The strategic provisioning plan developed by DHA to meet Defence needs in Darwin includes the construction of some 300 residences at Lee Point , with delivery spread over four to five years commencing in December 2005.3
|
Scope |
|
DHA’s strategic provisioning plan for Darwin includes construction of at least 300 Defence residences at Lee Point, with delivery spread over five years from December 2005.4
- Works to be undertaken at the site will include:
- installation of infrastructure and essential services including roads, drainage, water reticulation, sewerage, electricity, and telecommunications;5
- landscaping;6 and
- construction of approximately 725 dwellings
|
|
|
Project Delivery |
2.5 |
The project will be managed as a joint venture between DHA and a private developer7 |
2.6 |
The project will by financed by DHA by any or all of the following means:
- sale of surplus housing stock;
- public sale of development houses;
- sale and leaseback scheme profits;
- surplus operating capital; and/or
- debt financing.8
|
Cost |
2.7 |
The total estimated cost of the proposed project is $41, 381,480. This cost includes:
- Goods and Services Tax;
- construction costs;
- civil works;
- headworks charges;
- contingency; and
- professional fees.9
|
1 |
Appendix C, Submission No. 1 from the Defence Housing Authority, paragraph 1.1 Back |
2 |
Appendix C, op cit, paragraph 2.2 Back |
3 |
Appendix C, op cit, paragraph 2.3 Back |
4 |
ibid Back |
5 |
Appendix C, op cit, paragraphs 12.1 – 13.4 Back |
6 |
Appendix C, op cit, paragraph 16 Back |
7 |
Appendix C, op cit, paragraph 23.1 Back |
8 |
Appendix C, op cit, paragraph 22.1 Back |
9 |
Appendix C, op cit, paragraph 21.1 Back |