Chapter 3 RAAF Base Darwin Redevelopment Stage 2, Northern Territory
3.1
RAAF Base Darwin Redevelopment Stage 2, Northern Territory (RAAF Base
Darwin) proposes to improve the operational capability and rectify occupational
health and safety and environmental deficiencies currently existing at the
base. The estimated cost of the project is $49.832 million (excluding GST.)
3.2
RAAF Base Darwin was referred to the Committee for inquiry on
18 March 2008.
Conduct of the inquiry
3.3
The inquiry was advertised in the Northern Territory News on
29 March 2008. The Committee received one submission and a confidential
supplementary submission regarding the project costs. A list of submissions can
be found at Appendix A.
3.4
The Committee undertook a site inspection, in-camera hearing and public
hearing on 16 April 2008 in Darwin. A list of witnesses can be found at
Appendix B.
3.5
The transcript of the public hearing as well as the submission to the
inquiry are on the Committee’s website.[1] Plans for the proposed
works are detailed in Submission 1, Department of Defence.
Need for works
3.6
The Department of Defence (Defence) states that the proposed works are
necessary to upgrade the base in response to changing operational needs and
improve base capability to respond to increasing demands.[2]
3.7
Further, Defence states that works are necessary due to the fact that
most facilities on base were originally constructed in the 1940s to 1960s with
repairs following Cyclone Tracy in the 1970s. Facilities are now considered to
be ‘well below current industry and defence standards.’ It was not considered
cost effective to upgrade existing facilities in the majority of cases due to
the age.[3]
3.8
The Committee undertook a site inspection of the proposed works and
noted the age of base and the number of demountables being used as offices. The
Committee considers this to be substandard, particularly given the weather
conditions in Darwin. The Committee finds that there is need for the proposed
works.
Scope of works
3.9
The work consists of five elements as follows:
n Joint Logistics Unit
(North) Headquarters: a single-level building for the co-location of 70 staff
including office space, conference rooms, secure operations area, ablutions,
amenities and parking;
n fuel storage and
reticulation: decommissioning of three small fuel farms and replacement with
new fuel storage facility and associated pumps, services and pipe connection to
existing services and aprons;
n mechanical equipment
workshop: drive-through workshop bays, lubrication/inspection pits and
associated workshops, centralised administrative facility, petrol, lubricant
and battery stores and roads;
n administrative
facility for fuel equipment maintenance section: extension of existing facility
to provide office, library, first aid and storage; and
n vehicle wash bay.[4]
3.10
The Committee has assessed the scope of works and finds them suitable to
provide the facilities necessary to meet the needs of RAAF Base Darwin.
Cost of works
3.11
The total out-turn cost of the work is scheduled to be $49.832 million
(excluding GST) which includes construction costs, management and design fees,
internal fitout, information and communication technology and contingency and
escalation allowance.[5]
3.12
The Committee received detailed cost plans for the project and held an
in-camera hearing with Defence on the full project costs.
3.13
An estimated saving of $700 000 per annum is expected being the current
maintenance costs of the three fuel tanks that will be decommissioned as part
of the project.[6] In addition, savings are
expected through the provision of a purpose-built mechanical equipment workshop
given the increased operating costs imposed by the current inadequate facility.[7]
3.14
The Committee is satisfied that the costings for the project are adequate
and that suitable contingency planning is in place, including deferring
non-essential works should there be budget over-runs in any area, to ensure the
overall budget is not compromised.
Committee comment
3.15
Some concerns were raised about the need to demolish decommissioned
structures rather than put them to alternative use, for example as shade
structures. Defence noted that the age of the structures made it cost
prohibitive to upgrade them and in their existing state they posed a hazard to
those outside the base in the event of a cyclone due to the risk of flying
debris.[8]
3.16
While in this instance the Committee agrees with Defence’s assessment,
its preference is that re-use of existing structures be given priority
consideration in all instances.
3.17
The Committee also notes that common-use facilities are less apparent in
these redevelopment plans than on other bases. Defence explained that there was
only one project element suitable to be used as a common-use facility.[9]
The Committee urges the ongoing consideration of common-use facilities wherever
possible.
3.18
Overall, the Committee is satisfied that this project has merit in terms
of need, scope and cost. No other submissions were received raising issues with
the proposed works. The Committee is therefore satisfied that there are no
reasons to object to the work proceeding.
3.19
Having examined the purpose, need, use, revenue and public value of the
work, the Committee considers that it is expedient that the proposed
redevelopment at RAAF Base Darwin proceed.
Recommendation 4 |
3.20
|
The Committee recommends that the House of Representatives,
pursuant to Section 18 (7) of the Public Works Committee Act 1969,
resolve that it is expedient to carry out the following proposed work: RAAF
Base Darwin Redevelopment Stage 2, Northern Territory.
|