Managing Australia's World Heritage
CHAPTER 7: GOVERNMENT FUNDING OF WORLD HERITAGE AREAS
Introduction
7.1 World heritage areas require funding for maintenance, development,
conservation, presentation, and rehabilitation. There was agreement among
witnesses to the inquiry that funding needs should be established with
reference to detailed, agreed management plans for each area. DEST's policy
on this matter is that:
... with each of the states, we would have a management plan in place
for the property and the funding agreement between the Commonwealth and
the state would flow from that management plan and be for the life of
that management plan. [1]
The Tasmanian Government supported statutory management plans as the
basis for assessing the needs of world heritage areas. [2]
So too did the Western Australian Government. It stated that it would
finalise a funding agreement with the Commonwealth once management plans
for Shark Bay were complete and could be used to calculate the costs of
implementation. [3] Other groups
calling for this approach and its use in reaching funding agreements between
the Commonwealth and States included the Conservation Council of Western
Australia, the Tasmanian Wilderness World Heritage Area Consultative Committee
(TWWHACC), and the South Australian Farmers Federation. [4]
7.2 Just as Australia's 11 world heritage areas are very different from
each other, so too are the funding needs associated with their management
as required by the World Heritage Convention. [5]
As the WTMA pointed out, 'there is no case for a simplistic formula approach
based on area, number of visitors ... a small and threatened area could
have greater funding needs than a large area where threats are minimal'.
[6] On the basis of their experience,
the Tasmanian Government and the TWWHACC detailed a number of factors
that affect the level of expenditure that is needed for world heritage
management. They include:
- the number of significant features to be protected and the complexity
of the research and management required for this - for example, the
Tasmanian Wilderness meets all the natural criteria for world heritage
listing and three of the cultural criteria, which is more than in most
other Australian world heritage areas;
- the extent to which the area is to be presented and the acceptable
level of change permitted for presentation purposes;
- the size of the area -the Great Barrier Reef world heritage area is
bigger than Tasmania and Victoria put together and the Tasmanian Wilderness
covers almost 1.4 million hectares compared with Lord Howe Island with
an area of 1540 hectares;
- the range of topographic, soil and climatic conditions, which influence
the range of habitats in the area - the latter factor is recognised
by the Commonwealth Grants Commission in its use of species richness
as a measure of the impact of the physical environment on the funding
needs for national parks; [7]
- the fragility of the area that is being protected;
- the number of visitors;
- the number of major access points;
- external influences such as adjoining land use;
- problems associated with fire management;
- the demands made by the range and type of recreational activities
undertaken - for example, there are 1,000 kms of walking trails to maintain
in the Tasmanian Wilderness;
- the demands made by using the area for activities unrelated to its
world heritage status; and
- the remoteness of, and difficulty of access to and within, the property.
[8]
7.3 Funds for the ongoing management of world heritage areas come from
several sources. Over the years, the Commonwealth and State Governments
have provided the bulk of the funds for most world heritage areas, and
continue to do so. These funds have been supplemented in more recent times
by the introduction of levies on visitors and other beneficiaries of the
areas. In the face of dwindling budgets and larger demands for establishing
and maintaining protected areas, new sources of funds for world heritage
areas are also being sought.
The Commonwealth's responsibilities for funding
7.4 The Commonwealth has a responsibility under the Convention to ensure
that, as far as possible, appropriate financial measures are taken to
protect the world heritage areas in Australia. The Department of Finance
put this interpretation on the Commonwealth's responsibilities under the
World Heritage Convention:
As a signatory to the World Heritage Convention, the Commonwealth Government
on behalf of Australia has entered into certain obligations to ensure
protection of inscribed world heritage areas. Part of these obligations
require[s] provision of adequate levels of funding to maintain, promote
and where possible, enhance the integrity of each site. [9]
In the view of the Department, the obligations 'initially fall on the
Commonwealth as signatory to the Convention'. [10]
The New South Wales Government contended that the Commonwealth's 'ultimate
responsibility for World Heritage preservation incorporates a financial
responsibility' for, among other things, the management of that world
heritage. [11] The Western Australian
Government agreed. [12]
7.5 In cases where a State fails to deal adequately with its world heritage
areas, the ultimate responsibility for these properties lies with the
Commonwealth. Legal advice from the Attorney-General's Department, cited
by DEST, makes clear that:
... if there is a failure to implement commitments under the World Heritage
Convention (either at the Commonwealth or State level) it is the Commonwealth,
as representative for Australia for international purposes, which will
be responsible for a breach of the Convention. If there is a shortfall
in funding necessary to implement Australia's obligations under the Convention,
then the Commonwealth will not be able to excuse a breach of its international
obligations on the a basis that the constituent States of Australia have
not provided the relevant funding. [13]
7.6 In addition to the Commonwealth's international obligations, it is
also possible to argue on equity grounds, as the Royal Australasian Ornithological
Union did, that the Commonwealth, rather than other levels of government,
should bear the prime responsibility for providing adequate funding for
world heritage areas:
This is because it is not justifiable for the costs associated with World
Heritage listing to be carried by a single State when the country as a
whole benefits from the World Heritage listing and the prestige associated
with the listing. [14]
7.7 As described in Chapter 1, the arrangements
for world heritage management and funding vary from site to site. The
Commonwealth's role ranges from being wholly responsible for the Uluru-Kata
Tjuta and Kakadu world heritage areas to making only minor contributions
in the case of some of the State-managed areas, such as Fraser Island,
Shark Bay and Lord Howe Island. Yet others, such as the Great Barrier
Reef and Tasmanian Wilderness world heritage areas, receive considerable
funds from both the Commonwealth and State Governments. Information about
the funding of the 11 Australian world heritage areas is provided in Table
7.1.
Table 7.1Funding to Australia's World Heritage Areas
|
|
Environment portfolio |
|
|
|
Properties |
Year(s) of listing |
Funds to 1994-95a |
Expenditure 1995-96b |
Estimated expenditure
c1996-97 |
Commonwealth Dept of Tourism fundsd |
State funding |
Funds from cost recovery |
Willandra Lakes |
1981 |
$749 708 |
$122 375 |
Not yet known |
|
$377 000 in 1993-94
from NPWS funding
$530 000 in 1994-95
for Mungo NP
$350 000 since 1981
from Dept. of Land and
Water Conservatione |
$42 882 in 1994-95
from Mungo NPe |
Great Barrier Reef |
1981 |
$132 182 238 |
$16 633 000f
(net cost: $15 086 000) |
$18 600 000f
(net cost: $14 600 000) |
$39 424 in 1993-94
Sites of National Tourism
Significance - moorings in
GBRMP
$48 015 in 1993-94
Regional Tourism Development
Program - Tropical Island Coast
Tourism Strategy
$43 900 in 1993-94
National Ecotourism Program -
study on recreational scuba
diving in marine protected areas
and a study on the status of
fringing reefs at Brampton Island |
$23 783 714
1981-82 to 1994-95g |
$3 699 000 in 1993-94
$4 485 000 in 1994-95
GBRMPA cost recovery from
Environmental Management
Charge, Permit Application
Assessment Fee, External Services
Section, Industry/DEST funded
projects, Aquarium Revenue,
Interest, Educational/publicity
materialh |
Kakadu NP |
1981, 1987, 1992 |
$112 675 699 |
$12 480 000f
(net cost: $9 011 000)i |
$11 812 000f |
$40 000 in 1993-94
National Ecotourism Program -
CSIRO for monitoring the effect
of boat tours |
|
$2 562 000 in 1995-96
Park use feesj |
Lord Howe Island |
1982 |
$494 788 |
$60 000 |
Not yet known |
|
$864 597 in 1994-95
NSW Government
subsidies provided to
for electricity, hospital
and public works.
The bulk of the funding
comes from Lord Howe
Island commercial
business.e |
$136 000 in 1994-95
from charge on tourists prior to
departure. Some of the income from
departure tax, and sales of alcohol
and Kentia palm seeds are used for
world heritage management
(unknown amount).e |
Tasmanian Wilderness |
1982, 1989 |
$48 046 358 |
$5 177 000 |
$5 260 000 |
$8 000 in 1993-94
Sites of National Tourism
Significance - tour operator
training at Gordon River
$46 300 in 1993-94
National Ecotourism Program -
Ecological Sanitation Strategies |
$13 922 000
1987-88 to 1994-95g |
|
CERRA |
1986, 1994 |
$1 420 000 |
$175 000 |
Not yet known |
$15 000 in 1992-93
$13 400 in 1993-94
Forest Ecotourism Program -
Walk Interpretation in Washpool
NP & Gibraltar Range NP and
Coffs Harbour/New England
Forest Wildlife Research
$230 000 in 1993-94
Regional Tourism Development
Program - North Coast Regional
Ecotourism Plan |
NSW
$1 685 000 in 1993-94
$2 018 000 in 1994-95
Expenditure on world
heritage areas estimates
only. Includes recurrent
expenditure, resource
package allocation,
capital works and
salariese
QLD
$846 650 in 1993-94
$859 100 in 1994-95
Includes wages,
operations and state capital worksk |
$405 000 in 1994-95
for Dorrigo Rainforest Centre
$57 000 in 1994-95
for tour operator takings, cabins,
camping and entry feese |
Uluru-Kata Tjuta |
1987, 1994 |
$38 166 284 |
$7 141 000f
(net cost: $3 961 000)i |
$5 530 000f |
|
|
$3 065 000 in 1995-96
Park use feesg |
Wet Tropics |
1988 |
$26 000 000 |
$4 060 000 |
$2 825 000 |
$32 000 in 1993-94
Forest Ecotourism Program -
Bare Hill Aboriginal Rock Art
Preservation & Presentation
and Aboriginal Walking Trail,
Goldsborough Valley
$10 000 in 1993-94
Sites of National Significance -
Boulders Scenic Reserve
$266 800 in 1993-94
Regional Tourism Development
Program - Cape York Peninsula
Tourism Strategy, Injinoo
Tourism Strategy and Cairns
Region Tourism Strategy
$100 000 in 1993-94
National Ecotourism Program -
Ecotourism Implementation
Strategy and Australian Centre
for Tropical Freshwater Research |
$32 460 761
1990-91 to 1994-95g |
|
Shark Bay |
1991 |
$1 956 608 |
$169 000 |
Not yet known |
$34 000 in 1993-94
Sites of National Tourism
Significance - interpretation
facilities at Hamelin Pool and
for information video and panels
at Monkey Mia Reserve |
$861 400 in 1990-91-
1994-95
in consolidated funds
$15 000 in 1992-93-
1994-95
for management plan
preparation
$79 100 in 1993-94-
1994-95
for biological survey,
threatened species
research, recovery plans
$500 000 in 1994-95-
1996-97
for `Project Eden: feral
animal control,
reintroduction of
threatened species on
Peron Peninsulal |
$300 000 per annum
Monkey Mia Reserve feesl |
Fraser Island |
1992 |
$300 700 |
$317 500 |
Not yet known |
|
$10 800 000
1991-92 to 1994-95
The Great Sandy
Region Management
Plan has been allocated:
$4 700 000 in 1995-96
$5 200 000 in 1996-97
$5 800 000 in 1997-98k |
|
Fossil Mammal Sites |
1994 |
$213 233 |
$170 000 |
Not yet known |
$56 000 in 1993-94
Sites of National Tourism
Significance - Bat Cave video
system at Naracoorte Caves
$200 000 in 1993-94
Regional Tourism Development
Program - Mount Isa Riversleigh
Visitors Centre |
Riversleigh, QLD
$363 000 in 1993-94
$619 000 in 1994-95
This is expenditure for
Lawn Hill NP which
can not be separated
from Riversleighk |
|
Sources:
-
Nicholls, W. and King, D., Consistent Management
Arrangements, paper presented at AIUCN workshop, Richmond, NSW, 7-9
August 1995.
-
Department of the Environment, Sport and
Territories, letter dated 25 August 1996; Portfolio Budget Statements
1996-97: Environment, Sport and Territories Portfolio, Budget related
paper no. 15, p 6.
-
Portfolio Budget Statements 1996-97: Environment,
Sport and Territories Portfolio, Budget related paper no. 15, p 6;
Department of the Environment, Sport and Territories, submission (number
91), pp 1-2. The total funding for those world heritage properties
for which funds have still to be allocated is $1 965 000, part of
which will go towards meeting the Commonwealth's commitment to to
the Tasmanian Government for the Tasmanian world heritage area.
-
Department of Tourism, submission (number
68), appendix D.
-
New South Wales Government, exhibit (number
2).
-
Includes revenue from non-Budget sources.
-
Department of the Environment, Sport and
Territories, submission (number 62), attachment J.
-
The Great Barrier Reef Marine Park Authority,
submission (number 59), p 13; Annual Report 1994-95, pp 115, 119.
-
Australian Nature Conservation Agency, submission
(number 90), p 1.
-
Australian Nature Conservation Agency, submission
(number 37), p 22.
-
Queensland Government, submission (number
47), pp 4-5.
-
Western Australian Government, submission
(number 56), p 7.
7.8 In addition to funds from Commonwealth and State conservation departments
or agencies which are responsible for world heritage, smaller sums of
money were forthcoming from other departments under the previous Government.
Labour market programs, such as the Local Environmental Action Program
(LEAP) and the Regional Environmental Employment Program (REEP), were
run in some world heritage areas. [15]
The then Commonwealth Department of Tourism made grants for world heritage
area management through its programs for Sites of National Tourism Significance
(directed at sites under pressure or emerging pressures), the National
Ecotourism Program (set up under the National Ecotourism Strategy with
$10 million to spend over four years on research, planning and infrastructure
up to $250 000), the Forest Ecotourism Program (set up under the Forest
Policy Statement), and the Regional Tourism Development Program (for building
new developments or promoting new areas). [16]
Other sources of funds were grant programs administered by the Australian
Heritage Commission and ANCA. Commonwealth-funded research institutions,
such as the CSIRO, the Australian Institute of Marine Science, and some
of the Cooperative Research Centres, also expended funds in world heritage
areas on projects that assist management.
7.9 As at September 1996, full information was not available about the
provision by the new Government of funds of the type listed in the previous
paragraph. However, the Minister for Industry, Science and Tourism has
announced that $10 million will be spent over two years to develop new
tourism products and facilities in rural and regional areas. [17]
Shared funding responsibilities between the Commonwealth and States
Principles
7.10 Although the Department of Finance noted the responsibility of the
Commonwealth under the Convention, it did not consider that this necessarily
extended to the provision of all the resources necessary to manage and
protect world heritage areas:
... in the Australian Federal system, Commonwealth responsibility does
not necessarily extend to actual implementation of commitments under a
convention. Prime responsibility for on-the-ground activities to implement
a convention lies with the States. In this case, the Commonwealth's role
should be to focus on providing the States with broad-level advice and
assistance to ensure they can adequately discharge that responsibility.
[18]
The implications of this division of responsibilities between the Commonwealth
and the States is that the Commonwealth and State Governments have been
required to develop and establish collaborative arrangements' which cover,
among other matters, 'agreement as to the budget required to implement
management priorities'. [19]
7.11 DEST, which is responsible for disbursing Commonwealth funds for
world heritage areas, maintained that:
There has been general agreement between Commonwealth and State Governments
that it is primarily a State Government responsibility to fund the basic
level of management of those World Heritage Areas managed by State agencies.
Costs of assessment, nomination and subsequent structural adjustment and
compensation are usually borne jointly by the Commonwealth and relevant
State or Territory Governments. Costs of visitor presentation, interpretation
and damage mitigation are likewise jointly borne by Commonwealth and State
Governments. A major focus for Commonwealth Government assistance for
State-managed World Heritage Areas has been the provision of resources
for strengthening management and improving interpretation and visitor
facilities. [20]
At a public hearing, the officers of the Department expanded on departmental
views:
In essence, the Commonwealth's responsibility is to contribute to raising
the standard of management once a property is listed. The Commonwealth's
concern is to raise the standard of management of that place to what we
would see as being appropriate for a World Heritage area. Any property
will have some costs associated with its management. Prior to listing,
that cost is borne by the state or territory governments. We would expect
that that level of financial contribution to management would remain.
[21]
Certainly, most of the state agencies consider that the Commonwealth should
be making a greater contribution to the development - perhaps rather than
to the management costs - of Australia's World Heritage areas. [22]
7.12 The Premier of Tasmania agreed with DEST's view of its 'topping
up' role to the extent that he believed that 'all costs, beyond those
that would have been spent in the TWWHA [Tasmanian Wilderness World Heritage
Area] prior to World Heritage area listing are the responsibility of the
Commonwealth'. [23] This approach
appeared to be the basis of the practice of the New South Wales Government,
which stated that it was spending no more money on areas that are world
heritage listed than those that are not. [24]
The corollary of this position is that world heritage areas that were
protected before listing should be jointly funded, while the Commonwealth
should assume sole responsibility for those that were not previously managed
by the States. The National Trust of Australia (Victoria) espoused this
view, [25] and the MCA stated clearly
that:
If the Commonwealth is in fact intent on imposing a nomination against
the will of the states and local communities then, frankly, as far as
funding is concerned the Commonwealth ought carry the bill in totality.
It is its responsibility; it has taken it on itself. It should carry the
consequences. [26]
On this argument, management of the Wet Tropics world heritage area would
be substantially funded by the Commonwealth because only 29% of the area
is composed of land that was national park before listing. However, the
Commonwealth has never accepted the concept that it should have prime
responsibility for capital expenditure and running costs for world heritage
areas, except in cases where it had prior jurisdiction. [27]
7.13 The costs associated with protected areas increase after world heritage
listing, not only because of the added requirements of presentation, preservation,
monitoring and reporting, but also because of the larger numbers of visitors
expected after listing. [28] The
New South Wales Government suggested that:
The Commonwealth should make a contribution to both the increased capital
expenditure and running costs which may arise from an area's World Heritage
listing (including the provision or expansion of visitor facilities and
greater management and staffing costs). [29]
Funds for consultation and research which assist management may also
be needed. [30]
7.14 The Tasmanian Government believed that no distinction should be
made between capital and recurrent funding in relation to cost sharing
between the Commonwealth and the States. [31]
On the other hand, Mr Dutton from Southern Cross University suggested
establishing the same general types of funding arrangement which are working
well in the Great Barrier Reef Marine Park. Here, initial capital costs
are borne by the Commonwealth and recurrent costs jointly with the State
agencies, with the potential to move towards a sustainable level of cost
recovery from park users over time. [32]
7.15 The Committee takes the view that it is reasonable for the Commonwealth
to meet a share of the additional costs incurred by the State-managed
world heritage areas as a result of world heritage listing. In the light
of the Commonwealth's obligations under the Convention, it is appropriate
for the Commonwealth's funding to emphasise raising standards of management
and improving interpretation and visitor facilities. The Committee noted
the experience of some agencies that acquiring funds for maintenance is
more difficult than acquiring them for capital costs, [33]
and considers that Commonwealth funding should be available for both capital
and recurrent expenditure. A further suggestion was that funds should
be on call in the case of emergencies, such as cyclones, disease outbreaks
or bush fires in world heritage areas. [34]
7.16 The Committee recommends that:
(42) Commonwealth Government funding for State-managed world heritage
areas be provided to improve facilities and standards of management
but only as a supplement to that provided by the States.
The Committee's view is that State Governments should continue to
fund world heritage areas at least at the levels that existed prior
to world heritage listing, and the Commonwealth Government's role should
be to supplement State funding.
7.17 It is to be hoped that no more nominations of areas for world heritage
listing will go forward to the World Heritage Committee without State
Government approval. The Committee notes that the present Government has
undertaken to pursue further nominations 'in close cooperation with States
and affected local communities' and to provide for 'broadbased community
involvement in every step on the path to world heritage nomination'. [35]
Funding agreements
7.18 To date, a small number of funding agreements have been reached
between the Commonwealth and the States.
- A five year funding agreement for capital and recurrent expenses was
finalised by the Commonwealth and Tasmanian Governments in 1986-87,
for the period 1987-88 to 1991-92. It was renegotiated until 1993-94
with the expansion of the world heritage area in 1989, and the current
four year agreement was negotiated in 1994. [36]
As Table 7.1 shows, substantial sums have been
spent by both Governments on the Tasmanian Wilderness.
- The Environment Ministers of the Commonwealth and Western Australian
Governments signed an agreement in 1992 for matching expenditures of
$950 000 by both Governments, to be spent by March 1995. [37]
A new funding agreement will be negotiated once the management plan
for the Shark Bay world heritage area is concluded.
- Agreements are under negotiation with the New South Wales Government
for its world heritage areas, and with the Queensland Government for
the Wet Tropics. [38]
No agreements have been concluded for the Fossil Mammal Sites, and the
agreements concluded for Fraser Island in 1991 and 1993 focussed on structural
adjustment assistance rather than having support for world heritage values
as their primary aim. [39]
7.19 In Chapter 4, the Committee endorsed the
view of many witnesses to the inquiry, that finalising agreed management
plans before properties are world heritage listed contributes to the efficiency
with which these properties are managed subsequently and the backing that
they receive from the community. The same argument can be made in support
of concluding funding agreements for world heritage areas before they
are listed. In its submission, the MCA called for 'a negotiated arrangement,
forming an integral part of the management plan agreed to prior to nomination
of a property' rather than a mixture of ad hoc payments with one-off allocations
dependent on matched funding from the States and fixed term specific purpose
grants. The current arrangements, the MCA claimed, 'are unlikely to inspire
confidence and trust in a process which is supposed to provide for the
conservation and protection of Australia's unique natural and cultural
values'. [40] The Premier of Victoria
also supported the need for funding agreements to be concluded before
areas are nominated for listing. [41]
7.20 The Operational Guidelines for the Implementation of the World Heritage
Convention specify that 'inscriptions of sites shall be deferred until
evidence of the full commitment of the nominating government, within its
means, is demonstrated'. Among the evidence of the government's commitment
that is expected is relevant funding arrangements. [42]
DEST acknowledged that 'ideally prior to nomination', management plans
should be prepared for each property with 'costings attached to them at
a fairly detailed level' (italics added). [43]
This ideal position has yet to be reached. Even with the most recent nominations,
funding agreements were not automatically concluded before the areas were
listed. [44] Other witnesses also
commented on the necessity of finalising agreements before areas are listed,
[45] as did the 1995 review of the
IGAE. [46]
7.21 The Committee regards the finalisation of formalised funding arrangements
for all world heritage properties as essential. It is important, as DEST
suggested, that the Commonwealth and States should agree to these plans
'with legislative force on how those costs will be shared'. [47]
The Committee recommends that:
(43) the Commonwealth Government ensure that, with all future nominations
of properties for world heritage listing, funding agreements are finalised
before the properties are nominated for listing.
(44) the Commonwealth Government move immediately to finalise financial
agreements or memoranda of understanding for the world heritage properties
in Queensland, South Australia, Western Australia, and New South Wales,
with the governments of these States.
7.22 The Committee also endorses the view that funding must be related
to the requirements established by agreed management plans. It noted with
approval a recommendation from a recent evaluation of the World Heritage
Unit that 'future funding to individual properties should be more directly
linked to the achievement of improved, more consistent management arrangements
and to agreed management plans' than in the past. [48]
A model funding agreement
7.23 The Department of Finance acknowledged that
the Commonwealth's approach to world heritage funding had been inconsistent.
[49] There have been widespread calls
from the States for a more consistent and equitable approach to the distribution
of Commonwealth funds to world heritage areas and for greater funding certainty
to be provided.
[50] Another feature
that has been seen as desirable in the provision of funding is the distribution
of funds against transparent criteria, as recommended by a meeting of world
heritage area managers in 1993
[51]
and participants at the Committee's workshop. Following the Prime Minister's
1992 Statement on the Environment, efforts have been directed towards developing
better arrangements.
[52] $2.25 million
was provided to DEST for the establishment of the World Heritage Unit and
in 1993-94, for the first time, all world heritage areas received some funding
from the Commonwealth. The 1996-97 Budget continued funding for the Unit.
[53] In 1995 the original, comparatively
generous agreement between the Commonwealth and Tasmania with a funding
ratio of 3.5:1 was renegotiated at a rate of 1.7:1, thereby reducing somewhat
Tasmania's special status.
7.24 In its submission to the inquiry, the Department of Finance advocated
'a uniform and universally applicable process for developing and agreeing
funding agreements with each of the States'. It saw the agreement that
had been recently concluded with the Tasmanian Government as 'a benchmark
for future agreements with other States'. [54]
The agreement includes the following features:
- estimation of budgetary requirements based on priorities and costings
established in detailed management plans;
- close examination of options for increasing cost recovery in the world
heritage area;
- ensuring net receipts generated from the world heritage area are included
as part of the base funding for the area and are not claimed as part
of the State or Commonwealth contribution;
- ensuring receipts and levels of base funding available are revised
each year to take into account growth in revenue; and
- a commitment to maintain the funding agreement and work within the
budgetary parameters for a four year period. [55]
The Department of Finance also indicated that it was willing to conclude
resource agreements with the States such that they would be allowed to
borrow for heavy capital costs and pay them off over several years. [56]
7.25 DEST listed the above points as 'essential components of a model
for future agreements with States' and added to them 'a Commonwealth/State
funding ratio in the order of 1:1'. [57]
The Department of Finance also referred to a basic presumption on the
part of the States and the Commonwealth that, particularly in the jointly
funded areas, the funding split would be 'more or less one for one, or
perhaps a bit more on the Commonwealth['s] part'. [58]
Finance acknowledged that the 'final detail of what is agreed in each
funding agreement will be influenced by the unique circumstances of each
State'. [59] The extent of Commonwealth
contributions depended on factors such as the nature of the areas, how
able the States are because of their size to fund the areas themselves,
the costliness of maintenance or restoration to world heritage standards,
and the possibilities for recovering costs. [60]
The TWWHACC added that the benefit to the nation of the property being
on the World Heritage List and the cost of managing State-based uses of
world heritage areas are also relevant considerations. [61]
7.26 The Tasmanian Government endorsed Finance's view of the way in which
the fine detail of relative State and Commonwealth contributions to each
world heritage area should take account of the circumstances that apply
in each world heritage area. It commented that:
Proposals such as dollar for dollar matching between the State and Commonwealth
governments are quite inappropriate in Tasmania's case. Tasmania has a
very high level of debt, a much lower revenue raising capacity than other
states and reduced funding as a result of the 1994 Premier's conference.
Furthermore, as the Commonwealth has a revenue raising capacity to expenditure
responsibility advantage of greater than 2:1 over the States and Territories,
the expectation that States should match Commonwealth spending on such
a basis defies all reason; especially since WHAs are largely a Commonwealth
responsibility.[62]
The TWWHACC wrote in the same vein in its submission to the inquiry:
There is no constant relationship between the costs necessary to protect
and present world heritage values and the tax base of States. For example,
the TWWHA covers one fifth of a State with less than 450,000 inhabitants
who have a lower mean income than any other state. Similarly there is
no constant relationship between the costs necessary to protect and present
world heritage values and the potential for user cost recovery or enterprise
earnings. [63]
Alternatives to agreements
7.27 As an alternative to the form of agreement described above, Mr Dutton
suggested that a broad triennial allocation of funds could be made to
the States, based on the relative merits of competitive proposals. Such
proposals could be reviewed by the Commonwealth against management plans
or property status reports. [64]
Mr Dutton was the only witness to the inquiry to raise this option for
distributing Commonwealth funds to the States. The Committee recognises
that such a system would give priority to the most important proposals,
but considers that it would not provide the same consistency and commitment
to ongoing funding that agreements do.
7.28 Another alternative entails a more entrepreneurial approach than
that normally espoused by governments, taking a wider view of the role
of government funding and focussing on benefit maximisation rather than
cost minimisation.
Adequacy of funding
7.29 The Department of Finance felt that it was 'not in a position to
comment on the adequacy of funding for management' of world heritage areas.
[65] However, everyone else agreed
that the funds provided were inadequate. As discussed in earlier sections
of this chapter, the funds were also deemed to be inequitably distributed.
Dr David Kay of DEST's World Heritage and Biodiversity Branch admitted
that the Commonwealth's funding of certain world heritage properties had
been inadequate:
Only in the last two financial years has the Commonwealth been in a position
to make contributions to each of the properties. There are several properties
which, in a number of years, have received no Commonwealth support. I
still think our capacity to fund what we would see as desirable is inadequate.
[66]
Dr Kay also added that he had been disappointed on occasions by the States'
financial commitment to the management of some properties.
7.30 The disparity in funding between different world heritage areas
was reflected in some of the comments about the perceived priority given
to some areas. One submission, for example, suggested that what had resulted
was the appearance of 'A Team WHAs', such as the Reef, Kakadu, Uluru-Kata
Tjuta, the Wet Tropics, and the Tasmanian Wilderness, and 'B Team WHAs',
which include the three NSW properties. [67]
Fraser Island, which has been dubbed 'a Third World Heritage' property,
appears to be regarded as a B Team member. [68]
Tony Charters of the Kingfisher Bay Resort on Fraser Island (and President
of the Ecotourism Association of Australia) suggested to the Committee
that the disparity in funding seemed to reflect a hierarchy of priorities:
From my experience of World Heritage areas, and certainly from direct
experience in years gone by with the Commonwealth Department of the Environment,
the approach to World Heritage areas seems to be that there are the one-star
World Heritage areas and the five-star World Heritage areas. The five-star
ones are the Great Barrier Reef, Kakadu, the Wet Tropics and Uluru. Then
you have some three-star areas like south-west of Tasmania; some two-star
areas like Shark Bay and the forests of New South Wales, or what is now
called eastern Australia; and the one-star areas like Willandra. It was
said to me by a member of that department that this was the approach.
I think that it is totally the wrong approach. It is something that UNESCO
does not ascribe to. Yet it is quite evident when you look at the funding
that, even if it is not written down, this is the way it is being handled.
Looking at the allocations by the Commonwealth in the last financial year,
$13.74 million was allocated to the states for World Heritage area management.
Fraser Island got 1.1 per cent of that, which would not appear to be an
equitable distribution. I do not think $13.7 million is an adequate amount
either, but certainly there is a lot of inequity between the World Heritage
areas. [69]
7.31 A further criticism of the provision of Commonwealth funds for State-managed
world heritage areas was identified in a recent evaluation of the World
Heritage Unit's operation. The evaluation found that funds have tended
to be 'directed to major problem areas or obvious bottlenecks rather than
supporting model approaches'. [70]
The report foreshadowed that the latter approach will be more extensively
used in future in line with the priorities that have been established
for improved management at each world heritage area.
7.32 On the pages that follow, the funding for individual world heritage
areas is considered in the light of the comments of witnesses and in terms
of the needs of the areas that were brought to the Committee's attention.
Commonwealth managed world heritage areas - Uluru-Kata Tjuta and Kakadu
7.33 Dr Peter Bridgewater, ANCA's Chief Executive Officer told the Committee
in 1995 that:
... the levels of funding that are provided certainly allow us to do a
very effective and highly professional job. If the level of tourism continues
to increase ... however, I know where most of those tourists are going
to go and, under those circumstances, unless we get real plough back through
revenue our funding will start to look not very good. [71]
In the 1996 Budget, ANCA's funding for Uluru and Kakadu was reduced.
ANCA also reported that considerable pressure for funds for Kakadu and
Uluru comes from threats to biodiversity, such as weeds, feral animals
and changed fire regimes, the needs associated with maintaining assets,
meeting the Aborigines' aspirations in park management, and coping with
natural disasters. [72]
7.34 The Committee noted the claim by the Parks and Wildlife Commission
of the Northern Territory that Kakadu could be managed more cheaply than
at present. It pointed out that the funds available for salaries and the
operational budget at Kakadu in 1992-93, expressed as dollars per employee,
were 20% greater than at Commission parks. [73]
ANCA argued, however, that expenditure per staff member is not a reliable
benchmark for measuring costs. Other factors should be considered as well,
such as the area managed, the significance of the heritage features to
be protected, the number of visitors, the effectiveness of management
outcomes, and the management and financial obligations under leases, legislation
and international conventions. ANCA observed that:
- in 1994-95 the recurrent gross cost per hectare was $3.80 for all
ANCA parks and $4.07 for Commission parks;
- nearly a third of ANCA's costs are recovered from park users;
- the standard of park management is high as evidenced by such items
as the management awards received by ANCA, its success in controlling
the highly invasive weed, Mimosa pigra, and the cultural information
available to visitors; and
- annual payments of the order of $1 million are made annually to traditional
owners at Uluru and Kakadu, while payments are not generally made to
owners of Northern Territory parks.
Great Barrier Reef
7.35 The Chairman of the GBRMPA advised the Committee that:
From inception in 1975 until 1986/87, it can be said that the Marine
Park Authority received an appropriate level of funding given its responsibilities
and the levels of demand for its services. ....
A significant problem facing the Marine Park Authority since 1987/88 has
been a real reduction in our core funding while use of the GBRMP has increased
at an estimated 10% per annum. [74]
An analysis carried out by consultants for the GBRMPA showed that, while
visitor numbers have increased at a rate of 10% per annum, the resources
available per visitor in 1994 was slightly less than half that available
in 1987-88.
[75] This point is illustrated
in
Figure 7.1 with respect to broader management
tasks, such as planning, environmental impact, and education activities.
[76]
Figure 7.1Visitation to the Great Barrier Reef Marine Park and
appropriations for planning and management, environmental impact management
and education activities, 1987-88 to 1994-95
NOTE
The graph featured in the version of the report presented
to the House of Representatives
on 4 November 1996 has not been reproduced in this version.
|
Source: S Driml & P O'Clery, 'Resources for management of the Great
Barrier Reef Marine Park', October 1994, p 2, Figure 2.
Figure 7.2Visitation to the Great Barrier Reef Marine Park and
appropriations for day-to-day management, 1987-88 to 1994-95, and projected
requirements 1993-94 to 1997-98
NOTE
The graph featured in the version of the report presented
to the House of Representatives
on 4 November 1996 has not been reproduced in this version.
|
Source: S Driml & P O'Clery, 'Resources for management of the Great
Barrier Reef Marine Park', October 1994, p 2, Figure 1.
7.36 A 1992 estimate of the shortfall in the GBRMPA's budget for day-to-day
management indicated that $25 million more was needed over the next five
years than was anticipated on the basis of current levels of funding at
that time. This is shown in Figure 7.2. A 1995
review by an intergovernmental, interdepartmental committee appointed
bySenator Faulkner came to a more conservative conclusion. It concluded
that an additional $2 million was needed each year for the period 1995-96
to 1998-99, plus $500 000 a year for the Aquarium. [77]
The GBRMPA received an increase of $1.5 million in the 1995-96 Budget,
which is substantially less than the reviews of the Authority's operations
recommended. Commonwealth funding for the GBRMPA has been decreased in
1996-97, but the effect of increasing user charges is expected to outweigh
the effect of reduced Government funding by $1.5 million. [78]
7.37 In recent years, new management challenges have emerged which make
added demands on the Authority's resources.
- With increasing numbers of reef users, adjudicating between uses becomes
more difficult .
- Increasing the involvement of Aborigines and Torres Strait Islanders
in management requires time consuming education and consultation.
- In the absence of control over adjacent land uses, the Authority is
putting resources into cooperative planning and educational programs
in its attempt to minimise impacts from those sources on the Reef. For
better management of the Reef, a more precise definition of its world
heritage values is being sought through consultancies and in the course
of case by case examination of applications for permits for development
or activities. [79]
Additional funding is also needed to manage continuing needs, such as
coping with the backlog in permit assessment, reviewing zoning and planning,
and continuing long term research projects. [80]
Queensland's world heritage areas
7.38 The Queensland Government commented that:
The funding provided in some circumstances by the Commonwealth for particular
purposes for particular areas has been substantial and adequate. However,
Commonwealth funding for areas where there is a lesser level of community
interest has not been sufficient to make a significant improvement in
the management and presentation of Queensland's World Heritage properties.
[81]
The Queensland Government felt that 'the present Commonwealth funding
formula does not adequately recognise the additional costs directly associated
with World Heritage listing'.
a) The Wet Tropics
7.39 In its submission, the WTMA pointed out that it is now able to make
'considered estimates of the funding needs to reasonably "ensure
the protection" of the Area'. Its view is that 'perceived funding
needs presently exceed projected funding availability'. Furthermore, at
no time have funding allocations to the Wet Tropics been based solely
on an analysis of funds needed. [82]
The funding falls short in a major way of what is required to provide
essential protection for world heritage values with respect to:
- purchasing land and developing cooperative agreements with landholders
in order to protect world heritage values outside the world heritage
area and ensure the integrity of the area;
- rehabilitating degraded areas, especially obsolete roads;
- controlling and eradicating invasive weeds and feral animals, such
as pigs; and
- providing the infrastructure to manage and present the area. [83]
7.40 All the Queensland world heritage properties have been poorly funded
by both the Queensland and Commonwealth Governments, but the Wet Tropics
world heritage area has been less poorly funded than the rest. However,
the WTMA's Executive Director noted in the Authority's 1994-95 annual
report that:
The gradual decline in funding for the Area is ... of concern ... and
the future prognosis for funding is not encouraging. This is occurring
at a time of increasing visitation and public expectations of high standards
of management. [84]
These views were shared by the Far North Queensland Promotion Bureau.
[85]
7.41 In 1994 the then Commonwealth and Queensland Governments established
the Daintree Rescue Program. Funds totalling $23 million over three years
were contributed by the two governments for improved visitor facilities
and protecting rainforest areas by purchasing them or finalising cooperative
management agreements with their owners. In the 1996 Budget, the present
Government announced that it would continue funding the program but would
spread out the remaining Commonwealth payment over a longer period of
time. The funds available to the WTMA are thus even less adequate now.
[86]
b) Fraser Island
7.42 As is clear from Chapter 4, there was a
widespread view that the management of Fraser Island was not of a standard
appropriate for a world heritage area. Residents of the island complained
that maintenance was inadequate, the management complement for the island
was understrength, [87] and there
were insufficient 'amenities, toilet facilities, watering points and the
like for the hundreds of backpackers who come there every day'. [88]
7.43 It appears that much of the blame for this situation lies in the
absence of adequate funding. A management plan was prepared in 1994 for
the Great Sandy Region, which includes Fraser Island as well as Caloola
National Park on the mainland and the waters between the island and the
mainland. The indicative cost of implementing the plan over 16 years was
put at $220 million, [89] or approximately
$13.75 million per year. As Table 7.1 shows,
far less than this latter sum has been contributed by the Commonwealth
and the Queensland Government to date. The Commonwealth's contribution
has been, and continues to be, particularly paltry. Furthermore, there
was a perception in the local community and among visitors to the island
that Commonwealth funding was being withheld because of disagreements
between the Commonwealth and Queensland Governments over the management
arrangements for the island. [90]
c) Riversleigh Fossil Site
7.44 The Riversleigh Fossil Site did not, prior to its listing, have
protected status and so had not received any Government funding for its
management. Having been listed as recently as December 1994, there has
been little time for work to be carried out on the site. Unfortunately,
no agreement on a management plan or funding was finalised before listing
occurred. This omission is delaying progress in meeting Australia's obligations
to protect the world heritage values of the site.
7.45 Professor Mike Archer, Head of the Riversleigh Research Project,
warned that there was an urgent need for funds to purchase an access route
to the Riversleigh site and establish management infrastructure so that
the site is accessible, and can be protected and interpreted to visitors.
At present the site boasts a roadside sign and fencing round a nearby
part of the site. The sign dates from 1988, is partially damaged, and
covers only one period of the fossil record. For about $950 000, Professor
Archer estimated that housing for resident rangers, toilet and interpretation
facilities, a camp ground, sheds and a power supply could be provided.
[91] The cost of installing a guided
walkway, repairing the existing sign and providing further signs, and
securing the site and some of its special features would require an additional
$54 500. [92]
7.46 Professor Archer pointed to the expected increase in the number
of tourists to the Mount Isa region and expressed his fears that, in the
absence of on-site managers at Riversleigh, damage may be done to the
fossils:
Well-meaning ecotourists (as well as deliberate vandals) will: 1, pick
up fossils from one site and discard them at another all too easily, thereby
destroying the integrity of what are often very different aged sites;
2, collect exposed parts of an object thereby removing what may be a key
element required for the identification of the part of the object that
remains; 3, desecrate exposed fossils in efforts to remove keepsake fragments;
4, collect fossils with incorrect locality information, eventually passing
back into the research community bogus specimen/data associations; 5,
collect fossils from new locations but be unable to provide details about
the location of the new site; ...
Second, as many examples of late have shown, there is a booming international
as well as national trade in fossils. They have sometimes breath-taking
commercial value ... We have in the past been followed into Australian
fossil sites by commercial dealers whose stated intent was to collect
fossils in bulk for sale in shops and overseas. [93]
In addition, without improved interpretation, visitors will leave the
site uninformed about its significance and possibly disappointed, which
will do nothing to promote support for the concept of world heritage.
[94]
d) Central Eastern Rainforest Reserves
7.47 During a visit to the Queensland section of the reserves less than
a year after they were listed as part of the world heritage area, the
Committee gained the impression that only very limited funding had being
provided by the Commonwealth and Queensland Governments for the capital
works and maintenance needed to deal with the increasing numbers of visitors
to the reserves.
7.48 Being close to Brisbane and the Gold Coast, visitation to some of
the reserves is overwhelming, and access to the reserves must be managed
through the provision of parking areas and the construction of suitable
roads, paths and trails. The costs here are considerable; for example,
the Committee was told that it would cost $1.7 million to provide tracks
to benefit all visitors to the New England National Park, which is within
the CERRA but over the border in New South Wales. In addition to managing
visitors, both Queensland and the New South Wales NPWS require funds to
deal with problems associated with the scattered nature of this world
heritage area, such as eradicating weeds, liaising with communities and
landholders outside the reserves, and purchasing land to rationalise boundary
management and extend the coverage of vegetation types and their protection.
The purchase of land is not only expensive but often requires much negotiation.
[95] Officers of both the Queensland
and New South Wales NPWS commented to the Committee on the need for more
staff as their off-park duties have increased in recent years, more protected
areas have been added to their responsibilities, and tasks have been devolved
downwards.
Tasmania - The Tasmanian Wilderness world heritage area
7.49 It can be seen from Table 7.1 that large
sums have been made available by the Commonwealth for the management of
the Tasmanian Wilderness. Mr John Sinclair, who as an ecotourist operator
is familiar with Australia's world heritage areas, commented that 'there
is no doubt that the site has benefitted from tied grants from the Commonwealth
Government'. [96]
7.50 The Tasmanian Premier complained, however, that his State is currently
receiving less from the Commonwealth than in earlier years and is therefore
unable to fully implement its agreed management plan for the world heritage
area. [97] The Tasmanian Government's
submission pointed out that the current management plan was completed
in 1992, taking into account the agreed levels of State and Commonwealth
funding available at that time. It was assumed that funding would continue
at the same level, but the new agreement provides for less. [98]
The TWWHACC supported the Tasmanian Government's complaint and asserted
that it is 'important that funding exists for those actions necessary
to fulfil legal obligations [as set down in plans and] all committed actions
should be adequately funded'. [99]
New South Wales world heritage areas
a) Willandra Lakes
7.51 The New South Wales Government pointed out that its world heritage
areas have received significantly less Commonwealth funding than those
in other States, and drew attention to the consequent problems that had
arisen in the Willandra Lakes Region. It claimed that inadequate funding
of world heritage areas by the Commonwealth, as in the Willandra Lakes
Region, jeopardised cooperative relationships with State Governments and
might degrade areas such that they become 'World Heritage in Danger'.
[100] The ACF also saw a clear
connection between the inadequate funding of the Willandra Lakes Region
and the management failures there. Mr Robert Hadler, Deputy Director of
the NFF provided a specific example of damage to cultural values that
stemmed from a lack of resources:
When I visited that area in the last year it was quite obvious that landowners
had made some attempt to fence off specific sites that were of cultural
value, but they did not have the resources, and not enough resources were
being devoted by the federal and state governments to preclude feral animals,
for example, in particular rabbits, from the area which are doing enormous
damage to the cultural values, and to properly manage the area in toto.
[101]
As indicated in Chapter 4, a management plan
for the Region is now in place and the New South Wales and Commonwealth
Governments are negotiating funding arrangements for all the New South
Wales world heritage areas. In addition, the 1996-97 Budget provided $2
million for payment as compensation to the landholders in the Willandra
Lakes area. [102]
b) Lord Howe Island
7.52 The Lord Howe Island Board is responsible for the care, control
and management of the island, which includes matters relating to the island's
world heritage status. It has received intermittent, small grants from
the Commonwealth for world heritage management, and obtains a regular
subvention from the New South Wales NPWS. Some of the revenue that the
Board obtains from departure taxes and the sale of alcohol and Kentia
palm seeds is also directed to environmental services. The Board's earnings
provide a variable income that reflects the demand for palm seeds, and
there is competition with other island activities for the funds available.
7.53 The New South Wales Government's assessment of the Board's performance
was that:
The Board over the past few years has found it difficult to provide sufficient
funding to carry out specific projects. This situation may be seen as
a threat to the preservation of the World Heritage values of the Lord
Howe Island Region. [103]
At a public hearing, Mr Howard of the New South Wales NPWS was more definite
about the effect of funding shortfalls on the treatment of the world heritage
area:
... the level of funding that is available to the Lord Howe Island board
for the management of the World Heritage area is inadequate to actually
present it and conserve it in its best form. [104]
7.54 When Members of the Committee visited Lord Howe Island, the residents
expressed the view to them that it was unfair that the 300 residents should
have to carry the major burden of preserving and presenting the world
heritage values of the island. They pointed out that it would be more
appropriate for the funds to be spent on the Board's core functions of
providing community infrastructure and services. Under these circumstances,
additional funding would be needed from State and Commonwealth sources
for world heritage management.
7.55 During its visit the Committee also learnt of the threats to the
island's world heritage values from feral animals, contamination of ground
water by sewage and, particularly, the problem of weed infestation by
asparagus grass and bitou bush. It was suggested to the Committee that
the invasion by weeds is sufficiently serious for the island to be identified
as World Heritage in Danger. It is thought that eradication, or at least
control, of the weeds would be possible with a long term, continuous effort,
but establishing a suitable eradication program in the present funding
circumstances is difficult. A weed eradication program was established
but was later curtailed when a downturn in the palm seed industry reduced
the Board's operating budget and therefore its capacity to pay the 10
workers involved. Commonwealth funding was provided in 1993-94 and 1994-95
for weed control, including funds for the development of a weed control
strategy, but no more has been made available since then.
c) Central Eastern Rainforest Reserves
7.56 The Committee received few comments that related specifically to
the funding provided for the rainforest reserves managed by the New South
Wales Government. Like the other New South Wales properties, relatively
little Commonwealth funding has been made available for the rainforest
reserves. Yet these reserves, like those in Queensland, have the same
pressures on them. It was the Committee's impression, however, that, despite
facing problems in common with the Queensland NPWS, the New South Wales
rainforest reserves were more adequately funded than those in Queensland.
South Australia - Naracoorte Fossil Caves world heritage site
7.57 From a visit paid to the caves, the former Chairman of the Committee
gained the impression that the managers of the Naracoorte Caves were coping
as well as possible with limited funding. The most pressing need identified
then, an extension to the visitor centre and the facilities available
to researchers, is being met with the provision of Commonwealth\State
funding.
Western Australia - Shark Bay world heritage area
7.58 The evidence provided to the Committee with respect to Shark Bay
did not identify any specific funding deficiencies. It is possible that
no mention of funding problems by the Western Australian Government reflected
the fact that the area's management plan and management agreement were
under discussion.
The need for additional Commonwealth funding
7.59 During the public hearings held in 1995, the Committee found that
the only world heritage management agency that considered its funding
to be satisfactory was ANCA. All others, to a greater or lesser degree,
appeared to be in urgent need of significantly increased funding. Since
then the 1996 Budget has delivered cutbacks to the majority of world heritage
areas. Of particular concern is the effect that this will have on the
'B team' world heritage areas, which have been historically very poorly
funded by the Commonwealth. Slightly less than $2 million will be contributed
in 1996-97 to assist with the management of Willandra Lakes, Shark Bay,
the Fossil Mammal Sites, Lord Howe Island, CERRA, and Fraser Island, and
some of this amount will be used to meet the Commonwealth's commitment
to the Tasmanian Wilderness.
7.60 The deficiencies in funding should be a matter of serious concern
given the Commonwealth's responsibilities for world heritage. The Committee's
view is that more funds should be provided by the Commonwealth for world
heritage management and development; and this should be accomplished without
reducing Commonwealth funding to the more generously supported areas,
as seemed to have happened to the Tasmanian Wilderness world heritage
area when its funding agreement was renegotiated. Most of the additional
funding is required to meet world heritage obligations above the requirement
to generally manage the areas in question, and should therefore be provided
mainly by the Commonwealth. The Committee notes that, even if all world
heritage areas were to be funded in accordance with the 1:1 State/Commonwealth
funding principle espoused by DEST and the Department of Finance, substantially
more funds would be required.
7.61 The amount of additional funding required is difficult to prescribe
because the management authorities, while quick to assert that they were
under-funded or that recent allocations were insufficient, [105]
did not specify the additional amounts required. The ACF proposed a global
figure of $20 million for developing and implementing management plans.
[106] However, it did not indicate
how it arrived at this figure, and it is clear that the need for additional
funding can only be quantified by assessing specific needs in each of
the world heritage areas. The Committee agrees with the WTMA that the
adequacy of funding needs to be based on an examination of the merits
of each case:
Unless the funding needs are actually assessed against the scale and nature
of threatening processes operating in each and every WHA in Australia,
it is contended that an assessment of "adequacy of funding"
for Australia's World Heritage Areas could only be indicative at best.
[107]
7.62 Subject to a detailed assessment of funding needs as proposed in
recommendation 45, the Committee has come to the conclusion that significant
increases in funding are required. Assuming that the State Governments
would contribute half the additional funds needed for State-managed areas,
the Committee estimates on the basis of information provided to it that
an aditional $20.6 million are needed for recurrent and capital costs
in the first year, and $16 million in subsequent years. The Government
has indicated that it will be providing $12 million dollars over four
years from the Natural Heritage Trust of Australia. These additional funds
are welcome but will be insufficient to adequately meet the needs of world
heritage management. The Committee recommends that:
(45) the Commonwealth Government provide additional funds for the
protection, conservation and presentation of world heritage areas.
$20.6 million should be provided in the first year and $16 million
per annum thereafter.
(46) the Department of the Environment, Sport and Territories, in
consultation with world heritage area management authorities, identify
and quantify specific additional funding needs in each of the world
heritage areas as a basis for allocating the additional funds.
7.63 The major part of the additional funds will be needed for management
and capital works in the Wet Tropics, the Tasmanian Wilderness and the
CERRA and on Fraser Island, with lesser amounts for works at Riversleigh
and on Lord Howe Island and general expenditure in other world heritage
areas. The Committee identified Fraser Island and the Riversleigh Fossil
Site as areas of particular concern with respect to the funding they receive
in relation to their needs and the absence of financial agreements. The
Committee acknowledges that the Queensland Government has provided some
additional funding for Fraser Island but much more needs to be supplied.
With the management plan for the Great Sandy Region now in place, there
is a basis for the two Governments to draw up an agreement along the lines
of the model agreement described in paragraphs 7.23-7.26.
The Committee recommends that:
(47) the Commonwealth Government give a high priority to working
with the Queensland Government to finalise a financial agreement for
the Fraser Island world heritage area.
7.64 As indicated earlier in this Chapter, the Committee considers that
the world heritage values of the Riversleigh Fossil Site are in danger
for want of adequate protection, a situation that can only be rectified
if funds are available. An injection of funds is urgently required to
secure and staff the site. It should be provided by the Commonwealth Government
in keeping with its obligations under the Convention, if the Queensland
Government is unable to make funds available. The next steps that must
then be taken to provide world heritage standard management for Riversleigh
are the completion of the management plan, costing of its implementation,
and finalisation of a funding agreement. The Committee recommends that:
(48) the Commonwealth Government:
a) make funds available without further delay to provide adequate
protection to the world heritage values of the Riversleigh Fossil Site;
and
b) give high priority to finalising a funding agreement with the
Queensland Government for the management and development of the Riversleigh
world heritage area.
7.65 While Fraser Island and Riversleigh appeared to the Committee to
be most in need of additional funding, other state-managed world heritage
areas would also benefit from more generous funding. The Committee noted
that negotiations are well advanced over a management plan for Shark Bay,
with the Western Australian Government having indicated that it will then
seek to reach agreement with the Commonwealth on joint funding of the
area. Similarly, arrangements are being put in place for the Willandra
Lakes Region. However, no such steps have yet been taken for Lord Howe
Island and the CERRA. As pointed out in Chapter 4,
dealing with both these areas presents special difficulties, with the
CERRA being under two jurisdictions and Lord Howe Island under the control
of a Board and not the New South Wales NPWS. In both cases additional
funding is required, particularly for weed control on Lord Howe Island.
Finalisation of agreements regarding the management of these areas would
facilitate the identification of additional funding needs.
7.66 With the intention of having funding agreements between the Commonwealth
and State Governments cover four year periods, there is built into the
system the possibility of regularly reviewing both the management plans
and the funding to support them. No such automatic review is built into
the arrangements for the world heritage areas for which the Commonwealth
has prime responsibility. The Committee considers that, not only should
all management plans be regularly reviewed as recommended in Chapter
4, but so should the funds provided. The Committee recommends that:
(49) the Department of the Environment, Sport and Territories, in
cooperation with world heritage managing agencies, regularly review
the adequacy of funding provided for each world heritage area.
Other funding issues
Regional issues
7.67 There is an expectation that funds allocated to a particular world
heritage area will be spent within the area on its management and development.
A case can be made, however, for using them outside the area because expenditure
outside the area can reduce impacts within it. For example, upgrading
walking tracks in less sensitive areas outside the Tasmanian world heritage
area would attract some of the current users of tracks in the more sensitive
wilderness area. [108] The Committee
considers that it is acceptable for world heritage funds to be spent on
development and management outside world heritage areas where this can
be clearly seen to improve conditions within the area.
7.68 When world heritage listing greatly increases visitation to otherwise
sparsely populated regions, facilities within those regions may be overwhelmed.
Yet it may be beyond the capacity of local governments to provide adequate
facilities, because they tend to be funded in relation to the permanent
population of the area; tourist numbers are excluded when funding needs
are being established. [109] The
New South Wales Government drew attention to the effect on local services
of visitors to adjacent world heritage areas. It suggested that the Commonwealth
should make funds available to local governments to help them deal with
the increased demands placed on them by visitors. [110]
The problem of local road maintenance adjacent to world heritage areas
was highlighted during the Committee's inspection of the Wet Tropics area
near Cairns. The local government authorities there are facing increased
maintenance costs due to the additional traffic using regional roads to
access the world heritage area. The then Commonwealth Department of Tourism
pointed out that road funding could be regarded as a joint responsibility
between local residents, world heritage managers and the private sector.
[111]
7.69 Another case of cost impost on local government was mentioned to
the Committee by the GBRMPA. This related to inadequate sewage treatment
plants along the Queensland coast where tourist boats discharge their
holding tanks. [112] It is the
Committee's view that issues such as these should be considered in the
context of planning for the regions of which world heritage areas are
part and, where appropriate, partnerships between different agencies and
the private sector be sought to provide funds.
Compensation
7.70 The question of compensation for those affected by world heritage
listing of property on which they depended for their livelihood has been
one of the major issues in the history of establishing world heritage
areas. It has been, and continues to be, hard fought. As noted in Chapter
3, several submissions identified the lack of compensation as a matter
that needs to be addressed by legislative amendment. The Commonwealth
has an obligation to compensate land owners when it acquires property
and has acknowledged its moral obligation to compensate affected people
and businesses by providing ex gratia payments and payments through the
structural adjustment packages for the Wet Tropics and Fraser Island.
Payments will also be made to landholders in the Willandra Lakes Region.
7.71 Many regard existing compensation practices as unsatisfactory and
would like to see a statutory obligation to provide compensation in all
cases, not just when property acquisition is involved. On the other hand,
the World Wide Fund for Nature Australia (WWF) and the National Parks
Association of New South Wales, commenting on compensation arrangements
for landholders in the Willandra Lakes Region, questioned the wisdom of
setting this precedent for landholders. WWF also argued that funds spent
on compensation could be used more profitably for purchasing part, if
not all, of that world heritage site. [113]
The Committee considers, however, that the payment of compensation in
such cases is appropriate.
7.72 Ideally, the payment of compensation is a matter for consideration
at the time when an area is nominated for world heritage listing, and
any compensation that is due should be made around the time of listing.
The issue of major compensation payments should not therefore be a concern
to this inquiry which is dealing with the management of existing world
heritage areas. Two points, however, need to be made, one relating to
the past failures by the Commonwealth or the States to pay compensation
at the time of listing, and the other to the question of the need for
ongoing compensation.
7.73 The most glaring failure by the Commonwealth to address the payment
of compensation to people affected by world heritage listing is in the
Willandra Lakes Region. Despite the Region's having been listed as long
ago as 1981, funds for compensation were not made available until the
1996-97 Budget. This situation has caused immense economic hardship and
emotional stress to the landholders; the Uniting Church in Australia referred
to the people's:
1. Uncertainty about future viability of businesses in the area.
2. Frustration caused by the difficulty of finding out information.
3. Stress on families due to not knowing what the future holds.
4. Anger at delay of any compensation or the possibility of no compensation...
.[114]
7.74 In the Committee's view, this situation is most reprehensible. The
Committee therefore welcomes the efforts that are now under way to make
just recompense to these people, but notes that claims have been made
that a similar situation exists for the pastoralists in and abutting the
Shark Bay world heritage area, which was listed in 1991. [115]
7.75 Quite apart from the moral necessity to provide compensation at
the time when world heritage listing begins to affect individuals and
businesses, there is the practical consideration that future management
of any world heritage area will be much easier if the local community
at the very least does not feel too negative about that area's world heritage
status. As is clear from Chapter 4, support from
the local community can greatly assist development of the area and promote
its smooth management.
7.76 The Committee views the payment of compensation at the time of listing
as essential. It was pleased to note that the previous Government had
established that:
... any listing must bring forward a costing of the compensation required.
There are three areas of compensation: there is the area of acquisition
of land; the payment of ex gratia compensation to individuals who may
suffer indirectly as a result of the listing; and, finally, some sort
of structural adjustment package. All those elements are now required
by a Cabinet decision to actually be made transparent at the time of listing,
because those are the main areas where the Commonwealth is required to
meet its obligations. [116]
7.77 Calls have also been made for compensation payments to be required
by statute in cases where the Commonwealth does not acquire the land,
notably by five peak industry bodies. These bodies proposed that compensation
rights should be recognised through an appropriate statutory instrument,
and financial harm should be recompensed as soon as the harm and its value
are established. [117] AMEC and
the Western Australian Government also called for a statutory requirement
for the payment of compensation. [118]
7.78 The Committee anticipates that, once listing has occurred and compensation
has been paid, there should be no further need for compensation. However,
there may be the odd occasions when further extreme and unanticipated
impacts result from ongoing management of world heritage areas and the
payment of compensation might be appropriate. The Western Australian Government
called for 'compensation and/or structural adjustment funding in the event
of [the Commonwealth] taking action which causes a diminution in otherwise
lawful use of the Property'. [119]
Fishing in the Great Barrier Reef world heritage area was mentioned to
the Committee by workshop participants as an example of a case where compensation
might be considered. However, DEST was clearly hopeful that such situations
would not arise:
Essentially, the position that we take is that the management agreement
provides, or should provide, for decisions on use to be made collectively
by the ministerial council and not under direction by the Commonwealth.
[120]
7.79 It is the Committee's view that, just as the Commonwealth and States
have accepted responsibility for providing compensation and structural
adjustment packages at the time when world heritage areas are listed,
so they should be open to considering the need, in certain exceptional
circumstances, for funds to recompense for later management decisions.
The Committee recommends that:
(50) the Commonwealth Government, in cooperation with the State
Governments where appropriate, provide compensation in cases of substantial
disturbance to individuals and businesses as a result of the ongoing
management of world heritage areas.
Use of world heritage funds for non-world heritage purposes
7.80 The Committee observed that, in rare cases, funds have been used
in world heritage areas for purposes for which they were not originally
intended. At Uluru, for example, ANCA bears costs associated with house
maintenance and the provision of power in the local Mutitjulu Aboriginal
community. [121] While appreciating
the need for basic services for the Aboriginal community if members of
that community are to contribute to park management, the Committee considers
that it is inappropriate for ANCA to be providing services which are properly
the responsibility of other government agencies. The WTMA told the Committee
about the situations it has encountered in which its neighbours are experiencing
difficulties in ensuring their own welfare. It has dealt with such situations
by acting as a broker or a one-stop shop to involve the appropriate government
agencies. The Committee's view is that the WTMA's approach is a better
method of dealing with such situations than for world heritage managers
to fund the services themselves.
Footnotes
[1] Department of the Environment, Sport and
Territories, transcript, 27 November 1995, p 332.
[2] Tasmanian Government, submission (number
63), p 9.
[3] Western Australian Government, submission
(number 56), pp 9-10.
[4] Conservation Council of Western Australia,
submission (number 51), p 3; South Australian Farmers Federation, submission
(number 6), p 4; Tasmanian Wilderness World Heritage Area Consultative
Committee, submission (number 25), p 4.
[5] Department of the Environment, Sport and
Territories, transcript, 28 August 1995, p 79.
[6] Wet Tropics Management Authority, submission
(number 77), p 2.
[7] In its 1993 report, the Commission ranked
Tasmania third behind Western Australia and the Northern Territory in
terms of its funding needs on this criterion (Tasmanian Government, submission,
number 63, p 10).
[8] Tasmanian Government, submission (number
63), pp 9-12; Tasmanian Wilderness World Heritage Area Consultative Committee,
submission, number 25, p 5.
[9] Department of Finance, submission (number
9), p 2.
[10] Department of Finance, submission (number
9), p 3.
[11] New South Wales Government, submission
(number 66), p 2.
[12] Western Australian Government, submission
(number 56), p 8.
[13] Department of the Environment, Sport and
Territories, submission (number 62), p 21.
[14] Royal Australasian Ornithologists Union,
submission (number 19), p 1.
[15] Department of the Environment, Sport and
Territories, submission (number 62), p 19.
[16] Commonwealth Department of Tourism, submission
(number 68), p 3; transcript, 31 August 1995, p 114.
[17] The Hon John Moore, MP, 'Tourist industry
gains full access to EMDG scheme', media release, 20 August 1996.
[18] Department of Finance, submission (number
9), p 2.
[19] Department of Finance, submission (number
9), p 4.
[20] Department of the Environment, Sport and
Territories, submission (number 62), p 22.
[21] Department of the Environment, Sport and
Territories, transcript, 28 August 1995, p 79.
[22] Department of the Environment, Sport and
Territories, transcript, 28 August 1995, p 98.
[23] Premier of Tasmania, letter transmitting
the submission from the Tasmanian Government (number 63). The Tasmanian
Wilderness World Heritage Area Consultative Committee shared this view
too (submission, number 25, p 4).
[24] New South Wales Government, transcript,
1 November 1995, p 143.
[25] The National Trust of Australia (Victoria),
submission (number 48), p 15.
[26] Minerals Council of Australia, transcript,
30 November 1995, p 339.
[27] Department of the Environment, Sport and
Territories, transcript, 28 August 1995, p 90.
[28] New South Wales Government, submission
(number 66), pp 4-5; Queensland Government, submission (number 74), p
5; Western Australian Government, transcript, 13 July 1995, p 13.
[29] New South Wales Government, submission
(number 66), p 4.
[30] Australian Nature Conservation Agency,
submission (number 37), p 28; New South Wales Government, submission (number
66), p 6; S Kidman & Co., submission (number 13), p 10.
[31] Tasmanian Government, submission (number
63), p 14.
[32] Mr Ian Dutton, submission (number 1),
p 7.
[33] For example, the Australian Nature Conservation
Agency, transcript, 28 August 1995, p 103.
[34] Tasmanian Government, submission (number
63), p 14.
[35] Minister for the Environment, Senator
Robert Hill, 'Investing in our natural heritage', Budget statement, 20
August 1996.
[36] Tasmanian Government, submission (number
63), pp 5-6.
[37] Western Australian Government, submission
(number 56), pp 5-6.
[38] Department of the Environment, Sport and
Territories, submission (number 62), p 23.
[39] Department of the Environment, Sport and
Territories, submission (number 78), p 7.
[40] Australian Mining Industry Council, submission
(number 28), pp 10, 35.
[41] Premier of Victoria, submission (number
58), p 1.
[42] UNESCO, Operational Guidelines for
the Implementation of the World Heritage Convention, February 1996,
paragraph 6(v).
[43] Department of the Environment, Sport and
Territories, transcript, 28 August 1995, p 80.
[44] South Australian Government, submission
(number 60), p 2.
[45] For example, Tourism Council Australia,
submission (number 73), p 10.
[46] Intergovernmental Committee on Ecologically
Sustainable Development, Report to the Council of Australian Governments
on the Review of the Intergovernmental Agreement on the Environment,
July 1995, quoted by Ben Boer & Robert J Fowler, The Management
of World Heritage Properties in Australia: Report to the Department of
the Environment, Sport and Territories, Part II, undated, issued in
May 1996, p 29.
[47] Department of the Environment, Sport and
Territories, transcript, 28 August 1995, p 80.
[48] Evaluation Report: World Heritage Management
Arrangements, Department of the Environment, Sport and Territories,
November 1995, p 30.
[49] Department of Finance, submission (number
9), p 4.
[50] Western Australian Government, submission
(number 56), p 9; Premier of Victoria, submission (number 58), p 1; New
South Wales Government, submission (number 66), p 2; Queensland Government,
submission (number 74), p 5.
[51] Tasmanian Government, submission (number
63), p 13.
[52] P Keating, Australia's Environment:
a Natural Asset. Statement on the Environment, December 1992, pp 23-4.
[53] Portfolio Budget Statements
1996-97: Environment, Sport and Territories Portfolio, Budget related
paper no. 15, pp 9, 22.
[54] Department of Finance, submission (number
9), p 4.
[55] The Western Australian Government proposed
that Commonwealth financial assistance arrangements should be entered
into for periods of at least five years, to provide an appropriate level
of certainty and security (submission, number 56, p 9). The Queensland
Government also called for funding over longer periods than at present
(submission, number 74, p 5).
[56] Department of Finance, transcript, 28
August 1995, p 107.
[57] Department of the Environment, Sport and
Territories, submission (number 62), p 23.
[58] Department of Finance, transcript, 28
August 1995, p 107.
[59] Department of Finance, submission (number
9), p 4.
[60] Department of Finance, transcript, 28
August 1995, p 105.
[61] Tasmanian Wilderness World Heritage Area
Consultative Committee, submission (number 25), p 5.
[62] Tasmanian Government, submission (number
63), p 13.
[63] Tasmanian Wilderness World Heritage Area
Consultative Committee, submission (number 25), pp 3-4.
[64] Mr Ian Dutton, submission (number 1),
p 7.
[65] Department of Finance, submission (number
9), p 2.
[66] Department of the Environment, Sport and
Territories, transcript, 27 November 1995, p 332.
[67] Mr Ian Dutton, submission (number 1),
p 2.
[68] Eurong Beach Resort, submission (number
10), p 2.
[69] Mr Tony Charters, transcript, 15 November
1995, pp 213-14.
[70] Evaluation Report, p ii (see footnote
48, Chapter 7).
[71] Australian Nature Conservation Agency,
transcript, 28 August 1995, p 98.
[72] Australian Nature Conservation Agency,
submission (number 37), pp 25-8.
[73] Conservation Commission of the Northern
Territory, submission (number 33), p 16.
[74] Great Barrier Reef Marine Park Authority,
submission (number 59), pp 3-4.
[75] Great Barrier Reef Marine Park Authority,
submission (number 59), p 12.
[76] As Figure 7.2
shows, a less serious situation pertains to day-to-day management.
[77] Department of the Environment, Sport and
Territories, Review of Funding Arrangements for the Great Barrier Reef
Marine Park Authority, January 1995, pp 27, 36.
[78] Portfolio Budget Statements
1996-97: Environment, Sport and Territories Portfolio, Budget related
paper no. 15, pp 6, 9.
[79] Great Barrier Reef Marine Park Authority,
submission (number 59), pp 12-15.
[80] Department of the Environment, Sport and
Territories, Review of Funding Arrangements for the Great Barrier Reef
Marine Park Authority, January 1995, p 27.
[81] Queensland Government, submission (number
74), p 5.
[82] Wet Tropics Management Authority, submission
(number 77), p 4.
[83] Wet Tropics Management Authority, submission
(number 77), pp 7-8.
[84] Wet Tropics Management Authority, Annual
Report 1994-95, pp 2-3.
[85] Far North Queensland Promotion Bureau,
submission (number 85), p 1.
[86] Minister for the Environment, Senator
Robert Hill, 'Investing in our natural heritage', Budget statement, 20
August 1996.
[87] Mr Tony Charters of the Kingfisher Bay
Resort and Village, transcript, 15 November 1995, p 204; Eurong Beach
Resort, submission (number 10), pp 3-5; Fraser Island Association, submission
(number 46), p 3.
[88] Fraser Island Association, transcript,
15 November 1995, p 251.
[89] Queensland Government, Great Sandy
Region Management Plan 1994-2010, p 1.
[90] Eurong Beach Resort, submission (number
10), p 2; Fraser Island Defenders Organisation, submission (number 44),
p 2.
[91] Professor Mike Archer, submission (number
70), pp 14-15.
[92] Professor Mike Archer, submission (number
70), p 20.
[93] Professor Mike Archer, submission (number
70), p 19.
[94] Professor Mike Archer, submission (number
70), p 16.
[95] New South Wales Government, transcript,
1 November 1995, p 143.
[96] Fraser Island Defenders Organisation,
submission (number 44), p 3.
[97] Premier of Tasmania, letter transmitting
the submission from the Tasmanian Government (number 63).
[98] Tasmanian Government, submission (number
63), p 12. At current funding levels, the Commonwealth is providing about
$1.8 million per annum less than the Tasmanian Government had anticipated
('Submission to the Commonwealth Government by the State of Tasmania for
a joint five-year funding program, 1994-95 to 1998-99', Tasmanian Government,
submission, attachment 2)
[99] Tasmanian World Heritage Area Consultative
Committee, submission (number 25) p 3.
[100] New South Wales Government, submission
(number 66), pp 4-5.
[101] National Farmers' Federation, transcript,
27 November 1995, p 318.
[102] Portfolio Budget Statements
1996-97: Environment, Sport and Territories Portfolio, Budget related
paper no. 15, p 9.
[103] New South Wales Government, submission
(number 66), p 8.
[104] New South Wales Government, transcript,
1 November 1995, p 137.
[105] For example, the New South Wales National
Parks and Wildlife Service claimed that the additional $12 million over
four years included in the Coalition's election policy for world heritage
management was inadequate (submission, number 87, p 1).
[106] Australian Conservation Foundation,
submission (number 79), p 7.
[107] Wet Tropics Management Authority, submission
(number 77) p 2.
[108] Dr Ralph Chapman, submission (number
5), p 5; Tasmanian Government, submission (number 63), p 14.
[109] Tourism Council Australia, transcript,
27 November 1995, pp 309-10.
[110] New South Wales Government, submission
(number 66), p 9.
[111] Commonwealth Department of Tourism,
transcript, 31 August 1995, p 119.
[112] Great Barrier Reef Marine Park Authority,
transcript, 27 November 1995, p 288.
[113] National Parks Association of New South
Wales, submission (number 86), p 1; World Wide Fund for Nature Australia,
submission (number 83), p 1.
[114] Uniting Church in Australia, submission
(number 50), p 4.
[115] The Pastoralists and Graziers Association
of Western Australia, submission (number 22), p 3.
[116] Department of Finance, transcript, 28
August, p 105.
[117] Australian Mining Industry Council,
Australian Petroleum Exploration Association, Business Council of Australia,
National Association of Forest Industries & National Farmers' Federation,
World Heritage in Australia: Proposed Management Reforms, December
1994, p 6.
[118] Association of Mining and Exploration
Companies, submission (number 42), p 28; Western Australian Government,
submission (number 56), pp 3-4.
[119] Western Australian Government, submission
(number 56) p 12.
[120] Department of the Environment, Sport
and Territories, transcript, 28 August 1995, p 80.
[121] Australian Nature Conservation Agency,
submission (number 37), attachment E.
Back to top