Chapter 10 Uranium industry regulation and impacts on Aboriginal communities

Given this natural endowment Australia should be the world leader in the production of uranium. However Australia’s current regulatory environment dissuades investment in uranium exploration, favours the entrenched position of three existing producers and leaves limited opportunity for the development of other mines by new entrants. This environment is clearly anti-competitive and has sterilised the majority of Australia’s uranium deposits. It is in the National Interest that this environment is changed.1

Key messages
Introduction
Overview of current regulatory arrangements
Commonwealth statutes regulating uranium
Commonwealth regulatory agencies
State government responsibilities
Industry’s assessment of existing regulation
Adequacy of the current regulatory regime
Industry’s criticisms of existing regulations
Regulatory reform
Criticisms of current regulation
Environmental regulation
The Supervising Scientist
Agency conflicts of interest
Aboriginal communities and uranium mining
Social impact monitoring
Consultation practices and processes
Employment and training opportunities
Aboriginal Land Rights Act
Conclusions

 

Key messages —

 
 

Introduction

10.1

This chapter, which is divided into four sections, examines concerns about, and potential solutions to, perceived shortcomings of the current regulatory regime.

10.2

The chapter commences with a description of the current regulatory environment, focussing on the Australian Government’s involvement. It examines the responsibilities of Australian Government agencies and outlines the legislative bases of their roles.

10.3

The second section details the industry’s assessment of the current regulatory regime governing uranium mining in Australia. Industry’s views of the adequacy of the current framework, along with their concerns about regulatory consistency and efficiency, are summarised.

10.4

The third section assesses criticisms of the regulatory environment, which broadly go to the perceived inadequacies of the regulations in providing sufficient protection from the alleged harmful impacts of uranium mining on the environment. This section also addresses suggestions in relation to the activities of regulatory authorities and arrangements.

10.5

Finally, this chapter examines consultation with Traditional Owners and the social impacts of uranium mining on Aboriginal communities. This section focuses particularly on: social impact monitoring; the processes for engaging and consulting with Aboriginal communities; opportunities for Aboriginal employment and training; and the Aboriginal Land Rights Act.

 

Overview of current regulatory arrangements

10.6

Mining in Australia is largely conducted under state and territory legislation. In practice however, oversight of uranium mining is a shared responsibility between the Australian Government and the governments of the Northern Territory (for the Ranger and Jabiluka mines) and South Australia (for the Olympic Dam, Beverley and Honeymoon mines).

10.7

General Commonwealth power in uranium mining derives from the external affairs power under the Constitution (section 51 (xxix)). This constitutional power is manifested in an export control regime. Uranium is only mined in Australia for export and hence Commonwealth power is especially significant.

10.8

A second foundation of the Commonwealth’s role is its special position in the Northern Territory (NT). Although self-government was granted to the Territory in 1978, the Commonwealth retained control and ownership of uranium. The Ranger mineral leases were granted under the Atomic Energy Act 1953, although the mineral leases for the subsequent Jabiluka uranium prospects were issued under NT mining legislation.

10.9

Whilst the Commonwealth retains strong powers through its export permit processes, without which uranium mines would have no commercial viability, day-to-day administration of the mines is regulated by the state and territory governments. The Commonwealth is involved in the initial environmental impact assessment process and in the granting of an export licence for the uranium. The regulation of uranium mining operations, including environmental matters, the health of workers and the safety of the mine operation, is principally the responsibility of the relevant state and territory governments.

10.10

Regulation of mines in the NT is the responsibility of the NT Department of Primary Industry, Fisheries and Mines (DPIFM), with the Commonwealth Office of the Supervising Scientist (OSS) having a monitoring, research and supervisory role over uranium mining activities in the Alligator Rivers Region (ARR).

10.11

In South Australia (SA), day-to-day management of uranium mining is the responsibility of the Department of Primary Industries and Resources (PIRSA), with regulation of radiation safety aspects of mines being the responsibility of the Environment Protection Authority.

10.12

In addition to its special position in relation to uranium in the NT and environmental assessment and approval, the Australian Government also has responsibility for:

These matters were addressed in previous chapters.

10.13

The Committee notes that a number of other reports and inquiries, at both state and federal level, have examined aspects of uranium industry regulation. These have included, among others:

The Committee also notes the work of the Uranium Industry Framework, which is currently developing a uranium industry action plan.

10.14

In view of the extensive treatment that uranium industry regulation has received to date, the Committee does not propose to present a detailed examination of regulatory issues here. The Committee’s attention has been drawn specifically to the regulation of the environmental impacts of uranium mining and this chapter largely reflects that.

10.15

The following overview of the current regulatory environment draws on the Senate Environment, Communications, Information Technology and the Arts References Committee (SECITARC) report, Regulating the Ranger, Jabiluka, Beverley and Honeymoon uranium mines, and the Uranium Information Centre’s (UIC’s) paper, Regulation of Australian Uranium Mining.7

 

Commonwealth statutes regulating uranium

10.16

The Commonwealth’s involvement in the regulation of uranium derives from eight key statutes:

In 1993–94, the Act was amended to provide for the establishment of the following consultative bodies:

ARR Advisory Committee (ARRAC), which facilitates communication between community, government and industry stakeholders on environmental issues associated with uranium mining in the ARR; and

ARR Technical Committee (ARRTC), which performs reviews of the research and monitoring programs relevant to uranium mines in the ARR.

A Mine Site Technical Committee (MSTC) was also established. The OSS was initially incorporated within the then Department of Environment, Sport and Territories. Following leaks of tailings water at the Ranger mine during the 1999–2000 wet season, the role of the Supervising Scientist Division (SSD) was expanded to focus on environmental monitoring, on the basis that the OSS should collect its own data rather than rely solely on data gathered by the mining operator, Energy Resources of Australia (ERA), and DPIFM.

10.17

In addition to the operation of these Acts, ARPANSA publishes codes of practice for uranium mining. These are detailed in the descriptions of the key Commonwealth regulatory agencies which follow.

 

Commonwealth regulatory agencies

10.18

The Australian Government’s involvement in the regulation of uranium mining and nuclear matters is conducted principally through three portfolios: Environment and Heritage; Industry, Tourism and Resources; and Foreign Affairs and Trade, notably through ASNO. In addition, the Health and Ageing portfolio, through ARPANSA, has specific roles. A summary of each authority’s involvement in uranium regulation follows.

Department of Industry, Tourism and Resources

10.19

The Department of Industry, Tourism and Resources (DITR) develops policy and administers legislation relating to Australia’s resources and energy industries.8 DITR also plays an important role in formulating the national response to climate change issues. The Resources area is responsible for providing policy and legislative advice and administrative support to the Government on the resources sector of the economy, which includes uranium.

10.20

The Uranium Industry section is located within the Resources Development Branch and Resources Division of DITR. The goal of the section is to encourage the sustainable development and growth of Australia’s uranium mining industry. It focuses on ways to encourage and manage the development and operation of Australia’s uranium industry by:

10.21

The section works closely with agencies such as ASNO, the Department of Foreign Affairs and Trade and the Australian Customs Service to ensure procedures are followed in the exportation of uranium, thorium and other controlled ores listed under Schedule 7 of the Regulations.

10.22

DITR monitors and supports industry applications for environmental approval under the EPBC Act. As noted above, the Act legislates the need for environmental approval for new projects and/or extensions of existing projects that affect matters of national environmental significance. The Act requires that relevant Commonwealth Ministers are consulted when approval is sought for proposed projects within their area of responsibility. In addition, DITR is required under the Act to report annually on Australia’s environmental performance and contribution to ecologically sustainable development.10

Department of the Environment and Heritage

10.23

DEH advises the Commonwealth Government on policies and programs for the protection and conservation of the environment, including both natural and cultural heritage. It has four key responsibilities in relation to uranium mining:

… firstly, the assessment and approval of proposals for new uranium mines or the expansion of an existing uranium mine under theEnvironment Protection and Biodiversity Conservation Act 1999, known as the EPBC Act; secondly, the Supervising Scientist’s monitoring, research and supervisory role in relation to uranium mining activities in the Alligator Rivers region of the Northern Territory; thirdly, the management of Commonwealth reserves by the Director of National Parks, including Kakadu National Park, which surrounds the Ranger and Jabiluka sites; and, fourthly, through the delivery of the Australian government’s climate change strategy, a key interest in energy issues, including nuclear fuels.11

10.24

The Department administers environmental laws, and is responsible for Australia’s participation in a number of international environmental agreements. DEH explained that the EPBC Act is ‘the most fundamental reform of Commonwealth environmental laws since the first environmental statutes were enacted in the early 1970s,’ allowing streamlined environmental assessment and approval processes.12 Importantly, the Act also ‘ensure[s] that all future uranium mines are subject to a stringent and comprehensive environmental assessment process.’13

10.25

With regard to the uranium mining industry in SA, DEH’s role as an environmental regulator is demonstrated through the approvals process and in the Department’s authority to set strict conditions governing the operating procedures of the mines. In the NT, the OSS supervises the management of the uranium mining industry and conduct research into the industry’s impact on the ARR environment.

10.26

As described in the overview of relevant legislation in the preceding section, the SSD is responsible for environmental oversight of uranium mining activities in the ARR. The primary role of the SSD is to ensure, through research, assessment and the provision of technical advice, that the environment of the ARR is protected from the effects of uranium mining to the standard required by the Australian Government. The supervisory functions are carried out by the OSS, and the research functions of the SSD are performed by ERISS.

10.27

The world heritage values of the Kakadu and concerns of the Traditional Owners were said to demand a strict regulatory regime. The need for strict regulation also reflects that uranium is a radioactive element and hence measures must have a high degree of reliability for unusually long periods of time.14

10.28

DEH argued that this supervisory role is ‘demonstrably effective’ and that ‘the regime is one of the most rigorous regimes currently in place for any mining operation anywhere in the world.’15

Australian Safeguards and Non-Proliferation Office

10.29

The principal focus of ASNO is on international and domestic action against the proliferation of weapons of mass destruction (WMD)—nuclear, chemical and biological—and also radiological weapons. Thus, the Office’s work relates directly to international and national security. In particular, ASNO works to strengthen the operation of treaty verification regimes and their supporting technical methods. In addition, it performs domestic regulatory functions, ensuring that Australia complies with relevant treaty commitments, and that the public is protected through appropriate security standards for WMD-related materials.16

10.30

ASNO’s responsibilities cover nuclear materials—uranium, thorium and plutonium—not general radioactive materials as such. ASNO’s legislation applies to all persons or organisations in Australian jurisdiction having relevant materials, items or technology. Principally this applies to ANSTO, as Australia’s only nuclear operator, but also covers a diverse range of other entities including uranium mines and associated transport and storage operations, private sector laboratories, educational institutions, and patent attorneys. ASNO’s activities are based on a number of constitutional heads of power, especially the external affairs power.

10.31

Among his principal functions, the Director General of ASNO (currently Mr John Carlson) is responsible for ensuring the effective operation of the Nuclear Non-Proliferation (Safeguards) Act 1987, the Comprehensive Nuclear Test-Ban Treaty Act 1998 and fulfilment of Australia’s obligations under the treaties these Acts implement.

10.32

ASNO’s three key interests in the regulation of uranium mines are:

10.33

ASNO ensures that producers of uranium maintain accountancy records, including records of production, export licensing and shipping documentation. This contributes to ensuring that any uranium produced in Australia is properly accounted for.18

10.34

ASNO meets its obligation to effectively control uranium by requiring appropriate levels of physical protection at mine sites and storage areas, and by liaising with its counterparts in countries through which AONM will transit, alerting them to the need to protect such material in their jurisdiction.19

10.35

In addition to ensuring compliance with bilateral safeguards agreements, ASNO ensures that Australia’s international obligations are met under the Treaty on the Non-Proliferation of Nuclear Weapons (NPT), Australia’s NPT safeguards agreement with the International Atomic Energy Agency (IAEA), and the Convention on the Physical Protection of Nuclear Material 1979.20

Australian Radiation Protection and Nuclear Safety Agency

10.36

Established under the Australian Radiation Protection and Nuclear Safety Act 1998 (ARPANS Act) described above, ARPANSA is responsible for protecting the safety and health of people and the environment from the harmful effects of radiation.21

10.37

ARPANSA’s functions are to:

10.38

ARPANSA regulates a wide range of nuclear and radiation facilities and sources, including nuclear installations, waste facilities and radioactive materials. Among its other activities, ARPANSA reviewers assess applications for licences against international best practice in radiation protection and nuclear safety, undertake inspections and take any enforcement actions necessary to ensure compliance with the Act and Regulations. The CEO of ARPANSA (currently Dr John Loy) is required to report annually to the Minister for Health any breach of licence conditions by a licensee.

10.39

ARPANSA publishes the Radiation Protection Series to promote practices that protect human health and the environment from the possible harmful effects of radiation. The Series contains four categories of publication, two of which apply to uranium mining:

Codes of Practice are prescriptive in style and may be referenced by regulations or conditions of licence. They contain practice-specific requirements that must be satisfied to ensure an acceptable level of safety in dealings involving exposure to radiation.23 Requirements are expressed in ‘must’ statements.

Recommendations provide guidance on fundamental principles for radiation protection. They are written in an explanatory and non-regulatory style and describe the basic concepts and objectives of best international practice.

10.40

The Codes and Recommendations relevant to uranium mining include:

10.41

Compliance with the Codes of Practice, or aspects of them, is a requirement of authorisations issued by the NT Government or licences by the SA Government for the mining of uranium.

 

State government responsibilities

10.42

The day-to-day regulation of uranium mining activities is a responsibility of state and territory governments. State regulations encompass matters including health, safety and the environment, although, as described above, the Australian Government is also involved in the environmental regulation of uranium mining.24

10.43

The EPBC Act provides the Minister for the Environment and Heritage with a vehicle to directly issue approval conditions to a proponent of any new or expanded uranium mine. The proposed expansion of Olympic Dam in SA is the first uranium mine proposal to be considered under the EPBC Act.25

10.44

Under an agreement between the NT and Australian Governments on the regulation of mining in the Territory, before the NT Minister for Mines and Energy grants or varies an authorisation under Territory legislation the matter must be referred to the Supervising Scientist for comment. The Territory Minister must not act until that comment is received. The Supervising Scientist may refer the matter to the Australian Government Minister for the Environment and Heritage. If the matter is referred, the Territory Minister must act in accordance with the advice of the Australian Government Minister.

10.45

DEH explained that the Supervising Scientist’s monitoring, research and supervisory role is separate and independent from the regulatory responsibilities of the Australian Government’s industry portfolio and the Territory Government’s mines and energy portfolio.26

10.46

It was explained that the Environment Minister has a ‘considerable range of discretion’ as to the conditions he or she can impose on a mining operation, and that these conditions will vary depending on the assessment of the environmental impacts of each specific proposal.27

10.47

DEH emphasised the importance of having an independent supervisor for health and environmental aspects of uranium mining, as occurs with the Supervising Scientist in the ARR and ARPANSA, separated from the industry promotional functions of Government:

We think it is absolutely fundamentally important to have those regulatory functions at the Commonwealth level separated from the policy promotional functions of public health and that those processes be transparent and open …28

10.48

DEH explained that under the EPBC Act, the Minister for the Environment’s role will be limited to the approval and assessment process and that the Supervising Scientist’s role only applies to the ARR. The monitoring, research and supervisory role of the Supervising Scientist in relation to uranium mining only applies to the ARR in the NT. DEH mooted whether consideration could be given to expanding this role in order to ensure ‘independent, arms-length regulatory oversight’.29 The Committee returns to this matter following a discussion of the OSS.

10.49

As to the adequacy and appropriateness of federal regulation, the Supervising Scientist remarked that the ARR is particularly sensitive because of the overlay of three issues of concern to the public—uranium itself, the iconic nature of the Kakadu National Park, and mining taking place on Aboriginal land. In summary, the Supervising Scientist maintained that ‘those three issues come together to make it a highly significant area’ and that the regulation is therefore not excessive.30

10.50

Mining in the NT is conducted under two principal pieces of Territory legislation—the Mining Act, which regulates the issue of exploration licenses and leases, and the Mining Management Act which governs the operational aspects of mining in the Territory. Under the Mining Management Act, which came into force in 2002, companies are required to operate under a mining management plan, which covers both occupational health and safety and environmental aspects of mining operations. Mining management plans are approved and reviewed annually.31

10.51

NT Government officials noted that section 175 of the Mining Act requires the Territory Minister to consult with and have regard to the advice of the Commonwealth Minister in relation to most matters under the Act, including the granting of mineral leases. However, the NT Minister ‘could grant or reasonably refuse to grant an exploration license.’32 The new Mining Management Act contains similar provisions and requires the Territory Minister to consult with the Federal Minister in relation to issuing an authorisation under the Act.

10.52

In relation to the decision of the Australian Government to assume responsibility for the uranium mine approval process, Territory Government officials argued that at the operational level changes are unlikely: ‘the Northern Territory government is keen to continue to look after the day-to-day regulation of uranium mining and that is something that is supported by the Commonwealth.’33 Territory officials also stated that they ‘work well with the Commonwealth in relation to Ranger … if there were another [mine] in the equation we would work just as well.’34

 

Industry’s assessment of existing regulation

10.53

Uranium producers were supportive of state and territory governments regulating uranium mining and associated activities, given their experience and history in these areas.35 Compass Resources observed that state governments regulate mineral developments competently: ‘They are closest to the action, and that tends to result in more streamlined yet issue-focussed approval processes.’36

10.54

Some junior companies and other companies not presently mining uranium in Australia acknowledged their limited experience with the full scope of the regulatory framework but were positive about those aspects that they had so far encountered. Deep Yellow, for example, was very positive about its experience with the regulatory framework in the NT. Indeed, the regulatory environment was credited with being:

… a strong educational tool to companies regarding their obligations to the various stakeholders in the process including community, government, environment and traditional landowners.37

10.55

Compass Resources noted that, notwithstanding the Federal intervention in the NT which it welcomed, ideally, the Territory Government would continue to regulate mining.38 Similarly, in terms of the day-to-day regulation of the uranium industry in the NT, the Northern Territory Minerals Council (NTMC):

… continues to support the Mines Division of the Department of Primary Industries, Fisheries and Mines, as the prime regulator on a day-to-day basis, based on agreed arrangements between the Northern Territory and Commonwealth governments.39

10.56

The SA government was applauded for its progress with dovetailing the regulatory requirements of the state and federal systems. Paladin Resources observed that:

South Australia has developed a regulatory regime which seems to have married the requirements of the State and the Commonwealth across the wide range of issues affecting uranium mining.40

10.57

Further, Heathgate Resources praised SA regulatory bodies for being:

… extremely supportive in both the obtaining of approvals to operate and the ongoing regulation of an operating mine, while at the same time ensuring operations are conducted according to all legislative requirements.41

 

Adequacy of the current regulatory regime

10.58

Some submitters argued there is a need for stringent regulations governing uranium exploration, mining and exports, particularly:

… given the magnitude of environmental and human health damage that can be caused by radiation emanating from their waste materials or leaks from their processes …42

10.59

So long as Australia remains a dominant supplier of uranium, it will be incumbent on it ‘morally and politically, to play a very strong leadership role in regulating … the industry,’ and to make a significant contribution to developing international ‘best practice’ for the industry.43

10.60

Indeed, the Association of Mining and Exploration Companies (AMEC) and the UIC commented on progress Australia had already made in this respect. AMEC stated that ‘ Australia’s radiation safety regulations today are among the most comprehensive and str ingent in the world.’44 The UIC further observed that:

The str ingency of Australia’s approach, ensuring Australian involvement in regulating for the full life of its nuclear material through ASNO, is internationally recognised for the contribution it has made to ensuring such material is not diverted for military purposes.45

10.61

Several submitters were confident that the current regulatory regime was sufficiently stringent in ensuring the responsible export of uranium, and adequately protecting the physical environment and citizens’ safety.46 For instance, Heathgate Resources ‘support[s] the current high standards of regulatory controls’ in Australia.47 Compass Resources also felt that the current processes for approving and monitoring mining activities have generally performed well.48

10.62

Similarly, the Australian Nuclear Association (ANA) stated that environmental and export safeguards for uranium are adequate.49 It noted that efforts to ensure Australia’s uranium is only used for peaceful purposes had resulted in a stringently regulated industry:

The ANA believes that the uranium mining industry in Australia is adequately controlled by the Commonwealth and state governments with respect to environmental protection and safeguards for the peaceful use of the exported product.50

10.63

Nova Energy argued that regulation of uranium mining—from occupational health and safety to export controls and safeguards—is effective:

We firmly believe that the export licensing regime, the occupational health and safety regime from a mining perspective for the industry through to the export regime around uranium in this country is one of the best in the world and should give us all the confidence that we will only export uranium to where it is used for power generation, and that is well understood and can be tracked and monitored. The regimes exist to do that very effectively in this country.51

10.64

Mr Harry Kenyon-Slaney, Chief Executive of ERA, argued that the regulatory regime that governs ERA and its Ranger mine is very comprehensive:

We currently have five independent bodies who monitor our every move. We have the Alligator Rivers Region Technical Committee, we have the Alligator Rivers Region Advisory Committee, we have a mine site technical committee, we have the Australian Safeguards and Non-Proliferation Office, we have the Northern Territory Government and we have the Supervising Scientist, whose office was set up specially to monitor the environmental impacts that uranium mining has on the surrounding ecosystem. There is an extremely low threshold as to reporting and, as you have probably seen, an enormous amount of information is communicated widely and reported upon whenever anything happens. A spill of a litre of oil in the pit is communicated to the authorities. Personally, I feel that the regulatory environment is comprehensive. Certainly on my watch it is respected and accepted. I am sure that changes for the better could be made and that all the parties continually strive to make those. I certainly do not feel that there is in any way an environment where information is not communicated to stakeholders.52

 

Industry’s criticisms of existing regulations

10.65

The industry’s central concerns about existing regulations related to: cross-jurisdictional differences, incongruities and the complexity of the regulatory environment in the NT; and perceived excessive regulation of the uranium industry.

10.66

Although ERA ‘accept[ ed] that the regulatory regime needs to be strict and comprehensive’, it acknowledged that the regulations in the NT were complex:

… history has delivered a complex mix of issues—the Aboriginal Land Rights Act, the Local Government Act and the establishment of the Kakadu National Park—and that requires a complex mix of different laws and regulations.53

10.67

Noting the regulatory differences between Ranger and Jabiluka, ERA acknowledged that the existing regulatory environment in the NT was not ideal:

If we were at the very beginning of developing a uranium mining industry in this country we would probably develop a slightly different regulatory framework. But we are where we are and we have a number of differences between the regulatory environment for Ranger and for Jabiluka.54

10.68

ERA submitted that complying with the existing regulations in the NT is costly. Oversight by the OSS and three independent bodies in the ARR is unique and costs the company $10 million in compliance expenses each year.55

10.69

The uranium industry claimed that it is subject to regulations that are far more stringent than those imposed on other industries:

At the moment it would seem that the uranium industry is under much greater scrutiny than other industries, arguably with at least the same, if not greater, occupational health implications … That does not seem to me to be terribly reasonable.56

10.70

Existing producers were of the view that the current regime is ‘onerous’, especially when compared with regulation of other industries, and called for these perceived inequities to be reconsidered. The industry’s view is that:

The requirement for high standards of safety and environmental performance by the uranium mining industry is appropriate, but no more so than for any other industrial activity involving people as workers or neighbours, or having a potential impact on the environment. The current regulatory regime is onerous for the industry, particularly in comparison with industries such as agriculture, forestry, tourism and manufacturing.57

10.71

Another submitter suggested that the regulatory environment is ‘politically oriented and over zealous. It panders to the green movement and is not based on serious science or logic.’58

10.72

The NTMC was also critical of existing regulations preventing the development of the uranium industry:

… there is no justification for restricting the development of further uranium mines in the Territory … both the NT and Commonwealth governments need to work together to encourage the search for new deposits and provide the relevant support.59

 

Regulatory reform

10.73

Industry supported improving the regulatory system in order to:

… ensure the highest possible standards of occupational and public safety and environmental protection, while avoiding duplication and unnecessary administrative burdens and costs.60

10.74

What makes uranium unique among minerals is the requirement for Commonwealth review and companies want this to be kept as simple, efficient and timely as possible.61

10.75

The uranium industry did not argue that regulation should be softened, but expressed the hope that:

… as a result of this inquiry, policy at all levels of government will enable uranium mining in Australia to further develop under legislative and regulatory requirements that ensure the highest possible standards of occupational health, public safety, environmental protection and countering weapons proliferation.62

10.76

The MCA advocated adoption of a ‘minimum effective regulation’ approach to structuring the regulatory environment, which it describes as involving:

… minimum, efficient … and only necessary government regulatory intervention … consistent with meeting, inter alia, occupational and public safety and environmental requirements.63

10.77

Paladin Resources stated that:

The only “special treatment” needed is the maintenance of an effective safeguards regime and continuation of best practice standards for occupational health and safety.64

10.78

The Committee regrets that, other than one detailed set of regulatory reforms proposed by a group critical of uranium mining, no reform proposals were made by existing producers or juniors. Nonetheless, a range of impediments to the industry’s development were identified and these are discussed in the following chapter. The following section addresses criticisms of existing regulations, focussing on the alleged environmental impacts of the industry in Australia.

 

Criticisms of current regulation

10.79

Some 47 submitters were opposed to uranium mining outright and called for the industry’s closure. For example, one submitter’s view was that: ‘To continue mining shows contempt for the human race’.65

10.80

Those opposed to uranium mining altogether generally considered that the regulatory arrangements governing the industry were inadequate.66 A number of submitters provided detailed criticisms of the regulatory arrangements, much of which focussed on the following issues:

 

Environmental regulation

10.81

Much of the criticism of the regulatory regime focussed on the alleged paucity of environmental protection provisions. For example, Friends of the Earth (FOE) viewed the environmental impact assessment process as being ‘inadequate’.67

10.82

Witnesses noted that the Senate Environment Committee found that the industry is characterised by ‘under performance and non-compliance’ and concluded that the regulations were ‘complex, confusing and inadequate’.68

10.83

The Australian Conservation Foundation (ACF) also called for the 2003 Senate Environment Committee report to be responded to and its recommendations implemented.69 Areva, however, argued that some of the Senate Committee’s recommendations are ‘at odds with an objective and balanced assessment of the industry’.70 For example, Areva cited the Senate Committee’s suggestion that in-situ leach mining is an experimental technology as an indication that its conclusions were not necessarily realistic.71

10.84

The Gundjeihmi Aboriginal Corporation’s (GAC’s) concerns about regulation included:

10.85

The GAC recommended the overhaul and consolidation of regulations, rather than piecemeal reform.73 It made six specific recommendations in relation to the regulatory environment, which are summarised below, along with the DEH’s response to each:

10.86

The GAC suggested that its first five recommendations could be satisfied by consolidating the provisions of a number of pieces of legislation and regulation, including the 17 November 2000 Agreement, the Working Arrangements, Part III of the Commonwealth Atomic Energy Act 1953 and the EPARR Act.89

10.87

The ACF also made recommendations for regulatory reform, including a review of the regulatory regime in the NT to reduce complexity.90 Each of these issues is addressed, in turn, in the following sections.

10.88

Arguing that the current regulations were in fact adequate, ERA reported that complying with regulatory requirements presented a significant cost to the company:

The combined direct cost of all of our environmental, safety and health management activities, which includes payments to the Commonwealth Department of Environment and Heritage that are used to fund the Office of the Supervising Scientist, is well in excess of $10 million a year.91

10.89

The NTMC argued that companies advocate excellence in environmental performance and aim to achieve ISO 14001 certification—an internationally recognised standard for environmental management systems—which ERA has already attained.92 In addition, all major operators in the NT are signatories to the Minerals Industry ‘Enduring Value’ Code for Sustainable Development.93

10.90

In relation to environmental regulation, witnesses commented on a range of specific issues, which are detailed below:

Waste

10.91

In relation to waste generated by uranium mining, witnesses were specifically concerned at tailings management and the management of waste water. An overriding concern of submitters was that uranium mining leaves behind tailings which stay radioactive for long time periods. Earth movements may damage tailings dams and cause radium to escape. Leaking waste water may also contaminate groundwater.94

10.92

Another concern involved the possibility of tailings moving into groundwater or being dispersed by air as radon.95 GAC’s fundamental concern was that during uranium mining and after rehabilitation there could be increased concentrations of radionuclides released into the environment.96

10.93

GAC made a number of allegations about the management of tailings at Ranger, including:

DEH expressed its confidence in the current system of tailings management, provided the Committee with a detailed response to each of the GAC’s concerns and explained how tailings are currently managed.98

10.94

The NT Government advised that Ranger pumps approximately 2.3 million tonnes of tailings per annum at a density of 50 per cent solids to pit number one. This equates to a total volume of about 3.2 million cubic metres of tailings per annum. The Territory Government noted that uranium mine tailings are not classified as radioactive waste.

10.95

The GAC raised four concerns about water management at Ranger:

10.96

Again, DEH expressed its confidence in the current system of waste water management, and responded to each of the GAC’s stated concerns.100

10.97

The GAC proposed that statutory responsibility for monitoring environmental impacts be transferred from the NLC to the GAC, but this suggestion was rejected by the NLC.101

Incidents and spillages at uranium mines

10.98

A number of submitters expressed concern at the ‘large numbers of incidents’ occurring at uranium mines, the alleged reluctance of regulators to prosecute companies and the inadequacy of penalties.102

10.99

FOE alleged that the present regulatory structure fails to enforce environmental protection by:

10.100

FOE claimed that ERA has failed to report ‘severe uranium contamination events’ in a timely fashion:

[In its annual report] ERA … stated that the company operates in accordance with applicable environmental legislation. However the directors’ report fails to mention a number of severe uranium contamination events that occurred last year at ERA’s Ranger mine. One notorious incident in March 2004 resulted in 28 workers falling ill after drinking water contaminated with uranium levels 400 times greater than the maximum Australian safety standard.104

10.101

GAC echoed this view, claiming that regulatory agencies operate within a culture of downplaying incidents. It cited an example of the OSS stating in its 2000–01 Annual Report that no reportable incidents had occurred during the reporting period, while the GAC stated that:

A tailings spill such as that on 9 September 2000 is clearly of risk to mill workers, and would be of legitimate concern to the Mirarr and the general public. The Gundjeihmi Aboriginal Corporation is concerned that a poor management culture within ERA and regulating authorities that down play reportable incidents is a recipe for disaster.105

10.102

These concerns, however, were countered by the DEH, which responded that the number of reported incidents was not a cause for concern and merely reflected the stringency of the reporting regime.106 It contended that this has resulted in the reporting of incidents that would be considered to be below the threshold level at other mining operations.107

Mine closure and rehabilitation

10.103

A number of submitters were concerned about failures to rehabilitate former uranium mines in the South ARR and at Nabarlek in the East ARR.108 Environmental groups cited the environmental degradation following the closure of uranium mines in the NT which were not properly rehabilitated:

There have been former uranium mining operations, from Rum Jungle through South Alligator, across the East Alligator River, into the Nabarlek mine. Now there are continuing and unresolved rehabilitation issues at all of those sites.109

10.104

In particular, the Environment Centre of the Northern Territory (ECNT) argued that rehabilitation projects in the 1980s have merely reduced the rate of pollution.110 It alleged that Rum Jungle continues to pollute the environment:

… thousands of tonnes of potentially toxic pollutants such as copper, zinc, manganese, lead sulphate, uranium and radium were, and continue to be, washed into the Finniss River and adjacent wetland environments.’111

10.105

Mr John Schindler was also concerned that Rum Jungle remains contaminated, and questioned who is responsible for paying for the rehabilitation process in the event that the mine owner folds, which was the case with the Rum Jungle mine.112

10.106

Information available on the ARPANSA website was critical of the tailings management processes adopted at Rum Jungle, particularly during the early stages of mining, and noted that minimal rehabilitation was carried out on the site upon closure of the mine.113 They argued that within a few years of closure:

… the Rum Jungle mine had become one of Australia’s most notorious pollution problems, due to oxidation of sulphides by bacteria and the consequent release of acid and metals into the East Finniss River.114

10.107

In relation to Nabarlek, ACF pointed to the physical plant that remains on the site, a lack of revegetation, high levels of radiation in some areas of the site, and an alleged failure of ‘regulatory culture’ and communication between agencies.115

10.108

Compass Resources observed that the earlier generation of uranium mines, such as Rum Jungle, were not subject to the approval processes that apply today and ‘the regulations were very flimsy.’116 Compass Resources argued that there are now ‘substantially higher standards to meet’ for product control, occupational health and safety, and for reclamation of the proposed mine site.117

10.109

The Supervising Scientist corroborated this view, arguing that:

I would say that the regulations that apply today to uranium mining in Australia, as distinct from what used to occur, are such that the environment can be and has been protected to a very high degree. If one applied the same str ingency to other forms of mining you could achieve the same result, but the other forms of mining do not receive the same kind of attention that uranium mining does.118

10.110

Notwithstanding problems at some mines, the rehabilitation of mines at Mary Kathleen and Nabarlek has been successful:

The first major rehabilitation project of a uranium mine in Australia, Mary Kathleen in Queensland, won an award for engineering excellence upon completion in 1985, and the 1990s rehabilitation of Nabarlek is even better.119

10.111

The Director of Parks Australia noted that there are some 20 former mine sites in the upper South ARR dating from the 1950s and 1960s. Some of these sites were partially rehabilitated in 1990–91, before they became part of the Kakadu National Park. The sites are required to be properly rehabilitated by 2015 and planning work to achieve this commenced some five years ago. In partnership with the Traditional Owners, the NLC, the Supervising Scientist and the NT Government, Parks Australia reported that a plan has now been developed to remediate the simplest sites. This plan has been agreed to by the NLC and Traditional Owners.

10.112

Parks Australia reported that planning is now ‘well under way’ for dealing with the more complicated sites, but it was noted that at present National Parks does not have sufficient resources to properly rehabilitate all these sites: ‘The scale of what is necessary to be done properly is beyond our current capacity.’120

10.113

In June 2006, the Australian Government announced that it will move to incorporate 29 mining leases into Kakadu National Park, allocating $7.3 million over the next four years for this work which will involve ‘ the effective rehabilitation of abandoned uranium sites in Kakadu’s South Alligator River valley’.121

10.114

Concerns about the rehabilitation of decommissioned mines were accompanied by requests by environmental groups for further resources for Parks Australia for its rehabilitation work on former sites.122

10.115

In terms of the Ranger operation, ERA observed that the company is obliged to submit an annual amended Plan of Rehabilitation, underwritten by a bond (which is now in excess of $60 million), setting out how the company would rehabilitate the site in case of sudden closure. The company states that the net present cost of final closure at the end of the operation’s life is expected to be $176 million.123

10.116

The ACF alleged that both the Commonwealth and NT regulatory authorities have failed to give adequate regard and effect to minimising impacts on the Ranger Project Area despite this being clearly articulated in the Environmental Requirements. This failure has allegedly seen a consistent pattern of approvals being granted that increase ERA’s contaminant footprint and complicate future rehabilitation and final landform options.124

10.117

In response, the NT Government confirmed that under the Territory’s Mining Management Act and the mining management plans, companies are required to implement appropriate and approved mine closure processes.125 As a part of this process, companies are required to provide an environmental bond held by the Government which, in the case of ERA’s operations at Ranger noted above, is currently $63 million.126 Furthermore, the Commonwealth’s Environmental Requirements stipulate that the Ranger Project Area is to be rehabilitated such that it could be incorporated into the National Park.127

10.118

In relation to the rehabilitation of the mine site, Mr Harry Kenyon-Slaney explained the Environmental Requirements that ERA must meet:

We have set out in our environmental requirements, which are attached to our lease, very clear regulations as to what we have to achieve. We are required to return the ground, the five square kilometres, to a standard which will allow its incorporation into the Kakadu National Park. That is a very considerable obligation and it is one that we have already started work on. We are required to remove all infrastructure. We are required to move the power plant. We are required to remove everything to do with the mine site and put the waste rock back into the pit, fill them up and rehabilitate all of the water. We have recently constructed a $30 million water treatment plant to start the process of lowering water kept on site. Progressively, over the next five or six years before formal closure, we will move ahead with a range of technical projects to ensure that closure proceeds in an exemplary manner. I think we will be in the vanguard of scientific best practicable technology by the time we close Ranger, and I have every confidence that we will do it in an exemplary manner. But I think the issues are going to be more socioeconomic than technical.128

10.119

ERA is aware that the future of the community in the vicinity of Ranger will depend in large measure on the company’s ability to prepare for closure. Mr Kenyon-Slaney stated that the company has commenced a comprehensive closure management process and will be providing for it financially. ERA expressed that it is determined to ‘close Ranger in an exemplary manner’, but argued that the biggest challenge is likely to be the socio-economic implications of the mine’s closure:

I think the most significant issues and probably the most vexing of issues are going to be in the socioeconomic area, where the reliance upon Ranger in the community is very significant. Upwards of 70 per cent of the town of Jabiru is in one way or another connected with, or dependent upon, Ranger’s operation. We are working very actively with all the stakeholders, the traditional owners, the Northern Territory government, and Parks to try to ensure that those issues are addressed and that we can withdraw from the area in as sustainable a manner as possible.129

10.120

Although ERA is obligated under the Environmental Requirements attached to its mining license to remove the infrastructure at Ranger, including the power station which also supports Jabiru, the company will discuss with stakeholders what is to happen to the infrastructure:

… to try to ensure that we leave a sustainable community. We will be working over the next seven years or so to find ways of doing that, whether it is through employment, development for small businesses or opportunities to leave infrastructure that is of use to people in the future.130

10.121

In preparing for closure, ERA explained that in the past few years a Jabiru Regional Sustainability Project was initiated in partnership with the Traditional Owners, the NT Government and Parks Australia which had as its objective to understand what the impact is going to be on the community from the closure of the mine.131

10.122

The Committee concludes that the regulations governing uranium mine closure and rehabilitation are clearly now much improved over past requirements and practice. Recognising the importance of successfully rehabilitating decommissioned uranium mines, and taking into account the risks posed by poorly rehabilitated former mines, the Committee supports calls for increased funding to rehabilitate former uranium mines.

10.123

The Committee applauds ERA’s determination to eventually close Ranger in a way that leaves behind a sustainable community.

 

Recommendation 5

The Committee recommends that the Australian Government provide adequate funding to ensure the rehabilitation of former uranium mine sites, and for towns and similar facilities, rehabilitation to meet the expectations of the local community.

Operations in the Northern Territory

10.124

The ECNT argued that the regulation of uranium mining in the NT operates ‘through a confused tangle of legislation, ministerial agreements and bureaucratic processes.’132 It was alleged that the ‘regulatory mess’ has ‘marginalised the local Aboriginal people and contributed to the long-running mismanagement of the [Ranger] mine.’133

Impacts of mining on the Kakadu National Park
10.125

A number of submitters claimed that the existing monitoring and reporting regime in the ARR is inadequate.134 The ACF alleged that the regulatory frameworks are failing to protect the environment in Kakadu, leading to ‘unacceptable and unnecessary operational and procedural failures.’135

10.126

The ECNT alleged that the Australian Government has failed to act on a previous commitment to support a recommendation of the World Heritage Bureau to incorporate the proposed Koongarra mine area into Kakadu.136

10.127

Notwithstanding the concerns expressed by the GAC and environmental groups, the NLC stated that it was no more concerned about the environmental impacts of uranium mining than it was about any other mining that takes place. Indeed, the NLC expressed more concern about the impacts of mining to extract gold.137

10.128

The Director of Parks Australia, Mr Peter Cochrane, stated that uranium mining poses a low risk for the Park:

In terms of the risk issues that we deal with in managing the park and protecting its values, I would have to say that Ranger uranium mine and its impact on the landscape are very low down on that risk profile. There are a range of issues which are much higher priorities for us. It is not something that impacts on us greatly. I have every confidence that the Supervising Scientist and his staff prosecute their job with the utmost efficiency and effectiveness. Therefore, the mine, in terms of park management, does not have a major impact.138

10.129

It was noted that the major issue would be the rehabilitation effort following the closure of the mine, but that:

Kakadu is well known around the world for having probably the best managed mining operation in a World Heritage area, one which has a minimal impact on the area.139

10.130

The Supervising Scientist noted that his office had fully assessed the possible environmental impacts from the management of tailings were the Jabiluka mine to proceed in a report for the World Heritage Committee. It was found that the requirement that tailings be placed underground would generate ‘no impact in the very, very long term on the environment’.140 Thus, contrary to assertions by ACF and Dr Gavin Mudd, the OSS has assessed that long-term storage of tailings underground at Jabiluka will not harm the wetlands of Kakadu. Moreover, in 2000, the World Heritage Committee concluded that:

… the currently approved proposal for the mine and mill at Jabiluka does not threaten the health of people or the biological and ecological systems of Kakadu National Park.141

10.131

For its part, ERA noted that the Supervising Scientist’s reports have ‘continually stated that ERA’s operations have never adversely affected the ecosystems of the Park.’142

Incidents at Ranger
10.132

ACF expressed concern about the environmental impacts and safety of the operations at Ranger:

We have a current operation system at Ranger, where there are significant environmental and significant social impacts from that large-scale industrial activity … We have a situation where last year the Ranger uranium mine workers showered in and drank water containing 400 times the Australian safety standard of uranium. This year there are continuing health and safety challenges and prosecutions in court in Darwin. There is growing radioactive contamination in the footprint of the current mine.143

10.133

Similarly, the ECNT drew the Committee’s attention to the incident in which workers were exposed to contaminated water and alleged that, by not responding to the Senate inquiry into Ranger the Commonwealth is ‘showing that it is not interested in protecting the environment, workers or the community in relation to uranium mining in the Northern Territory.’144

10.134

The ECNT alleged that mining at Ranger has caused elevated levels of toxic contaminants downstream of the mine and is also producing a contaminated groundwater plume arising from a supposedly leaking tailings dam.145

10.135

The Supervising Scientist noted that over the life of the Ranger mine there have been some 120 occasions on which formal reporting of an incident was required. However, until 2004 when two serious incidents occurred, there had only been one incident over the past 25 years in which people were affected by a very small radiation dose and one other in which a number of birds died on a pond at the mine. The Supervising Scientist ‘assessed that all the other 120-odd incidents as being of negligible impact on the environment.’146

10.136

In relation to the two incidents that occurred at Ranger in 2004, the Supervising Scientist again concluded that although the incidents were ‘very serious in that they did threaten the health of both people and the environment’, it is expected that there ‘will be no long-term health hazard for the workers involved and the environment was protected to a very high degree during the entire incidents.’147

10.137

In relation to an incident involving a leakage of tailings water in 2000, DEH argued that the ACF were incorrect in their assertion that 2 million litres had left the mine site. The actual figure was only 85 000 litres and the Supervising Scientist had subsequently concluded that ‘the leakage of tailings water had no adverse ecological impact on Kakadu National Park.’148

10.138

Mr Kenyon-Slaney stated that the incidents that occurred at Ranger in 2003 and 2004, which related to the contamination of the potable water system and pieces of equipment leaving the mine site, were unacceptable. While it was argued that there were no health impacts, the incidents breached the company’s own internal standards and procedures. The Supervising Scientist investigated and reported on the incidents and these reports were followed by an audit launched by the Australian Government. Mr Kenyon-Slaney explained that ERA complied with the requirements of all three audits and has put in place:

… a whole series of new procedures and practices which strengthened our compliance with our water systems in the plant and the radiation clearance procedures. Those have been signed off and given a ringing endorsement by ARPANSA.149

10.139

In sum, ERA argued that it had acknowledged recent failures, taken actions deemed satisfactory to regulators and expressed a desire to improve performance.150 The Minister for Industry, Tourism and Resources’ view was that ERA had made considerable progress towards meeting conditions arising out of two Supervising Scientist reports: the company had complied with all conditions but one, and had made substantial progress towards complying with the final condition relating to a workplace safety standard.151

10.140

As to the robustness of regulatory oversight and the two incidents at Ranger, the NT Government pointed out that the Territory’s Mining Management Act places a duty of care on companies to conduct themselves in a certain way. In addition to mechanisms such as the MSTCs, an environmental audit is performed by the Government once a year to ensure that management systems are in place. In relation to the incident in which contaminated equipment left the mine site, the NT Government stated that these incidents were identified and reported, as required, by ERA:

We do not have anybody on the gate to check whether or not equipment is leaving the site with mud on the tyres. ERA is supposed to do that. They know they were supposed to do that. They fell down on that occasion and they brought that to the attention of government. From that point of view, I suggest that the system is working … absolutely. If they did not bring it to our attention, then we probably would not have known about it, but we work within a regulatory environment where people will bring that to our attention.152

10.141

As to the number of incidents that have been reported, the Supervising Scientist concluded that this reflects the str ingency of the reporting regime rather than reflecting adversely on the company’s performance:

In absolute environmental protection terms, the record of the company has been very good. It is my view that the reason why we have so many incidents reported is that it is more a measure of the str ingency of the reporting regime that is imposed on the company by the regulations than it is a reflection on the company’s performance.153

10.142

DEH concurred, responding that the number of reported incidents at Ranger is indicative of the rigorous reporting regime, which has resulted in the reporting of incidents that would be considered to be below the threshold level at other mining operations.154 Moreover:

Monitoring and research by the Supervising Scientist since 1978 has concluded that there has been no harm to the environment in Kakadu as a result of mining operations at Ranger, confirming the efficacy of the regulatory regime.155

Operations in South Australia

Expansion of Olympic Dam
10.143

The ACF and other submitters argued that there are four ‘significant and unresolved issues’ associated with the proposed expansion of Olympic Dam: the long-term management of radioactive mine tailings; potential for the degradation of the Great Artesian Basin (GAB), if additional water supplies were to be sourced from the GAB; the significant power demand for the expanded mine; and the provisions of the Indenture Act under which the mine operates, which are alleged to provide the mine operator with ‘unacceptable legal privileges’.156 For instance, the FOE claimed that the Roxby Downs Indenture Ratification Act overrides the SA Aboriginal Heritage Act.157

10.144

A number of submitters were concerned about possible increases in tailings at Olympic Dam if the mine is expanded.158 For instance, Dr  Gavin  Mudd noted that Olympic Dam is:

… already Australia’s largest single radioactive waste dump, currently about 73 million tonnes and growing by some 9 million tonnes per year. This radioactive waste dump, the tailings left from milling and smelting, has leaked profusely in the past. If the full ore resource is ever mined at Olympic Dam … the tailings dump could reach some 4,000 million tonnes …159

10.145

Similarly, ACF claimed that the increased tailings from the expansion of operations at Olympic Dam will:

… massively increase the scale of the current problem without providing any credible answer to tailings containment.160

10.146

The proposed expansion was also criticised for its increased power and water requirements from the GAB.161 ACF claimed that:

Mining demands on water supply threaten the Great Artesian Basin and the unique Mound Spring ecosystems dependent on natural groundwater flows for their survival.162

10.147

Dr Gavin Mudd asserted that the average ore grade at Olympic Dam will decline over time, leading to higher energy requirements for extraction and more radioactive waste created per tonne of U3O 8 produced.163 ACF was also opposed to the expansion of Olympic Dam on the basis that the operation’s energy requirements had yet to be resolved, and that the additional power requirements would impose burdens on the State’s electricity grid.164

10.148

The ACF also asserted that the owners of Olympic Dam operate the mine ‘under a set of privileges available to no other company operating in SA’ and that ‘the State Government should repeal these unacceptable legal privileges’.165

10.149

BHP Billiton contested this view, stating that Olympic Dam has and continues to be subject to a range of environmental management systems and requirements. These include:

10.150

In relation to the extraction of water from the GAB, BHP Billiton argued that the company already recycles and desalinates water, both for its mining processes and for consumption at Roxby Downs. Moreover, the company has spent several million dollars in support of the State Government’s program of capping pastoral bores and argued that, in combination, these efforts save the same amount of water that Olympic Dam uses. Dr Roger Higgins, Vice President and Chief Operating Officer of BHP Billiton’s Base metals Australia, argued that:

Collectively, those programs have resulted in reduced water being extracted from the GAB of about twice what we use. We consider that our contribution to that is about equal to what we use. So, while we take 32 megalitres a day out of the Great Artesian Basin, by working with the pastoralists helping to cap bores, to put covered piping in rather than open drains and generally to avoid losses, we believe that we are about in balance in our total effort in relation to the GAB. That is, the water extracted is roughly equivalent to the water saved by a more judicious use of water on the pastoral properties. It has been a good program.167

10.151

The expanded mine will require 130 megalitres of water a day, up from 30 megalitres currently, and BHP Billiton is examining three possible sources of supply: further use of the GAB; other aquifers in the region that are not connected to the GAB; and a desalination plant. If the company were to opt for the desalination plant, it expressed the hope that communities in the region could also benefit from the facility.168

10.152

DEH noted that the potential environmental impact of any expansion of Olympic Dam will be formally assessed during the approval process. DEH expected that such matters ‘will be subject to a very thorough examination through the EIS process.’169

Beverley and Honeymoon deposits
10.153

A number of submitters were concerned about allegedly ‘severe groundwater pollution caused by acid ISL mining’ at Beverley and Honeymoon.170 Dr Gavin Mudd insisted that the ISL mining technique contaminates groundwater, and alleged that no scientific evidence to the contrary has yet been produced.171 Specific criticisms were made of: the use of acid in the leachate at Beverley; re-injection of waste liquids into the aquifer; and the potential for excursions of contaminated groundwater into other aquifers.172

10.154

Dr Mudd argued that there is no scientific evidence of claims that the waste liquid re-injected into the aquifer at Beverley will naturally attenuate—that is, over a period of time the composition of the waste liquid will naturally return to its precontaminated state. It was also argued that Heathgate Resources, the mine’s owners, have yet to release any research refuting his published criticisms of acid ISL mining.173 However, Dr Mudd conceded that: ‘There is an extremely remote possibility that Beverley could affect the Great Artesian Basin’.174

10.155

In response to claims that acid ISL mining of uranium and disposal of wastes will contaminate groundwaters, in 2003 the SA Government requested that the State’s Environment Protection Authority conduct an independent review of the environmental impacts of the ISL mining process. CSIRO Land and Water was commissioned to conduct the review, which was completed in August 2004. The CSIRO review methodology consisted of visits to the Beverley and Honeymoon operations, a study of company and government documents, a literature review (the bibliography of the CSIRO report lists several of Dr Mudd’s publications), consultation with the community, and consideration of written submissions.175

10.156

The CSIRO’s overall conclusion was that ISL mining has considerably less environmental impact than other conventional mining techniques. As to the use of acid rather than alkaline leaching and disposal of liquid wastes by re-injection into the aquifer, the report concluded that these processes should be allowed to continue, subject to monitoring showing that there are no excursions of leach solution or waste liquids into other aquifers. The report stated that ISL mining and associated waste disposal is more environmentally responsible and cost effective than any suggested alternative techniques. Furthermore, CSIRO concluded that the Beverley operation has initiated and implemented world best practice methods.176

10.157

In reaching these conclusions, the CSIRO noted that the pre-mining groundwater at Beverley was highly saline and contained relatively high concentrations of radionuclides. In its untreated form, the groundwater was unsuitable for human consumption and generally unsuitable for stock use. The groundwater has no apparent beneficial use other than for the mining industry. Further, the study found that re-injection of waste is preferable to surface disposal. CSIRO concluded that although it has not yet been proven, it is widely believed and accepted that natural attenuation will result in the contaminated water chemistry returning to pre-mining conditions within a timeframe of over several years to decades.177 Finally, CSIRO considered that there is ‘no potential for mining-affected water from the Beverley project to enter the GAB.’178

10.158

However, Dr Mudd claimed that the CSIRO report provided ‘no data to justify their claims that there would be no long-term impacts on groundwater.’179 Dr Mudd also criticised the CSIRO report because it was ‘not based on good science’.180

10.159

Heathgate Resources rejected the criticism made of the appropriateness of the ISL mining method used at its Beverley operation and defended the CSIRO study.181

 

The Supervising Scientist

10.160

The ACF made a number of criticisms specifically concerned with the OSS and DITR.182 Each concern raised is followed by a response from DEH in turn:

Whilst the DEH confirmed that ERISS staff had relocated from Jabiru to Darwin in 2002, it argued that the OSS’s on-ground presence had increased since that time.184 The OSS now has ‘a full chemical, radiological and biological monitoring program and all of the staff conducting this program reside at Jabiru’, and this was not the case prior to 2001.185 Furthermore, since 2002, the OSS ‘has had a person located in Jabiru who is in a position to respond quickly to incidents at the [Ranger] mine.’186

The DEH refuted this claim, stating that OSS programs are directed at ensuring the adherence to Environmental Requirements.188 The supervisory program ensures their implementation, and the monitoring program ensures compliance with Environmental Requirements.189 In relation to the suggestion that the OSS pursue legal action, the DEH noted that ‘the Supervising Scientist has only an advisory role’ and that decisions relating to taking legal action are for the NT regulator or the Australian Government Minister for Industry, Tourism and Resources.190

The DEH rejected criticisms of the OSS’s independence and refuted claims that the OSS had been captured by industry.192 It suggested that the Supervising Scientist’s independence had been demonstrated by the ‘thoroughness and impartiality of investigations conducted on incidents at Ranger in 2000, 2002 and 2004’ and the highly critical reports that resulted from these investigations.193 The DEH noted that the NT Government had used two OSS reports as the basis for a successful prosecution of ERA, concluding that the OSS was therefore ‘not subject to regulatory capture.’194 It was also argued that the acceptance by an OSS staff member of a position with ERA was ‘not evidence of a decline in the organisational independence of the Supervising Scientist.’195

In contrast, the DEH stated that ‘the funding currently provided to the Supervising Scientist is considered adequate’ for the fulfilment of the OSS’s functions.197 It noted that the ARRTC can recommend, if it believes it is necessary, that additional funding be provided to the ERISS, and that no such recommendation had been made in the last five years.198

The DEH refuted this claim, noting that the OSS runs an ‘independent chemical, biological and radiological monitoring program’ in the ARR, and it is on the basis of this data, not only those produced by ERA, that the OSS reaches its conclusions.200 The DEH added that all of the data collected by the OSS is made public as quickly as possible, through the OSS website, Annual Report, and biannual reports to ARRAC.201

The DEH rejected this claim, on the basis that it did not believe there was any evidence to support the assertion.203 Indeed, correspondence between the OSS and ERA, made public in the former’s report into the 2004 Ranger water contamination incident, demonstrates the OSS’s determination to ensure that ‘the environment and health of workers and the local people would not be put at risk’ despite ERA’s operational considerations.204

The DEH countered this assertion, noting that the OSS has a full-time employee in Jabiru whose specific role involves communication and engagement with the Traditional Owners on a daily basis. It also noted that the Executive Officer of the GAC had recently ‘stated publicly that the Traditional Owners trusted the Supervising Scientist.’206

The DEH noted that no reason had been given for the ACF’s assertion.208

10.161

Responding to a proposal to merge ERISS with ARRAC and split the combined organisationfrom the SSD, the Supervising Scientist advised that this had been considered and rejected on a number of occasions. It was argued that the current model has the important benefit of being able to provide the Supervising Scientist with immediate capacity and ‘expertise on hand immediately’, should the need arise—as was required with the potable water contamination incident at Ranger in 2004:

We were able to respond instantly, essentially, to that incident. I was able to go out to Jabiru within days of the incident and assure the workers and the people of Jabiru that we had already measured the radionuclide content of the water and that no one had received a significant radiation dose. That was possible only because I was able to turn to my institute immediately and say, ‘I need you off. Stop doing everything you’re doing and work on this.’209

10.162

The NTMC was supportive of the role of the OSS:

… the Minerals Council supports the work of the Office of Supervising Scientist and believes that the office is independent in its work and completely impartial and unbiased in its reviews and regulation.210

10.163

Among the ACF’s recommendations for reforming the regulatory environment, was the suggestion that the ‘on-ground’ role of the OSS be expanded.211

10.164

The Committee notes the important function performed by the OSS, but that this is limited to oversight of uranium mines in the ARR of the NT. The Committee considers that the expertise of the OSS could perhaps be utilised in relation to approvals and monitoring of other uranium mines throughout Australia. In particular, the Committee notes that under the EPBC Act the Minister for the Environment must assess and approve proposals for new uranium mines or the expansion of existing mines. Expanding the scope of the Supervising Scientist’s responsibilities to examine and monitor all future uranium mines may have merit, for example, in providing the most thorough analysis and advice to the Environment Minister.

10.165

The Committee notes evidence by industry that, in the main, state governments regulate mining very effectively and that the industry wishes to see any unnecessary duplication across levels of government eliminated. Mindful of the importance of minimising further burdens on industry, the Committee urges that any expanded role for the OSS minimise any additional complexity for industry.

 

Recommendation 6

The Committee recommends that the Australian Government examine expanding the role performed by the Office of Supervising Scientist ( OSS) in relation to the monitoring and approvals for uranium mines. As an example, the OSS could be given a formal role in advising the Minister for the Environment and Heritage in relation to all uranium mine assessments and approvals under the Environment Protection and Biodiversity Conservation Act and the Minister for Industry, Tourism and Resources in relation to the conditions for granting uranium export licenses.

Given the proposed expanded role for the OSS, the Committee further recommends that the Environmental Research Institute of the Supervising Scientist (ERISS) be provided with additional resources, potentially in partnership with a suitable university, so as to provide a national research function. The OSS should continue to be able to refer matters to ERISS for research, but ERISS’s autonomy should be preserved in terms of the conduct of research and the release of its findings.

10.166

The ECNT raised concerns of staff moving between ERA, the OSS and the NT Department of Mines:

… over the years there has been quite a steady flow of personnel between senior management of the Office of the Supervising Scientist and the uranium mining company itself and also the Northern Territory Department of Mines. So you have what can appear to a bit of a revolving door happening, where you have got the regulators moving off to work for the company and then company people going off to work for the regulators and it all starts to become pretty murky.212

10.167

ACF also alleged regulatory capture of the OSS by the uranium industry, and specifically by ERA.213 The Supervising Scientist responded that:

… I find it strange that anyone could suggest that the Supervising Scientist has been captured by the industry when you look at the number of inquiries we have conducted over the last five years and at the reports that I have given to the minister, which have been tabled in the parliament and which have been highly critical of the ERA. Indeed, if you look at the water contamination incident that occurred last year you will see in the report that we wrote all the correspondence between me, the mining company and the Northern Territory regulator. You will find that it is absolutely clear in that correspondence that I insisted that, before I would support recommencement of milling activities, I would need to be absolutely convinced that all necessary steps had been taken to ensure that an incident of that kind could not be repeated. As a result, the mining company could not operate for 14 days. That is a very significant impost on any operation and financially a very significant cost.

So I refute any suggestion that there was regulatory capture. It is not just a statement; I think the evidence is quite clear in the way we have conducted ourselves over the years and in the reports that we have written.214

10.168

The Territory Government listed the type and frequency of monitoring, audit and inspection undertaken of the Ranger mine site, as well as the environmental monitoring of surface and groundwater around the mine.215 The NT Government rejected claims of regulatory capture by ERA and over reliance on company derived data:

Yes, Ranger does monitoring and provides results to us and the Supervising Scientist, and I understand that is publicly available … No, we do not rely on that advice. Both the Northern Territory government and the Commonwealth do what we call ‘check monitoring programs’. They do not always know when we are going there. We take samples. We get our own results and the Commonwealth gets their own results. We would look at those results against ERA’s results at approximately the same time—maybe even at the same time—and if there were any anomalies there we are onto that.216

 

Agency conflicts of interest

10.169

A number of submitters alleged that there is a failure to properly separate regulatory and industry development support functions within state and territory governments. Dr Gavin Mudd criticised the current regulatory framework for what he perceived to be a ‘fundamental conflict of interest’.217 Dr  Mudd’s concerns related to the potential for agency-based conflicts of interest due to the incongruous roles of agencies as both promoters and regulators of the uranium industry:

There is a fundamental conflict of interest for a department of mines type of agency, whether it is in South Australia or the Northern Territory, to be both the active promoter and developer of the mining industry and its environmental regulator. They need to be separate … If they are legislated to be both a promoter and a regulator, that is a fundamental conflict of interest. They cannot do their job properly because in one sense they want to promote the industry but in the other sense they cannot regulate it to the extent that it really needs in order to meet legitimate community expectations. Olympic Dam is a good case study because most of the powers for normal regulation of most types of mining do not apply because of the Roxby Downs Indenture Act.218

10.170

The ECNT called for the creation of a regulator:

… that is open and transparent, does not have conflicts of interest, is not subject to manipulation by the government or minister of the day, and does its job diligently. So far, we are still waiting to see that in relation to uranium mines in the Northern Territory.219

10.171

The NT Government argued that following a recent regulatory review, new mechanisms have now been put in place:

… to make sure that those development issues are kept separate from the regulatory issues to the point where we could come to loggerheads with our mine development people if we thought there were issues there.220

10.172

While industry were appreciative of the Commonwealth’s decision to intervene in the approvals process for uranium mining in the NT, the ECNT expressed opposition:

The Commonwealth has said that it intends taking over the approval of new uranium mines in the Northern Territory but the Commonwealth has shown over many decades that it cannot be trusted with uranium mines in the Northern Territory. From Rum Jungle to Ranger and Koongarra to Jabiluka, the Commonwealth has always put commercial gain and perceived political and strategic interests ahead of the environment, Indigenous people, public health and safety and future generations.221

10.173

ECNT felt that although they were members of the ARRAC the information on which decisions are based is not available to the ECNT.

10.174

In the remainder of the chapter, the Committee considers issues associated with the impact of uranium mining on Aboriginal communities.

 

Aboriginal communities and uranium mining

10.175

The Committee received evidence in relation to the social impact of uranium mining on Aboriginal communities. This included concerns regarding the present regulatory environment in providing adequate consultation and benefits for Traditional Owners and Aboriginal groups. Four specific issues are described in further detail below:

 

Social impact monitoring

10.176

One specific concern expressed by submitters was an alleged lack of reporting and attention given to cultural and social impacts and the failure to adequately or appropriately engage Aboriginal Traditional Owners. For example, APChem argued that the social impacts of uranium mining have not been adequately examined.222

10.177

The NLC stated that uranium mining has had an ‘profound effect’ on the lives of Aboriginal people in the ARR. Justice Fox allegedly predicted negative impacts of uranium mining on local Aboriginal communities, and the NLC assessed that these consequences have come to pass.223 The GAC concurred with this view, alleging that uranium mining has been socially destructive for Aboriginal communities.224 The Medical Association for the Prevention of War (MAPW) claimed that the further development of the uranium industry in Australia would only add to the burdens of Aboriginal communities.225

10.178

Several submitters were critical of uranium mining’s social impacts on Aboriginal communities and maintained that monitoring of this dimension is inadequate.226 FOE argued that ‘social impact assessment, consultation and approval processes with traditional owners and affected Aboriginal people is inadequate.’227

10.179

In relation to the monitoring of the social impacts outlined above, the GAC’s view was that such monitoring was lacking, and that:

… the limited social impact monitoring that has occurred has been more a process of documenting devastation caused by development, rather than seeking to ameliorate its effects.228

10.180

The NLC argued that no specific provision has been made for the ongoing monitoring of the extent to which NT uranium mines have a social impact on Traditional Owners and Indigenous communities.229

10.181

To this, the DEH responded that the Aboriginal Project Committee, set up in October 1996 to examine experiences of development in the Kakadu region, had rejected the recommendation of an independent consultant for the ERISS to conduct ongoing social impact assessments.230

10.182

The GAC argued that social impact monitoring must be reflected in the regulatory arrangements for the management of uranium mines. It advocates a statutory role to participate in MSTCs, but the NLC rejected this proposal.231

10.183

The DEH noted that major social impact consideration was included in the Kakadu Regional Social Impact Study (KRSIS), a project undertaken in 1997 that intended to identify the potential social impact on Aboriginal communities of the Kakadu region being developed.232 The NLC suggested that, as a first priority, the Australian Government should act on those recommendations of the KRSIS which have not yet received attention of Government.233

10.184

The GAC was critical of the KRSIS process, instead calling for a new system for assessing social impact. The GAC argued that social impact monitoring and reporting should be conducted independently, in close consultation with the Traditional Owners.234

10.185

The Committee is not clear as to why the KRSIS proposals have not been progressed but has been informed that disengagement by the Traditional Owners may have contributed. The Committee regrets that the GAC chose not to appear before the Committee at its public hearing in Darwin.

10.186

The NLC conceded that services in Jabiru are better because of the presence of the mine, but are still not adequate.235 However, it was also observed that the KRSIS found that ‘whether a mine was next to a large Aboriginal community or 1,000 miles away, most of the social problems were identical.’236 Similarly, APChem argued that social dysfunction is ‘not particular to uranium mining, but is endemic to the mining industry and becomes more noticeable where industrial developments occur in remote areas.’237

10.187

For its part, the uranium industry stated that it seeks to ensure local communities benefit from its presence and Australia’s three operating mines are subject to extensive assessment.238 Existing producers recognised that the viability of local communities is dependent on the sustainability of the mines, and therefore seek to:

 

Consultation practices and processes

10.188

A number of submitters were critical of consultation practices and processes adopted by industry and government. For instance, FOE asserted that mining companies unduly pressure Indigenous communities and use divisive tactics.240 However, one submitter replied that ‘Aboriginal people have been shamelessly used and abused by the anti-development lobby.’241

10.189

The GAC insisted that the key issue with the current process is a lack of a ‘sense of control’ by the Traditional Owners. The GAC was particularly critical of service provision being dependent on mining activity, and called for service provision and social impact monitoring to be separated from mining activity.242

10.190

The GAC was of the view that negotiations should be administered by an independent body and a:

… comprehensive plan for future engagement in processes should be designed, in consultation with Aboriginal people, and implemented before further development occurs.243

10.191

Claims of poor consultation practices were rejected by government and industry, with various examples of proactive and successful consultation being offered by submitters. For example, the DEH noted that Indigenous communities are engaged through the EPBC Act referral, assessment and approval processes:

Indigenous groups have utilised the EPBC Act public comment processes to comment on referrals and environmental assessments. For example, comments were received from Indigenous groups on the Waste Repository proposal in South Australia. Comments on proposed actions are also received in letters to the Minister.244

10.192

Furthermore, the DEH advised that ongoing engagement with Aboriginal communities is facilitated through:

… Aboriginal representation on the Alligator Rivers Region Advisory and Technical Committees, various Minesite Technical Committees, the Gunlom Land Trust rehabilitation program of the South Alligator Valley legacy mining sites and numerous ad hoc consultations.245

10.193

The OSS employs a full-time staff member in Jabiru whose role involves day-to-day communication and engagement with Aboriginal communities, including Traditional Owners.246 The DEH noted successful Traditional Owner involvement in revising guidelines, and the positive working relationship between the SSD and OSS, and Aboriginal communities:

The Supervising Scientist Division (SSD) has developed very successful relationships with the Traditional Owners to the extent that some of them now regularly work in the SSD monitoring program. Recently, the Executive Officer of the Gundjeihmi Aboriginal Corporation stated publicly that the Traditional Owners trusted the Supervising Scientist.247

10.194

In response to criticisms of the uranium mining industry’s—and the minerals industry more generally—alleged history of failure to consult and take Indigenous issues seriously, the MCA argued that whilst this was once an entirely valid criticism, the industry’s performance has now dramatically improved:

I think the criticism of the industry’s performance in that area of a decade and a half ago is quite valid … If you had to pick something that has been a paradigm shift in the operations of the Australian minerals industry, I suspect that would be right up the top. We currently have some 350-plus [mainly Indigenous land use] agreements on foot across 200 mining companies … We have not only proclaimed our respect for rights, cultures, interests and special connections to land and waters but also practised and performed it … The memorandum of understanding that we have with the federal government, signed by three ministers, to move beyond corporate Indigenous employment programs to build sustainable communities beyond the life of the mine is a great platform … it will come from local communities identifying needs and expectations in terms of enterprise facilitation, Indigenous employment and the social fabric of society …248

10.195

Mr Harry Kenyon-Slaney observed that the relationship between ERA and the Gundjeihmi people has improved markedly in recent years and that the company has ‘a very active, ongoing dialogue with the Traditional Owners on a whole range of issues.’249 As noted above, the company has expressed its desire to work with the Traditional Owners to ensure that a sustainable community remains following the closure of the mine.

10.196

In relation to the possible eventual development of Jabiluka, Mr Kenyon-Slaney remarked that whilst Jabiluka remains a very valuable asset for the company:

… it is not going to be developed without the consent of the traditional owners—we are not going to go back to an adversarial, acrimonious environment where we force development on a people who do not want it—and I believe that that is fundamentally the right way to progress. If benefits can be identified that meet everybody’s desires then the project will go ahead.250

10.197

Heathgate Resources described the successful negotiation and consultation process the company undertook with the Indigenous communities in the Beverley area over a period of some nine months:

The Beverley mine was the first mine to start in South Australia after the introduction of the native title federal legislation, and some complementary South Australian legislation was also introduced. At the time we were publishing our environmental impact statement and preparing for the construction of the mine, we had four overlapping native title claims over the area of the mine. We were struck with the problem of how to negotiate and achieve agreements with these groups, because without them the mine would not have gone ahead.

… The consultation process we undertook, after a great deal of thought and discussion with legal advisers and others … was a process whereby we worked out what we thought would be an advantageous program of benefits for the Aboriginal people, which was generally modelled on what had happened in the Northern Territory on Aboriginal land as distinct from native title claimed land.

We called and held … the largest meeting of the Adnyamathanha and Kuyani people ever held in the Flinders Ranges area. There were about 400 people present, and we presented the program to them. The meeting was held under the adjudication of the local member of parliament. We presented an offer and then we proceeded over subsequent months to negotiate with the parties involved.251

10.198

The essential components of the agreement include:

… royalties to the Aboriginal people, the Adnyamathanha people and to each of the claim groups … There are undertakings in respect of employment. Our target is 20 per cent of the site work force and … we are currently at 25 per cent. There are some other undertakings in respect of contracts for the supply of goods and services for the mine. It was, in many respects, a groundbreaking exercise in South Australia …252

10.199

Currently, BHP Billiton has an agreement in place with three Aboriginal claimant groups and these were negotiated at the time of the most recent expansion of the mine in the late 1990s. The agreement deals with how heritage issues are managed. BHP Billiton noted that during those negotiations the company provided the claimants with resources to fund their administrative needs. Annual funding continues to be provided to the groups as an element of the agreement.253

10.200

For the proposed expansion of Olympic Dam, BHP Billiton noted that the company is currently in negotiations with the three native title claimants, none of whom live in the area of the mine. The company reported that it has signed terms of reference for discussions with the claimants and expects negotiations to be successfully concluded within a year. Mr  Richard Yeeles of BHP Billiton explained that:

In fact, we had all the groups up in Olympic Dam a couple of weeks ago with their legal advisers. They wanted an understanding of where this open pit would go and the sort of impact it would have on the land. We showed them that. We showed them where the waste rock dump may go. I must say, the negotiations so far have been conducted in a very cooperative spirit. The groups are obviously interested in the benefits that may be available to their communities from what we would hope to finalise as an Indigenous land use agreement. We are very optimistic that over the next 12 months we will be able to put something in place which will deliver what we need in terms of land access, and also give to the community some sustainable benefits in terms of training and employment programs and other benefits.254

10.201

Jindalee Resources, owners of the Bigrlyi uranium deposit in the NT, also mentioned the importance of the involvement and support of the local Indigenous community to the viability of the company’s project:

The local Aboriginal community is a shareholder in the Bigrlyi uranium mine in the Northern Territory, which we will hopefully bring on in a couple of years time. They have quite a significant chunk of it and they are already doing a bit of contracting for us. This is part of getting the community involved, and those people are enormously on-side.255

10.202

Summit Resources, which is currently prevented from mining its uranium deposits in Queensland, stated that it has the complete support of the Traditional Owners—the Kalkadoon and Walwuwarra Peoples:

We have the traditional owners supporting us at Mt Isa. We have resolved all the native title claim matters with them and we are able to get on with our work.256

10.203

Moreover, Summit explained that the Kalkadoon People supply the company with some equipment for its exploration activities. The agreements the company has in place with the Traditional Owners provides the opportunity for the Aboriginal people to provide the company with services and workers.257

10.204

Junior uranium exploration companies also expressed a keenness to work with and to support Indigenous communities. Nova Energy, owners of the Lake Way and Centipede deposits in WA commented that:

I think the big opportunity that presents itself is probably to have a greater engagement from the Aboriginal community at Wiluna. We have worked a great deal towards encouraging the development of Indigenous businesses. We assist the community in many ways: we put money into trust funds for the community, we part-fund doctors, we help the local school. But all of this is quite challenging in the current gold price environment, because margins are very thin in Australian goldmining these days. A business such as this—a new business that has very high margins—would have much greater capacity for assisting with community development from day one.258

10.205

In relation to capacity, there was some question as to whether Traditional Owners have the educational background to effectively engage in consultation and negotiations.259 The role of the Land Councils was also noted, and there was some suggestion that these bodies may not, in all cases, be constructive in facilitating clear communication between mining companies and the Traditional Owners.260

 

Employment and training opportunities

10.206

The Committee received evidence in relation to employment and training opportunities available to Indigenous communities. The following section provides some background on current employment and training initiatives, details some criticisms relating to perceived inadequacies of such initiatives, and outlines industry’s response.

10.207

In general, mining companies and exploration companies expressed a strong interest in providing employment for Aboriginal people at mine sites. For instance, as a junior exploration company with interests in the NT, Compass Resources indicated its intention to work with the NLC and the local Indigenous communities to provide employment opportunities for the Aboriginal people in the area of its proposed developments.261

10.208

In relation to Indigenous employment at Olympic Dam, BHP Billiton reported that the company has two initiatives: Aboriginal people from the claimant groups are employed at the mine, although not in large numbers, and these people commute from Whyalla; and the company conducts ‘job readiness’ programs:

We bring people in to the site, run them through training programs so that they have tickets to operate heavy equipment—to operate a forklift or a crane—and are therefore available. If they choose to apply for jobs, they are then qualified to apply for them. We put a lot more people through the job readiness programs than actually come back and apply for jobs, but we do have a program to make sure people are in a position to compete in the market for jobs.262

10.209

Heathgate Resources explained that the company’s success in achieving
25 per cent employment for Aboriginal people at the Beverley mine site was due, firstly, to a real commitment by the company to achieve an Indigenous employment outcome. Heathgate also explained that the company initiated a program whereby two Aboriginal liaison officers report directly to the General Manager on matters affecting Aboriginal people in order to ensure that these issues are addressed quickly. In addition, the company conducts quarterly meetings with claimants to allow the Aboriginal communities to communicate issues of concern to the company and for Heathgate to update the communities on the company’s activities. Heathgate also claimed to have made a substantial investment in training.263

10.210

Heathgate Resources explained that the company perceives that the issue of greatest concern to Aboriginal people in the area of the Beverley mine is employment, not royalties:

When we have meetings with the Aboriginal community, they want to know what the employment numbers are. We get more credibility from the Aboriginal people when we can say that we are not 20 per cent, we are 25 per cent. If we are at 25 per cent, we are going to try to go to 30 per cent and to 35 per cent. We are not going to stop at 25 per cent.264

10.211

However, in the NT, the NLC was critical of the allegedly ‘glaring failures’ of ERA in the lack of employment opportunities for Aboriginal people in the area, with few of the Aborigines employed at Ranger coming from the local Mirrar people.265 However, the NTMC noted that of a total staff of 300, ERA employs some 45 Aboriginal people at its operations and noted that:

There have been difficulties in employing local Aboriginal people because the traditional owners in that area did not approve of their people working at the mine and they expressed discomfort with other Aboriginal people coming in from outside the area. However, the company is engaged in discussions with the local people on these issues, and those discussions are ongoing.266

10.212

Mr Harry Kenyon-Slaney noted that ERA is actively involved in a range of employment, educational and social programs for the community in the vicinity of the Ranger mine:

The broader work that we do in the community is very significant. We are actively involved with the local traditional owners on a range of social programs. We have been working with them on a youth centre, Aboriginal employment opportunities and trying to improve opportunities for schooling at years 11 and 12. There are programs in respect of alcohol and management. We work on the ground in the community on these issues constantly, and have done for many years. These are difficult issues that have no immediate solution but they require everyone to participate. We try to do that very actively.267

10.213

The ERA Social and Environmental Report 2005 identifies a real increase in the number of Aboriginal employees in the company, and communicates the company’s undertaking to give greater focus to providing more employment and training opportunities to Aboriginal communities:

The Aboriginal participation rate in the company was 13 per cent, an increase from 10.5 per cent at the end of 2004, but also reflecting higher numbers of overall ERA permanent and fixed-term employees (2005: 305; 2004: 277; 2003: 238). ERA has announced it will make increased Aboriginal employment and training a key objective in 2006.268

10.214

Notwithstanding this marginal improvement, the NLC claimed that such poor outcomes for Aboriginal employment and training must not continue, particularly given successes with Indigenous populations in other parts of Australia and overseas.269 For instance:

… Queensland Mines employed over 200 local Aboriginal people (out of a population of around 800) at Nabarlek between 1980 and 1987 …270

10.215

Mr Jerry Grandey, President of Cameco Corporation, which mines uranium in the Canadian province of Saskatchewan, stated that 80 per cent of the company’s 1 500 employees in the northern part of the province are of Aboriginal descent and 60 per cent are residents of the north. Cameco argued that a key to its success in winning public support for uranium mining has been its efforts at working with Aboriginal people:

… the issues about aboriginal employment, bringing on aboriginal business, creating trucking and mining consultations and catering, and expertise and infrastructure within the aboriginal community are things that we have been working on over the course of about 20 years.271

10.216

Cameco has implemented a number of different strategies to increase Aboriginal employment and training in Saskatchewan, including:

10.217

This last initiative, of supporting Indigenous businesses used by the mining operation, has resulted in over 70 per cent of Cameco’s contracted services being provided by 16 local suppliers, 10 of which are majority owned by aboriginal people.276

10.218

Several submitters highlighted impediments to higher rates of Aboriginal employment in the uranium industry, including low educational attainment and geographical isolation. For instance, BHP Billiton noted that a barrier to employment for Aboriginal people at Olympic Dam is the remoteness of the mine and the decision of many not to live at Roxby Downs.

10.219

The NTMC also observed that mining companies operating in the Territory often want to employ more Aboriginal people, but one of the main impediments to doing so is poor literacy and numeracy among Aboriginal people:

Companies embark on their own bridging programs to get the young adults up to a level of literacy and numeracy such that they can work on a mine site in any capacity. The most obvious component is safety: you must be able to read the safety signs and everything that goes with the safety regime of a mine site. Yes, it is a problem, but the companies are always trying to address that issue in order to get more employment opportunities for the local Aboriginal people.277

10.220

Low educational attainment also impacts on the capacity of Indigenous peoples to take advantage of employment opportunities in the uranium industry. The importance of education was demonstrated by Cameco’s success with aboriginal employment in Canada:

In Canada there has been a very long period of effort towards education in the communities: of making sure that you had maths, science and some engineering introduced to the stage of the school curriculum where you could capture junior high and high school level students and of giving them opportunities and scholarships, of public education programs and of community involvement.278

10.221

For their part, the NLC readily conceded that literacy and numeracy is an important issue, and called for equitable funding for education in remote Aboriginal communities.279

10.222

Despite these challenges, the NLC noted previous examples of successful mining operations which facilitated increased employment and training opportunities for Aboriginal communities. It therefore called for enforceable employment targets, employment and training clauses in mining agreements, and the introduction of Indigenous business support and tax incentives similar to those in place in Saskatchewan.280

10.223

The NTMC, however, observed that the situation in the NT is ‘quite different’ from Cameco’s successes in providing employment for Indigenous people. Whilst Australia should strive to achieve the Canadian outcomes, the NTMC warned against setting specific targets:

I think we should strive to work very closely with the land council and the traditional owners to improve that, but not on a target driven basis, particularly where there are potential penalties. I think the thing to bear in mind is that it has taken us a long time in Canada to achieve those results, and unfortunately it is going to take a long time here. The industry has to strive to get to that point if it can.281

10.224

In relation to the inclusion of employment and training clauses in mining leases, the NTMC responded that these are ‘standard in all agreements. Whether they are native title agreements or land rights agreements, there are always provisions for employment and training.’282

10.225

The Committee recognises some of the complexities associated with these issues, not the least of which is the opposition to Ranger’s continued operation by the Traditional Owners. This in turn makes it difficult for the company to provide employment if the local Aboriginal people are effectively barred from seeking employment with the company. The Committee is sympathetic to the position in which the company finds itself in this respect.

10.226

The Committee is very pleased to note the success that Heathgate Resources has achieved in its employment of Aboriginal people at its Beverley operation in SA. The Committee notes that this outcome was achieved through the company’s commitment to increasing Aboriginal employment and its implementation of a number of specific initiatives, including the employment of Aboriginal liaison officers with direct access to management, and an investment in training.283

10.227

The Committee hopes that Heathgate Resources’ success in Aboriginal employment can be emulated by other companies so that the benefits of mining can be enjoyed by greater numbers of Aboriginal people and their communities nationwide.

10.228

The Committee believes that strategies should be developed to improve industry’s training and employment outcomes at uranium mines in Australia, with consideration given to studying and, if possible, emulating Cameco’s experience in Saskatchewan. The Committee is conscious of the observation by industry and Cameco itself that the success in Saskatchewan took decades to achieve. Nonetheless, the Committee believes that industry, Aboriginal communities and governments should strive to achieve similar outcomes in Australia.

 

Recommendation 7

The Committee recommends that the Australian Government work with industry, Indigenous groups and state/territory governments to develop strategies to improve Indigenous training and employment outcomes at uranium mines, with consideration given to studying and, if possible, emulating the strategies employed by Cameco Corporation and governments in Canada. The Committee further recommends that, where appropriate, mining companies consider employing Aboriginal liaison officers with direct access to management.

To ensure adequate local community consultation, the Committee further recommends that a process be established whereby it and its successor committees be formally given access to new uranium mine sites, with customary powers of inquiry and report to the Parliament. This process should formally provide for affected local governments to nominate a person to liaise with the Committee about any community concerns.

 

Aboriginal Land Rights Act

10.229

The NLC drew the Committee’s attention to the Canadian model of joint ventures between mining companies and Indigenous businesses. Again, the NLC emphasised that:

… we want all of the constraints to really getting us to the table of commercial reality removed from the Land Rights Act so that we can really play on the same landscape as everybody else.284

10.230

When asked whether it agreed with the opposition to new uranium mines by the NT Government, the NLC responded:

Utterly not … That is quite a silly situation for government to get itself into, and the only losers in this are traditional owners and mining companies in the Australian and Territory economies.285

10.231

In terms of increasing the social dividend for Aboriginal people in the NT, the NLC argued that mining agreements be commercially defined and of a commercial nature. To achieve this, the NLC called for the amendments to part four of the Aboriginal Land Rights Act (ALRA), previously agreed to by the four land councils and the NT Government, to be enacted in the Federal Parliament.286 The NLC claimed that the large mining companies support this approach.287

10.232

While noting that there have been no new mines developed on Aboriginal land in the NLC area since the ALRA was introduced, the NTMC noted that the NLC has a ‘very commercial focus’ and that ‘it is easier to get things done.’288 However, the NTMC rejected the argument by the Land Council that amendments are required to part four of the ALRA in order facilitate mining agreements:

Contrary, perhaps, to what Mr Fry said earlier, there is not really a need to change part 4 to facilitate agreements being reached, or to facilitate any terms of those agreements. I do not think the proposed package of reforms that has been put by the land councils or the Northern Territory government does much more than fiddle around the edges. At a fundamental level, the Minerals Council would prefer that the exercise of the veto was up the front rather than at the back end of negotiation, but that is something that we have agreed to disagree on.289

10.233

In addition to seeing the Aboriginal right of veto exercised up front, the NTMC also argued that the division of royalty monies be adjusted so that the monies that currently go to the Aboriginal Benefits Reserve (30 per cent of the total) are instead allocated to the Traditional Owners and others directly affected by mining operations. In this way, the Traditional Owners would receive 60 per cent of royalty monies, with the remaining 40 per cent continuing to be split between the Land Councils.290

10.234

The Committee notes the intention of the Australian Government to introduce changes to the ALRA so as to improve the workability of the legislation for the benefits of mining companies and traditional land owners. 291

 

Conclusions

Regulation

10.235

While the regulation of uranium mining is principally a state and territory government responsibility, the Australian Government’s interests and responsibilities in this area include:

10.236

Criticisms of existing regulatory arrangements were largely directed to the adequacy of provisions for environmental protection from the impacts of uranium mining in the Kakadu National Park and the ARR. Criticisms were also made of the performance of the OSS which, among a number of allegations, was said to have been ‘captured’ by ERA. The OSS provided convincing rebuttals to each of these allegations, as well as to arguments relating to the adequacy of tailings and water management at Ranger.

10.237

The Committee rejects the claim that the regulation of uranium mining in the ARR is inadequate. The owners of the Ranger mine meet some of the most rigorous reporting regimes in Australia and there is extensive formal oversight of its operations. The Ranger operation is monitored and regulated by a range of independent bodies including Australian Government agencies ( OSS, DITR and ASNO), NT Government agencies (particularly DPIFM), and independent review bodies, namely the MSTCs, ARRTC and ARRAC.

10.238

Moreover, the Committee notes that monitoring and research by the OSS since 1978 has concluded that uranium mining operations at Ranger have had no detrimental impact on the Kakadu National Park. This confirms that the regulatory regime governing uranium mining in the ARR has indeed succeeded in protecting the environment from any harmful impacts caused by uranium mining.

10.239

Uranium mining regulation in the ARR has, however, evolved into what appears to be an unduly complex regime, comprised of arrangements underpinned by a range of Commonwealth and Territory legislation. The Committee recognises that the complexity may well have been unavoidable because of the combination of factors, including that: mining is taking place on Aboriginal land; the need to protect the Kakadu National Park; and the special nature of uranium. Nonetheless, if a regulatory framework were to be designed from ‘scratch’ in 2006, it seems unlikely that a similar framework would be developed. The Committee will not recommend specific improvements but suggests that the entire regulatory regime in the NT should be reviewed with a view to consolidation and simplification.

10.240

The Committee notes the GAC’s recommendation to consolidate the provisions of the 17 November 2000 Agreement, the Working Arrangements, Part III of the Commonwealth Atomic Energy Act 1953 and the EPARR Act in order to clarify the responsibilities of the governments and agencies involved in uranium mining activities. The Committee considers that the merits of this proposal should be considered as part of the comprehensive review of NT uranium mining regulation suggested above.

10.241

The Committee recommends that consideration should be given to utilising the expertise of the OSS in assessment and approvals processes for uranium mines generally. Mindful that industry wishes to see any unnecessary duplication across levels of government eliminated, the Committee urges that an expanded role for the OSS not add to what is already a highly regulated industry.

10.242

Groups critical of uranium mining argued that environmental and health oversight functions are not clearly or adequately separated from industry promotion functions in SA and the NT, or indeed at the Federal level. The NT Government stated that following a recent regulatory review, new mechanisms have now been put in place to ensure industry development and regulatory functions are kept separate. No submission was received from the SA Government.

10.243

The Committee is not in a position to judge the veracity of these claims but believes that industry promotion and regulatory/environmental impact assessment functions ought to be clearly separated at all levels of government. The Committee urges the Australian Government to examine this issue and, where necessary, to encourage state governments to rectify any agency-based conflicts of interest and to clearly separate industry promotion and regulatory functions.

10.244

Although the Committee believes there have been clear improvements in environmental regulations relating to mine closure and rehabilitation, some partially rehabilitated former mines continue to present pollution problems. The Australian Government’s recent decision to allocate some additional funding to address this problem is welcome, but the Committee recommends that the Australian Government redouble efforts to completely rehabilitate former uranium mines in the ARR and elsewhere.

Aboriginal communities

10.245

Despite professing concern that Indigenous groups be consulted, environmental groups revealed that, should Traditional Owners approve a mining development, they would still oppose uranium mining. This seems to support the observation made by one submitter who remarked that Aboriginal groups are being used by some ‘no development’ groups to support their opposition to uranium mining. Traditional Owners’ views are clearly not to be respected if they happen to support resource development.

10.246

Notwithstanding this, care must be taken to ensure that uranium mining does not impact negatively on local Aboriginal communities. The Committee is of the view that the social impacts of mining operations must be adequately monitored, and Aboriginal communities and Traditional Owners should have an opportunity to share in the benefits associated with a vibrant minerals industry.

10.247

The Committee is not convinced that social problems are peculiar to uranium mining, or to Jabiru, Ranger and ERA, but rather that the social problems and issues of service provision in Jabiru are common to large Aboriginal communities wherever they are located.

10.248

In relation to employment, the Committee notes impediments to increasing Aboriginal engagement in the uranium industry, including the opposition by some Aboriginal groups and low levels of educational attainment. The Committee sees merit, however, in industry seeking to emulate the examples of mining operations that have succeeded in achieving benefits for Indigenous communities. In particular, the Committee was impressed by the successes of Heathgate Resources at Beverley and Cameco Corporation in Saskatchewan. The Committee strongly urges industry, governments and Indigenous communities themselves to continue to strive to ensure Aboriginal people benefit from uranium mining operations through employment, business and training opportunities.



Footnotes

1

Jindalee Resources Ltd, Submission no. 31, p. 1. Back

2

Senate Uranium Mining and Milling Select Committee, Uranium Mining and Milling in Australia, Parliament of Australia, Canberra, 1997, viewed 17 August 2006, <http://www.aph.gov.au/Senate/committee/uranium_ctte/report/contents.htm> Back

3 Senate Environment, Communications, Information Technology and the Arts References Committee (SECITARC), Jabiluka: The Undermining of Process—Inquiry into the Jabiluka Uranium Mine Project, Parliament of Australia, Canberra, 1999, viewed 17 August 2006, <http://www.aph.gov.au/Senate/committee/ecita_ctte/completed_inquiries/1999-02/jabiluka/report/contents.htm>. Back
4

SECITARC, Regulating the Ranger, Jabiluka, Beverley and Honeymoon uranium mines, Parliament of Australia, Canberra, 2003, viewed 17 August 2006, <http://www.aph.gov.au/Senate/committee/ecita_ctte/completed_inquiries/2002-04/uranium/report/index.htm>. Back

5

H Bachmann, Report of the Independent Review of Reporting Procedures for the SA Uranium Mining Industry, 2002, viewed 18 August 2006, <http://www.heathgateresources.com.au/contentmine.jsp?xcid=62>. Back

6

G Taylor et. al., Review of Environmental Impacts of the Acid In-situ Leach Uranium Mining Process, CSIRO, Melbourne, 2004, p. 1, viewed 12 July 2005, <http://www.environment.sa.gov.au/epa/pdfs/isl_review.pdf> Back

7

SECITARC, Regulating the Ranger, Jabiluka, Beverley and Honeymoon uranium mines, op. cit., pp. 1–20; UIC, Regulation of Australian Uranium Mining, UIC, Melbourne, 2006, viewed 17 August 2006, <http://www.uic.com.au/mineregulation.htm>. Back

8

See: Uranium Industry Section at DITR, ITR Homepage, Australian Government, Canberra , viewed 17 August 2006 , <http://www.industry.gov.au>. Back

9

ibid. Back

10

ibid. Back

11

Mr David Borthwick (DEH), Transcript of Evidence, 10 October 2005, p. 2. See also: DEH, Submission no. 55, p. 5. Back

12

DEH, ibid., p. 24. Back

13

ibid. Back

14

ibid. Back

15

ibid., p. 25. Back

16

ASNO, ASNO website, Australian Government, Canberra, viewed 17 August 2006, <http://www.asno.dfat.gov.au>. Back

17

The Hon Alexander Downer MP, Minister for Foreign Affairs, Submission no. 33, p. 8. Back

18

ibid. Back

19

ibid. Back

20

ibid., p. 9. Back

21

ARPANSA, Submission no. 32, pp. 2–3. Back

22

ibid. Back

23

ARPANSA, Exhibit no. 67, Radiation Protection and Radioactive Waste Management in Mining and Mineral Processing. Back

24

For an overview of state-level arrangements, see: UIC, loc. cit.; and for arrangements in the NT in particular, see: ERA, Submission no. 46, pp. 4-9. Back

25

Mr Gerard Early (DEH), Transcript of Evidence, 10 October 2005 , p. 3. Back

26

ibid. Back

27

ibid., p. 4. Back

28

ibid., p. 14 Back

29

ibid., pp. 4, 7, 14. Back

30

Dr Arthur Johnston (Supervising Scientist, DEH), Transcript of Evidence, 10 October 2005, p. 4. Back

31

Mr Richard Jackson (NT Government), Transcript of Evidence, 24 October 2005, p. 58. Back

32

ibid., p. 59. Back

33

ibid. Back

34

ibid. Back

35

UIC, Submission no. 12, p. 16. Back

36

Dr Malcolm Humphreys (Compass Resources NL), Transcript of Evidence, 16 September 2005, p. 62. See also: Mr Mark Chalmers (Heathgate Resources Pty Ltd), Transcript of Evidence, 19 August 2005, p. 96. Back

37

Deep Yellow Ltd, Submission no. 16, p. 2. See also: Cameco Corporation, Submission no. 43, p. 1. Back

38

Dr Malcolm Humphreys, loc. cit. Back

39

ibid. Back

40

Paladin Resources Ltd, Submission no. 47, p. 7. Back

41

Heathgate Resources Pty Ltd, Submission no. 49, p. 3. See also: Mr Cedric Horn (Southern Gold Ltd), Transcript of Evidence, 19 August 2005, p. 18. Back

42

APChem, Submission no. 38, p. 7. Back

43

CFMEU Mining and Energy, Submission no. 26, p. 4; Compass Resources NL, Submission no. 6, p. 2. Back

44

AMEC, Submission no. 20, p. 4 Back

45

UIC, op. cit., p. 11. Back

46

See for example: ANA, Submission no. 19, p. 4; ibid., p. 16; ERA, op. cit., pp. 5–6; Paladin Resources Ltd, op. cit., p. 2; Nova Energy Ltd, Submission no. 50, p. 9. Back

47

Mr Mark Chalmers, loc. cit. Back

48

Compass Resources NL, op. cit., p. 3. Back

49

ANA, loc. cit. Back

50

ibid., pp. 3–4. Back

51

Mr Richard Pearce (Nova Energy Ltd), Transcript of Evidence, 23 September 2005, p. 77. Back

52

Mr Harry Kenyon-Slaney (ERA), Transcript of Evidence, 24 October 2005, p. 51. See also: ERA, Submission no. 46, p. 5; ERA, Exhibit no. 76, op. cit., pp. 6–7. Back

53

ibid.Back

54

ibid., p. 48. Back

55

ERA, Exhibit no. 76, What is it really like to operate a large uranium mine in Australia?, p. 6. Back

56

Mr Ian Hore-Lacy (UIC), Transcript of Evidence, 19 August 2005, p. 91. Back

57

UIC, loc. cit. Back

58

Name withheld, Submission no. 25, p. 1. Back

59

Ms Kezia Purick (NTMC), Transcript of Evidence, 24 October 2005, p. 33. Back

60

op. cit., pp. 4, 16. Back

61

Compass Resources NL, loc. cit. Back

62

Mr Ian Hore-Lacy, op. cit., p. 89. Back

63

MCA, Submission no. 36, p. 12. Back

64

Paladin Resources Ltd, op. cit., p. 3. Back

65

Ms Rita Warleigh, Submission no. 83, p. 2. See also: Ms Stephanie Riddel, Submission no. 80, p. 1. Back

66

See for example: FOE, Submission no. 52, p. 9; Mr Justin Tutty, Submission no. 41, p. 7; GAC, Submission no. 44, p. 26. Back

67

FOE, op. cit., p. 10. Back

68

Mr Dave Sweeney (ACF), Transcript of Evidence, 19 August 2005, p. 79. Back

69

ACF, Submission no. 48, p. 25. See also: Mr Justin Tutty, op. cit., p. 9; GAC, op. cit., p. 5. Back

70

Areva Group, Submission no. 49, p. 16. Back

71

ibid. Back

72

GAC, op. cit., pp. 26–35. Back

73

ibid., pp. 26–34. Back

74

ibid., pp. 33–4. Back

75

DEH, Submission no. 55.2, p. 2. Back

76

ibid. Back

77

GAC, op. cit., p. 34. Back

78

DEH, Submission no. 55.2, loc. cit. Back

79

GAC, loc. cit. Back

80

DEH, Submission no. 55.2, loc. cit. Back

81

GAC, loc. cit. Back

82

DEH, Submission no. 55.2, p. 3. Back

83

DEH, Submission no. 55.2, loc. cit. Back

84

loc. cit. Back

85

DEH, Submission no. 55.2, loc. cit.Back

86

DEH, Submission no. 55.2, loc. cit. Back

87

loc. cit. Back

88

DEH, Submission no. 55.2, loc. cit. Back

89

loc. cit. Back

90

ACF, op. cit., p. 29. Back

91

ERA, Exhibit no. 76, op. cit., p. 6. Back

92

NTMC, Submission no. 51, p. 7; ibid., p. 7. Back

93

NTMC, ibid. Back

94

Ms Janet Marsh, Submission no. 2, p. 1. Back

95

Mr Daniel Taylor, Submission no. 85, p. 10. Back

96

GAC, op. cit., p. 36–37. Back

97

ibid., p. 43. Back

98

DEH, Submission no. 55.2, pp. 4–6. Back

99

GAC, op. cit., p. 46. Back

100

DEH, Submission no. 55.2, p. 16. Back

101

NLC, Submission no. 78, p. 10. Back

102

APChem, loc. cit.; FOE, op. cit., p. 10. Back

103

FOE, ibid., pp. 9–10. Back

104

ibid., p. 9. Back

105

GAC, op. cit., pp. 35–6. Back

106

DEH, Submission no. 55.1, p. 4. Back

107

ibid. Back

108

ACF, op. cit., pp. 27, 28; G. M. Mudd, Exhibit no. 14, Uranium mill tailings wastes in Australia: past, present and future management, p. 6; G. M. Mudd, Exhibit no. 15, Remediation of uranium mill tailings wastes in Australia, pp. 4–5; G. M. Mudd, Exhibit no. 21, A compendium of radon data for the rehabilitation of Australian uranium projects, p. 9. Back

109

Mr Dave Sweeney, op. cit., p. 78. Back

110

Mr Peter Robertson (ECNT), Transcript of Evidence, 24 October 2005, pp. 1–2. Back

111

ibid .Back

112

Mr John Schindler, Submission no. 10, p. 2. Back

113

Crouch et al, Rehabilitation of Uranium Mine Waste Sites in Australia, p. 5, viewed 24 July 2006 , <http://www.arpansa.gov.au/pubs/radwaste/frenchpaper.pdf>. Back

114

ibid. Back

115

Mr Dave Sweeney, op. cit., p. 86. Back

116

Dr Malcolm Humphreys , op. cit., p. 66. Back

117

ibid. Back

118

Dr Arthur Johnston, op. cit., p. 7. Back

119

AMEC, op. cit., p. 6. Back

120

Mr Peter Cochrane (DEH), Transcript of Evidence, 10 October 2005, p. 10. Back

121

The Hon Greg Hunt MP, Parliamentary Secretary to the Minister for the Environment and Heritage, Media Release: Old mining leases to become part of Kakadu, Australian Government, Canberra, 5 June 2006, viewed 17 August 2006, <http://www.deh.gov.au/minister/ps/2006/psmr05jun206.html>. Back

122

ACF, op. cit., p. 29. Back

123

ERA, Exhibit no. 76, , op. cit., p. 7. Back

124

ACF, op. cit., pp. 21–2. Back

125

Mr Richard Jackson, op. cit., p. 61. Back

126

ibid. Back

127

DEH, Submission no. 55, p. 16. Back

128

Mr Harry Kenyon-Slaney, op. cit., p. 52. Back

129

ibid., p. 51 Back

130

ibid., p. 55. Back

131

ibid., p. 56. Back

132

Mr Peter Robertson, op. cit., p. 2. Back

133

ibid. Back

134

ACF, op. cit., pp. 18–21; Mr Justin Tutty, op. cit., p. 5 ; FOE, loc. cit. Back

135

ACF, ibid., p. 21. See also: Mr Justin Tutty, ibid., p. 7. Back

136

Mr Peter Robertson, op. cit., p. 3. Back

137

Mr Norman Fry (NLC), Transcript of Evidence, 24 October 2005, p. 21. Back

138

Mr Peter Cochrane, op. cit., p. 8. Back

139

ibid. Back

140

Dr Arthur Johnston, op. cit., p. 12. Back

141

Cited in DEH, Submission no. 55.1, p 7. Back

142

Mr Harry Kenyon-Slaney, op. cit., p. 47. Back

143

Mr Dave Sweeney , op. cit., p. 78. Back

144

Mr Peter Robertson, op. cit., pp. 2–3. Back

145

ibid., p. 2. Back

146

Dr Arthur Johnston, op. cit., p. 6 Back

147

ibid. Back

148

DEH, Submission no. 55.1, p. 3. Back

149

Mr Harry Kenyon-Slaney, op. cit., p. 53. Back

150

See for example: ERA, Social and Environmental Report, ERA, Darwin, 2005, viewed 10 July 2006, <http://www.energyres.com.au/corporate/ERA_SE_Rep05ART.pdf>. Back

151

Supervising Scientist, Annual Report 2004–05, Department of the Environment and Heritage, Australian Government, Canberra, 2005, pp. 34–5. Back

152

Mr Richard Jackson, op. cit., p. 65. Back

153

Dr Arthur Johnston, op. cit., p. 6. Back

154

DEH, Submission no. 55.1, p. 4. Back

155

ibid. Back

156

Mr David Noonan (ACF), Transcript of Evidence, 19 August 2005, p. 78. Back

157

FOE, op. cit., p. 15. Back

158

G. M. Mudd, Exhibit no. 13, Mound springs of the Great Artesian Basin in South Australia: a case study from Olympic Dam, p. 474; ACF, op. cit., pp. 8–9; FOE, op. cit., p. 10. Back

159

Dr Gavin Mudd , Submission no. 27, p. 8. See also: G. M. Mudd, Exhibit no. 14, loc. cit. Back

160

ACF, op. cit., p. 7. Back

161

Dr Gavin Mudd, Submission no. 27, p. 8; ACF, op. cit., p. 7. Back

162

ACF, ibid., pp. 7, 8. See also: Dr Gavin Mudd, ibid. Back

163

Dr Gavin Mudd, ibid., p. 4. Back

164

ACF, op. cit., p. 9. Back

165

ibid., pp. 7, 8. Back

166

BHP Billiton Ltd, Exhibit no. 78, Presentation by DrRogerHiggins, p. 10. Back

167

Dr Roger Higgins (BHP Billiton Ltd), Transcript of Evidence, 2 November 2005, pp. 10–11. Back

168

ibid., p. 11. Back

169

Mr Gerard Early, op. cit., p. 21. Back

170

Dr Gavin Mudd, Submission no. 27, p. 8; Mr John Schindler, Submission no. 10, p. 1; Back

171

Dr Gavin Mudd, ibid.. See also: G. M. Mudd, Exhibit no. 16, Critical review of acid in situ leach uranium mining: 1. USA and Australia, pp. 401–2; G. M. Mudd, Exhibit no. 17, Critical review of acid in situ leach uranium mining: 2. Soviet Block and Asia, pp. 414–5; G. M. Mudd, Exhibit no. 19, Environmental hydrogeology of in situ leach uranium mining in Australia, pp. 56–7; G. M. Mudd, Exhibit no. 20, Uranium mill tailings in the Pine Creek Geosyncline, northern Australia: past, present and future hydrogeological impacts, p. 839. Back

172

FOE, op. cit., p. 8; Mr John Schindler, op. cit., p. 1. Back

173

Dr Gavin Mudd, Submission no. 27, p. 8. See also: G. M. Mudd, Exhibit no. 16,loc. cit.; G. M. Mudd, Exhibit no. 17, loc. cit.; G. M. Mudd, Exhibit no. 19, loc. cit.; G. M. Mudd, loc. cit. Back

174

Dr Gavin Mudd, Transcript of Evidence, 19 August 2005, p. 46. Back

175

G Taylor et. al., loc. cit. Back

176

ibid., pp. iii, 47. Back

177

ibid., p. 44. Back

178

ibid., p. 23. See also: Mr Mark Chalmers, op. cit., pp. 98–99. Back

179

Dr Gavin Mudd, Transcript of Evidence, op. cit., p. 47. Back

180

ibid., p. 48. Back

181

Mr Mark Chalmers, loc. cit. Back

182

ACF, op. cit., pp. 21–3. Back

183

ibid., p. 22. Back

184

DEH, Submission no. 55.1, p. 4. Back

185

ibid. Back

186

ibid. Back

187

ACF, op. cit., p. 22. Back

188

DEH, Submission no. 55.1, loc. cit. Back

189

ibid. Back

190

ibid. Back

191

ACF, loc. cit. Back

192

DEH, Submission no. 55.1, pp. 4–5. Back

193

ibid. Back

194

ibid., p. 5. Back

195

ibid. Back

196

ACF, loc. cit. Back

197

DEH, Submission no. 55.1, loc. cit. Back

198

ibid. Back

199

ACF, loc. cit. Back

200

DEH, Submission no. 55.1, loc. cit. Back

201

ibid. Back

202

ACF, loc. cit. Back

203

DEH, Submission no. 55.1, loc. cit. Back

204

ibid. Back

205

ACF, op. cit. , p. 23. Back

206

DEH, Submission no. 55.1, loc. cit. Back

207

ACF, loc. cit. Back

208

DEH, Submission no. 55.1, p. 6. Back

209

Dr Arthur Johnston, op. cit., p. 7. Back

210

Ms Kezia Purick, op. cit., p. 33. Back

211

ACF, op. cit., p. 29; GAC, op. cit., pp. 33–4. Back

212

Mr Peter Robertson, op. cit., p. 7. Back

213

ACF, op. cit., p. 22. Back

214

Dr Arthur Johnston, op. cit., pp. 12–13. Back

215

Mr Keith Tayler (NT Government), Transcript of Evidence, 24 October 2005, pp. 62–64. Back

216

Mr Richard Jackson, op. cit., p. 60. Back

217

Dr  Gavin  Mudd, Submission no. 27, p. 14. Back

218

Dr Gavin Mudd, Transcript of Evidence, op. cit., pp. 43–44. Back

219

Mr Peter Robertson, op. cit., p. 7. Back

220

Mr Richard Jackson, op. cit., p. 66. Back

221

Mr Peter Robertson, op. cit., p. 1. Back

222

APChem, op. cit., p. 6. Back

223

NLC, op. cit., p. 7. Back

224

GAC, op. cit., pp. 48-9. Back

225

MAPW (WA Branch), Submission no. 8, p. 2. Back

226

See for example: GAC, op. cit., p. 49; Miss Michaela Stubbs (FOE), Transcript of Evidence, 19 August 2005, p. 58; ACF, op. cit., p. 21. Back

227

Miss Michaela Stubbs, ibid. Back

228

GAC, ibid. Back

229

NLC, op. cit., p. 7. Back

230

DEH, Submission no. 55.1, p. 6. Back

231

GAC, op. cit., p. 57. Back

232

DEH, Submission no. 55, p. 22; Bob Collins, Kakadu Region Social Impact Study—Community Report, KRSIS Implementation Team, Darwin, 2000, p. 1, viewed 20 August 2006, <http://www.deh.gov.au/ssd/publications/krsis-reports/impact-study/pubs/krsis-report.pdf>. Back

233

Mr Norman Fry, op. cit., p. 20. Back

234

GAC, op. cit., pp. 32, 47–9. Back

235

Mr Norman Fry, op. cit., p. 27. Back

236

ibid. Back

237

APChem, loc. cit. Back

238

UIC, Submission no. 12, p. 44. Back

239

ibid. Back

240

FOE, op. cit., p. 16. Back

241

Name withheld, Submission no. 25, p. 1. Back

242

GAC, op. cit., p. 49, 54. Back

243

ibid., p. 49. Back

244

DEH, Submission no. 55, p. 21. Back

245

ibid., p. 22. Back

246

DEH, Submission no. 55.1, p. 6. Back

247

ibid. Back

248

Mr Mitch Hooke (MCA), Transcript of Evidence, 5 September 2005, p. 32 Back

249

Mr Harry Kenyon-Slaney, op. cit., p. 55. Back

250

ibid., p. 56. Back

251

Mr David Brunt (Heathgate Resources), Transcript of Evidence, 19 August 2005, p. 99. Back

252

ibid., p. 100. Back

253

Mr Richard Yeeles (BHP Billiton Ltd), Transcript of Evidence, 2 November 2005, pp. 18. Back

254

ibid., p. 17. Back

255

Mr Donald Kennedy (Jindalee Resources Ltd), Transcript of Evidence, 23 September 2005, p. 58. Back

256

Mr Alan Eggers (Summit Resources Ltd), Transcript of Evidence, 3 November 2005, p. 6. Back

257

ibid., p. 11. Back

258

Dr Timothy Sugden (Nova Energy Ltd), Transcript of Evidence, 23 September 2005, p. 80. Back

259

Mr James Pratt (Deep Yellow Ltd), Transcript of Evidence, 23 September 2005, pp. 84–85. Back

260

ibid. Back

261

Dr Malcolm Humphreys, op. cit., p. 66. Back

262

Mr Richard Yeeles, op. cit., p. 18. Back

263

Mr Mark Chalmers, op. cit., p. 100. Back

264

ibid., p. 102. Back

265

Mr Norman Fry, op. cit., p. 20. Back

266

Ms Kezia Purick, op. cit., pp. 32–33. Back

267

Mr Harry Kenyon-Slaney, op. cit., p. 55. Back

268

ERA, Social and Environmental Report 2005, ERA, Darwin, 2005, p. 10, viewed 7 August 2006 <http://www.energyres.com.au/corporate/ERA_SE_Rep05ART.pdf>. Back

269

NLC, op. cit., p. 8. Back

270

ibid. Back

271

Mr Jerry Grandey (Cameco Corporation), Transcript of Evidence, 11 August 2005, p. 2. Back

272

Cameco Corporation, Exhibit no. 69, Speech presented by MrJamieMcIntyre, p. 3; Cameco Corporation, Exhibit no. 70, Speech presented by Chief Harry Cook, p. 19. Back

273

Cameco Corporation, Exhibit no. 69, ibid., p. 4; Cameco Corporation, Exhibit no. 70, ibid., p. 14. Back

274

Cameco Corporation, Exhibit no. 69, ibid.Back

275

ibid. Back

276

ibid., p. 5; Cameco Corporation, Exhibit no. 70, op. cit., p. 9. Back

277

Ms Kezia Purick, op. cit., p. 44. Back

278

Mr Jerry Grandey, op. cit., p. 6. Back

279

Mr John Daly (NLC), Transcript of Evidence, 24 October 2005, p. 26; Mr Norman Fry, op. cit., p. 29. Back

280

NLC, op. cit., p. 9. Back

281

Dr Ron Matthews (NTMC), Transcript of Evidence, 24 October 2005, p. 44. Back

282

Mr Neville Henwood (NTMC), Transcript of Evidence, 24 October 2005, p. 43. Back

283

Mr Mark Chalmers, op. cit., p. 100. Back

284

Mr Norman Fry, op. cit., p. 22. Back

285

ibid., p. 21. Back

286

ibid., p. 20; NLC, Submission no. 78.1, p. 4. Back

287

Mr Norman Fry, ibid., p. 28. Back

288

Mr Neville Henwood, op. cit., p. 37. Back

289

ibid., p. 38. Back

290

ibid., p. 41. Back

291

NLC, Transcript of Evidence, 24 October 2005, pp. 20-29. Back


Print Chapter 10 (PDF 317KB) < - Report Home < - Chapter 9  : Chapter 11 - >

Back to top