Chapter 3 Issues and Conclusions
Lease Arrangements
Lease Incentive
3.1
ASIC submitted that the project will cost $9.85 million.[1]
However, ASIC has also managed to negotiate a $6.5 million lease incentive
which
…is to be taken in the form of a contribution towards the
cost of the fit-out, payable (upon lease completion and upon the lessors’
approval) via progress payments.[2]
3.2
At the hearing, the Committee was satisfied that the total cost of the
work would be $9.85 million. The $6.5 million lease incentive would be used to
offset the cost of the fit-out, which equalled a total cost to the Commonwealth
of $3.35 million.[3]
Site Selection
3.3
During the public hearing, the Committee enquired whether ASIC was
satisfied that due probity had been undertaken, particularly as the lessor of
the current and new ASIC premises was the same.[4]
3.4
ASIC responded that it was satisfied that it had selected and negotiated
the best deal possible, and that
…there are advantages in having the same owner at either end,
particularly in the crossover period… but essentially 120 Collins Street won
this on the basis of the offer and the standard of the building.[5]
Green Lease Arrangements
3.5
ASIC submitted that its lease contains a section that is
…dedicated to green issues and describes and quantifies the
commitment of both parties to ensuring that the environmental performance
criteria are met and exceeded.[6]
3.6
The Committee heard that ASIC is one of the top three tenants of the new
building with regards to size of the lease. ASIC stated that it is continually
talking to the lessors with regards to green issues, and where it can influence
the lessors, it will try to influence them.[7]
Project Schedule
3.7
At the time of its submission, ASIC anticipated that the project would
be completed over a five-month period and that relocation would take place in
late September 2006.[8]
3.8
ASIC amended this timeline at the public hearing to reflect a new
program completion date of mid-November.[9] ASIC further added that
it was seeking parliamentary approval within 25 to 30 days, as the tender
process had already commenced. [10]
Environmental Considerations
Australian Building Greenhouse Rating
3.9
ASIC submitted that an Australian Building Greenhouse Rating (ABGR) of
three stars was a criterion used in the EOI evaluation process.[11]
3.10
The Committee enquired why a higher rating was not sought, and ASIC
responded that the rating of three stars was the current rating of the Collins
Street premises; however the lessor was seeking to improve this. Further, ASIC
added that the age of the building impacted on the ABGR rating it could achieve.[12]
Environmentally Sustainable Management
3.11
The Committee heard that an ABGR was only one factor in ASIC’s
environmental management strategy, and that other issues included:
n the green element in
ASIC’s lease;
n the provision of cycle
parking;
n the use of motion
sensitive lighting;
n minimising the use of
after hours air conditioning; and
n utilising waste
management strategies.[13]
3.12
Further, ASIC stated that it had engaged the services of Tour Andover
Controls, which monitors the use of electricity, to advise on methods to reduce
electricity use.[14]
Access Equity
3.13
ASIC submitted that the design solution will:
…provide access and utilities for disabled persons that meet
the minimum requirements of the Building Code of Australia (BCA) and all
relevant state and Commonwealth legislation and are in accordance with ASIC’s
OH&S [Occupational Health and Safety] and Equal Employment Opportunities
policies.[15]
3.14
The Committee enquired further about access for people with a
disability, and ASIC responded that there is ramp access to the building and informed
the Committee that:
A lot of the issues that perhaps need to be addressed will be
dealt with on a micro rather than a macro basis – for instance, the width of
passageways between desks needs to be a certain size for the code. We will
make sure that that is adhered to.[16]
Benefits of Collins Street Location
3.15
ASIC stated in its submission that, when analysing the expression of
interest applications, properties outside of the CBD were discounted, as the
CBD is ideally located amongst stakeholders, and provides greater amenity for
staff.[17]
3.16
At the hearing, the Committee heard that:
The commercial and business hub of Melbourne is Collins
Street rather than La Trobe Street… Much of the legal fraternity that we deal
with are at this end of the city, rather than at the other end, and many of the
other stakeholders we deal with across the financial services base are
headquartered down this way rather than at that end.[18]
Staff Consultation
3.17
ASIC informed the Committee that it has engaged its staff in extensive
consultation throughout the process. This has involved briefings for staff and
staff involvement in the project management structure. Further, ASIC added
that:
The survey that we ran at the commencement of the project
will be rerun in six months, or maybe a little longer, into the move once all
the teething problems have started so we can check and balance exactly whether
we have hit those success criteria that we were aiming to hit.[19]
Child Care
3.18
ASIC submits that while child-care was raised in staff feedback, it did
not feature as prominently as other issues.[20] ASIC does not intend to
include a child-care facility in its new premises as there is no outdoor
access, which is a mandatory requirement for a child-care centre.[21]
However ASIC stated that:
…work is underway to assess the accessibility for ASIC staff
to these facilities [nearby childcare centres] and to gain a clear
understanding of the alternatives available in the area.[22]
3.19
The Committee heard that the issue of child care was raised as a
question rather than a request.[23] ASIC has approached
three of four outlets in the area and determined that they might be suitable
subject to waiting lists.[24] Further, ASIC stated
that it has flexible working arrangements which allow it to attract good
quality professional staff.[25]
Recommendation 1
|
|
The Committee recommends that the proposed fit-out of the
new leased premises for the Victorian Regional Office of the Australian
Securities and Investments Commission at 120 Collins Street, Melbourne
proceeds at the estimated cost of $9.85 million. The Committee notes that the
$6.5 million lease incentive will be used to offset the cost of the fit-out.
|
Hon Judi Moylan MP
Chair
21 June 2006