Chapter 8 Infrastructure and upgrade works to establish a regional
processing centre on Manus Island, Papua New Guinea
8.1
The Department of Immigration and Citizenship (DIAC) proposes to
construct a permanent regional processing centre (RPC) on Manus Island, Papua
New Guinea.
8.2
The purpose of the project is to implement the recommendations of the
Expert Panel on Asylum Seekers Report, by establishing the capacity to process
transferee claims at permanent facilities on Manus Island. The permanent RPC will
replace the temporary facility currently in use.
8.3
The cost of the project is $171.69 million.
8.4
The project was referred to the Committee on 21 March 2013.
Conduct of the inquiry
8.5
Following referral to the Committee, the inquiry was advertised on the
Committee’s website, by media release and in The Australian and the Australian
Financial Review newspapers.
8.6
The Committee received one submission and eleven supplementary
submissions from DIAC. The Committee also received submissions from various
organisations and individuals. The list of submissions can be found at
Appendix A.
8.7
The Committee received a private briefing on the project and conducted a
public hearing and an in-camera hearing on 1 May 2013 in Melbourne.
8.8
A transcript of the public hearing and the submissions to the inquiry
are available on the Committee’s website.[1]
Need for the works
8.9
The Expert Panel on Asylum Seekers Report outlined an expectation that
asylum seekers who have their claims processed on Manus Island will be provided
with protection and welfare arrangements consistent with Australian and Host
Nation responsibilities under international law.
8.10
Those protections and welfare arrangements include treatment consistent
with human rights standards, appropriate accommodation, appropriate physical
and mental health services, and access to educational training programs. For
these reasons, the proposed works will provide a level of amenity consistent
with the features of Australian mainland immigration detention centres.
8.11
Transferees may be accommodated on Manus Island for an extended period
in consideration of the ‘no advantage’ principle which states that Refugee
Status Determination (and re-settlement of those found to be refugees) will not
receive a higher priority than for refugees in transit countries. As a result,
there is an urgent need to establish permanent facilities.[2]
8.12
The existing temporary facility has a very limited life span, provides
little amenity for transferees, and does not have the adequate infrastructure
required to support the processing of claims.[3]
8.13
The Committee is satisfied that there is a need for the works.
Scope of the works
8.14
The works will include the following facilities:
- A 600 person regional
processing centre able to accommodate families and other vulnerable groups and
other cohorts if required
- Health, welfare and
recreational facilities
- Staff accommodation
for 200
- All engineering
infrastructure to support the facility.[4]
8.15
The Committee finds that the proposed scope of works is suitable to meet
the need.
Cost of the works
8.16
The project cost is $171.69 million. The Committee received a
confidential supplementary submission detailing the project costs and held an
in-camera hearing with the proponent agency on these costs.
8.17
The Committee is satisfied that the costings for the project provided to
it have been adequately assessed by the proponent agency.
Project issues
Land agreement and lease arrangement
8.18
The RPC will be built on a site called Portion 244 near Lorengau, Manus
Island. DIAC stated that final agreement on the land and the lease arrangements
are yet to be confirmed, although there is a high level of certainty that this
will occur:
… we have been given agreement from the Papua New Guinea
government that 244 is agreed. The processes that need to occur within the
Papua New Guinea government for the transfer of title to the Papua New Guinea
Immigration & Citizenship Service Authority, who will then proceed to
negotiate a lease with the Australian government for access to it. We do not
have a lease in place yet. Our intention therefore would be to include in that
lease a term of 15 years with options for further renewal. That is consistent
with what we have achieved on Nauru, where we have a 20-year lease for the
sites that we are constructing on Nauru.[5]
8.19
DIAC also indicated that a memorandum of understanding and the
underpinning administrative arrangements have been agreed between Australia and
Papua New Guinea. These agreements refer to the lease.[6]
Committee comment
8.20
The Committee is satisfied that DIAC has taken all required steps to
ensure the required land and lease agreements for the RPC will be confirmed in
the near future.
Size and location of Portion 244 and the RPC
8.21
The current temporary site is approximately 2.5 hectares and has
capacity for approximately 500 clients. In comparison, Portion 244 is 102
hectares, of which approximately 40 to 50 hectares at the front of the site
will be used for the RPC. It would have capacity for 600 clients and 200 staff.[7]
The site is located on the outskirts of the town of Lorengau.
8.22
DIAC also clarified that the new site is approximately a 45 minute drive
from the temporary site.[8]
Committee comment
8.23
The Committee notes that Portion 244 is significantly larger than the
existing temporary site, without a proportional increase in the number of
clients.
Design of the RPC
8.24
DIAC explained that the RPC is not an immigration detention centre, and
as such, would have different security arrangements:
The intention of all three governments—Nauru, Papua New
Guinea and Australia—in agreeing to establishing the regional processing
centres was that they would be open—that is, that transferees would have the
capacity, once effective arrangements were developed and agreed and put in
place, for people to come and go during daylight hours. There would be an
evening curfew, largely for the safety of transferees, and in the event that
there were public disturbances that occurred, once again, for the safety of the
remainder of the community, a gate would be able to be closed that would
prevent freedom of access from inside—movement both sides of the centre.
As you know, in immigration detention centres in Australia
and on Christmas Island in particular, there is quite sophisticated electronic
detection and deterrent system fencing in place. That would not be in place for
the regional processing centres. The type of fencing that would be in place
would be standard what we would call pool-fence perimeter fencing. There would
be a standard gate—no more than you would see in many rural properties or
industrial properties in Australia—that could be closed or opened to regulate
access, to operate both in normal operation and, if necessary, the closed down
operation.[9]
8.25
Accordingly, although the design of the facility is based on DIAC’s Standards
for the Design and Fitout of Immigration Detention Facilities[10],
there are some key differences:
The design for the Manus Island Regional Processing Centre
has been guided by the performance criteria of the [standards] but will apply
its own acceptable design solution that addresses the unique site conditions,
local climate and that can provide flexibility in accommodating different
client cohorts and family groupings. The Centre therefore does not differ from
the [standards] but uses the design principles embodied in them to inform the
masterplan.[11]
8.26
DIAC believes that the design of the RPC meets all of the
recommendations of the report of the Expert Panel on Asylum Seekers.[12]
8.27
DIAC confirmed that the design provides for the physical separation of
clients, such as children and single adult males.[13]
8.28
DIAC has consulted with key stakeholders, including the Papua New Guinea
government, and will conduct ongoing consultation with them, existing and
future service providers and transferees as the project progresses.[14]
DIAC also noted that it receives input from a ministerial council on asylum
seekers and a health immigration advisory committee.[15]
8.29
The design of the RPC will provide suitable facilities for the Manus
Island climate. DIAC explained that air conditioning will be included in the
staff quarters, but not throughout the general living facility:
The standard of accommodation that we are looking to provide
for the transferees is the standard of accommodation that is available for
people who are normally resident on Manus. The staff who are not locals and
therefore for whom we need to provide accommodation at the centre are, by and
large, at least at this stage, people who have been recruited from Australia.
They are used to a standard of accommodation that they would find in Australia
and many of them may not necessarily live in a tropical environment. So we are trying
to provide the balance between sympathy with the local community and the
capacity to attract and retain skilled staff to deliver the services.[16]
… while the client accommodation in the three compounds is
not air conditioned, they do meet better practice design, as I understand, in
terms of how air can flow through them and such. So while you have got the
local Manus population and what they have got, the design of these is quite
contemporary in terms of ventilation and a range of other areas—not being air
conditioned but not being something that does not get the air flow.[17]
8.30
This design principle has also been implemented in Nauru. DIAC reported
that this has significantly improved ventilation and cooling in the Nauru accommodation.[18]
Committee comment
8.31
The Committee is satisfied that the design of the RPC addresses the
specific requirements of Manus Island, and meets DIAC’s standards.
8.32
The Committee appreciates DIAC’s willingness to engage in consultation
regarding the design of the RPC. The Committee expects DIAC to continue this
approach and to enable increased consultation wherever possible, particularly
with the organisations that provided submissions to this inquiry.
8.33
The Committee notes that some communal areas will be air conditioned. The
Committee expects DIAC to monitor this and other design issues and address them
where necessary.
Delivery of the project
8.34
DIAC assured the Committee that it has the experience to deliver this
project on time, on budget and fit-for-purpose:
We have an onshore detention network of 23 centres that we
have worked on over time. In the course of the last five years, I think we have
done between 12 and 15 of those.[19]
8.35
DIAC indicated that despite Nauru being a challenging environment, DIAC
is on track to complete the facilities there. DIAC also confirmed that it has
learnt from the experiences of past on- and off-shore facilities, and has
engaged with the relevant experts to ensure this RPC meets best practice.[20]
Committee comment
8.36
The facilities in Nauru were subject to an urgency motion in the House
of Representatives, thus excluding them from an inquiry by the Committee. Despite
this, DIAC has provided to the Committee regular updates on the progress of the
works in Nauru. The Committee thanks DIAC for enabling scrutiny of the project
in this manner.
8.37
Given DIAC’s experience in delivering these projects, and the fact that
this project is based on the ones in Nauru, the Committee expects that it will
also be delivered on time, on budget and fit-for-purpose.
Climate, health and education
8.38
Climate, health and education concerns were raised during the public
hearing. DIAC described the climate of Manus Island as similar to that of
northern Australia:
[Manus Island] is situated a few degrees south of the
equator. It is a very tropical environment, not dissimilar to that which you
would encounter in northern Australia and Christmas Island. Rather than the
traditional four seasons, it is more like a monsoonal two seasons—a wet season
and a dry season. It has very lush, tropical vegetation, which comes about
because of heavy rains during the wet period. It is not affected by cyclones,
but it is affected by monsoonal rain. There are times of the year when it is
quite hot and has high humidity. There are other times of the year when it is
less hot but still quite warm without necessarily the high levels of humidity.[21]
8.39
DIAC provided a supplementary submission that demonstrated that flooding
of the RPC site had been considered and was not an issue.[22]
8.40
The RPC will have self-sufficient waste management systems and power
supplies, although DIAC intends to use local drinking water:
The intention is to make use of the Lorengau town water
supply. The indication so far is that that water supply is of very good
quality, but we will also be putting in place water management arrangements in
the centre which will further ensure that we have good quality water made
available for transferees.[23]
8.41
The RPC will draw on both local and imported food supplies:
If you look at what we have done in Nauru, for example, our
garrison provider has initially brought in supplies from offshore and, in the
processing of establishing, has looked at local providers and proceeded to
develop in concert with those local providers a strategy where gradually we
shift from total importing arrangement to a joint procurement arrangement with
the local providers so that we do not all of a sudden swamp the local market
and denude it of its full access to products. It is the same sort of approach
we are adopting in Manus. Initially we bring in all of our supplies externally
and then over time develop arrangements with local providers to gradually
replace that with local providers.[24]
8.42
However, DIAC would ensure that it would have contingency measures:
So in the event that we had supply difficulties we would have
identified alternative supply measures. It also goes to the quantity of
material that is held in supply, to cover off that eventuality. It is the same
experience that we had in place, for example, with Christmas Island. We go
through the same sort of contingency planning because of the high reliance on
Christmas Island around a regular ship transport of foodstuffs, goods and
materials. Sometimes there are weather problems that delay that ship, so it
goes to things like that around managing inventory supplies.[25]
8.43
With regard to health, malaria is a key issue on Manus Island:
We have put in place a very active management strategy for
managing that risk. We would propose to continue with an active management
strategy in the permanent centre once it is operating.[26]
8.44
DIAC has undertaken health risk assessment activities for the existing
temporary site and the proposed RPC:
Together with our healthcare provider IHMS, we have done a
full health risk assessment prior to the establishment of the temporary centre.
We will continue to work with them to manage any additional risks that might
emerge and obviously, as we get closer to the operation—the stand-up of the new
centre—and as we move into an operational mode, there will be a full
operational risk assessment from a health perspective for that permanent site.
We will be consulting with them throughout the design and construction process
as well.[27]
8.45
DIAC also provided further details on the assessments undertaken in a
supplementary submission.[28]
8.46
DIAC outlined its strategy for managing the risk of malaria:
… we already have a very active management strategy for
managing the risk of malaria with, for example, extensive fogging programs
undertaken at the site. We will put in place appropriate management plans to
deal with … health risks in the site. Once we get closer to finalising the
construction we will have a better idea of the topography of where the various
risk elements lie and what the different strategies are that we need to put in
place to manage that. It would be the same as what we have done, for example,
with the operation of Wickham Point where one of the risks identified during
the commissioning phase there was a large number of biting insects. I believe
this is the first facility we have in Australia with a biting insect management
plan. That is unique to that particular site. We would similarly have a full
risk assessment and the implementation of appropriate plans to deal with those
health risks.[29]
8.47
Regarding education and recreation, DIAC stated that a range of
facilities would be available:
… for example, faith rooms for the different cultural groups
who might be accommodated there to worship in. There will be a classroom to
provide lessons for children. There will be a programs and activities space
where a range of activities could occur that could be as diverse, say, as
English language classes through to cooking demonstrations, bingo or card
playing. There will be a basic gymnasium space for people to have physical
exercise and a range of those facilities similar to what you would see in our
onshore detention network would be made available.[30]
8.48
This will include ensuring that children will have access to relevant
educational facilities. DIAC stated that the teachers currently on Manus Island
hold full teaching accreditation in Australia.[31]
Committee comment
8.49
The Committee is satisfied that DIAC has considered these climate,
health and education issues. The Committee expects DIAC to continue to assess
the suitability of its services, and to adapt them to meet the needs of clients.
Final Committee comment
8.50
The Committee was satisfied with the evidence provided by the Department
of Immigration and Citizenship regarding the proposed project. The Committee is
satisfied that the project has merit in terms of need, scope and cost.
8.51
Proponent agencies must notify the Committee of any changes to the
project scope, time and cost. The Committee requires that a post-implementation
report be provided on completion of the project. A template for the report can
be found on the Committee’s website.
8.52
Having regard to its role and responsibilities contained in the Public
Works Committee Act 1969, the Committee is of the view that this project
signifies value for money for the Commonwealth and constitutes a project which
is fit for purpose, having regard to the established need.
Recommendation 7 |
|
The Committee recommends that the House of Representatives
resolve, pursuant to Section 18(7) of the Public Works Committee Act 1969,
that it is expedient to carry out the following proposed work: Infrastructure
and upgrade works to establish a regional processing centre on Manus Island,
Papua New Guinea. |