The 2011–12 MPR reports on 29 major projects, an increase of one project
on the 2010–11 MPR. The total approved budget for the 29 projects, as at 30
June 2012, was $47.3 billion. The projects and their approved budgets appear in
Table 2.1 below.
2.9
The inclusion of projects in the MPR was based on the following
criteria:
- projects only
admitted one year after Year of Decision;
- a total approved
project budget of more than $150 million;
- a project should have
at least three years of asset delivery remaining;
- a project must have
at least $50 million or 10 per cent (whichever is greater) of its budget
remaining over the next two years; and
- a maximum of eight
new projects in any one year.[4]
Table 2.1 2011–12 MPR projects and approved budgets at 30
June 2012
Project
|
DMO Abbreviation
|
Budget $m
|
Air Warfare Destroyer Build
(SEA 4000 Ph 3)
|
AWD Ships
|
7 853.1
|
Airborne Early Warning and
Control Aircraft (AIR 5077 Ph 3)
|
Wedgetail
|
3 829.5
|
Multi-Role Helicopter (AIR
9000 Ph 2/4/6)
|
MRH90 Helicopters
|
3 628.4
|
Bridging Air Combat
Capability (AIR 5349 Ph 1/2)
|
Super Hornet
|
3 538.5
|
Field Vehicles and Trailers
(LAND 121 Ph 3)
|
Overlander Vehicles
|
3 171.2
|
Amphibious Ships (LHD) (JP
2048 Ph 4A/4B)
|
LHD Ships
|
3 052.1
|
Future Naval Aviation Combat
System (AIR 9000 Ph 8)
|
MH-60R Seahawk
|
2 910.2
|
New Air Combat Capability
(AIR 6000 Ph 2A/2B)
|
Joint Strike Fighter
|
2 334.0
|
Armed Reconnaissance
Helicopter (AIR 87 Ph 2)
|
ARH Tiger Helicopters
|
2 028.9
|
F/A-18 Hornet Upgrade (AIR
5376 Ph 2)
|
Hornet Upgrade
|
1 875.5
|
C-17 Globemaster III Heavy
Airlifter (AIR 8000 Ph 3)
|
C-17 Heavy Airlift
|
1 844.4
|
Air to Air Refuelling
Capability (AIR 5402)
|
Air to Air Refuel
|
1 795.7
|
Guided Missile Frigate
Upgrade Implementation (SEA 1390 Ph 2.1)
|
FFG Upgrade
|
1 449.6
|
Bushmaster Protected
Mobility Vehicle (LAND 116 Ph 3)
|
Bushmaster Vehicles
|
1 032.1
|
Next Generation SATCOM
Capability (JP 2008 Ph 4)
|
Next Gen Satellite
|
861.1
|
ANZAC Anti-Ship Missile
Defence (SEA 1448 Ph 2B)
|
ANZAC ASMD 2B
|
675.8
|
High Frequency Modernisation
(JP 2043 Ph 3A)
|
HF Modernisation
|
580.1
|
Additional Medium Lift
Helicopters (AIR 9000 Ph 5C)
|
Additional Chinook
|
550.9
|
Armidale Class Patrol Boat
(SEA 1444 Ph 1)
|
Armidales
|
537.2
|
Collins Replacement Combat
System (SEA 1439 Ph 4A)
|
Collins RCS
|
449.9
|
Indian Ocean Region UHF
SATCOM (JP 2008 Ph 5A)
|
UHF SATCOM
|
432.5
|
Replacement Heavyweight
Torpedo (SEA 1429 Ph 2)
|
Hw Torpedo
|
425.1
|
Collins Class Submarine
Reliability & Sustainability (SEA 1439 Ph 3)
|
Collins R&S
|
411.4
|
SM-1 Missile Replacement
(SEA 1390 Ph 4B)
|
SM-2 Missile
|
398.8
|
ANZAC Anti-Ship Missile
Defence (SEA 1448 Ph 2A)
|
ANZAC ASMD 2A
|
386.0
|
Follow On Stand Off Weapon
(AIR 5418 Ph 1)
|
Stand Off Weapon
|
340.8
|
Artillery Replacement (LAND
17 Ph 1A)
|
155mm Howitzer
|
320.6
|
Battlefield Command Support
(LAND 75 Ph 3.4)
|
Battle Comm. Sys.
|
305.8
|
Counter – Rocket, Artillery
and Mortar (LAND 19 Ph 7A)
|
C-RAM
|
251.4
|
TOTAL
|
|
47 270.6
|
Source Australian
National Audit Office, 2011–12 Major Projects Report, p. 15.
2.10
Twenty-seven of the projects were previously reported in the 2010-11 MPR
(i.e. ‘repeat’ projects). The following two projects have been added:
- AIR 9000 Phase 8 –
Future Naval Combat System (MH-60R Seahawk); and
- LAND 19 Phase 7A –
Counter – Rocket, Artillery and Mortar (C-RAM).
2.11
The 2011–12 MPR Guidelines stipulated that projects which have achieved
both Final Materiel Release (FMR) and Final Operational Capability (FOC) would
be expected to be removed from future MPRs. One project was ‘exited’ from the
2011–12 after meeting this criteria:
- AIR 5376 Phase 3.2 –
F/A-18 Hornet Upgrade Structural Refurbishment (Hornet Refurb).
Australian National Audit Office review
2.12
Although the ANAO conducts an assurance audit of the MPR, it cautions
that the level of assurance is more limited than for an individual project performance
audit. The ANAO does not provide any assurance in regards to PDSS data on the
achievement of future dates or events, project financial assurance statements
or major risks and issues. These items were excluded from the scope of the
ANAO’s review.[5]
2.13
During its review of the 2010–11 MPR, the Committee identified the MPR
as a ‘Priority Assurance Review’ under section 19A(5) of the Auditor-General
Act 1997.[6] This designation has
allowed the ANAO full access to the information gathering powers available under
the Act, without necessitating the agreement of the DMO to perform its review.[7]
2.14
After reviewing the PDSS data, the ANAO’s conclusion was that:
... nothing has come to the attention of the ANAO that causes
us to believe that the information in the PDSSs, within the scope of our
review, has not been prepared, in all material respects, in accordance with the
2011–12 MPR Guidelines.[8]
2.15
The ANAO provided more detailed analysis on the following aspects of the
MPR:
- Project cost,
schedule and capability performance
- Governance and
business processes.
Cost performance
2.16
In relation to cost, the ANAO concluded that within the review period,
all projects continued to operate within their approved budget.[9]
2.17
At 30 June 2012, the total approved budgeted costs for the 29 projects
was $47.3 billion, a net increase of $5.9 billion compared to their Second Pass
Approval approved budgeted costs ($41.4 billion). The $5.9 billion comprised:
- price indexation
increases of $7.5 billion;
- real variation
increases of $2.7 billion; and
- foreign exchange rate
decreases of $4.3 billion.[10]
2.18
While variations due to price indexation and exchange rates were
‘outside the direct control of project management’, real variations to budgeted
costs:
… primarily reflect changes in the scope of projects,
transfers between projects for approved equipment/capability, and budgetary
adjustments such as administrative savings decisions.[11]
2.19
During the 2011–12 financial year, the approved budgeted cost of the 29
Major Projects decreased by $1.1 billion (or 2.4 per cent) due to foreign
exchange decreases of $894.6 million and real decreases of $267.3 million.[12]
Schedule performance
2.20
According to the ANAO’s review, maintaining major projects on schedule
remained the ‘most significant challenge for the DMO and its industry
contractors’.[13]
2.21
Across the 29 major projects, 18 projects had experienced schedule
slippage. Total schedule slippage to date was 859 months when compared to the
initial predictions when the projects were first approved by government. This
represented a 32 per cent increase on the expected schedule since the main investment
decision was made (compared to 31 per cent in the 2010–11 MPR).[14]
2.22
In-year slippage for 2011–12 was a total of 99 months for the 27
projects that were also included in the 2010–11 MPR, representing a four per
cent increase in the scheduled timeframe.[15]
2.23
According to the ANAO, ‘the reasons for schedule slippage vary but
primarily reflect the underestimation of both the scope and complexity of work,
particularly for Australianised Military Off-the-Shelf (AMOTS) and
Developmental projects’.[16]
2.24
The ANAO noted that 87 per cent of the total schedule slippage across
the Major Projects covered in the 2011–12 MPR was made up of projects approved
prior to the DMO’s demerger from the Department of Defence in July
2005—projects which tended to be more developmental in nature.[17]
Capability performance
2.25
The ANAO noted that ‘… the DMO expects to deliver almost all
capabilities associated with the Major Projects in this report’.
2.26
The capability of a project concerns its capacity or ability to achieve
a particular operational effect.[18] Due to national security
considerations, only the overall status from each project’s capability
assessment is disclosed in the MPR.[19]
2.27
Expected capability delivery had decreased from 94 per cent for projects
in the 2010–11 MPR to 91 per cent in 2011–12. Although outside the scope of its
formal review conclusion, the ANAO indicated that the DMO’s assessment of
capability to be delivered was ‘in some cases overly optimistic’.[20]
2.28
The ANAO added that
… the DMO’s key capability measures should be interpreted with
some caution due to their lack of rigour as a data system and the high level of
uncertainty in forecasting outcomes.[21]
and that there was
… not a clear underlying consistency in the identification
and articulation of the [Materiel Release Milestones] and Completion Criteria’.[22]
Governance and business processes
2.29
The ANAO reviewed the following key governance aspects relating to major
projects:
- Gate Reviews, in
which DMO-appointed boards periodically assess projects at key milestones to
provide assurance that the project is ready to progress to the next stage. Gate
Reviews ‘have emerged as the DMO’s most prominent internal project assurance
activity’.[23]
- The management of
Projects of Concern, in which projects facing significant cost, schedule or
capability delivery challenges are listed in order to focus the attention of
senior management on remediating issues. Six MPR projects were Projects of
Concern during 2011–12.[24]
- The Early Indicators
and Warnings system, which is used to identify problems with projects early in
order for appropriate action to take place to remediate them. In 2011–12, four
MPR projects had Gate Reviews as a result of triggering Early Indicators and
Warnings threshold criteria.[25]
- The use of Joint
Project Directives (JPDs) for projects approved by government after 1 March
2010. JPDs are designed to provide a single authoritative source of project
detail, and are the base document from which all Materiel Acquisition
Agreements (MAAs) will be designed.[26]
2.30
Finally, the ANAO’s overview also made the following observations
regarding the application of business systems and processes:
- The large range of
corporate and project management applications being used by project offices
continues to result in inconsistency between information produced by risk
management, financial management and document management systems. This will be
an area of continuing focus for the ANAO’s next review of the MPR.[27]
- The change in
supplementation policy associated with out-turned budgeting has ‘emerged as a
major risk or issue’ for some MPR projects, for which contingency funds may
need to be drawn upon:
- The emergence of any indexation risk has, to some extent,
changed the nature and use of the contingency budget from dealing with project
risk management to broader price management …[28]