Appendix 4
Roles and responsibilities for Murray–Darling Basin water reforms[1]
In broad terms, the roles and responsibilities for water
reform in the Murray–Darling Basin are as follows:
-
The Minister for Water approves the Basin Plan (and any
amendments), approves the use of program funding (water recovery, SDL
adjustment measures etc.), considers evaluations of overall progress, and
chairs the MDB Ministerial Council.
-
Department of Agriculture and Water Resources is responsible for
policy advice and program implementation, in particular investing in water
recovery and SDL adjustment measures. The Department also chairs the Basin
Officials Committee.
-
Murray–Darling Basin Authority oversees implementation of the
Basin Plan, including the Sustainable Diversion Limits, reporting direct to the
Minister.
-
Commonwealth Environmental Water Holder manages the use of
Commonwealth-held environmental water consistent with the Basin Plan, to
achieve best possible environmental outcomes.
-
Basin States own water and are responsible for allocating it to
licence holders consistent with their water resource plans. They also hold and
deliver environmental water, and are responsible for implementing the Basin
Plan in their own jurisdictions.
-
Australian Competition and Consumer Commission provides advice to
the Minister on water market rules and water charge rules which are intended to
free up trade and regulate costs of monopoly infrastructure (e.g. access to
irrigation schemes), and to monitor and enforce these rules.
-
Productivity Commission conducts 5 yearly audits of Basin Plan
implementation.
Roles and responsibilities for
Murray–Darling Basin water reforms
|
Minister for
Water
|
REVIEWS
|
SDL Adjustment Process
|
Support SDL adjustment package through Ministerial
Council.
Adopt amendments to Basin Plan giving effect to the
proposed SDL adjustment.
|
Constraints
|
Support constraints measures as part of SDL
adjustment package. Note that some constraints projects are also likely to be
SDL adjustment projects.
|
Northern Basin Review
(mid 2016)
|
Adopt any proposed amendments to Basin Plan and
revisions to water recovery strategy in light of northern basin review.
|
WATER RECOVERY
|
Buybacks & Infrastructure
|
Decide on water recovery strategy.
|
BASIN PLAN
|
Prepare & implement Basin Plan
|
Adopt Basin Plan (done).
Consider regular reports on Basin Plan
implementation, including those to Ministerial Council.
|
State Water Resource Plan (WRP) Accreditation
|
Decision to accredit each state WRP based on MDBA
advice. There are 36 plans required by 2019.
|
Environmental water planning and delivery
|
Considers reports on use of environmental water.
|
Water Trade
|
Makes Water Market and Charge Rules on advice of
ACCC (done).
|
Monitoring and evaluation
|
Consider 5 yearly evaluations and PC audits.
|
|
Department of
Agriculture and Water Resources
|
REVIEWS
|
SDL Adjustment Process
|
As Chair of BOC, facilitate agreed package of SDL
adjustment measures (see State role).
Implement efficiency measures program and part-fund
states to implement supply measures.
|
Constraints
|
Manage $200 million to address constraints.
|
Northern Basin Review
(mid 2016)
|
Participate in the review.
Consider changes to water recovery strategy in light
of the review.
|
WATER RECOVERY
|
Buybacks & Infrastructure
|
Implement the Commonwealth's water recovery strategy
including cap on buybacks, and recovery of water for enhanced environmental
outcomes (efficiency measures) under the SDL adjustment mechanism.
|
BASIN PLAN
|
Prepare & implement Basin Plan
|
Input to draft Plan (done).
As BOC Chair, facilitate development of agreed state
comments (done).
|
State Water Resource Plan (WRP) Accreditation
|
|
Environmental water planning and delivery
|
|
Water Trade
|
Participate in water market as per water recovery
strategy.
|
Monitoring and evaluation
|
Annual and five yearly reports on water recovery and
investment to MDBA.
|
|
Murray–Darling
Basin Authority
|
REVIEWS
|
SDL Adjustment Process
|
Develop method for assessing ‘supply’ measures based
on Basin Plan (done).
Apply method and modelling to determine amount of
adjustment.
Advise Minister on proposed SDL adjustment to Basin
Plan.
|
Constraints
|
Develop Constraints Management Strategy.
Provide technical advice to states on measures to
best implement the strategy, where requested.
|
Northern Basin Review
(mid 2016)
|
Conduct ‘triple bottom line’ review to test if there
is a case to change SDLs or pattern of water recovery in the northern basin.
Advise Minister on amendments to Basin Plan and
changes to water recovery strategy based on the review.
|
WATER RECOVERY
|
Buybacks & Infrastructure
|
Monitor and report progress with water recovery
('Bridging the Gap').
|
BASIN PLAN
|
Prepare & implement Basin Plan
|
Develop Basin Plan including consultation with
states and stakeholders (done).
Enforce Basin Plan including through annual
assessment of state SDL compliance.
|
State Water Resource Plan (WRP) Accreditation
|
Assess state water resource plans and advise
Minister on their accreditation.
|
Environmental water planning and delivery
|
Set long term outcomes for environmental watering
across Basin (done) and set annual priorities.
Coordinate environmental watering at a basin scale.
|
Water Trade
|
Ensure compliance with Basin Plan water trading
rules.
|
Monitoring and evaluation
|
Monitor and evaluate economic and social outcomes
across Basin with input from Dept on investment.
Monitor and evaluate environmental outcomes with
input from CEWO and States. PC to audit each 5 years.
|
|
Commonwealth
Environmental Water Holder
|
REVIEWS
|
SDL Adjustment Process
|
|
Constraints
|
Input as required.
|
Northern Basin Review
(mid 2016)
|
Participate in the review.
|
WATER RECOVERY
|
Buybacks & Infrastructure
|
Input as required.
|
BASIN PLAN
|
Prepare & implement Basin Plan
|
|
State Water Resource Plan (WRP) Accreditation
|
|
Environmental water planning and delivery
|
Manage Commonwealth environmental water holdings
consistent with the Basin Plan.
|
Water Trade
|
Manage Commonwealth water portfolio – including
trading – in accordance with Water Act (under review).
|
Monitoring and evaluation
|
Monitoring and evaluation of CEWO watering
activities. Annual and five yearly reports to MDBA.
|
|
Basin States
|
REVIEWS
|
SDL Adjustment Process
|
Develop proposed supply measures.
Agree on package of SDL adjustment measures by 30
June 2016.
|
Constraints
|
Develop proposals to address constraints by
mid-2016.
Implement agreed measures.
|
Northern Basin Review
(mid 2016)
|
Qld and NSW are participating in the review.
They will need to advise on their preferred
apportionment of the ‘downstream’ component before the review is finalised.
Provide views on any proposed amendments to Basin
Plan.
|
WATER RECOVERY
|
Buybacks & Infrastructure
|
Work with Commonwealth to identify ways to maximise
water savings made through existing and proposed infrastructure projects
(IGA).
|
BASIN PLAN
|
Prepare & implement Basin Plan
|
Advise state views on draft Basin Plan (done).
States report on SDL compliance post 2019.
|
State Water Resource Plan (WRP) Accreditation
|
Prepare WRPs suitable for C’wealth accreditation.
|
Environmental water planning and delivery
|
Prepare valley-based long term environmental
watering plans and annual priorities. Have regard to MDBA published
priorities when conducting environmental watering.
|
Water Trade
|
Implement state trade rules consistent with Basin
Plan trade rules and processing trades.
|
Monitoring and evaluation
|
Monitoring and evaluation of environmental outcomes
at valley/local scale. Annual and five yearly reports to MDBA.
|