Chapter 3 Proposed Robertson Barracks electrical reticulation system upgrade, Darwin, Northern Territory

3.1                   The proposed Robertson Barracks electrical reticulation project aims to provide a major upgrade to the electrical distribution system on the base in order to meet existing demand, with sufficient redundancy, and to meet future demand resulting from continuing developments on the base.

3.2                   The primary objectives of this project are to:

3.3                   The proposal was referred to the Committee on 23 March 2011.

Conduct of the inquiry

3.4                   The inquiry was advertised in local and national newspapers and submissions sought from those with a direct interest in the proposal. The Committee received one submission and one confidential supplementary submission detailing the project costs. A list of submissions can be found at Appendix A.

3.5                   The Committee undertook a site inspection, public hearing and an in-camera hearing on the project costs on 4 May 2011 in Darwin.

3.6                   The transcript of the public hearing as well as the submissions to the inquiry are available on the Committee’s website.[1]

Need for the works

3.7                   The Department of Defence stated that there has been significant growth within the base, including:

3.8                   The Department explained that growth within the base has led to increased demands on the electrical reticulation system throughout the base, resulting in almost no spare capacity within the existing system. The Department also stated that the system is prone to failure during tropical and electrical storms and does not provide adequate redundancy.

3.9                   The Committee finds that there is a need for the works.

Scope of the works

3.10               The proposed scope of the works is detailed in Submission 1: Defence.

3.11               To support the upgrade works proposed by this project, the Northern Territory’s Power and Water Corporation (PaWC) has agreed to complete staged increases in the high voltage power supply to the base.

3.12               The on-base works will include the following:

3.13               Construction will commence in late 2011 and be completed in mid 2013.

3.14               The Committee finds that the proposed scope of works is suitable to meet the needs of Robertson Barracks.

Cost of the works

3.15               The total out-turn cost for this project is $43.4 million, excluding GST, which includes the cost of management and design fees, construction, equipment, contingencies and an allowance for escalation. The Committee received a confidential supplementary submission detailing the project costs and held an in-camera hearing with the Department on the project costs.

3.16               The Committee is satisfied that the costings for the project provided to it are adequate.

Project issues

Project partner

3.17               The Committee sought more detail regarding the relationship between the Department and the PaWC, in relation to this particular project.

3.18               When asked whether there were any particular difficulties foreseen in completing the work in the proposed time, in light of the need to work closely with the PaWC, the Department explained:

We do have an undertaking from Power and Water Corporation where they have indicated to us their master planning for electrical supply in that area, and we have had an exchange of letters to the effect that we understand exactly what they are planning to do and the time frames that they are planning to do it. We have developed this project around the time frames of Power and Water Corporation. So the expectation is that we will have the infrastructure ready and in place within the base at around the same time that Power and Water Corporation are in a position where they can turn on the larger feeders to the base.[2]

3.19               The Department’s project manager explained that they had been working with the PaWC for more than a year to ensure that they are abreast of all of the requirements of the Department and the base itself.[3]

3.20               The Department provided to the Committee a letter from PaWC outlining its commitment to the Department’s project objectives and timelines.

3.21               The Department also explained that the program of works for the Robertson Barracks upgrade project is achievable, including trade and supply issues, despite a significant amount of work being conducted in the Darwin area over the next two to three years.

Committee comment

3.22               Overall, the Committee is satisfied that this project has merit in respect of need, scope and cost.

3.23               Having examined the purpose, need, use, revenue and public value of the works, the Committee considers that it is expedient that the proposed works proceed.

Recommendation 4

 

The Committee recommends that the House of Representatives resolve, pursuant to Section 18(7) of the Public Works Committee Act 1969, that it is expedient to carry out the following proposed work: Robertson Barracks electrical reticulation system upgrade, Darwin, NT.

Navigation: Previous Page | Contents | Next Page

Back to top

We acknowledge the traditional owners and custodians of country throughout Australia and acknowledge their continuing connection to land, waters and community. We pay our respects to the people, the cultures and the elders past, present and emerging.

Aboriginal and Torres Strait Islander people are advised that this website may contain images and voices of deceased people.