|
Parliamentary Joint Committee on National Broadband Network
Navigation: Previous Page | Contents | Next Page
Chapter 1 Introduction
1.1
The Telecommunications Legislation Amendment (Fibre Deployment) Bill
2011 (the Bill) was preceded by a similar bill which was introduced into the
Senate in March 2010, but lapsed on the proroguing of the 42nd
Parliament. The Fibre Deployment Bill 2010 shared a similar purpose to the Bill
under inquiry, that is, to ‘ensure fibre-ready and fibre infrastructure
installation in new developments.’[1] This Bill differs from its
predecessor in that the Fibre Deployment Bill 2010 ‘was more dependent on
subordinate legislation for activation of the key provisions in the Bill’,
while the current Bill includes those key provisions.[2]
1.2
This Bill intends to facilitate the fibre rollout of the National
Broadband Network (NBN) by ensuring that fibre-ready passive infrastructure is
installed in new developments within the fibre footprint of the NBN. This can
be undertaken either by a fibre provider (chosen by the developer) or NBN Co as
the ‘fibre infrastructure provider of last resort in new developments’[3]
in the long term, if required.[4]
Background
1.3
In April 2009, the Government established NBN Co Limited (NBN Co)[5]
to design, build and operate the NBN. The NBN will offer a high-speed national
broadband service in the form of a wholesale only, open-access network. The NBN
is planned to be rolled-out across Australia in accordance with the
Government’s NBN policy, NBN Co’s Corporate Plan and the Statement of
Expectations[6] issued by the Stakeholder
Ministers to NBN Co.[7]
1.4
NBN Co’s Corporate Plan states that its objectives for the NBN are to:
-
establish a network
design which is an open access, wholesale only, national network
- rollout fibre to 93
per cent of premises (including Greenfields developments) to provide for download
internet speeds of 100 [Megabits per second] Mbps,[8]
and provide fixed wireless to four per cent of premises and satellite to
three per cent of premises at a speed of at least 12 Mbps
- offer uniform
national wholesale pricing over the network, from a point of interconnect to a
premises on a non discriminatory basis
- ‘the expected rate of
return should, at a minimum, be in excess of current public debt rates.’[9]
1.5
In June 2010, following stakeholder consultation,[10]
the Government announced that NBN Co would be the fibre infrastructure provider
of last resort in new developments. This would require NBN Co to provide at no
cost, the fibre in new developments (that are within the NBN long term fibre
footprint) where a developer[11] did not opt to use an
alternative fibre infrastructure provider.[12]
1.6
In December 2010, the Government announced its implementation and
transitional arrangements for this policy. Transitional arrangements under the
implementation strategy provided that Telstra will service infill developments
of less than 100 premises pending NBN Co’s fibre rollout.[13]
1.7
To enable NBN Co to be the fibre provider of last resort in all new
developments within the fibre footprint, it would negotiate with developers for
the transfer of ownership of infrastructure through contractual arrangements. NBN
Co would install fibre at no cost.[14]
1.8
In the event that NBN Co would be unable to service developments
immediately, developers could request other telecommunications providers to
provide infrastructure in their estate.[15]
1.9
It is estimated that 150 000 new dwellings and approximately 60 000
other types of premises (commercial, industrial and government) are constructed
annually. NBN Co has calculated that 94 per cent of these new premises (or
around 197 000) will be within the fibre footprint.[16]
1.10
The cost of installing fibre-ready infrastructure has been estimated at
about $800 per lot or building unit. The cost of retrofit of fibre where no passive
infrastructure has been supplied is estimated to be approximately $1300 a lot
or unit.[17]
1.11
The Government’s policy carries the assumption that most developers will
install fibre-ready infrastructure in new developments, with the risk that a
small percentage of developers will not. If this number were up to five per cent,
the Government estimates this would cost $12.8 million per annum[18]
to retrofit.[19]
1.12
To ensure that developers (who are constitutional corporations) install
fibre-ready infrastructure in new developments, there are ‘civil penalties’[20]
attached to the sale or lease of land where passive fibre-ready infrastructure
is not installed.[21]
1.13
The legislation will be reviewed in five years to assess if it is still
required. Review will involve consultation with carriers including: NBN Co, developers,
consumer groups, and State and Territory planning bodies.[22]
Overview and purpose of the Bill
1.14
The legislative intent of the
Bill is to amend the Telecommunications Act 1997 (Cwlth) to ensure ‘that
developers have fibre-ready passive infrastructure installed for the future
provision of fibre, potentially for use by any fibre provider.’[23]
1.15
Other key provisions of the Bill will:
-
require developers
that are constitutional corporations to install fibre-ready passive
infrastructure in developments in the long term fibre footprint of the NBN;
- provide Ministerial
authority to determine specifications for fibre-ready passive infrastructure,
if required;
- ‘provide for NBN Co
to issue a statement that premises are not in the NBN’s long term fibre
footprint;
- allows carriers to
access passive infrastructure that is owned by non-carriers, and provides for
the Australian Competition and Consumer Commission to be the default
arbitrator;
- enable the Minister
to specify developments in which fixed lines must be optical fibre and
determine specifications for such lines, if necessary;
- provide for statutory
and Ministerial exemptions from the requirements to install fibre-ready
facilities or optical fibre lines; and
- enable the Australian
Communications Media Authority to develop technical standards for customer
equipment and cabling for connection with the NBN and other superfast networks,
on its own initiative or if directed by the Minister.’[24]
Financial impact of the Bill
1.16
The financial impact of the Bill will be met through funding accorded to
NBN implementation and is expected to be ‘small’.[25]
Policy underpinning the Bill
1.17
The policy on Fibre in New Developments underpins the provisions
contained in the Bill. This policy was announced by the Minister for Broadband,
Communications and the Digital Economy, Senator the Hon Stephen Conroy (the
Minister) on 20 June 2010, with further enhancements announced to the policy on
9 December 2010, reiterated on 15 June 2011 and further updated on 22 June 2011.[26]
This policy also reflects the Government’s Statement of Expectations.[27]
1.18
Further to an earlier announcement on 20 June 2011, on 9 December 2010, the
Minister announced ‘very significant changes to the way telecommunications
infrastructure and services [could be] provided in new developments.’[28]
1.19
New developments encompassed residential, commercial, industrial,
government and other types of developments and constructions ‘regardless of the
number of lots, premises or units involved, whether they are broadacre greenfield
or brownfield infill.’[29]
1.20
The Ministerial statement on Fibre in New Developments[30]
reiterated that from 1 January 2011:
- NBN Co Limited would
be the wholesale provider of last resort in new developments within or adjacent
to its long term fibre footprint and meet the associated cost of this
obligation.
- Developers and on
their properties, property owners would be responsible for trenching and
ducting.
- Telstra would be the
retail provider of last resort. Telstra would not have infrastructure
responsibilities.
- Developers could use
any fibre provider of choice on the proviso they meet NBN specifications and
open access requirements.[31]
1.21
NBN Co would be responsible for fibre installation for all premises in
the fibre footprint which are at the development stage.[32]
These include:
- ‘all broadacre
developments;
- all infill
developments where it has fibre that is ready for service and capable of
connection; and
- new approved infill
developments of 100 or more premises.’[33]
1.22
The earliest practical date of effect of NBN Co’s responsibilities occurred
on 1 April 2011.[34]
1.23
The policy also provides detail about the role of NBN Co and Telstra in
new developments, pre-existing service applications, expectations on
developers, and the role of competing fibre providers. The main elements of
these are:
- NBN Co can choose the
operational arrangements under which it services new developments, ‘including
sub-contracting and build-operate-transfer [BOT] arrangements’ enabled through
its own tender process arrangements.[35] NBN Co will ‘establish a
panel of appropriately qualified and experienced providers who can bid to
install fibre on its behalf.’[36]
- Telstra is
responsible for the delivery of infrastructure and services for infill developments
of less than 100 premises, pending NBN rollout. In this circumstance, Telstra
will generally provide copper infrastructure or depending on the timing of NBN
rollout may provide a ‘high quality wireless service as an interim solution.’
Telstra is also retail provider of last resort for standard telephone services.[37]
- The policy sets out
four scenarios and handling arrangements, which do not override existing
developers’ contractual arrangements, but take into account the developers requests
for infrastructure for developments that will not be completed before 1 January
2011.[38] These are:
- For lots
where Telstra has installed passive fibre-ready infrastructure, but has not
provided a fixed line, NBN Co will have access to this infrastructure on
commercial terms with NBN Co subcontracting to deliver fibre to the premises.[39]
- In
developments that are design-ready, but do not yet have passive fibre
infrastructure installed and require services from 1 January to 30 June 2011,
NBN Co will subcontract to deliver fibre through a BOT arrangement. Subject to
any existing legal arrangements between a provider and the developer, for
efficiency, Telstra may, in arrangements with NBN Co, build the infrastructure.[40]
- In
developments that are design-ready but do not yet have passive fibre
infrastructure installed and require services after 1 July 2011, developers can
redirect requests to NBN Co for fibre service delivery as determined by the NBN
Co. This is subject to any existing legal arrangements between a provider and
the developer. For efficiency, Telstra may, in arrangements with NBN Co, build
the infrastructure.[41]
- For those
developments ‘land-banked’ (approved for development some time ago and have not
proceeded to completion), developers will be required to re-lodge their
requests with NBN Co. This is subject to any existing legal arrangements
between a provider and the developer. For efficiency, Telstra may, in
arrangement with Telstra, build the infrastructure.[42]
- From 1 January 2011,
for all new developments, developers are expected to ensure the installation of
fibre-ready passive infrastructure in line with NBN Co specifications.
Developers will meet the cost of this infrastructure. Where a developer does
not provide this infrastructure, NBN Co is not required to provide services to
these developments.[43]
- NBN Co will provide
its specifications for use to developers that opt to use NBN Co. NBN Co
infrastructure specifications will also be provided to the Communications
Alliance[44] with the aim of
endorsement.[45]
- NBN Co will require
through contract the transfer of ownership of infrastructure as a condition of
serving a development.[46]
- Developers can
‘source fibre from competing fibre providers’ and ‘providers can compete to
provide infrastructure in new developments.’ They could do this ‘by offering
more tailored solutions to developers or more expeditious delivery.’[47]
- ‘Where the installed
infrastructure meets NBN Co specifications, NBN Co may seek to acquire the
infrastructure, but this is a commercial decision for NBN Co.’[48]
- To ensure all
consumers have access to the same service outcomes as serviced by NBN Co,
providers are legally required to build to NBN specifications to offer a Layer 2
service on an open access basis. ‘Providers who fail to do this will otherwise
risk being overbuilt when NBN Co rolls out the network in their area.’[49]
Scope of the Inquiry
1.24
The aim of this inquiry was to examine the legislative and practical
consequences of the Bill, rather than the underlying policy intent of the
proposed legislation.
1.25
While the majority of contributors to the inquiry agreed with the
general premise of the Bill, a number of commercial fibre providers and
industry groups raised concerns about the Bill’s potential to:
- stifle competition
in the Greenfield fibre provider market in the medium to long term;
- potentially exclude
commercial fibre providers from the market place if developers preferred to
wait for NBN Co to lay fibre at no charge; and
- limit the
telecommunications services available to developments with less than 100
premises within the fibre footprint that are awaiting the NBN rollout.
1.26
These issues have been included in this report as they are relevant in
the broader context of the rollout and future operation of the NBN.
Conduct of the Inquiry
1.27
The Bill was introduced into the House of Representatives on 23 March 2011
and referred by the House of Representatives Selection Committee to the Joint
committee on the National Broadband Network for inquiry on 10 May 2011.
The committee subsequently resolved to adopt the inquiry on 12 May 2011.
1.28
The inquiry was announced and submissions invited through the issue of a
media release on 13 May 2011 and an advertisement in The Australian on
18 May 2011. Submissions to the inquiry were invited to be received by
20 May 2011.
1.29
The committee received 20 submissions and 4 exhibits to the inquiry
which are listed at Appendix A. The committee held two public hearings on 16
May 2011 in Sydney and 17 June in Canberra. Witnesses who appeared before the
committee and gave evidence to the inquiry at these public hearings are listed
at Appendix B.
Report structure
1.30
Chapter 2 outlines the key proposed amendments included in Schedule 1,
Part 1 of the Bill and outlines the issues presented in relation to these
provisions.
1.31
Chapter 3 outlines the issues raised in relation to the potential impact
of the proposed Bill on the Greenfield fibre provider market.