Chapter 4 Australian Federal Police proposed new forensic facility at Majura,
ACT
4.1
The Australian Federal Police (AFP) proposes to deliver a
fit-for-purpose facility that will be fully operational by the end of 2015,
assuring AFP forensic and technical intelligence operations and projected
growth of specialist disciplines over the next 20 years.
4.2
The objectives of the project are to:
- meet current and
future business needs associated with continued growth in forensic requirements
for the next 20 years
- overcome increasing
risks associated with poor design and non-compliance with contemporary building
standards of the currently leased facility
- resolve potential
problems associated with expiry of the current lease at Weston or decisions of
the landlord which may affect the future use and intent of the property
- enable important
productivity gains through system and business process reforms, based on
fundamental redesign of the workplace and application of the collaborative
forensic model
- overcome constraints
that inhibit the implementation of new and future forensic and technical
intelligence capabilities.[1]
4.3
The cost of the project is $106 million, excluding GST.
4.4
The project was referred to the Committee on 29 November 2012.
Conduct of the inquiry
4.5
Following referral to the Committee, the inquiry was advertised on the
Committee’s website, by media release and in the Canberra Times
newspaper.
4.6
The Committee received one submission and one supplementary submission
from the AFP. The list of submissions can be found at Appendix A.
4.7
The Committee received a private briefing and conducted a site
inspection, a public hearing and an in-camera hearing on 8 February 2013 in Canberra.
4.8
A transcript of the public hearing and the submission to the inquiry are
available on the Committee’s website.[2]
Need for the works
4.9
The AFP’s ability to perform its role in forensic science and technical
intelligence, both now and in the future, is constrained by a number of key problems
and challenges with the current facility at Weston.
4.10
These constraints include:
- anticipated growth in
forensic requirements
- functional design
problems
- site planning and
tenure constraints
- vulnerable forensic
systems and processes.[3]
4.11
During its inspection of the AFP’s current facilities in Weston, the
Committee viewed an evidence collection space, the armoury and a demountable
forensic laboratory. The Committee notes that these spaces were crowded and limited
the efficiency of the AFP’s evidence collection and analysis. The Committee
also observed a lack of storage space, particularly in the armoury.
4.12
The AFP considered four options to meet the need for improved forensic
facilities:
- do a minimal upgrade
of the existing Weston facility
- do a major refurbishment
and upgrade of the existing Weston facility
- lease a new
purpose-built facility
- construct a new
purpose-built facility at the AFP’s Majura Complex.[4]
4.13
The Committee is satisfied that the AFP considered various options for
improving its forensic capabilities. The Committee commends the AFP for
providing detail on each option’s advantages and disadvantages, and for clearly
outlining in the public submission why it chose the fourth option.[5]
4.14
The Committee is satisfied that there is a need for the works.
Scope of the works
4.15
The facility would accommodate the following specialist forensic and
technical intelligence disciplines:
- Australian Bomb Data
Centre
- Australian Chemical,
Biological, Radiological and Nuclear Data Centre
- Crime Scene Sciences
- Forensic Intelligence
- Search Precinct
(combining Exhibit Management and Rapid Laboratory)
- Facial
Identification, Imagery and Geometrics
- Firearms
Identification and Armoury Team (FIAT)
- Fingerprint
Identification
- Biological
Criminalistics
- Chemical
Criminalistics
- Electronic Evidence
(Computer Forensics and Audio & Video Signal Processing)
- Document Sciences
- Planning, Deployment
and Systems (combining Operational Planning and Deployment and Operational
Systems)
- Policy Projects and
Planning
- Capability
Development and Training
- Executive, Chief
Scientist and Quality Management.[6]
4.16
The facility will comprise the following spaces:
- office spaces
- conferencing and
training laboratory facilities
- meeting rooms
- laboratories
(biological, chemistry, document sciences, ballistics, fingerprint, specialist
hazards)
- search precinct
- exhibit storage
- Fire Arms Identification
and Armoury Team (industrial areas)
- central store and logistics
(general storage, garaging/vehicle store, workshops)
- mechanical plant
rooms
- staff facilities.[7]
4.17
Subject to Parliamentary approval, construction is planned to commence
in late 2013 and be completed by mid-2015.[8]
4.18
The Committee finds that the proposed scope of works is suitable to meet
the need.
Cost of the works
4.19
The cost of the project is $106 million, excluding GST. The Committee
received a confidential supplementary submission detailing the project costs
and held an in-camera hearing with the AFP on these costs.
4.20
The Committee is satisfied that the costings for the project provided to
it have been adequately assessed by the proponent agency.
Project issues
Childcare
4.21
The AFP’s submission stated that the new facility does not have any
provision for childcare.[9] At the public hearing, the
AFP indicated that it has a predominantly female workforce, and explained why
childcare provisions have not been included:
We are very aware of the implications that you are talking
about. We have had the same concerns. We had the same question about what needs
needed to be met. As a consequence, we ran a survey of our staff.
Of the Weston based staff, we had 92 respondents to that
survey—which is approaching half of our staff—of which, 84.8 per cent do not
currently use childcare facilities. Where they did use childcare facilities,
the preference was to have childcare facilities in closer proximity to their
home than the workplace. For them that was logistically the best option and
gave them greater flexibility. So we are fairly satisfied that we did not need
to pursue a childcare facility on site. Although we are aware that there are
two childcare facilities in close proximity, at Brindabella Park and Majura
Park.[10]
Committee comment
4.22
The Committee accepts that the AFP sought and considered the views of
its staff in assessing the need for a child care facility in the project.
Construction traffic and site security
4.23
The AFP stated that construction traffic will have a minimal impact on
local traffic networks.[11] The access and exit
point for construction activities and traffic at the Majura site will be
separate from the staff entry:
There is a side road adjoining Defence to the north of the
property that we will use as the access point for all of the construction
works.[12]
4.24
The AFP also affirmed that it would institute security measures to keep
the construction and staff areas of the site separate:
We expect that the 300-odd workers, together with heavy
vehicles and all the rest of it, can be quite quarantined from the AFP
operations to the front of the property.
We are looking at the measures applicable there in terms of
making sure that the areas that are construction zones are dedicated and zoned
off accordingly [from the operational areas of the Majura Complex].[13]
Committee comment
4.25
The Committee accepts that the AFP has considered the traffic and
security issues that surround construction on an operational site, and that the
AFP will make arrangements to ensure that the construction activities do not
impinge on the traffic flow or security of the Majura Complex.
Final Committee comment
4.26
The Committee commends the AFP for its clear, comprehensive, accurate
and succinct presentation of information in the submissions, private briefing,
inspection, public hearing and in-camera hearing.
4.27
The Committee considers this inquiry to be an example of efficient and satisfactory
participation in the inquiry process. In particular, the Committee appreciates
the clear presentation of relevant information in a logical order to justify
the need, scope and cost of the project.
4.28
Further, the Committee encourages other proponent agencies to use the
AFP’s experience as an excellent example of how to proceed with an inquiry.
4.29
The Committee found that the new facility has been designed to enable
more efficient business processes. The Committee acknowledges that the new facility
will increase the capabilities of the AFP.
4.30
The Committee met many AFP personnel during the briefing and inspection
and thanks them for their contributions to the inquiry.
4.31
The Committee was satisfied with the evidence provided by the AFP
regarding the proposed new forensic facility at Majura, ACT. The Committee is
satisfied that the project has merit in terms of need, scope and cost.
4.32
Having regard to its role and responsibilities contained in the Public
Works Committee Act 1969, the Committee is of the view that this project
signifies value for money for the Commonwealth and constitutes a project which
is fit for purpose, having regard to the established need.
Recommendation 2 |
|
The Committee recommends that the House of Representatives
resolve, pursuant to Section 18(7) of the Public Works Committee Act 1969,
that it is expedient to carry out the following proposed work: Australian
Federal Police proposed new forensic facility at Majura, ACT. |