House of Representatives Committees

Chapter 2 The Proposed Works

Purpose
Need
Scope
Project Delivery
Cost

Purpose

2.1

The purpose of the proposed work is to provide 50 houses to meet the operational requirements of Defence, mainly to service the nearby Enoggera Army Base. It is intended that the houses will be ready for occupation in November 2006.

 

Need

2.2

The proposed project will represent the total of new houses to be constructed by DHA in Brisbane for the 2006/07 financial year.

2.3

While the number of Defence personnel is not expected to increase dramatically over the next three years, DHA states that the proposed new housing is required to reduce reliance on Rental Assistance. At present, 24 per cent (336 houses) of the Defence housing requirement in Brisbane is provided through Rental Assistance.

2.4 DHA believes that, in areas where the demand for Defence housing is high, constructed housing delivered through bulk procurement contracts represents the best provisioning option.
 

Scope

2.5

The proposed development will comprise:

 

Project Delivery

2.6 It is anticipated that the project will be delivered by means of a competitive lump sum tender by experienced developers from the local construction industry.
 

Cost

2.7 The estimated overall project cost is $17.5 million. This figure includes:


Footnotes

  1. Appendix C, Submission No. 1, paragraph 22.2 Back
Print Chapter 2 (PDF 46KB) < - Report Home < - Chapter 1  : Chapter 3 - >

Back to top

We acknowledge the traditional owners and custodians of country throughout Australia and acknowledge their continuing connection to land, waters and community. We pay our respects to the people, the cultures and the elders past, present and emerging.

Aboriginal and Torres Strait Islander people are advised that this website may contain images and voices of deceased people.