Chapter 1 Introduction
Inquiry into the Defence Annual Report 2007-08
Background
1.1
The Defence Sub-Committee of the Joint Standing Committee on Foreign
Affairs, Defence and Trade held public hearings into the Defence Annual
Report 2007-08 in Canberra on Thursday 16 April, Friday 19 June, and Friday
21 August, 2009.
1.2
Witnesses from various parts of Defence, including uniform and civilian
personnel, appeared before the Sub-Committee. Four submissions were received.
1.3
This Report reflects the Committee’s key areas of interest, which are:
n the ADF’s ability to
encompass its current range of tasks, including its current force structure in
Afghanistan, and the influence of new factors on Defence, in particular the
Global Economic Crisis and the release of the 2009 White Paper;
n progress on major
Defence procurement projects.
n the management,
recruiting, development and retention of Defence personnel, including pay
systems;
n constraints on
Defence’s ability to deliver on the ADF’s capacity to fulfil its role, such as questions
over oil security and climate change; and
n new and emerging
areas of attention for the ADF, including the Proliferation Security Initiative
and management of cyber warfare threats.
The Kinnaird Reforms
1.4
With regard to the procurement projects, the Committee notes the
representations made to it, across a range of Defence’s submissions that, under
the Kinnaird process, future projects will not suffer the same fate. It is also
noted that, at such an early stage in this reform process, Defence have not yet
concluded a complex project under the new arrangements.
1.5
Throughout the committee hearings a number of major projects were
characterised by delay and failure to provide contracted capability. It was
common for Defence to state that these problems were in part, or in large
measure, the result of pre-Kinnaird procedures.
1.6
These reforms should provide Defence with a more agile stance on
procurement, allowing both rapid acquisitions and termination of arrangements
where performance is considered unacceptable. These, in effect, increase
Defence’s power to manage relationships with contractors, and augur well for
the future capacity of projects to be delivered within projected timelines.
1.7
However, the Committee is mindful these reforms will require continued
follow-through, and championing from management in Defence, if they are to
achieve their stated objectives. Cultural change in Defence requires effort
over a sustained period, otherwise changes will be cosmetic.
1.8
The extent to which the Kinnaird reforms fully address these problems will
be subject to close scrutiny by future Committee reviews.
Unique or leading Edge Military Off-The-Shelf and Commercial Off-The-Shelf
solutions
1.9
The Committee is mindful of common factors that have led to delays or
cancellations in the projects considered within this review. One is the
tendency to adopt relatively unique or leading edge systems. This is at odds
with current initiatives for Defence to adopt Military Off-The-Shelf (MOTS) and
Commercial Off-The-Shelf (COTS) solutions where possible.
1.10
The unique nature of Australia’s security environment sometimes requires
tailored or special design assets and solutions. That said, many Australian
defence needs can be properly met with appropriate MOTS acquisitions. The
adoption of high-risk first-of-type acquisitions should only be entered into
where it is clear that such an outlay, in terms of time and money, can be
clearly justified by Australia’s defence requirements. In the absence of a
clear strategic case for such purchases, MOTS should be the default option.
1.11
A second common factor is a high level of technical complexity,
involving a requirement to generate significant amounts of new software code.
In the Committee’s view, while this may be necessary in some instances, it
would be reduced the more Defence adopts off-the-shelf solutions.
Recommendation 1 |
|
The Committee recommends that, in the absence of a clear
strategic case for high-risk first-of-type acquisitions, military
off-the-shelf purchases should be the default option for procurement
projects.
This recommendation does not necessarily relate to any particular
acquisitions currently under consideration but rather represents a broader
statement of policy reflecting on issues relating to past acquisition programs.
|
Rapid Procurement
1.12
The Committee recognises the need for a rapid acquisition process
capable of responding to emerging operational needs. This issue was raised
during the public hearings by the Deputy Chair:
I would like to ask you about the rapid acquisition program.
Can you tell me a little bit about it: how it operates; how requests go up
through line; how they are determined; how they come back for approval; and
what the time frames normally are for rapid acquisition programs?[1]
1.13
In response Defence stated:
Generally speaking, what will
happen is, first of all, there will be a given set of circumstances on the
ground in one of the operations we are conducting. The one at the moment that
probably creates the circumstances for rapid acquisition potential is
Afghanistan. So, if something happens in Afghanistan, we get into the rapid
acquisition process. A classic case occurred when the government recently
announced a fairly large expenditure on counter-improvised-explosive-device
equipment. Fundamentally, what happens? Something happens on the ground which
indicates a change in the circumstances. We make an assessment. We say, ‘We
need this to counter that.’[2]
1.14
At the public hearing on 21 August 2009 the Chair raised the following
question:
I want to ask questions on a different topic: the rapid
acquisition program, particularly for TAG-East and TAG-West. The committee has
had the benefit of visiting those units over the course of the last year or so.
Whilst there are examples of that rapid acquisition program working well, there
were certainly examples drawn to our attention where it does not seem to work
very well at all. I am not sure where in the chain of events these things break
down. Examples include the provision of the night-vision goggles that TAG-East people use and interchangeable short barrels for weapons. These things seem to be
comparatively low cost and straightforward but are nonetheless essential for
the sorts of operations engaged in. However, the rapid acquisition program does
not seem to produce an outcome. Can you tell us anything about that?[3]
1.15
Defence replied:
I would not categorise the night-vision goggles as an easy
thing to procure. First of all, there are very strong release-ability issues
with the US as to what technology we have access to. Secondly, some of the
delivery periods out of the manufacturers are very long. We are hearing figures
like one, two and three years for certain components of some of the most modern
night-vision goggles. So I do not think it is some form of bureaucratic delay.
I think it is just a delay related to how long it takes to get things from the
manufacturers.[4]
Committee comment
1.16
Rapid acquisitions are highly specialised and not straightforward and
may be beyond the control of the Department of Defence. Nevertheless, there
will be occasions where operational requirements drive the need for rapid
acquisition and it is important that Defence has a processes capable of
responding.
Recommendation 2 |
|
The Committee recommends that the Department of Defence review
its current procedures for rapid acquisition to ensure that it is meeting the
ADF’s needs, particularly where they are linked directly to overseas
operational commitments.
|
Scope Creep
1.17
The issue of scope creep is covered in Chapter 2 with regards to the
High Frequency Modernisation Project. This aspect of the Kinnaird review is an
important part of the procurement process. The Committee notes that this issue
was raised in last years report and the Committee will continue to scrutinise
the effectiveness of specification scoping in the first phase of each project.[5]