House of Representatives Committees

Chapter 2 The Proposed Works

Purpose
Need
Scope
Design
Consultation
Environmental and Heritage Considerations
Project Delivery
Cost

Purpose

2.1

The department’s Statement of Evidence describes the purpose of the proposed redevelopment as entailing:

2.2

Priority elements for the proposed works are:

 

Need

2.3

In its Statement of Evidence, the department states that the facilities at Lavarack Barracks have been progressively updated over three redevelopment stages, but that there are still considerable works required to fully refurbish the facilities at the Barracks.4 Each of the sites that are the subject of the proposed works are characterised by the poor condition of buildings, layout inefficiencies, and occupational health and safety deficiencies arising from substandard, cramped and temporary working accommodation, that no longer provide the functionality required for a modern army.5

Scope

2.4

The scope of the proposed development will entail a combination of the construction of new buildings and the refurbishment of existing facilities.6

2.5

Works associated with the refurbishment of existing buildings will include repairs and maintenance, rectification of occupational health and safety deficiencies, and the general upgrading of finishes.7

2.6

The works will include:

 

Design

2.7

The design of the proposed facilities will embrace the following design features:

Consultation

2.8

Consultation has occurred or will occur with the following stakeholders during the development of the proposal:

 

Environmental and Heritage Considerations

2.9

The initial environmental review for Lavarack Barracks Redevelopment Stage 4 has indicated that the siting of the works will overlay existing developed areas, and that there are no floras or fauna impacts. Accordingly it is not anticipated that an environmental referral under the Environment Protection and Diversity Act (1999) will be required. The proposed works will, however address organochloride and hydrocarbons contamination.11

2.10

The project has been considered by the department’s Environment, Heritage and Risk Branch against the background of the requirements of the Environment Protection and Diversity Act (1999) with reference to the impact of National Environmental Significance in the context of the preservation of buildings used during the 1960s by Australian forces deploying to Vietnam.12

Project Delivery

2.11

Defence is proposing to deliver this project by way of a managing contract. Under this arrangement, the managing contractor is in effect a project manager, responsible for project tendering for sub contractors on behalf of the department.

2.12

In the context of scheduling, the project works has been broken down to the level of precincts with work being staged at each site. Construction of facilities for 11th Combat Services Support Battalion and B Squadron 3rd/4th Cavalry Regiment are expected to begin in August 2007 and be complete during the latter part of 2008. The works for the 3rd Combat Field Regiment precinct will be begin mid-2008 with completion scheduled for 2010. The works for 4th Field Regiment will begin in 2009 with a scheduled completion of mid-2011.13

2.13

Works associated with the gymnasium and the Regimental Aid Post will be scheduled over the entire duration of the project timetable taking into account the best distribution of resources engaged on the project.14

Cost

2.14

The estimated out-turn cost of this project is $207.2 million which includes all planning and approval costs, management and design fees, construction costs, furniture and fittings, equipment, escalation and contingencies.15



Footnotes

1

Appendix C, Submission No. 1, paragraph 2 Back

2 Some works associated with B Squadron 3rd/4th Cavalry Regiment were undertaken as part of the Lavarack Barracks Redevelopment Stage 3. See Lavarack Barracks Redevelopment Stage 3, Report of the Parliamentary Committee on Public Works, Eighth Report 2001, paragraphs 2.39 – 2.42. Back
3

Appendix C, Submission No. 1, paragraph 11 Back

4

ibid., paragraph 11 Back

5

ibid., paragraphs 3 and 13 - 23 Back

6

ibid., paragraph 25 Back

7

ibid., paragraph 27 Back

8

ibid., paragraphs 28 - 33 Back

9

ibid., paragraph 42 Back

10

ibid., paragraph 56 Back

11

ibid., paragraph 57 Back

12

ibid., paragraph 58-59 Back

13

ibid., paragraph 64 Back

14

op.cit. Back

15

ibid., paragraph 49 Back


Print Chapter 2 (PDF 159KB) < - Report Home < - Chapter 1  : Chapter 3 - >

Back to top

We acknowledge the traditional owners and custodians of country throughout Australia and acknowledge their continuing connection to land, waters and community. We pay our respects to the people, the cultures and the elders past, present and emerging.

Aboriginal and Torres Strait Islander people are advised that this website may contain images and voices of deceased people.