Chapter 3 Fitout of Tuggeranong Office Park, Greenway, ACT
3.1
The fitout of leased premises at Tuggeranong Office Park (TOP) is
proposed to provide office accommodation for the Department of Families,
Housing, Community Services and Indigenous Affairs (FaHCSIA). The estimated
cost of the project is $29.8 million (including GST).[1]
3.2
The project was referred to the Committee on 4 June 2009.
Conduct of the inquiry
3.3
The inquiry was advertised in local and national newspapers and
submissions sought from those with a direct interest in the project. The
Committee received two submissions and one confidential supplementary
submission detailing the project costs. A list of submissions can be found at
Appendix A.
3.4
The Committee undertook a site inspection on 4 August 2009 followed by a
public hearing and an in-camera hearing on the project costs. A list of
witnesses can be found at Appendix B.
3.5
The transcript of the public hearing as well as submissions to the
inquiry are detailed on the Committee’s website. Plans for the proposed works
are detailed in Submission 1: Department of Families, Housing, Community
Services and Indigenous Affairs.[2]
Need for works
3.6
The FaHCSIA submission states that the works are needed to:
n provide accommodation
to an appropriate standard for staff;
n consolidate existing
leases and co-locate staff currently located across eight sites (including TOP);
n mitigate a range of
high-risk occupational health and safety building issues;
n demonstrate the
highest level of disability access standards;
n improve physical
security in line with government standards.[3]
3.7
At the site inspection, FaHCSIA noted that it employed a high number of
people with disabilities and the site currently does not meet appropriate
standards. The Committee observed this at the site inspection and agrees that
there is significant need for the premises to be brought up to standard.
3.8
Therefore, the Committee finds that there is a need for the proposed
works.
Scope of works
3.9
The proposed scope of works is detailed in Submission 1: FaHSCIA. In short,
the project will provide:
n base building works,
including:
- lift
upgrades;
- removal
of hazardous materials; extension of handrails, upgrading stairs to comply with
access standards, extend balustrade and panels to terrace and balcony openings;
- replace
Building Management System; upgrade Data Centre diesel generator controls;
replace and upgrade chiller controls and refrigerant monitoring system and
water treatment system;
- replacement
of emergency and exit light fittings; and
- replacement
of fire and smoke detectors and signage to comply with current regulations.
n tenancy upgrades,
including:
- upgrade
of the mechanical system to provide better environmental performance through
replacement of sheathed ducting, rectifying leaks, additional temperature
sensors and improvement in room design to make use of natural light;
- electrical
and hydraulic services upgrade;
- provisions
for people with disabilities and compliance with the Draft Disability (Access
to Premises – Buildings) Standards, which will include reconfiguring doorways,
toilets and kitchens.
n office fitout
including:
- internal fitout
of blocks A, B and C[4], retaining workstations,
partitions and storage units where possible;
- sub-floor
structural support;
- new floor
finishes and paint; and
- upgrading
mechanical, electrical, hydraulic and fire services.[5]
Additional works
3.10
In addition to the proposed works, a range of other works have been
undertaken at TOP, namely:
n Block A minor fitout
project to ... accommodate staff who relocated from three expiring leases in
Canberra in August 2008;
n Replacement of the
obsolete and failing Electronic Access Control System at TOP;
n Replacement of the
obsolete Fire Indicator Panel for TOP;
n Fitout of 6,450
square metres of office space in Block E to accommodate information management
and technology staff relocating from four expiring leases in Canberra by 29
June 2009; and
n Fitout of 6,484
square metres of office space in Block D to accommodate staff relocating from a
large Woden lease in 2010.[6]
3.11
The notification of these works is discussed below.
3.12
At the site inspection, the Committee noted the poor condition of some
parts of the site, including the poor access arrangements for people with
disabilities. The Committee is pleased to note that the planned works will
significantly improve the amenity for people with disabilities.
3.13
The Committee finds that the proposed scope of works is suitable to meet
the stated need for the project.
Cost of works
3.14
The total cost of the proposed works is scheduled to be $29.8 million,
including GST. The Committee received a confidential submission detailing the
project costs and held an in-camera hearing with FaHCSIA on the detailed
project costs.
3.15
The Committee commends FaHCSIA for the quality of the cost summary
submitted as part of this inquiry.
3.16
However, additional works were completed without notification to the
Committee as outlined above. In total, $15.205 million worth of additional
works have either been commenced or completed. Therefore, the total cost of
works at TOP for FaCHSIA is in the order of $45 million.
Lease period and obligations
3.17
These fitout works refer to a lease period of seven years. The short
lease has arisen due to the sale of TOP and the continued tenancy of FaHCSIA as
a condition of the sale. The leasing arrangement negotiated as part of this
sale placed significant fitout responsibilities on FaHCSIA. The Committee was
told:
The building was privately financed with the Commonwealth
guaranteeing a rental stream for investors for seventeen years under the terms
of a lease known in the industry as a 'triple net lease', after which the
building would be sold with proceeds returning to the Government. The original
lessee was with the Department of Social Security, which subsequently split to become
Centrelink and FaHCSIA. Centrelink managed the facility on behalf of the Commonwealth
until it relocated to the Caroline Chisholm Centre in May 2008. At this time, FaHCSIA
assumed responsibility for the management of the complex.
A trust deed with a sinking fund provided for a $30 million
refurbishment in 2001, by the then owner, TOP Pty Ltd. The refurbishment was
subject to there being sufficient monies in the sinking fund after liabilities
to the bond holders were extinguished. TOP Pty Ltd, in July 2006, advised that
the funds were not available for the refurbishment. FaHCSIA understands that
the shortfall in the value of the sinking fund was a trigger for the sale of
the building.
The building was sold in June 2008 with the similar sub-lease
arrangements to those previously in place, but excluding the requirement for
the new owners to undertake the $30 million refurbishment of the facility.
Under the conditions of the sale of TOP to the Cromwell
Group, FaHCSIA as the current tenant was required to enter into a new eight and
a half year sub-lease for the premises, based on similar triple net lease
terms.
The sub-lease details are summarised as follows:
n Sub-lease
commencement - 30 June 2008
n Sub-lease expiry - 5
December 2016
n Rental, Outgoings,
Repairs and Maintenance Costs and Responsibilities - The lease requires that
the tenant effectively assumes the normal 'building owner' responsibilities for
statutory and operating outgoings, maintenance, building management and major
repair expenditure for the premises in addition to paying the rent. Under the
lease the building owner only has responsibility to replace certain assets once
they are no longer economically repairable.[7]
3.18
FaHCSIA noted that:
The cash flows that we worked with assumed a substantial
incentive from the market, if we went to the market in 2016. One of the reasons
to select the option for the current way forward was that we would access the
market at maximum market participation for any future property acquisition, including
the option to stay at TOP, long term.[8]
3.19
The Department of Finance and Deregulation (Finance) confirmed that the
sinking fund was used to pay investors rather than fund building refurbishment.
Finance also confirmed that this arrangement was put in place when TOP Pty Ltd
was established in 1988.[9]
3.20
The Committee has serious concerns that the sale negotiations have left
FaHCSIA in an untenable position in regards to funding necessary fitout works. Nonetheless,
FaHCSIA did provide independent evidence that the cost plan had been assessed
to be reasonable in the current construction environment. The Committee also notes
that the fitout cost per m2 is lower than average and received
assurances that furniture and fittings would be reused wherever possible to reduce
costs.
3.21
The Committee acknowledges that FaHCSIA has little control over the
terms of its lease due to the building sale conditions and is thus required to
undertake a range of works under the terms of its lease. In addition, the
Committee acknowledges that there are savings to be made with the consolidation
of existing leases.
3.22
The Committee is satisfied that the cost plans for the project as
presented to it and discussed at the in-camera hearing are adequate.
Project issues
Works completed without approval
3.23
In May 2009, FaHCSIA notified the Committee that a number of ‘early
works’ had already been completed. Some of these works were relatively minor
and therefore fall under the threshold for individual notification to the
Committee, namely:
n minor fitout works at
Block A in August 2008 at a total cost of
$1.02 million;
n replacement of the
electronic access control system at a total cost of
$670 000.
n replacement of the
fire indicator panel at a total cost of $285 000.[10]
3.24
Two packages of works were also commenced that require individual
notification to the Committee as ‘medium works’, namely:
n fitout of 6450 square
metres of office space in Block E at a total cost of $7.22 million;
n fitout of 6848 square
metres of office space at Block D at a total cost of $6.01 million.[11]
3.25
The Committee was not notified of these works until 20 May 2009.
Although the delivery of these works was appropriate to manage various leases
ending, these works should not have commenced without the approval of the
Committee as ‘medium works’.
3.26
The Committee acknowledges that FaHCSIA has disclosed the failure to
provide appropriate notification on the public record:
FaHCSIA acknowledge that formal notification should have been
provided to the Public Works Committee at the time of Commissions Block E in
July 2008. FaHCSIA has taken steps to ensure that it has a clearer
understanding of our responsibilities to notify the Public Works Committee of
such projects.[12]
3.27
Nonetheless, the additional works completed without the appropriate
parliamentary approvals are a matter of serious concern for the Committee,
particularly as the works already completed form part of the fitout of TOP as
referred to this Committee.
3.28
The Committee considers that the failure to notify it of these works
represents a lack of awareness in agencies of their obligations in relation to
the Public Works Committee.
3.29
The Committee is aware that the Department of Finance and Deregulation
(Finance) is in regular contact with all government agencies regarding the
requirements of the Act and that both Finance and the committee secretariat are
available to provide advice to agencies whenever required.
3.30
The Committee has since received further notifications of medium works
being undertaken by FaHCSIA and is satisfied that FaHCSIA is now aware of its
obligations to the Committee.
3.31
However, the Committee also notes that the failure to notify it of works
occurs on occasion for those agencies which only undertake capital works irregularly,
largely due to the loss of corporate knowledge that occurs with staff turnover.
3.32
Therefore, the Committee is recommending that FaHCSIA document its
procedures for notifying ‘medium works’ to the Public Works Committee and
provide these procedures to Finance for circulation as it deems appropriate in
order to assist other agencies to avoid breaching the Committee’s Act and
procedures.
3.33
The Committee encourages FaHCSIA to liaise with the committee
secretariat on the development of these procedures and requests to be provided
with the procedures once finalised.
Recommendation 2 |
|
The Committee recommends that the Department of Families,
Housing, Community Services and Indigenous Affairs document procedures for notifying
‘medium works’ to the Public Works Committee and provide these to the
Department of Finance and Deregulation for circulation as appropriate. |
Environmental standards
3.34
All commonwealth agencies have an obligation to undertake building
fitout to a 4.5 star rating under the National Australian Built Environment
Rating System (NABERS). Agencies are also required to meet the requirements of
the Energy Efficiency in Government Operations (EEGO) policy.
3.35
FaHCSIA told the Committee that given the short lease period, it may be
difficult to reach the 4.5 star rating on Block E, which contains the
Centrelink Data Centre, but the rating would be met in all other areas of TOP.[13]
3.36
The Committee notes that FaHCSIA is working closely with the Department
of Environment, Heritage, Water and the Arts and has every intention to comply
with these standards.
3.37
In addition to fitout standards required under NABERS and EEGO, FaHCSIA
is implementing the following:
n The establishment of
a rainwater collection system for the artificial river which runs between the
east and west wings of the buildings. The current system is supplemented with
potable water from the main water supply which increases costs to FaHCSIA and
is not an efficient use of this resource;
n The establishment of
improved waste management and recycling systems including the installation of a
green waste composting facility.
n Improved monitoring
of the diesel storage tank systems which service the Centrelink Data Centre
power generation systems to protect the Murrumbidgee Corridor and catchments;
n Other water recycling
and reduction measures including the waterless urinals, low water using shower
heads, dishwashers, faucets and grey water recycling for the grounds
maintenance where cost effective; and
n Reuse of existing
furniture and partitioning where appropriate.[14]
3.38
In particular, the Committee commends FaHCSIA for the significant number
of rainwater tanks being installed at TOP. The site hosts an artificial river
which is currently serviced by potable water. The tanks will allow this river as
well as other grounds maintenance to be serviced with grey water. Including the
cost of installation, savings are expected to be in the order of $30 000 to $40
000 per year.[15]
3.39
The Committee is extremely pleased to see the use of rainwater tanks as
part of this fitout, particularly given the limitations related to the lease
payback period placed on FaHCSIA as discussed above. In this regard, the
Committee considers that FaHCSIA is setting an example that other agencies
should be working towards.
Committee comment
3.40
Overall, the Committee is satisfied that this project has merit in terms
of need, scope and cost. The Committee is satisfied that FaHCSIA is responding
appropriately to the need to provide improved working conditions for staff
balanced with the short term of the building lease.
3.41
Having examined the purpose, need, use, revenue and public value of the
work, the Committee considers that it is expedient that the proposed works
proceed.
Recommendation 3 |
|
The Committee recommends that the House of Representatives
resolve, pursuant to Section 18 (7) of the Public Works Committee Act
1969, that it is expedient to carry out the following proposed work:
fitout of leased premises at Tuggeranong Office Park, Greenway, ACT. |
Senator the Hon Jan
McLucas
Chair
10 September 2009