|
House of Representatives Public Works
Navigation: Previous Page | Contents | Next Page
Chapter 3 Issues and Conclusions
Amendment to the Statement of Evidence
3.1
At the commencement of the Public Hearing, Defence proposed the
following amendments to its Statement of Evidence:
At paragraph 17 (c): delete the
words ‘and upgrade of messing facilities’.
Amend heading to paragraph 37 by
deleting the words: ‘and Mess Upgrade’.
Amend the opening sentences to
paragraph 68 to read, ‘Efficient water use is a key aspect of the design. Key
water saving measures to be investigated will include…’[1]
Background
3.2
According to its opening statement to the Committee, Defence describes
the proposed works to be undertaken at HMAS CRESWELL as addressing concerns
over the deteriorating Defence estate that has served as a disincentive to
Naval recruitment and retention, as well as having an effect on training.
3.3
The nature of the proposed works is as wide in scope as it is in
diversity. According to Defence the works will encompass the modernisation of
the Royal Australian Navy School of Survivability and Ship Safety (RANSSSS) training
units, infrastructure and amenities facilities; the provision of new and the
upgrade of existing engineering services and infrastructure; the refurbishment
of existing living-in accommodation and the provision of new living-in
accommodation; the refurbishment of existing and the provision of new working
accommodation and instructional facilities; the provision of new physical
fitness and training facilities; the upgrade of cadet recreational facilities;
waterfront environmental works and a new classroom and amenities facility, and
an upgrade to the armoury.[2]
3.4
The Committee was pleased to hear that unlike some other projects that
had been referred to it by Defence, the extent of the adaptive reuse and
refurbishment of existing facilities and infrastructure was a feature of the
proposed redevelopment.
3.5
In its Statement of Evidence, Defence suggests that the use of HMAS CRESWELL
has fluctuated over time as a consequence of the priorities given to the
training of Navy personnel by the department. Defence states that:
With the end of the war [World War I] came changes in Defence
strategy and the requirement for naval officer training was reduced. The
College was affected and in 1930, it was relocated to Flinders Naval Depot in Victoria. By 1937, most of the buildings at Jervis Bay were leased to private individuals and
companies and the site was developed as a tourist town. The return of the RAN College to Jervis Bay was the culmination of a successful campaign beginning in 1950. The
College was re‑opened and commissioned as HMAS CRESWELL in February 1958.[3]
3.6
However, the use of facilities at HMAS CRESWELL has been variable rather
than serving as the focus of training of naval personnel. In its submission to
the Inquiry, the department informed the Committee that:
Changes to RAN officer initial entry training arrangements in
recent times has seen fluctuating demands on facilities in HMAS CRESWELL. This
uncertainty has resulted in minimal investment in facilities and infrastructure
on the Base over the past 20 years and a consequential deterioration of the [its]
overall condition. The demand on facilities in HMAS CRESWELL to support the
training capability is on the increase, with an approximate annual throughput
of 900 trainees.[4]
The Future of HMAS CRESWELL
3.7
Against the background of uncertainties attached to the base as the principal
training facility for Navy personnel, the Committee sought assurances from
Defence that as a result of the base being ‘mothballed to some extent over 20
years’ that allowed the facilities to deteriorate and the now significant
proposed investment in HMAS CRESWELL, the facility would be fully utilised over
the lifetime of the proposed redevelopment.[5]
3.8
According to the Navy witness, the review of Naval training conducted in
2005, and approved by the Minister in 2006, confirmed HMAS CRESWELL as the RAN
College for initial entry officers, and that the base would continue to support
all of the current training courses for the Navy and visiting Army and Air
Force units over the long term, which would translate to 30 years or the life
of the works covered by the current project. In addition, the base would
continue to operate as the key support facility for the Australian Defence
Forces (ADF) and associated activities in the Jervis Bay and the east
Australian exercise area.[6]
3.9
In adding to this, the Defence witness, referring to the proposed works
associated with the RANSSSS informed the Committee that personnel from all arms
of the ADF that were deployed to Navy ships were required to undertake survival
and safety training. HMAS CRESWELL was one of three sites capable of providing
survival and safety training, the others being located in Victoria and Western Australia.[7]
3.10
Drawing on the figures quoted in the department’s Statement of evidence
that the approximate throughput of trainees was in the vicinity of 900 annually
and having regard to the Commonwealth’s investment in the project, the
Committee queried the basis of this estimate.
3.11
Defence confirmed that the numbers passing through the Naval College was in the order of 900 annually. This figure would increase by around 2,500
personnel passing through the RANSSSS annually. In terms of the occupancy of
living-in accommodation this would translate to an average of 280 personnel
living on base at any one time.
3.12
The Committee was subsequently informed by Defence that the average of
280 trainees per day is based on target courses for 2008 taken over 50 weeks of
the year. This will achieve an annual occupancy rate of living-in accommodation
of 75 percent, allowing for some residual capacity to accommodate courses
organised at short notice or for operational reasons.[8]
Project Delivery
3.13
The Committee sought details from Defence as to the methodology used to
deliver the project, including when expressions of interest were sought, how
many companies responded and the current position regarding the selection of
the final tenderer. The Committee was also interested in whether the panel of
selected tenderers mentioned during a previous Inquiry[9]
had participated in the tender process.
3.14
The department explained that the HMAS CRESWELL project would be
delivered under a managing contractor delivery method. This would be a
two-stage process that would provide the department with the flexibility to
develop scope and design options that best meet the needs of both Defence and Navy.[10]
3.15
The Project Manager/Contract Administrator was engaged by way of a ‘request
for proposal’ that Defence confirmed had been sent to the members of the
Defence Infrastructure Panel that currently comprises 10 companies. Responses
were received from eight of the 10 panellists from which one was selected based
on a technical and value for money basis.[11]
3.16
A Managing Contractor was selected through an open tender process in
response to advertisements in the press. The preferred tenderer was selected
on a similar basis to that employed in the selection of the Project
Manager/Contract Administrator. The Managing Contractor will be responsible on
a two-stage basis for the project development phase, including the engagement
of design contractors followed by the project delivery phase including the
letting of sub-contracts for construction on behalf of Defence, the supervision
and management of construction, and the commissioning and hand-over of the
completed facilities.[12]
Options
3.17
The Committee made reference to the design options canvassed by Defence,
and sought further details of the options considered in developing the proposal
for HMAS CRESWELL.
3.18
In responding Defence informed the Committee that initially the
department had looked at the demolition of some 300 living-in accommodation
units, but concluded that this would exceed available funding. It was then
decided that the option of adaptive reuse of a number of facilities and the
construction of new facilities would deliver greater cost effectiveness, as
well as providing an acceptable solution that would meet the requirements of Navy.[13]
3.19
The department further added that there were two elements of the
proposed redevelopment of HMAS CRESWELL regarded as priorities. The first of
these were the works associated with the RANSSSS because of the priority
attached to the training provided by the school by both the department and Navy.
The second was the decision to undertake the full scope of engineering
infrastructure works that according to the department’s Statement of Evidence
are currently in poor condition, and require an increase in capacity so as to
reduce maintenance liabilities.[14]
Heritage Issues
3.20
In relation to the department’s proposal to refurbish Cerberus House, a
building of some 50 years old, the Committee expressed some reservations that
the works associated with this aspect of the project could be met from within
the existing budget assigned to it – particularly having regard to the
condition of the building.
3.21
In responding, Defence acknowledged that there was a premium in
retaining heritage listed buildings, but that since Cerberus House was heritage
listed there was no option but to ensure its preservation. The works
associated with the building’s preservation would involve gutting the interior and
constructing a steel frame inner structure followed by a new internal fit-out
including the restoration of ceilings and walls, and new electrical, plumbing
and sewerage works.[15] According to Defence, the
cost of the proposed refurbishment could be met through from the estimate
provided.
3.22
The Committee enquired as to how Geelong House a building that had been
demolished some years previously would be reconstructed to complement Cerberus
House.
3.23
Defence informed the Committee that while it is intended that the
external facade of Geelong House would reflect the heritage appearance of
Cerberus House, it would incorporate more recent trimmings including aluminium
look-alike windows, and that ecologically sustainable development design
principles would be applied including meeting Defence’s requirement of an ABGR
4.5 energy rating. The department further stated that:
Some of the design measures which have been identified for
that building are natural ventilation, with supplementary fans for cooling and
convective heating in the inner living accommodation; low-flow shower heads…and
individual variable refrigerant volume air-conditioning in the offices and
training rooms…[16]
3.24
On the broader question of heritage related issues, the ACT Government
witness in responding to a question from the Committee on the jurisdiction of
the ACT to exercise responsibility over the heritage values of HMAS CRESWELL
stated that his agency was not aware of the heritage aspects of Creswell. The
witness stated however that the laws of the ACT apply in the Jervis Bay Territory unless there exist Commonwealth laws or regulations that overrode the ACT.[17]
3.25
The witness subsequently informed the Committee that:
The buildings of heritage significance at HMAS CRESWELL are
listed on the National Heritage Register under the Environment Protection
and Biodiversity Conservation Act 1999. Where there is Commonwealth
legislation in place it overrides the ACT legislation. In this case the heritage
values are protected by the Commonwealth legislation administered by the
Commonwealth Department of Environment and Water Resources.[18]
3.26
Notwithstanding, the witness stated that the Environment and Protection
Branch the TAMS (TAMS) was prepared to provide advice on any heritage aspects
of the development should it be approached by Defence. However, the witness
was uncertain as to whether ACT legislation was applicable on a Commonwealth
Defence establishment. [19]
Water and Sewerage
3.27
The Committee enquired as to the impact that the proposed works, once
complete, would have on the demand for water and power, and was informed by the
department that current water consumption was in the vicinity of 56 million
litres of water annually. According to Defence this will be reduced when
treated water for toilets comes on line delivering savings of about 15 million
litres annually, inclusive of the proposed new 25-metre swimming pool.
3.28
The Committee noted the Submission by the Department of Transport and
Regional Services seeking clarification of the source of water for the proposed
new 25 metre indoor swimming pool, against a background of water restrictions
in the Jervis Bay area and the pressure that this might place on existing water
resources in the Territory.[20]
Recommendation 1
|
|
The Committee recommends that Defence provide further
information regarding the concerns raised by the Department of Transport and
Regional Services regarding water to the proposed swimming pool.
|
3.29
Defence acknowledged that the new development would increase power usage
on base as a result of the increase in occupiable area delivered by the new
facility.[21] The department did not
offer any insights into the likely increase of consumption, nor did it indicate
what impact proposed energy ratings might have on power consumption. Further
it was unclear whether Integral Energy had the capacity to sustain the supply of
the energy needs of the base without major upgrades to the electricity
infrastructure.
Recommendation 2
|
|
The Committee recommends that Defence inform it of potential
energy savings flowing from the initiatives it proposes to incorporate into
the redevelopment of HMAS CRESWELL, and the outcomes of consultations with
Integral Energy regarding the supply of power to HMAS CRESWELL, with particular
regard to any additional infrastructure that might be required.
|
3.30
The Committee sought a response from Defence as to whether the new
living-in accommodation and some other new buildings would include water
capture measures.
3.31
In addressing the Committee’s question, Defence stated that it had not
included rainwater tanks on new buildings. The department explained that the
overflow from the effluent holding pond could provide irrigation to
non-inhabited areas of the base, and that once treated could also be used in all
of the toilets in the new and refurbished buildings. In the view of the
department treatment of water from the effluent holding pond was more cost
effective than capturing rainwater, although the opportunity to install water
tanks was an option in the future if required.[22]
3.32
As to whether there was a possibility of untreated water run-off into
Jervis Bay, Defence explained that the current processes whereby water
discharged from the effluent holding pond was reused precluded untreated water
being discharged into the Bay.[23]
3.33
The issue of the use of recycled water was of concern to the witness
from the ACT Government. The witness informed the Committee that the use of
recycled water was the subject of legislation in the ACT, and that it required
an agreement with the Environmental Protection Agency in order to provide
assurances to the local community that the environment has been adequately
protected.[24]
3.34
The witness acknowledged the in principle preparedness of Defence to
sign-off on that agreement, noting that there already existed a similar
agreement in the Canberra region relating to the use of recycled water on
Defence sporting grounds.[25]
Recommendation 3
|
|
In order to resolve the concerns of the ACT government
regarding the use of recycled water, the Committee recommends that Defence
continues to consult in detail with the Government of the ACT and ensure that
the department complies with ACT legislation.
|
3.35
Following up on the potential for low grade water entering Jervis Bay the witness informed the Committee that the Environment and Heritage Branch of TAMS
undertakes a water sampling regime of discharges of both groundwater and
surface water. This sampling regime is also conducted on the sewerage
treatment area. The two sampling regimes referred to produce a level of
certainty in respect to treated water that all of the Jervis Bay occupants can rely on.[26]
Consultations with the ACT Government
3.36
The Committee sought reasons why Defence had not consulted with the ACT
Government in the development of this project, particularly since the Territory
of Jervis Bay was part of the ACT.
3.37
Defence acknowledged that this had come about as a result of a
misunderstanding. The department believed that TAMS were the responsible
department for operations within the Jervis Bar area. Having become aware of
the role of the ACT in administering the Jervis Bay Territory, it had initiated
meetings with officials of the ACT Government to explain the project, and
reached agreement on providing feed-back on environmental matters to ensure
that the department meets its obligations under ACT environmental legislation.[27]
3.38
The ACT Government witness confirmed that meetings had occurred, and
that a mechanism for consultation between the parties had been agreed.[28]
3.39
However, as the witness explained, the ACT Government is still not privy
to a number of aspects of the proposal that are yet to be clarified. Further
owing to the stage reached by Defence in the development of the project
particularly related to water-sensitive urban design it may be difficult to
agree with or change measures proposed by Defence.[29]
3.40
Although acknowledging that Defence has undertaken to provide the
details requested by the ACT, the ability to modify or change design works was
perceived as being difficult, particularly where a need might arise to
retro-fit measures to preserve the sensitivities associated with the
environment. Further, the witness indicated that the Defence response to the
Government’s submission was vague, using words like ‘where necessary’ which was
not indicative of a sufficient level of commitment. The witness expressed the
hope that some of these issues could be resolved through the Public Health and
Environment Working Group.[30]
Recommendation 4
|
|
In the interests of ensuring water-sensitive urban design
Defence give consideration to water capture measures to service living-in
accommodation. The Committee recommends that water capture facilities be
installed as part of the development in preference to retro-fitting in the
future.
|
3.41
The witness also informed the Committee that there were aspects of the
proposed development relating erosion control that had been raised by the ACT.
It had not been possible for the government to make any assessment as to the
likelihood of sediment run-off since the construction management plans were
unavailable limiting the opportunity for the government to assess whether
suitable controls were in place to protect the marine environment of Jervis Bay.[31]
3.42
In its submission to the Inquiry, TAMS expressed concerns over the
proximity of the proposed works to what it describes as a ‘sensitive receiving
environment’, and recommended that:
…the proposed Environment Management Plans for the works
specifically detail the controls to be established and maintained during the
works to prevent any discharges.
3.43
The details that Defence has been asked to comply with by the ACT
government are consistent with the ACT Environment Protection Authority’s 1998 guidelines
‘Erosion and Sediment Control during land Development’
Recommendation 5
|
|
So as to meet ACT requirements relating to erosion control
sediment run off and other discharge potentially likely to occur during the
project works, the Committee recommends that Defence obtain a copy of the ACT
Environment Protection Authority’s 1998 guidelines ‘Erosion and Sediment
Control during land Development’ and work toward compliance with these
obligations.
|
Hazardous Waste
3.44
In response to a reference to the removal and disposal of hazardous
waste included in the submission received from the Government of the ACT,[32]
the Committee sought details from the departmental witness as to how the disposal
of hazardous waste would be regulated in the event of being present on the
site.[33]
3.45
The witness confirmed that oversight of the disposal of hazardous waste
would definitely be monitored if it was identified. The witness acknowledged
that Defence had committed itself to providing the Public Health and
Environment Committee of the Jervis Bay Territory with details of hazardous
materials surveys and other remedial works done on Creswell, which in the ACT
is a standard part of any redevelopment work. Should there be a requirement to
remove asbestos Defence would be obliged to provide the detail in its
management plan for the site.[34]
3.46
In terms of disposal, the witness stated that the Department would be
closely watching this, and would be available to Defence to provide advice as
to whether the management of the disposal of hazardous materials was being
undertaken consistent with ACT regulations.[35]
3.47
On the question of the extent of hazardous waste the witness informed
the Committee that the department was not privy to the extent and nature of
site contamination, including in addition to asbestos, the presence of any
potential hydrocarbon contamination from old fuel storage sites and possible
PCBs.
Recommendation 6
|
|
Having regard to the concerns of the ACT Department of
Territory and Services regarding the management and disposal of hazardous
waste, the Committee recommend that Defence undertake an appropriate
hazardous materials survey of proposed works at HMAS CRESWELL, and furnish the
ACT Department of Territory and Services with a plan for the management and
disposal of any hazardous waster identified.
|
Project Cost
3.48
The estimated out-turn cost of the works is $83.6 million. This figure
includes all design works; construction costs; management fees; furniture,
fittings and equipment, and an escalation and contingency provision.
Recommendation 7
|
|
The Committee recommends that HMAS CRESWELL Redevelopment
proceed at an estimated cost of $83.6 million.
|
Hon Judi Moylan MP
Chair
9 October 2007