Chapter 5 RAAF Base Tindal Redevelopment Stage 5, Northern Territory
5.1
The RAAF Base Tindal Redevelopment Stage 5, Northern Territory (Tindal
Stage 5) proposes to improve the facilities which support the overall
capability of the base. The estimated cost of the project is $58.7 million
(excluding GST.)
5.2
The Tindal Stage 5 works proposal was referred to the Committee for
inquiry on 19 March 2008.
Conduct of the inquiry
5.3
The inquiry was initially advertised in the Northern Territory News
on 28 June 2007. The inquiry was readvertised in the Katherine Times
on 26 March 2008 and the Northern Territory News on 29 March 2008. The Committee received one submission to the inquiry and one confidential
supplementary submission detailing the project cost estimates. A list of
submissions can be found at Appendix A.
5.4
The Committee undertook a site inspection, in-camera hearing and public
hearing on 17 April 2008 in Katherine. A list of witnesses can be found at
Appendix B.
5.5
The transcript of the public hearing as well as the submission to the
inquiry are on the Committee’s website.[1] Plans for the proposed
works are detailed in Submission 1, Department of Defence (Defence).
Need for works
5.6
The Committee was advised that the proposed works would address existing
limitations and deficiencies in base facilities following an increase in use of
the Base. The project elements aim to improve quality to current industry
standards, address occupational and health and safety risks, develop more
usable facilities with appropriate security protection.[2]
5.7
The Committee recognises the need to maintain defence establishments to
current industry and occupational regulatory requirements and ensure that
facilities continue to be fit for their purpose and are safe and effective for
Australian defence force personnel. The Committee finds that there is need for
the proposed works and supports this redevelopment initiative.
Scope of works
5.8
The proposed scope of works are detailed in Submission 1, Department of
Defence. The works consist of the following 12 project elements:[3]
n Security fence extension:
extend the existing base security fence to enclose the explosive ordnance storage
and preparation areas. approximately 7.2km of fencing is to be constructed;
n Central emergency power
station: supply and install an additional 1MW diesel generator in the emergency
power station;
n Ordnance loading apron
water supply: reticulate mains water to the 75 Squadron aprons to replace the
current reliance on tank water;
n Liquid dry breathing oxygen
facility: construct a covered area for two 7000L storage tanks, a drive through
facility for off-loading liquid oxygen from road trains and a covered parking
area for the trolleys and tow motors which handle the transfer of oxygen to the
flightlines. Construct an evaporation pit, security fencing, security lighting,
lightning protection and a light vehicle access road to connect the facility to
the 75 Squadron precinct;
n Aircraft maintenance annexes:
extend each annex, to rearrange some internal spaces and to construct new
toilet, shower and locker facilities adjacent to each annex;
n Inflight and surge catering:
construct a new facility for the preparation of meals for crew and passengers,
operational sites personnel and a sit down dining area for operational staff.
This element includes a central, common stores area, and separated kitchen
areas for domestic and inflight preparation and distribution operations;
n Ordnance loading
apron security: construct a security system comprising one fixed and two pan
tilt zoom CCTV cameras with motion detection fitted to the roof of each of the
ten ordnance loading aprons;
n Tanker maintenance
and refuelling facilities: construct a tanker maintenance and tanker drivers’
facility providing four fire separated maintenance bays, a small parts repair
workshop, a store and a vehicle wash bay. A separate building will provide
offices, training, amenities and change facilities;
n Fire station: upgrade
fire facilities including two additional fire fighting vehicle bays, a stores
area and a new change/toilets/laundry area. Construct a two metre wide awning
on both sides of the existing vehicle bays to accommodate the new, larger fire
trucks;
n Supply services warehouse:
extend the existing warehouse to increase pallet racking space and to provide
additional receipt and dispatch floor area. Refurbish office space, replace the
carousel and refurbish and augment the warehouse fire protection system;
n Messing improvement: replace
worn and obsolete equipment and undertake a general refurbishment of all
finishes in the Airmen’s, Sergeants’ and Officers’ messes; and
n Passenger terminal: expand
both indoor and outdoor spaces in the current terminal. Enclose existing
baggage collection space and relocate baggage collection to an outside,
partially covered area.[4]
5.9
The Committee has assessed the scope of works and finds them suitable to
improve the overall capability at RAAF Base Tindal.
Cost of works
5.10
The total out-turn cost of this work is estimated to be $58.7 million
(excluding GST) which includes construction costs, management and design fees, internal
fit-out, information and communication technology and contingency allowance.[5]
5.11
The Committee received detailed cost plans for the project and held an
in-camera hearing with Defence on the full project costs.
5.12
The Committee is satisfied that the costings for the project are adequate
and that suitable contingency planning is in place (including deferring
non-essential works should there be budget over-runs in any area) to ensure the
overall budget is not compromised.
Project issues
Consultations on the project
5.13
In addition to the local construction industry briefings for the four
Northern Territory Defence referrals discussed in Chapter 6, Defence informed
the Committee that they have ongoing consultations with the following bodies in
relation to Tindal Stage 5:
n Northern Territory
Department of Defence Support;
n Northern Territory
Department of Planning and Lands;
n The Chamber of
Commerce Northern Territory;
n The Australian
Industry and Defence Network in the Northern Territory;
n The Member for
Lingiari, the Hon Warren Snowdon MP;
n The Member for Katherine (Northern Territory); and
n The Katherine Town Council.[6]
5.14
The Committee notes that consultations have not taken place with the
Northern Territory Departments of Business and Economic Development and Natural
Resources, Environment and Heritage despite efforts to arrange a meeting by
Defence.
5.15
The Committee considers that it is important for Defence to consult with
all relevant external authorities, particularly Northern Territory Government
Departments, and Defence should continue to ensure that necessary consultations
are undertaken.
Local wallaby population
5.16
Recent environmental conditions in Northern Australia have lead to a
rapid increase in the wallaby population creating a hazard for both civilian
and military aircraft at Tindal. In 2007, Defence were forced to cease all
night flights due to the risk of aircraft hitting the animal. Medical rescue
planes were also diverted following two collisions with wallabies.
5.17
Defence considers that media reports have exaggerated claims that the
existing fence at RAAF Base Tindal was responsible for increasing the risk of
aircraft collision with wallabies by trapping them on the base. [7]
5.18
Wing Commander Rohan Gaskill, RAAF Base Commander, advised the
Committee:
Last year on four occasions aircraft operating at Tindal did strike wallabies. A wallaby management program has been developed and is
being implemented. That was in consultation with the RSPCA, a local vet and all
the appropriate organisations. This has seen the removal of over 700 wallabies
from inside the security fence using both lethal and nonlethal means.[8]
5.19
The Committee was concerned that the proposed security fence extension
would be of the same design as the existing fence and may not adequately prevent
the entry of wallabies.
5.20
The Committee heard that there had always been a population of wallabies
at the Base and the fence did function to both restrict the entry of wallabies
and trap wallabies held within. The Committee acknowledges that it is very difficult
to eliminate the wallaby population within the Base because of the size of the
property and the variety of locations for the animal to hide, such as spear
grass and limestone caves.
5.21
The Committee is satisfied with the wallaby management plan at the Base
and considers that the wallaby population does not pose a significant issue for
the proposed extension of the perimeter fence. Further, Defence considers that
it is now safe for the Northern Territory Department of Health to resume emergency
medical evacuation flights to and from the Base.
Committee comment
5.22
Overall, the Committee is satisfied that this project has merit in terms
of need, scope and cost. No other submissions were received raising issues with
the proposed works. The Committee is therefore satisfied that there are no
reasons to object to the work proceeding.
5.23
Having examined the purpose, need, use, revenue and public value of the
work, the Committee considers that it is expedient that the proposed redevelopment
at RAAF Base Tindal proceed.
Recommendation 7 |
5.24
|
The Committee recommends that the House of Representatives,
pursuant to Section 18 (7) of the Public Works Committee Act 1969,
resolve that it is expedient to carry out the following proposed work: RAAF
Base Tindal redevelopment Stage 5, Northern Territory.
|