Chapter 5 Larrakeyah housing
project budget update
5.1
In 2009, the Parliamentary Standing Committee on Public Works conducted
an inquiry into the proposed construction and renovation of housing for defence
at Larrakeyah Barracks, Darwin. The works were proposed by Defence Housing
Australia (DHA), and had an estimated total cost of $57.6 million (including
GST) or $52.4 million (excluding GST).
5.2
This budget figure was included in the statement made by the
Parliamentary Secretary for Defence Support, when the proposal was referred to
the Committee for inquiry on 17 September 2009. The Committee undertook an
inquiry between September and November 2009.
5.3
The Committee tabled its report on 23 November 2009. The House of
Representatives resolved that it was expedient for the works to proceed on 26
November 2009.
5.4
In early 2011, DHA wrote to the Committee seeking its agreement for the
project to proceed with an amended budget. The original budget proved to be
insufficient to complete the works, and DHA proposed both a reduced scope and larger
budget to complete the project.
5.5
The Committee held a public hearing into the budget problems on
21 March 2011, and subsequently agreed to the project proceeding with an
amended budget. This chapter deals with the issues raised in the hearings, and
the Committee’s findings about risk management by DHA and in the Australian
Government more broadly.
The original inquiry
5.6
As noted above, the Committee conducted its original inquiry in 2009. The
Committee held public and in-camera hearings on 9 November 2009 in Darwin. During
the in-camera hearing, the Committee undertook its usual inquiries about the
strength of the budget, the risks to the project and the robustness of the
budget’s projections.
5.7
The Committee is always diligent in testing the assumptions underlying
project budgets. In this case, the Committee had no reason to believe that the
budget presented by DHA was problematic. In its report (Report 7/2009), the
Committee wrote that:
The Committee is satisfied that the costings for the project
provided to it are adequate.[1]
5.8
As noted above, the Committee recommended that the House of
Representatives approve the works, which it did on 26 November 2009. DHA
subsequently proceeded with the project.
Correspondence received in 2011
5.9
As also noted above, the Committee received correspondence from DHA in
early 2011, notifying it that the total budget of the project was insufficient
to complete the works. DHA also sought the Committee’s agreement to complete
the project with an amended budget.
5.10
The Committee advised DHA that it would be holding public and in-camera
hearings into the budget overrun, and DHA provided the Committee with an
updated brief on the budget problems. This has been placed on the Committee’s
website.[2]
5.11
At its public hearing in March 2011, the Committee heard evidence from
representatives of DHA about the reasons for the budget overrun, and some
details of the proposed new budget. A transcript of this hearing is also
available on the Committee’s website.[3]
Budget overrun
5.12
In its correspondence to the Committee, DHA outlined the main deficiency
of the original budget. The original budget was $57.6 million (including GST),
and DHA was seeking the Committee’s agreement to proceed with a new budget of
$63.8 million (including GST).
5.13
The civil and housing construction works accounted for the vast majority
of the budget overrun. As DHA informed the Committee, initial tenders for these
parts of the project ranged from $68 million to $97 million, well above the project
budget. DHA commenced negotiations with the preferred tenderer, attempting to
reduce the tender (with some success). DHA also negotiated with the Department
of Defence, in order to save costs by reducing the project scope.
5.14
However, these negotiations did not result in a scope and tender that
could be funded under the original budget, hence DHA’s request for agreement to
proceed with a larger budget.
Hearings in 2011
5.15
In its background paper, DHA advised the Committee that there were three
main reasons for the inadequacy of the original budget:
- Darwin market
conditions;
- cost uncertainties
associated with architectural design; and
- DHA’s inexperience
with building high-set tropical homes.[4]
5.16
During the hearings, the Committee sought DHA’s explanation as to why
these cost pressures were not sufficiently accounted for during the budget
process. It is unacceptable that these risks were only properly understood
after the project had been considered by the Committee and Parliament.
Darwin market conditions
5.17
Members of the Committee raised the question of market conditions at the
hearing in early 2011:
Senator TROETH—... [We] are certainly aware that there
are higher costs not only in Darwin but also in most of North Queensland
because labour and building is higher than the rest of Australia. Again, given
that Defence has been building in Darwin, I think, since the 1970s, why
wouldn’t Defence already factor that in? Is there is a sudden leap in the cost
of building and labour?
5.18
DHA responded to the Committee that there are significant pressures on
the construction industry in Darwin, due to population growth and the limited
months in which construction can be undertaken, given the climate patterns.[5]
5.19
The Committee is not satisfied with these answers. All the market
conditions cited by DHA for the budget inadequacy were foreseeable. The
conditions were well known in the local community.
House design
5.20
Members of the Committee reminded DHA that, during the original hearing
in 2009, it advised that:
The houses we intend to construct will be tropical-style,
high-set homes promoting design principles specific to Darwin and the site
conditions.[6]
5.21
No mention was made of the risks associated with the design or construction
of this style of house. The Committee’s usual inquiries about risks were
satisfied with assurances from DHA that it had a suitably large contingency to
cover any project risks that materialised.
5.22
In its original report, the Committee commended DHA for constructing
houses that were designed for Darwin’s climate.[7] The Committee continues
to support DHA’s efforts to improve the capability of the Darwin construction
industry to deliver houses that are designed for the local climate.
5.23
DHA must properly assess projects on an individual basis. DHA builds a
large number of houses around Australia each year, and it cannot simply rely on
general assumptions about the cost of housing design and construction. In this
case, it was clear that the project differed significantly from previous
projects, and DHA should have properly taken this into account.
5.24
DHA is conscious that it is pushing the Darwin design and construction
industry forward by its decision to build high-set homes. Indeed, at a hearing
for a different proposal in 2010 DHA noted:
The committee also witnessed DHA’s strategy to reinvigorate
the local building industry to be more innovative in taking account of the
tropical climate in future housing constructions ... The building industry in
Darwin is currently geared to delivering southern style homes and the committee
members would have seen much evidence of this this morning while driving around
various suburbs to get to Muirhead and to this facility today. DHA has already
implemented a strategy leading to affordable house constructions in Muirhead to
be more attuned to Darwin climatic conditions, so it has developed a pilot
home, which the committee visited this morning, to test various ideas and to show
the local building industry the direction in which an important customer is
heading.[8]
5.25
Again, the Committee is fully supportive of DHA’s efforts to encourage
housing in Darwin that is more attuned to the local climate. However, DHA must
ensure that, if it is seeking tenders for house designs that it knows to be
uncommon in the market, it must make sufficient budget allowances.
Committee comment
5.26
The Committee is concerned that the reasons for the budget overrun in
this case were not unforeseeable. DHA must have been aware that there were
local market and industry conditions that could cause problems with the project
budget. The Committee considers it unacceptable that DHA did not do more work
to identify these risks before the project commenced. The Committee has sought
DHA’s assurances that its internal budgeting processes have been improved to
take account of this unfortunate turn of events. At the budget update hearing
in March 2011, DHA assured the Committee that:
Wherever we introduce a new product we need to revisit our
process of validating prices, and we have done that recently with some
additional broadacre land...We have done the same thing with engineering
estimates, where we have employed a couple of different engineers. One will do
the estimates, another will do a review of those estimates, but we do not take
the halfway measure. We get them all into the room together and keep them there
until we come out with what they agree is the right number. So we have changed
that process for new and different products.
5.27
The purpose of risk management is to ensure that projects are not
derailed by events or decisions that may or may not occur. In this case, there
were numerous market conditions and cost pressures that DHA knew to be risks.
They were not entirely unforseen. However, DHA did not sufficiently investigate
their likelihood and impact on the project.
5.28
The Committee is left to conclude that either DHA was not properly
informed about the extent of the risks to the project, or that it failed to
include sufficient budget provision to protect the project. Either way, DHA
must improve its internal budget process to ensure that this does not occur
again.
5.29
The Committee notes that DHA operates on a commercial basis, and that it
returns profits to the government by way of dividends. Nonetheless, DHA is a
public authority spending public money, and it has a responsibility to ensure
that the money is well spent. Robust budgeting is a fundamental part of getting
good value for money, and the Committee expects all agencies to ensure that
project budgets are properly prepared.
Ms Janelle Saffin MP
Chair
16 June 2011