Chapter 2 Major Projects Report Work Program

Introduction

2.1                   The Australian National Audit Office (ANAO) commented that the 2009-10 MPR includes ‘a greater level of information about each project’s performance’[1] and progresses the data analysis undertaken on the 2008-09 Major Projects Report (MPR). In this way, the 2009-10 MPR also ‘provides a basis for greater longitudinal analysis on project performance in future years.’[2]

2.2                   Issues surrounding cost and scheduling of major defence capital acquisition projects (projects) is regularly reported in the public domain. In this respect, the MPR also provides a level of public visibility of the issues relevant to incorporated projects for initially approved budgets and schedules. The Defence Materiel Organisation (DMO) acknowledged that schedule delay is an area of improvement over the coming years.[3]

2.3                   This chapter outlines the main elements of the MPR Work Plan and issues raised in regard to the 2009-10 MPR and lists those projects proposed for incorporation into the 2010-11 MPR. These include the criteria for selecting projects in terms of their classification, and excluding projects in the 2010-11 MPR in regard to the defined points of completion. The qualified audit opinion given by the ANAO is also discussed.

Major Projects Report Work Plan

2.4                   The MPR Work Plan has been provided to the committee annually (shortly after the committee has held its public hearing for the review of the previous year’s MPR) and forms part of the forward MPR Work Program. The committee has an active role in considering and endorsing the MPR Work Plan including the list of projects to be added to each MPR and the Guidelines for the Project Data Summary Sheets (PDSS). The MPR Work Plan for 2009-10 included:

Guidelines for the Project Data Summary Sheets

Purpose of Guidelines

2.5                   Major projects included in the MPR are reported on through individual PDSS. These PDSS are collected and collated with an overview by the DMO, together with the findings and audit opinion of the ANAO’s formal review.

2.6                   The DMO in consultation with the ANAO has developed a set of Guidelines to provide a framework for the production and provision of the PDSS and form a basis for review. The Guidelines also require endorsement by the Joint Committee of Public Accounts and Audit (JCPAA). A revised set of Guidelines is usually made available to the committee for its consideration prior to drafting of the upcoming MPR (in this case the 2010-11 MPR).

2.7                   The PDSS contain information about each project contained in the MPR. The basis of the ANAO’s review is to assess whether the information contained in the PDSS meet the requirements included in the Guidelines.

Guidelines for the 2010-11 Major Projects Report

2.8                   The DMO in conjunction with the ANAO has provided the committee with revised Guidelines for the 2010-11 MPR. The changes refine the PDSS and are designed to ‘provide more concise reporting and ... improve the flow of information.’[5]

2.9                   Proposed revisions to the Guidelines include:

2.10               In its review of the 2007-08 MPR, the previous committee recommended that no later than 31 August each year, the JCPAA be consulted on the projects for inclusion and exclusion in the following year’s MPR.[7]

2.11               The committee received the DMO’s proposed list of projects and accompanying project synopsis for inclusion in the 2010-11 at the start of the 43rd Parliament. The Guidelines for the 2010-11 MPR were included in the DMO Work Plan which was forwarded to the committee in late March 2011.

Selection and exit criteria for projects

2.12               The 2009-10 MPR reported on 22 projects which is an increase of seven projects from the previous MPR. The 2010-11 will include six additional projects to bring the total number of projects reported on to 28.[8] The MPR will eventually include summaries of a maximum of 30 projects.

2.13               The DMO stated that the maximum number of projects reported on in the MPR has been determined taking into consideration the cost of reporting on selected projects and the utility of this information to the committee. The DMO explained:

It is a question of cost versus utility. Each of these projects is very resource intensive to report in this way. There would have to be a law of diminishing returns somewhere, and how far do you take it? We have 200 projects and it would be physically impossible to do all 200, so it really does become a balance between cost and utility to the committee.[9]

2.14               The projects which are included in the MPR are subject to the following criteria:

Major projects included in 2009-10

2.15               Taking into consideration the project inclusion criteria, seven new projects were added to the 2009-10 MPR and joined the 15 repeat projects which appeared in the 2008-09 MPR. These projects represented approximately $41 Billion or just over half of DMO’s approved major capital investment program.[11] These projects and their approved budgets appear in Table 2.1.


Table 2.1 2009-10 MPR Projects and their approved Budgets at 30 June 2010

Project

DMO Abbreviation

Approved Budget $m

New projects included in the MPR

 

 

Field vehicles and trailers (LAND 121 Ph 3)

Overlander vehicles

2 879.2

Next Generation Satellite Communications System (JP 2008 Ph 4)

Next Gen Satellite

894.1

Replacement Heavyweight Torpedo (SEA 1429 Ph 2)

HW Torpedo

441.5

Follow-On Stand Off Weapon (AIR 5418 Ph 1)

Stand Off Weapon

399.6

Anzac Anti-Ship Missile Defence (SEA 1448 Ph 2A)

ANZAC ASMD 2A

377.1

Anzac Anti-Ship Missile Defence (SEA 1448 Ph 2B)

ANZAC ASMD 2B

458.5

Collins Class Submarine Reliability and Sustainability (SEA 1439 Ph 3)

Collins R&S

407.7

Repeat projects updated since the 2008-09 MPR

 

 

Air Warfare Destroyer Build (SEA 4000 Ph 3)

AWD Ships

7 740.1

Airborne Early Warning and Control Aircraft (AIR 5077 Ph 3)

Wedgetail

3 883.5

Multi-Role Helicopter (AIR 9000 Phs 2/4/6)

MRH90 Helicopters

3 754.6

Bridging Air Combat Capability (AIR 5349 Ph 1)

Super Hornet

3 629.1

Amphibious Deployment and Support (JP 2048 Ph 4A/4B)

LHD Ships

3 160.8

Armed Reconnaissance Helicopter (AIR 87 Ph 2)

ARH Tiger Helicopters

2 076.3

F/A-18 Hornet Upgrade (AIR 5376 Ph 2)

Hornet Upgrade

1 946.6

Air to Air Refuelling Capability (AIR 5402)

Air to Air Refuel

1 889.4

C-17 Globemaster III Heavy Airlifter (AIR 8000 Ph 3)

C-17 Heavy Airlift

1 834.6

Guided Missile Frigate Upgrade Implementation (SEA 1390 Ph 2.1)

FFG Upgrade

1 529.6

F/A-18 Hornet Upgrade Structural Refurbishment (AIR 5376 Ph 3.2)

Hornet Refurb

943.5

Bushmaster Protected Mobility Vehicle (LAND 116 Ph 3)

Bushranger Vehicles

926.2

High Frequency Modernisation (JP 2043 Ph 3A)

HF Modernisation

662.7

Armidale Class Patrol Boat (SEA 1444 Ph 1)

Armidales

536.7

Collins Replacement Combat System (SEA 1439 Ph 4A)

Collins RCS

458.0

TOTAL

 

40 829.4

Source Australian National Audit Office, 2009-10 Major Projects Report, p. 14.

Major projects to be included in 2010-11

2.16               In addition to the 22 projects included in the 2009-10 MPR as listed in Table 2.1, the DMO has proposed that the 2010-11 MPR incorporate the following six projects:

Options for 2010-11 projects’ selection criteria

Projects of concern

2.17               On 26 November 2010, the Minister for Defence, the Hon Stephen Smith MP and the Minister for Defence Materiel, the Hon Jason Clare MP, jointly announced an updated list of those defence capital acquisition projects which were considered to be Projects of Concern (PoC).[13]

2.18               Projects are classified as PoC when they encounter ‘significant challenges with scheduling, cost, capability delivery or project management.’[14] Established in 2008 by the Minister for Defence, the PoC list focuses ‘the attention of Defence and Industry senior management on remediating listed projects.’[15]

2.19               Five of the 12 currently listed PoC are reported on in the 2009-10 MPR.[16] The DMO stated that there is no direct link between the projects included in the MPR and those that are listed as PoC.[17] Rather, the projects included in the MPR are those that have met the requirements of the agreed criteria (as outlined in paragraph 2.15).

2.20               The ANAO suggested that the committee could consider adding PoC to the MPR. However, this would increase the cost of producing the MPR. In addition, the ANAO stated there are issues surrounding the length of time a PoC would be reported on in the MPR and the associated value of reporting on PoC’s that are smaller projects in terms of their approved budget. The ANAO stated:

... we would suggest to the committee that you may consider adding additional criteria ...specifically ...  including any projects of concern for the MPR. We are conscious that once they get in, there is the question of how long they stay, and if they are not big spends but they are still a worry, do we want to keep them in? It all adds to the cost of running this.[18]

2.21               The ANAO advised that the areas for consideration when assessing possible inclusion of PoC into the MPR could include:

2.22               The DMO was concerned about adding PoC to the selection criteria for MPR projects as PoC are determined on an ad hoc basis, whereas the projects selected for inclusion into the MPR occurs at a particular point in the calendar year. Another issue relates to the length of time a project remains a PoC and if it enters the MPR based on its meeting the PoC criteria, when does it exit the MPR if it is no longer classified a PoC.[20]

2.23               The DMO added that the PoC list is ‘subject to frequent reviews, adjustment and Ministerial oversight, and is quite separate in its intent to the MPR.’[21] Further, there could be an adverse effect in adding PoC to the MPR in terms of trend analysis and competition with reporting on other projects. The DMO explained:

To include PoC projects would have adverse impacts; in particular it has the potential to compromise overall MPR trend analysis if PoC projects are frequently moved on and off the MPR. It would also mean the removal or deferment of other current/potential MPR projects (which represent significant spend and capability) in order to not exceed the agreed cap of 30 projects.[22]

2.24               There was also the issue of whether a project should be included in the MPR if it was classified in the pre-PoC stage of being a Project of Interest (PoI). The DMO was not in favour of including PoIs in the MPR as such projects did not yet require more management attention and could more readily be resolved. The DMO stated:

We would probably suggest that not be one of the criteria. A project of interest is a signal to Defence, to DMO and to industry that these require a lot more management attention. They have not quite met the threshold where you would declare them to be a very difficult project or a project of concern. It is like an amber light when you come to the traffic lights—you have just got to be cautious. I would prefer to keep that one as a management prerogative and we put our efforts into it in the short term to try to get it fixed.[23]

2.25               The ANAO further stated that even with the inclusion of specific PoC reporting into the MPR, the focus of the MPR is different to that of what is required to report specifically on PoC. The ANAO suggested that the committee could request a list annually of those PoC which are not included in the MPR and seek further information on these projects ‘on a shorter term basis than would be the case for MPR projects.’ The ANAO also stated that ‘under this approach, consideration would also need to be given ... to any possible commercial sensitivity attached to such reporting.’[24]

2.26               Determining exit criteria that could be used for removing projects from the MPR was also raised in relation to ascertaining when a project is completed.

Exit criteria

2.27               As a number of projects will be completed in the upcoming MPRs, the issue of how long a project should continue to be reported on in the MPR and when it should be removed from the MPR was raised.

2.28               In accordance with the 2010-11 MPR selection of projects’ criteria, projects would be removed from the MPR once Final Materiel Release (FMR) and Final Operational Capability (FOC) have been achieved.[25]

2.29               The ANAO provided an explanation of FMR and FOC and stated:

Final materiel release ... is basically when DMO consider they have completed their contract. They hand the equipment over to the Department of Defence and the Department of Defence then undertake training, testing and all the rest of the things that they need to do to put it into use. Final operational capability is that period of time when the capability manager accepts that it is ready for use.[26]

2.30               The ANAO commented that the DMO in its relationship with the Department of Defence ascertains completion of a project as the point where FMR is achieved, and that the Department of Defence uses FOC.[27] In addition, the ANAO stated:

By way of background, in February 2010 the Defence Committee (Departmental) agreed to the adoption of the concepts of Initial Materiel Release (IMR) and Final Materiel Release (FMR) to clearly and explicitly define the mechanisms where the materiel element of capability is formally transferred from the DMO to the Capability Manager. This change acknowledges that achievement of FOC is the responsibility of the Capability Manager (and not the DMO), and includes the addition of items such as training for pilots, and completion of aircraft hangers, which are part of the Fundamental Inputs to Capability.[28]

2.31               The DMO is currently transitioning from using Initial Operational Capability (IOC) and FOC to Initial Materiel Release (IMR) and FMR. The DMO stated that:

IMR and FMR will mark the DMO milestones for delivery and release to the Capability Managers or materiel supplies to support the Capability Manager’s achievement of IOC and FOC. The IOC and FOC are Defence milestones that represent the estimated timeframe for when a capability system ... will achieve full capability. Consequently, the shift to IMR and FMR will provide greater clarity of responsibilities between the DMO and Capability Managers.[29]

2.32               The DMO acknowledged that there is a tension between initial and final materiel release and achieving full operating capability.[30] The DMO further stated that IMR and FMR, not FOC provide the best measures of the DMO’s effectiveness as this is the point where DMO’s responsibility in terms of project management ends and the project becomes the responsibility of the Capability Manager (who is attached to the Department of Defence). The DMO stated:

When the MPR was developed several years ago, Final Operating Capability was considered to be the logical end point at which projects would qualify for removal from the MPR. However, in February 2010 the Department’s Defence Committee agreed to the concepts of Initial Materiel Release and Final Materiel Release to explicitly define the points at which the materiel element of capability is formally transferred from the DMO to the capability manager. This change acknowledges that achievement of Final Operational Capability is the responsibility of the Capability Manager and not the DMO. Hence, Initial Materiel Release and Final Materiel Release, - not Final Operational Capability – provide the best measurement of the effectiveness of DMO.[31]

2.33               The ANAO suggested that the exit criteria for an MPR project include both the FMR and FOC stages as the MPR is an accountability document on DMO’s performance, but importantly also reports on project visibility.[32]

2.34               The ANAO also stated that the DMO is undertaking an analysis of the ‘difference in scale, size and incidence of requirements to be completed between the FMR and FOC.’ The Guidelines for the 2010-11 MPR include for both FMR and FOC to be reported.[33]

2.35               In addition, the DMO suggested that following their completion, projects could stay in the MPR for an additional year to report on lessons learned. The DMO stated:

.. a project should probably stay on for another year after it has finally met the criteria so that we can all do the lessons learned. It also requires some reflection to say, ‘What did we get right on that project, what did we get wrong and how can we apply it to future projects.’[34]

Concluding comments

Accountability and transparency of project and project management information

2.36               The committee acknowledges and accepts the comments made by the Australian National Audit Office (ANAO) that the 2009-10 Major Projects Report (MPR) includes a greater level of information about each project’s performance and that it provides a basis for greater longitudinal analysis on project performance in future years.

2.37               The committee also notes the Defence Materiel Organisation’s (DMOs) comments in relation to cost ‘blow-outs’ and schedule delay of projects as reported in the media from time to time and believes that the DMO could do more to ensure that systems are in place to prevent schedule delays. The committee believes that, if not already occurring to a large extent, that it is inevitable that schedule delays will, in the long term lead to increased costs associated with managing and completion of projects, especially where those delays are lengthy.

Guidelines for the project data summary sheets

2.38               The committee has noted the changes associated with the 2010-11 MPR Guidelines and exit criteria for projects and endorses them as the framework for the Project Data Summary Sheets (PDSS).

2.39               The committee received the DMO’s proposed list of projects for inclusion at the commencement of the 43rd Parliament which afforded adequate time for the consideration and endorsement of the list.

2.40               The 2010-11 Guidelines were requested at the public hearing for the review of the 2009-10 MPR on 28 February 2011 and made available to the committee in late March 2011.

2.41               Given the short time frame for the production of each annual MPR (which includes the ANAO’s review), the committee could undertake its role more effectively if it were provided with the Guidelines for the following year’s MPR at the same time that it receives the list of possible projects for inclusion. This would provide more time for the committee’s annual review of the MPR. This would also avoid possible inefficiencies for the DMO in meeting the annual MPR work schedule.

Projects of concern

2.42               Projects are classified as Projects of Concern (PoC) when they encounter significant challenges with scheduling, cost, capability delivery or project management. The list of POC was created in 2008 by the Minister for Defence and is separate to the annual MPR process of the reporting of selected major capital acquisition projects.

2.43               The committee notes that five of the 12 currently listed PoC are reported on in the 2009-10 MPR. All projects that are included in the MPR have met the requirements of the agreed criteria as specified in the 2009-10 MPR Guidelines.

2.44               The option for DMO to report to the committee specifically on PoC within the MPR was considered in regard to two main issues. These are: the possible increase in the cost of producing the MPR, and the possible increase in the length of time a project continues to be reported on in the MPR.

2.45               The committee believes that projects classified as PoC should not specifically be reported on simply because they are PoC projects, but rather because they meet the criteria of being major projects as included in the Guidelines for the PDSS.

Exit criteria

2.46               For the first time since review of the MPRs commenced, projects that have been completed may be exited from the MPR. In this regard, the committee was asked to consider the criteria for the exit of projects from the MPR.

2.47               The point at which projects are considered complete and so able to be taken out of the MPR was presented to the committee as the points at which either Final Materiel Release (FMR) or Final Operational Capability (FOC) is achieved.

2.48               The committee understands that FMR is when the DMO considers it has completed its contract for a particular capital acquisition project and FOC is the point at which the Department of Defence accepts that the capital or equipment is ready for use.

2.49               The DMO put forward the view that FMR should be the point at which a project is considered complete for the purpose of the MPR and hence should no longer be reported on in the MPR. At the point of FMR, the DMO’s responsibility in relation to project management ends and the project becomes the responsibility of the Department of Defence.

2.50               The ANAO suggested that the exit criteria for projects from the MPR include both FMR and FOC as the MPR is an important accountability document on the DMO’s performance and allows for project visibility.

2.51               The committee notes both the viewpoints presented by the DMO and the ANAO, and also notes that the 2010-2011 MPR Guidelines include both FMR and FOC as the point of exit for projects for the MPR.

2.52               The committee acknowledges that the MPR document is an accountability document and understands the difference in the role of the DMO and the Department of Defence in regard to projects included in the MPR. However, the committee also believes there is value in terms of increased transparency and improved accountability in including reporting on both FMR and FOC before projects are removed from the MPR.

2.53               The committee also acknowledges and supports DMO’s efforts in its current analysis of the difference in scale, size and incidence of requirements to be completed between FMR and FOC. The committee awaits the DMO’s report on this analysis. The committee will consider seeking further comment on this point from each of the three services, the Department of Defence, the ANAO and industry generally.

2.54               The DMO also suggested that completed projects remain on the MPR for an additional year so that lessons learned may be reported on in the consecutive MPR. The committee believes there is merit in reporting on lessons learned from projects and understands this is a strategic approach to planning which should already be part of the DMO’s internal practice of monitoring and review of projects.

2.55               In the interest of visibility of projects and in the spirit of the MPR, the committee agrees that lessons learned on projects that will be retired from the MPR should be reported on in regard to whole-of-organisation best practice improvement. The committee does not see a reason for these projects to delay the listing of future possible projects. However, the listing of completed projects (for example in an appendix) would seem to be a reasonable compromise.

Recommendation 1

2.56

The committee recommends that the Major Projects Report (MPR) Work Plan (which contains the MPR Guidelines) be provided to the Joint Committee of Public Accounts and Audit concurrently with the list of proposed projects for inclusion and exclusion in the following year’s MPR, no later than 31 August each year.


Recommendation 2

2.57

The committee recommends that Projects of Concern (PoC) not be specifically included in the selection criteria for projects to be reported on in the Major Projects Report (MPR), but where projects reported on in the MPR are also PoC, that they continue to be identified as such.


Recommendation 3

2.58

The committee recommends that the exit criteria for projects reported on in the Major Projects Report be the point at which both Final Materiel Release and Final Operational Capability (as currently defined by the Defence Materiel Organisation and Department of Defence respectively) is achieved.


Recommendation 4

2.59

The committee recommends that in determining whether the exit criteria is appropriate for future Major Projects Reports (MPRs), that the Defence Materiel Organisation’s assessment of the difference in scale, size and incidence of requirements to be completed between Final Materiel Release and Final Operational Capability be provided to the Joint Committee of Public Accounts and Audit as soon as possible to allow for the implementation of any changes to occur for the 2011-12 MPR. In conducting its analysis, the DMO should consult with the three services, the Department of Defence, the Australian National Audit Office and industry representatives.


Recommendation 5

2.60

The committee recommends that once projects have met the exit criteria, they be removed from the Major Projects Report (MPR) and for each project which has been removed, the lessons learned at both the project level and the whole-of-organisation level are included as a separate section in the following MPR.



Navigation: Previous Page | Contents | Next Page

Back to top

We acknowledge the traditional owners and custodians of country throughout Australia and acknowledge their continuing connection to land, waters and community. We pay our respects to the people, the cultures and the elders past, present and emerging.

Aboriginal and Torres Strait Islander people are advised that this website may contain images and voices of deceased people.